2. Project Goals – Key points taken into consideration
during design
Overview
Background– Fuel Depot location and current
condition
Impact – Fuel spill affect on local region
Deliverables – Support type, construction process,
timeline and cost report
Conclusion – Summary of project, next steps toward
construction
1
2
3
4
5
WSU Engineering 2
3. Manchester Fuel Depot
• 37 monuments with nylon
supports
• 2 monuments with fixed
points
• 775’ pipeline
• 1- 10” diameter
• 1- 14” diameter
WSU Engineering 3
4. Current State
• Nylon pads buckling
and failing
• Difficult visual
inspection
• Possible pinhole leaks
developing
• Corrosion developing
• Costly to maintain
WSU Engineering 4
5. Impact
• Marine life
• Fisheries
• Whale pods
• Public beaches
• Navy operation
• Native American tribes
• Cost
http://canadiantruths.files.wordpress.com/2008/05/duck2.jpg
http://www.ecoosfera.com/wp-content/imagenes/dead-fish1.jpg
http://imagecache6.allposters.com//LRG//%5C27%
5C2750%5CTQ1TD00Z.jpg
http://lh6.ggpht.com/_1RasRrVkr5Y/R4L-
FieJJwI/AAAAAAAAAEk/ndpNIu2Epuc/seattle_alki_beach_crowd
http://upload.wikimedia.org/wikipedia/
commons/d/d2/Aerial_Bremerton_Shipyard.jpg
http://www.hickerphoto.com/images/500/alaska_f76t4736.j
WSU Engineering 5
12. Project Direction Options
Basic Construction
• Keep same
monuments, change
pipeline elevation
• Build new monuments
• Pour concrete cap
• Modify Existing
Monuments
Lifting
• Crane operations
• Jacking systems
• Monuments- Temporary
Supports
WSU Engineering 12
13. Proposed Design
• Reduce number of monuments
• Use existing monuments
• Cut down to desired height
• Use proven welded T-cradle support type
WSU Engineering 13
14. Monument Calculations
Reducing Monuments
Unknowns and spreadsheets
Load on the monuments 7694 lbs
Average stress = F/A = 16 psi
Maximum compressive stress = 28 psi
Ultimate strength of concrete = 2900 psi
Minimum factor of safety = 103
Weight
force
Friction
force
WSU Engineering 14
16. Construction Process
• Use existing
Monuments for
support
• Install Temporary
support
• Work between
supports
• Cut old monuments
supports once
complete
WSU Engineering 16
17. Installation Detail
• Cut down monuments
• Install t-cradle pipe
supports
• Elevate baseplate to
proper height
• Grout at desired
elevation
WSU Engineering 17
20. • Use proven support type
• Reduce unneeded monuments
• Project duration is 37 days
• Projected cost was $300,000 to $500,000
• Actual project estimate is under $179,000
• Simple, proven system for 30+ years of operation
Summary
WSU Engineering 20
21. Thank You For Your Time!
Questions?
Danny Cornutt Giovanni Juarez
Beau MabenBarrett Makrecky
Background credit: Presentermedia.com
Editor's Notes
Danny 20min total 11min members (10min me)
Danny
Danny
Danny
Danny
Beau
Beau
Beau
Beau
Gio
Gio
Gio
Gio
Barrett 1.5min
Barrett 1.5 min
Danny “now we have verified loading we can develop a construction process
Danny (Beau can you work your magic on the picture? We talked about breaking down the picture into steps like your progress report. I tried to keep the editing but it won’t let me)