What is power transmission?
Basic structure of electric system
Generation, transmission, distribution, electricity in Pakistan
(NTDC) Pakistan
Transmission lines in Pakistan
Transmission pole design
Power transmission losses
The document discusses India's restructuring of its power grid. It explains that India is undergoing power sector restructuring like other countries around the world. It then provides details on the components that make up the grid like transformers and circuit breakers. It discusses the need for restructuring due to financial constraints and the goal of improving efficiency. The document examines models used internationally and suggests the Transmission System Operator model is most suitable for India. It outlines features of the Electricity Act of 2003 that facilitates the restructuring.
The document discusses the restructuring of power systems from monopolistic to deregulated markets. It explains that restructuring separates generation, transmission, distribution and supply functions. This creates new business opportunities and lower costs for consumers. Various restructuring models are presented including poolco, bilateral contracts and hybrid models. The poolco model uses a centralized market to set prices while bilateral contracts allow direct negotiations. The hybrid model combines features of the first two. An independent system operator maintains grid operations.
The document compares AC and DC power transmission. It discusses three main factors: economics of transmission, technical performance, and reliability. For economics, DC transmission has lower costs for conductors and insulation for long distance transmission over 500-800 km. However, converter equipment for DC is more expensive. Technically, DC allows faster control of power flow and is not limited by stability with increasing distance. Reliability of DC transmission has also improved with advances in thyristor converters. The document provides details on the technical differences between AC and DC transmission under each of the three factors.
1) HVDC transmission was first developed in the late 19th century by Rene Thury. Early systems used DC series generators and mechanical converters.
2) HVDC became more viable with the development of mercury arc valves in the 1950s and thyristor valves in the 1960s, allowing more efficient conversion between AC and DC.
3) HVDC is preferable to HVAC for long distance bulk power transmission, asynchronous connections, offshore wind connections, and other applications where HVDC has technical advantages over HVAC. Key components of HVDC systems include converters, smoothing reactors, filters, and the DC transmission line.
This document discusses multi-terminal DC (MTDC) systems. It begins with an introduction stating that MTDC systems have more than two converter stations that can operate as either rectifiers or inverters. It then describes the two types of MTDC systems - series and parallel (including radial and mesh configurations). The document outlines some applications of MTDC systems, as well as typical problems. It notes advantages like reversible power flow and lack of commutation failures, and disadvantages such as need for large smoothing reactors. Finally, it discusses future aspects like microgrids and renewable integration, and concludes that VSC-HVDC technology may help address challenges and enable more MTDC system implementation.
This document provides an overview of a 220/132 kV substation in Barahuwa, India. It includes a single line diagram showing the incoming and outgoing sections. The substation has three main parts: a panel section containing control and relay panels, a yard section with 220 kV, 132 kV and 33 kV sections, and a battery room powering the station. It describes the various components used in the substation like transformers, circuit breakers, isolators etc. The training program helped broaden the author's knowledge of power transmission and distribution.
The document discusses India's restructuring of its power grid. It explains that India is undergoing power sector restructuring like other countries around the world. It then provides details on the components that make up the grid like transformers and circuit breakers. It discusses the need for restructuring due to financial constraints and the goal of improving efficiency. The document examines models used internationally and suggests the Transmission System Operator model is most suitable for India. It outlines features of the Electricity Act of 2003 that facilitates the restructuring.
The document discusses the restructuring of power systems from monopolistic to deregulated markets. It explains that restructuring separates generation, transmission, distribution and supply functions. This creates new business opportunities and lower costs for consumers. Various restructuring models are presented including poolco, bilateral contracts and hybrid models. The poolco model uses a centralized market to set prices while bilateral contracts allow direct negotiations. The hybrid model combines features of the first two. An independent system operator maintains grid operations.
The document compares AC and DC power transmission. It discusses three main factors: economics of transmission, technical performance, and reliability. For economics, DC transmission has lower costs for conductors and insulation for long distance transmission over 500-800 km. However, converter equipment for DC is more expensive. Technically, DC allows faster control of power flow and is not limited by stability with increasing distance. Reliability of DC transmission has also improved with advances in thyristor converters. The document provides details on the technical differences between AC and DC transmission under each of the three factors.
1) HVDC transmission was first developed in the late 19th century by Rene Thury. Early systems used DC series generators and mechanical converters.
2) HVDC became more viable with the development of mercury arc valves in the 1950s and thyristor valves in the 1960s, allowing more efficient conversion between AC and DC.
3) HVDC is preferable to HVAC for long distance bulk power transmission, asynchronous connections, offshore wind connections, and other applications where HVDC has technical advantages over HVAC. Key components of HVDC systems include converters, smoothing reactors, filters, and the DC transmission line.
