STAFF REPORT ON INTERLOCAL AGREEMENT BETWEEN
CITY OF SAN ANTONIO FOR SIDEWALK INSTALLATION
ON N. NEW BRAUNFELS
ITEM # 7
JANUARY 23, 2023
2. SUMMARY
Plan developed with City of San Antonio (COSA)
to add sidewalks to western side of N. New
Braunfels
Castano to Claywell
If approved, COSA to install sidewalks & curbs
on their ROW on City side
Interlocal agreement to be developed for 50-50
split funding of project
3. BACKGROUND
N. New Braunfels boundary between City &
COSA from Austin Hwy to Claywell
Approx. 1.2 miles
COSA maintains & controls ROW
Sidewalks currently on eastern (COSA) side
Sidewalks on western side end at Claywell, do
not continue south into City
4. BACKGROUND
City has received multiple citizen requests over
past several years
Pedestrian & ADA accessibility limited to
eastern side of N. New Braunfels
Inefficient access between AH Junior School &
High School
5. PROJECT SCOPE
Improvements on western side of
N. New Braunfels
Claywell to Castano
Project to include
Sidewalk
Curb
Retaining walls
Wheel chair ramps
Approaches
COSA Public Works to oversee
construction management &
engineering
18. PROJECT SCOPE
Extends pedestrian access
& ADA accessibility
additional 0.4 miles
Continuous sidewalks from
AH Junior School to
Castano & AH High
School
19. PROJECTED COSTS
$232,000 estimated project cost
Per COSA Public Works (as of September 2022)
Estimate includes contingency; final cost subject to
change
COSA Council District 10 agreed to 50-50 split of
final project costs
City portion currently unbudgeted
Available funds identified if Council elects to proceed
20. NEXT STEPS
Interlocal agreement for funding transfer
COSA currently developing
Council approval needed by COSA & City
Council appropriation of City’s portion of
project cost