This document discusses multi-terminal DC (MTDC) systems. It begins with an introduction stating that MTDC systems have more than two converter stations that can operate as either rectifiers or inverters. It then describes the two types of MTDC systems - series and parallel (including radial and mesh configurations). The document outlines some applications of MTDC systems, as well as typical problems. It notes advantages like reversible power flow and lack of commutation failures, and disadvantages such as need for large smoothing reactors. Finally, it discusses future aspects like microgrids and renewable integration, and concludes that VSC-HVDC technology may help address challenges and enable more MTDC system implementation.
This document provides an overview of a 220/132 kV substation in Barahuwa, India. It includes a single line diagram showing the incoming and outgoing sections. The substation has three main parts: a panel section containing control and relay panels, a yard section with 220 kV, 132 kV and 33 kV sections, and a battery room powering the station. It describes the various components used in the substation like transformers, circuit breakers, isolators etc. The training program helped broaden the author's knowledge of power transmission and distribution.
The document discusses converter configurations and analyzes a 12 pulse converter. It begins by explaining pulse number and valve/switch types in converters. It then discusses how converter configuration is selected based on pulse number to maximize valve and transformer utilization. It provides equations for peak inverse voltage, utilization factor, and transformer rating calculations. Finally, it analyzes a 12 pulse converter, explaining how two transformers connected in star-star and star-delta configurations produce 12 pulses of output with each pulse having a 30 degree duration.
A substation is a high-voltage electric facility used to switch generators, equipment, and circuits in and out of a system. It also changes AC voltages and converts between AC and DC. Substations can be classified by their service, mounting, function, type of apparatus, and control. They include transformers, switches, circuit breakers, and other equipment to distribute power at appropriate voltages for transmission and utilization.
The document discusses conductor materials used for electric power transmission and distribution. It describes the properties and characteristics of commonly used materials like copper, aluminum, steel-cored aluminum, and galvanized steel. It also explains the Ferranti effect, where the receiving end voltage is higher than the sending end voltage under light or no load conditions due to the charging current of transmission lines. This effect can be reduced by using shunt reactors at the receiving end to compensate for the capacitive current from long transmission lines.
This document discusses unit commitment in power systems. Unit commitment aims to schedule generating units to meet forecasted load at minimum cost while maintaining reliability. It considers startup costs, operating costs, and shutdown costs over a daily load cycle. Dynamic programming is used to solve the unit commitment problem by evaluating combinations of generating units at each time interval and carrying minimum costs backward from the final interval to find the overall lowest-cost solution. The objective is to determine the optimal set of units to operate at each time period to supply predicted load economically.
The document discusses electrical power distribution systems. It defines primary and secondary distribution systems based on voltage level. Primary distribution exists between distribution substations and transformers, while secondary distribution receives power from transformer secondaries and supplies various loads. The document also describes radial and ring main distribution network configurations and their relative advantages. Requirements for good distribution systems like continuity of supply and limited voltage variation are also outlined.
The document provides an overview of grid code technical recruitments in India. It discusses the roles of various organizations in electricity transmission planning and operations. The National Load Dispatch Center oversees national grid operations while Regional Load Dispatch Centers control regional operations. State Load Dispatch Centers control operations within states. Transmission utilities and state transmission utilities plan and develop inter-state and intra-state transmission systems respectively. The Central Electricity Authority issues technical standards and guidelines for transmission planning. Regional Power Committees facilitate coordination between states. The document also summarizes various codes related to transmission planning, grid connections, grid operations, and scheduling and dispatch of electricity.
EHV (extra high voltage) AC transmission refers to equipment designed for voltages greater than 345 kV. Higher transmission voltages increase efficiency by reducing transmission losses and current, decrease infrastructure costs, and increase transmission capacity. However, they also present safety and interference risks. New technologies like FACTS (flexible AC transmission systems) help maximize the benefits of EHV transmission by enabling voltage control and power flow management. There is growing support for expanding national EHV transmission grids to facilitate large-scale renewable energy integration and inter-regional power sharing.
Unit 5 Economic Load Dispatch and Unit CommitmentSANTOSH GADEKAR
ย
This document provides information on economic load dispatch and unit commitment in power systems. It discusses the input-output and incremental cost characteristics of thermal and hydro power plants. It also describes the equal incremental cost method for economic load dispatch using Lagrange multipliers. A numerical example with two generating units is provided to illustrate solving for optimal dispatch considering varying load demand over different time periods.
Measurement of high_voltage_and_high_currentunit_iv_full_versionAman Ansari
ย
This document discusses various techniques for measuring high voltages, including DC, AC, and high frequency voltages. For DC voltages, it describes using a series resistance microammeter, resistance potential divider, and generating voltmeters. For AC voltages, it outlines series impedance voltmeters, potential transformers, electrostatic voltmeters, potential dividers, and sphere gaps. It provides details on measuring peak voltages using series capacitor peak voltmeters and using a peak voltmeter with a potential divider. It also discusses measuring RMS voltages with a peak voltmeter or electrostatic voltmeter.
This document is a project report submitted by Girish Gupta about his training at the 132 KV substation in Purukul, Dehradun. It includes an index listing the topics covered in the report such as the substation, transformers, circuit breakers, and protection systems. The report provides details about the Power Transmission Corporation of Uttarakhand Limited and describes the components and layout of the 132 KV substation in Purukul, including its two incoming transmission lines, transformers, buses, feeders, and capacitor bank. It also defines different types of substations and their characteristics.
The document discusses protection of alternators from various faults. It describes 7 types of faults that alternators require protection from: (1) failure of prime mover, (2) failure of field, (3) overcurrent, (4) overspeed, (5) overvoltage, (6) stator winding faults, and (7) unbalanced loading. It then provides details on differential protection and the Merz-Price circulating current scheme, which is commonly used to protect against stator winding faults. It also discusses limitations of this scheme and modified schemes for protection in other situations.
This document is an industrial training report submitted by Swapnil Kumar Gupta for their Bachelor of Technology degree in Electrical Engineering. The report provides an overview of Swapnil's 2-week industrial training at the 220kV substation in Rewa Road, Allahabad, which is operated by Uttar Pradesh Power Transmission Corporation Limited. The report includes details about the equipment and processes at the substation, as well as declarations, acknowledgements, and chapters covering topics like the selection of substation sites, common equipment used in 220kV substations, and descriptions of the transformer and other components.
Economic load dispatch(with and without losses)Asha Anu Kurian
ย
The document discusses unit commitment in power systems. Unit commitment involves determining the optimal schedule for starting up and shutting down generators to meet changing load at minimum cost while satisfying operational constraints. These constraints include minimum up and down times for generators, crew constraints, transition costs, and constraints related to different generator types like hydro, nuclear, and generators requiring minimum output. The objective is to determine the combination and scheduling of generators that supplies the load as economically as possible over a given period.
AC Distribution System - Generation Distribution and TransmissionGowtham Cr
ย
It include the introduction, requirements, types of distribution system, explanation of Ac Distribution system ,it's Classifications, calculations and types.
1. The document discusses a static synchronous series compensator (SSSC), a type of flexible AC transmission system (FACTS) device that controls electric power flow by injecting a controlled voltage in series with a transmission line.
2. The SSSC can provide either capacitive or inductive compensation, depending on whether the injected voltage lags or leads the line current.
3. Digital simulations show that the SSSC can increase or decrease the dynamic power flow in the transmission line depending on the mode of compensation.
VTU Notes for Testing and commissioning of Electrical Equipment Department of Electrical and Electronics Faculty Name: Mrs Veena Bhat Designation: Assistant Professor Subject: Testing and Commissioning of Electrical equipment Semester: VII
This document discusses issues related to interconnecting microgrids. It describes how a DC microgrid system utilizes a DC bus to distribute power from photovoltaic units and battery storage to local households. Interconnection can be done directly through switchgear or power electronic interfaces. Key issues that can arise include voltage and frequency fluctuations that occur due to imbalance between supply and demand, power factor correction needs, and harmonics produced by some loads. Unintentional islanding is also a safety concern that must be addressed when connecting microgrids to the main power grid.
This document discusses the distribution of a transmission line project among group members and provides background information on electricity distribution in Pakistan. It outlines the members of the group working on the transmission line distribution project and their registration numbers. It then provides an introduction to transmission and distribution lines. The document continues by describing the basic concepts of energy transmission and providing historical context of electricity in Pakistan. It outlines the various organizations involved in electricity production and distribution in Pakistan. Finally, it describes the layout of Pakistan's power system and classifications of transmission lines.
This document summarizes a student's three-week vocational training at the 132/33 kV Salt Lake substation owned by the West Bengal State Electricity Transmission Corporation Limited. The training took place from February 6th to 27th, 2017 under the guidance of Assistant Engineer Mr. Debayan Mandal. The student thanks all those involved for their guidance and for providing an insight into the practical applications of electrical systems and equipment. The document includes sections acknowledging those who supported the training and providing background on the organization and an introduction to electrical substations and power transmission systems.
Bulk transmission of electricity over long distances at high voltages helps transfer power from surplus to deficit regions in India. The transmission network in India has expanded significantly from 3,708 circuit km in 1950 to over 280,000 circuit km today. A national grid connecting regional grids was established in stages, achieving a single national grid with one frequency in 2013. High voltage transmission above 132kV is preferred for reduced transmission losses. The Power Grid Corporation of India manages the national transmission system and ensures integrated operation.
The document discusses converter configurations and analyzes a 12 pulse converter. It begins by explaining pulse number and valve/switch types in converters. It then discusses how converter configuration is selected based on pulse number to maximize valve and transformer utilization. It provides equations for peak inverse voltage, utilization factor, and transformer rating calculations. Finally, it analyzes a 12 pulse converter, explaining how two transformers connected in star-star and star-delta configurations produce 12 pulses of output with each pulse having a 30 degree duration.
A substation is a high-voltage electric facility used to switch generators, equipment, and circuits in and out of a system. It also changes AC voltages and converts between AC and DC. Substations can be classified by their service, mounting, function, type of apparatus, and control. They include transformers, switches, circuit breakers, and other equipment to distribute power at appropriate voltages for transmission and utilization.
The document discusses conductor materials used for electric power transmission and distribution. It describes the properties and characteristics of commonly used materials like copper, aluminum, steel-cored aluminum, and galvanized steel. It also explains the Ferranti effect, where the receiving end voltage is higher than the sending end voltage under light or no load conditions due to the charging current of transmission lines. This effect can be reduced by using shunt reactors at the receiving end to compensate for the capacitive current from long transmission lines.
This document discusses unit commitment in power systems. Unit commitment aims to schedule generating units to meet forecasted load at minimum cost while maintaining reliability. It considers startup costs, operating costs, and shutdown costs over a daily load cycle. Dynamic programming is used to solve the unit commitment problem by evaluating combinations of generating units at each time interval and carrying minimum costs backward from the final interval to find the overall lowest-cost solution. The objective is to determine the optimal set of units to operate at each time period to supply predicted load economically.
The document discusses electrical power distribution systems. It defines primary and secondary distribution systems based on voltage level. Primary distribution exists between distribution substations and transformers, while secondary distribution receives power from transformer secondaries and supplies various loads. The document also describes radial and ring main distribution network configurations and their relative advantages. Requirements for good distribution systems like continuity of supply and limited voltage variation are also outlined.
The document provides an overview of grid code technical recruitments in India. It discusses the roles of various organizations in electricity transmission planning and operations. The National Load Dispatch Center oversees national grid operations while Regional Load Dispatch Centers control regional operations. State Load Dispatch Centers control operations within states. Transmission utilities and state transmission utilities plan and develop inter-state and intra-state transmission systems respectively. The Central Electricity Authority issues technical standards and guidelines for transmission planning. Regional Power Committees facilitate coordination between states. The document also summarizes various codes related to transmission planning, grid connections, grid operations, and scheduling and dispatch of electricity.
EHV (extra high voltage) AC transmission refers to equipment designed for voltages greater than 345 kV. Higher transmission voltages increase efficiency by reducing transmission losses and current, decrease infrastructure costs, and increase transmission capacity. However, they also present safety and interference risks. New technologies like FACTS (flexible AC transmission systems) help maximize the benefits of EHV transmission by enabling voltage control and power flow management. There is growing support for expanding national EHV transmission grids to facilitate large-scale renewable energy integration and inter-regional power sharing.
Unit 5 Economic Load Dispatch and Unit CommitmentSANTOSH GADEKAR
ย
This document provides information on economic load dispatch and unit commitment in power systems. It discusses the input-output and incremental cost characteristics of thermal and hydro power plants. It also describes the equal incremental cost method for economic load dispatch using Lagrange multipliers. A numerical example with two generating units is provided to illustrate solving for optimal dispatch considering varying load demand over different time periods.
Measurement of high_voltage_and_high_currentunit_iv_full_versionAman Ansari
ย
This document discusses various techniques for measuring high voltages, including DC, AC, and high frequency voltages. For DC voltages, it describes using a series resistance microammeter, resistance potential divider, and generating voltmeters. For AC voltages, it outlines series impedance voltmeters, potential transformers, electrostatic voltmeters, potential dividers, and sphere gaps. It provides details on measuring peak voltages using series capacitor peak voltmeters and using a peak voltmeter with a potential divider. It also discusses measuring RMS voltages with a peak voltmeter or electrostatic voltmeter.
This document is a project report submitted by Girish Gupta about his training at the 132 KV substation in Purukul, Dehradun. It includes an index listing the topics covered in the report such as the substation, transformers, circuit breakers, and protection systems. The report provides details about the Power Transmission Corporation of Uttarakhand Limited and describes the components and layout of the 132 KV substation in Purukul, including its two incoming transmission lines, transformers, buses, feeders, and capacitor bank. It also defines different types of substations and their characteristics.
The document discusses protection of alternators from various faults. It describes 7 types of faults that alternators require protection from: (1) failure of prime mover, (2) failure of field, (3) overcurrent, (4) overspeed, (5) overvoltage, (6) stator winding faults, and (7) unbalanced loading. It then provides details on differential protection and the Merz-Price circulating current scheme, which is commonly used to protect against stator winding faults. It also discusses limitations of this scheme and modified schemes for protection in other situations.
This document is an industrial training report submitted by Swapnil Kumar Gupta for their Bachelor of Technology degree in Electrical Engineering. The report provides an overview of Swapnil's 2-week industrial training at the 220kV substation in Rewa Road, Allahabad, which is operated by Uttar Pradesh Power Transmission Corporation Limited. The report includes details about the equipment and processes at the substation, as well as declarations, acknowledgements, and chapters covering topics like the selection of substation sites, common equipment used in 220kV substations, and descriptions of the transformer and other components.
Economic load dispatch(with and without losses)Asha Anu Kurian
ย
The document discusses unit commitment in power systems. Unit commitment involves determining the optimal schedule for starting up and shutting down generators to meet changing load at minimum cost while satisfying operational constraints. These constraints include minimum up and down times for generators, crew constraints, transition costs, and constraints related to different generator types like hydro, nuclear, and generators requiring minimum output. The objective is to determine the combination and scheduling of generators that supplies the load as economically as possible over a given period.
AC Distribution System - Generation Distribution and TransmissionGowtham Cr
ย
It include the introduction, requirements, types of distribution system, explanation of Ac Distribution system ,it's Classifications, calculations and types.
1. The document discusses a static synchronous series compensator (SSSC), a type of flexible AC transmission system (FACTS) device that controls electric power flow by injecting a controlled voltage in series with a transmission line.
2. The SSSC can provide either capacitive or inductive compensation, depending on whether the injected voltage lags or leads the line current.
3. Digital simulations show that the SSSC can increase or decrease the dynamic power flow in the transmission line depending on the mode of compensation.
VTU Notes for Testing and commissioning of Electrical Equipment Department of Electrical and Electronics Faculty Name: Mrs Veena Bhat Designation: Assistant Professor Subject: Testing and Commissioning of Electrical equipment Semester: VII
This document discusses issues related to interconnecting microgrids. It describes how a DC microgrid system utilizes a DC bus to distribute power from photovoltaic units and battery storage to local households. Interconnection can be done directly through switchgear or power electronic interfaces. Key issues that can arise include voltage and frequency fluctuations that occur due to imbalance between supply and demand, power factor correction needs, and harmonics produced by some loads. Unintentional islanding is also a safety concern that must be addressed when connecting microgrids to the main power grid.
This document discusses the distribution of a transmission line project among group members and provides background information on electricity distribution in Pakistan. It outlines the members of the group working on the transmission line distribution project and their registration numbers. It then provides an introduction to transmission and distribution lines. The document continues by describing the basic concepts of energy transmission and providing historical context of electricity in Pakistan. It outlines the various organizations involved in electricity production and distribution in Pakistan. Finally, it describes the layout of Pakistan's power system and classifications of transmission lines.
This document summarizes a student's three-week vocational training at the 132/33 kV Salt Lake substation owned by the West Bengal State Electricity Transmission Corporation Limited. The training took place from February 6th to 27th, 2017 under the guidance of Assistant Engineer Mr. Debayan Mandal. The student thanks all those involved for their guidance and for providing an insight into the practical applications of electrical systems and equipment. The document includes sections acknowledging those who supported the training and providing background on the organization and an introduction to electrical substations and power transmission systems.
Bulk transmission of electricity over long distances at high voltages helps transfer power from surplus to deficit regions in India. The transmission network in India has expanded significantly from 3,708 circuit km in 1950 to over 280,000 circuit km today. A national grid connecting regional grids was established in stages, achieving a single national grid with one frequency in 2013. High voltage transmission above 132kV is preferred for reduced transmission losses. The Power Grid Corporation of India manages the national transmission system and ensures integrated operation.
Power System electrical and electronics .pptxMUKULKUMAR210
ย
The document discusses transmission lines, including their objectives, classification, key terms, and components. It aims to minimize energy costs, maintain reliable power supply to consumers, and allow flexible power transfer. Transmission lines are classified based on voltage level, distance, and whether AC or DC. Common conductor types include ACSR, AAAR, and bundled conductors. Insulators provide electrical insulation from supporting structures. Skin effect causes current to flow near the surface of conductors. An equivalent circuit models the parameters of an actual transmission line.
The document discusses the key elements of an electrical supply system including power generation, transmission, distribution, and consumption. It notes there are four main elements: power production/generation, power transmission through high voltage transmission lines, power distribution to load locations through medium voltage transmission lines, and power consumption by industrial, commercial, and residential users. It also mentions the need for monitoring and control systems to oversee the electrical supply system.
This document provides information about operating and maintaining high voltage direct current (HVDC) stations. It discusses several existing and upcoming HVDC projects in India, including key details like transmission capacity, voltage levels, and converter station specifications. It also outlines important aspects of HVDC station operation like startup procedures, shutdown types, protection and control systems, and types of maintenance activities. The major areas of an HVDC back-to-back station that require maintenance are identified as the valve hall, AC switchyard equipment, valve cooling system, auxiliary systems, and AC/DC control and protection systems.
CHAPTER 1 Distribution Systems and Tariffs.pptxLiewChiaPing
ย
This document provides an overview of Malaysia's electricity generation and distribution systems. It discusses the following key points:
- Malaysia's electricity is generated through various thermal and hydro power plants. The generation mix is changing with more natural gas and renewable sources being utilized.
- Electricity is transmitted through high voltage networks before being stepped down and distributed to consumers through medium and low voltage distribution systems.
- Distribution systems have multiple levels including transmission main intakes, main distribution substations, main switching stations, and distribution substations before reaching end users.
- Low voltage distribution networks supply residential, commercial and small industrial customers while high voltage networks supply large industrial customers.
This document provides an internship report on Power House UET Lahore. It includes:
- An overview of electrical power systems, which have three main components: generation, transmission, and load. Electricity is generated at power stations and transmitted through transmission lines before reaching loads.
- A brief history of electric power, including early developments like the transformer and three-phase transmission lines.
- Details about Pakistan's energy sources, including its reliance on natural gas, hydropower potential, and coal resources. The report also examines electricity demand, supply, consumption trends, and future power generation projects.
- Descriptions of key aspects of power systems like transmission, distribution, and three-phase power.
Design & Simulation of Energy Storage Unified Power Quality Conditioner (EUPQ...IJERA Editor
ย
Rapid consumption of energy from conventional sources can be limited by connecting more no. of distributed generation systems with the support of smart grid technology. But the impact of variation in DG power out putted may lead to power quality problems in the distributed system in which it is connected. In addition to this power system faults, non- linear loads and non-linear characteristics of converter circuits used in DG s further deteriorate quality of the power. Implementation of UPQC in the network itself solves the problems addressed but crowding of more no of DG in the network will suppress the effect of UPQC. However energy storage system integration can suppress the large power fluctuations outputted by DGs. In this paper energy storage based unified power quality conditioner (EUPQC) has been implemented using fuggy logic controller. For energy storage ultra (Super) capacitor has been used for fast rate of charging and discharging. The performance of the implemented UPQC with fuggy logic controller is compared with PI controller with the MATLAB simulation.
This document is a project report on industrial training completed at a 220kV grid transmission substation in Naubasta, Kanpur, India. It discusses the components typically found at electrical substations including conductors, transformers, capacitor banks, isolators, circuit breakers and lightning arresters. It provides details on the types of substations, components used at the specific 220kV substation where training took place, and thanks those involved in the training experience.
Ishank Ranjan completed an industrial training project at the 220kV Grid Transmission Substation in Naubasta, Kanpur. The report acknowledges the contributions of staff at the substation who helped explain the various equipment. It includes sections on the components used at grid transmission substations such as conductors, transformers, capacitor banks, isolators, circuit breakers and lightning arresters. The report provides details on the panel section which contains control and protection panels, and the substation yard layout.
- The document discusses the need for a national power grid in India to connect regional grids and ensure reliable electricity delivery across the country.
- India's electricity grid is divided into five regional grids that operate mostly asynchronously. A national grid would improve power transfer capabilities across regions.
- The development of new technologies like HVDC transmission, FACTS devices, and smart grid capabilities can further improve the efficiency and reliability of India's power grid.
- However, building a national grid also presents challenges like high investment costs, transmission losses, and ensuring stability across a large interconnected system.
A Power Flow Analysis of the Nigerian 330 KV Electric Power SystemIOSR Journals
ย
This document analyzes the power flow of Nigeria's 330kV electric power system. It describes the system which includes 30 buses and 9 generating stations connected by 330kV transmission lines totaling 5000km. The document aims to determine causes of power failures in Nigeria and evaluate individual bus voltages to ensure they remain within statutory limits. A power flow analysis is conducted using Newton-Raphson's method in MATLAB. Results show several bus voltages outside limits. Capacitive compensation is implemented on problem buses, improving voltages to acceptable levels and enhancing system efficiency.
A Power Flow Analysis of the Nigerian 330 KV Electric Power SystemIOSR Journals
ย
This document analyzes the power flow of Nigeria's 330kV electric power system. It describes the system which includes 30 buses and 9 generating stations connected by 330kV transmission lines. Power demand exceeds supply due to limited generation and transmission expansion. Some bus voltages are outside statutory limits of 0.95-1.05 pu. The study implements capacitive shunt compensation on problem buses to improve voltages. Simulation results show compensation brings voltages like bus 14 (Jos) from 0.8171 pu to 0.9823 pu, meeting acceptable levels. The analysis aims to address network issues, identify causes of power failures, and ensure bus voltages meet demand through reactive power control and compensation.
This document analyzes the power flow of Nigeria's 330kV electric power system. It finds that several bus voltages are outside the statutory limits of 0.95-1.05 pu under normal conditions. Capacitive shunt compensation is implemented on these problematic buses, improving the voltages to acceptable levels. For example, bus 14 (Jos) increases from 0.8171 pu to 0.9823 pu with compensation. The analysis aims to improve system efficiency and stability through reactive power control and compensation.
EPT LEcture 1 Introduction to Pakistan Power System.pptxmansoorahmed57478
ย
The document provides an overview of Pakistan's power system, including its generation, transmission, and distribution infrastructure. It notes that generation comes from hydroelectric, thermal, nuclear, and renewable sources. The largest power plants are the Tarbela and Mangla hydroelectric dams. Thermal power accounts for over 60% of installed capacity. Transmission is handled by NTDC, while the 10 DISCOs are responsible for distribution. Key organizations that govern the various aspects of the power system are also summarized.
The document discusses the evolution of electric power systems from the late 19th century to the present. Key developments include the shift from DC to AC systems in the late 1880s, increasing transmission voltages from the early 1900s to the 1990s, and the development of HVDC transmission in the 1950s to overcome limitations of HVAC systems. It also summarizes the present state of the Indian power system and projected scenarios by 2012 with increasing installed capacity, demand, and the need for stronger inter-regional transmission networks. Emerging transmission technologies discussed include UHVAC, gas insulated lines, HVDC-Light, and FACTS devices.
This document provides an overview of an industrial training report submitted by Shivam Upadhyay at the Uttar Pradesh Power Transmission Corporation Limited (UPPTCL) 220/132 kV substation in Dadri, Uttar Pradesh from July 2-29, 2023. The report describes the electricity transmission and distribution processes at UPPTCL, the equipment used at the Dadri substation like transformers, circuit breakers, and instrumentation. It also includes a single line diagram of the substation and discussions of transformer and insulator types.
Wireless power transmission involves transmitting electrical energy through electromagnetic fields without physical connections like wires. It works by generating time-varying electromagnetic fields at a transmitter device powered by an energy source, which transmits power across space to a receiver device that extracts power from the field and delivers it to a load. Common techniques for wireless power transfer include inductive coupling using coils, resonant inductive coupling as developed by the WiTricity project at MIT, microwave power transmission using antennas, and laser power transmission for long-range applications. Wireless power holds advantages over wired transmission such as reliability, reduced environmental impact, and efficiency by eliminating energy losses during transmission.
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxEduSkills OECD
ย
Ivรกn Bornacelly, Policy Analyst at the OECD Centre for Skills, OECD, presents at the webinar 'Tackling job market gaps with a skills-first approach' on 12 June 2024
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumMJDuyan
ย
(๐๐๐ ๐๐๐) (๐๐๐ฌ๐ฌ๐จ๐ง ๐)-๐๐ซ๐๐ฅ๐ข๐ฆ๐ฌ
๐๐ข๐ฌ๐๐ฎ๐ฌ๐ฌ ๐ญ๐ก๐ ๐๐๐ ๐๐ฎ๐ซ๐ซ๐ข๐๐ฎ๐ฅ๐ฎ๐ฆ ๐ข๐ง ๐ญ๐ก๐ ๐๐ก๐ข๐ฅ๐ข๐ฉ๐ฉ๐ข๐ง๐๐ฌ:
- Understand the goals and objectives of the Edukasyong Pantahanan at Pangkabuhayan (EPP) curriculum, recognizing its importance in fostering practical life skills and values among students. Students will also be able to identify the key components and subjects covered, such as agriculture, home economics, industrial arts, and information and communication technology.
๐๐ฑ๐ฉ๐ฅ๐๐ข๐ง ๐ญ๐ก๐ ๐๐๐ญ๐ฎ๐ซ๐ ๐๐ง๐ ๐๐๐จ๐ฉ๐ ๐จ๐ ๐๐ง ๐๐ง๐ญ๐ซ๐๐ฉ๐ซ๐๐ง๐๐ฎ๐ซ:
-Define entrepreneurship, distinguishing it from general business activities by emphasizing its focus on innovation, risk-taking, and value creation. Students will describe the characteristics and traits of successful entrepreneurs, including their roles and responsibilities, and discuss the broader economic and social impacts of entrepreneurial activities on both local and global scales.
This document provides an overview of wound healing, its functions, stages, mechanisms, factors affecting it, and complications.
A wound is a break in the integrity of the skin or tissues, which may be associated with disruption of the structure and function.
Healing is the bodyโs response to injury in an attempt to restore normal structure and functions.
Healing can occur in two ways: Regeneration and Repair
There are 4 phases of wound healing: hemostasis, inflammation, proliferation, and remodeling. This document also describes the mechanism of wound healing. Factors that affect healing include infection, uncontrolled diabetes, poor nutrition, age, anemia, the presence of foreign bodies, etc.
Complications of wound healing like infection, hyperpigmentation of scar, contractures, and keloid formation.
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...EduSkills OECD
ย
Andreas Schleicher, Director of Education and Skills at the OECD presents at the launch of PISA 2022 Volume III - Creative Minds, Creative Schools on 18 June 2024.
Gender and Mental Health - Counselling and Family Therapy Applications and In...PsychoTech Services
ย
A proprietary approach developed by bringing together the best of learning theories from Psychology, design principles from the world of visualization, and pedagogical methods from over a decade of training experience, that enables you to: Learn better, faster!
How Barcodes Can Be Leveraged Within Odoo 17Celine George
ย
In this presentation, we will explore how barcodes can be leveraged within Odoo 17 to streamline our manufacturing processes. We will cover the configuration steps, how to utilize barcodes in different manufacturing scenarios, and the overall benefits of implementing this technology.
A Visual Guide to 1 Samuel | A Tale of Two HeartsSteve Thomason
ย
These slides walk through the story of 1 Samuel. Samuel is the last judge of Israel. The people reject God and want a king. Saul is anointed as the first king, but he is not a good king. David, the shepherd boy is anointed and Saul is envious of him. David shows honor while Saul continues to self destruct.
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.pptHenry Hollis
ย
The History of NZ 1870-1900.
Making of a Nation.
From the NZ Wars to Liberals,
Richard Seddon, George Grey,
Social Laboratory, New Zealand,
Confiscations, Kotahitanga, Kingitanga, Parliament, Suffrage, Repudiation, Economic Change, Agriculture, Gold Mining, Timber, Flax, Sheep, Dairying,
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
ย
Power Transmission In Pakistan
1. POWER SYSTEM IN PAKISTAN
PRESENTATION BY
MUHAMMAD USAMA
INSTRUCTOR & SUBJECT
SHUAIB KAKA | BASIC MECHANICALTECHNOLOGY
B-TECH ELECTRICAL SECOND SEMISTER
2. POWERTRANSMISSION
Content
๏ฑ What is power transmission?
๏ฑ Basic structure of electric system
๏ฑ Generation, transmission, distribution, electricity in Pakistan
๏ฑ (NTDC) Pakistan
๏ฑTransmission lines in Pakistan
๏ฑTransmission pole design
๏ฑ Power transmission losses
3. POWERTRANSMISSION
โข Electric power transmission is the bulk movement of electrical energy
from a generating site, such as a power plant, to an electrical
substation. The interconnected lines which facilitate this movement
are known as a transmission network. This is distinct from the local
wiring between high-voltage substations and customers, which is
typically referred to as electric power distribution.
5. ELECTRICITY IN PAKISTAN IS GENERATED,
TRANSMITTED, DISTRIBUTED
Electricity in Pakistan is generated,
transmitted, distributed, and retail supplied
by two vertically integrated public sector
utilities: Water and Power Development
Authority (WAPDA) for all of Pakistan
(except Karachi), and the Karachi Electric
(K-Electric) for the city of Karachi and its
surrounding areas.There are around 42
independent power producers (IPPs) that
contribute significantly in electricity
generation in Pakistan.
6. POWERTRANSMISSION
NATIONAL TRANSMISSION & DESPATCH COMPANY (NTDC) PAKISTAN
There 12436 km transmission line of 500KV,220 KV
transmission line in Pakistan.
NTDC operates and maintains fourteen 500 KV and thirty eight
220 KV Grid Stations, 5110.48 km of 500 KV transmission line and
9686.32 km of 220 KV transmission line in Pakistan.
7. POWER TRANSMISSION
๏ The three-phase system has three sets of phase conductors.
๏ There 5077 km of 500 KV transmission line in Pakistan.
๏ There are Thirty Two 220 KV Grid Stations.
๏ Total length is 7359 km of 220 KV transmission line in
Pakistan.
9. POWERTRANSMISSION LOSSES
The safe and reliable transmission and distribution of electricity
remains a major problem in Pakistan.
There are following main causes of loss
๏ง Poor conductor material
๏ง Weak grid infrastructure and substantial
๏ง Theft of electricity
๏ง Low time to time maintenance of network
๏ง Resistive losses