Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Permit to Work software proves to be a very useful and convenient tool to establish control, co-ordination and communication, following correct work sequences among the participating agencies.
Web based software lets you use intranet or the internet to run Permit To Work to every desktop and work location in an organization. It replaces the need for "paper based" permit to work systems with approvals via electronic signatures, while the final output is a printed "permit" for display at the worksite with all the details of the work, the risk assessment and isolation & other certificates.
Permit To Work Software has capability to adapt the client's existing procedure and its work environment. No requirement to change whole system, boost system implementation on time.
Learn More about ASK-EHS Permit to Work Software - http://www.ask-ehs.com/software/permit-to-work-software.html
A quick introduction about PMP certificate, how to obtain one and what is process groups and knowledge areas, PDUs and other certificates offered by PMI.
PMI - Project Management
Project Management Professional (PMP) is an internationally recognized professional designation offered by the PMI. There are currently 773,840 active PMP certified individuals and 286 chartered chapters across 210 countries and territories worldwide. The exam is based on the PMI Project Management Body of Knowledge (PMBOK), and the prerequisites are:
Secondary degree (high school diploma, associate’s degree or the global equivalent)
7,500 hours leading and directing projects
35 hours of project management education
OR
Four-year degree
4,500 hours leading and directing projects
35 hours of project management education
A candidate who passes the exam and meets the professional requirements is awarded the PMP certification.
We are starting a series of questions and answers targeting PMP examination for PMP aspirants. Check out below video for first series of 25 questions with answers and explanation about answer.
How To Build A Credible Performance Measurement Baselineguest9da059
IPM 2009 Conference briefing. The Performance Measurement Baseline is the project controls vehicle that connects Cost, Schedule, and Technical Performance in a single database.
Here is our free CAPM exam sample question from the PM Exam Simulator.
*Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
Here is our free PMP exam sample question from the PM Exam Simulator.
*Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
Biological screening of herbal drugs: Introduction and Need for
Phyto-Pharmacological Screening, New Strategies for evaluating
Natural Products, In vitro evaluation techniques for Antioxidants, Antimicrobial and Anticancer drugs. In vivo evaluation techniques
for Anti-inflammatory, Antiulcer, Anticancer, Wound healing, Antidiabetic, Hepatoprotective, Cardio protective, Diuretics and
Antifertility, Toxicity studies as per OECD guidelines
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
Acetabularia Information For Class 9 .docxvaibhavrinwa19
Acetabularia acetabulum is a single-celled green alga that in its vegetative state is morphologically differentiated into a basal rhizoid and an axially elongated stalk, which bears whorls of branching hairs. The single diploid nucleus resides in the rhizoid.
Introduction to AI for Nonprofits with Tapp NetworkTechSoup
Dive into the world of AI! Experts Jon Hill and Tareq Monaur will guide you through AI's role in enhancing nonprofit websites and basic marketing strategies, making it easy to understand and apply.
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
A Strategic Approach: GenAI in EducationPeter Windle
Artificial Intelligence (AI) technologies such as Generative AI, Image Generators and Large Language Models have had a dramatic impact on teaching, learning and assessment over the past 18 months. The most immediate threat AI posed was to Academic Integrity with Higher Education Institutes (HEIs) focusing their efforts on combating the use of GenAI in assessment. Guidelines were developed for staff and students, policies put in place too. Innovative educators have forged paths in the use of Generative AI for teaching, learning and assessments leading to pockets of transformation springing up across HEIs, often with little or no top-down guidance, support or direction.
This Gasta posits a strategic approach to integrating AI into HEIs to prepare staff, students and the curriculum for an evolving world and workplace. We will highlight the advantages of working with these technologies beyond the realm of teaching, learning and assessment by considering prompt engineering skills, industry impact, curriculum changes, and the need for staff upskilling. In contrast, not engaging strategically with Generative AI poses risks, including falling behind peers, missed opportunities and failing to ensure our graduates remain employable. The rapid evolution of AI technologies necessitates a proactive and strategic approach if we are to remain relevant.
1. PMP® Sample
Questions
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the
development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every
attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam.
However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially
published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or
expressed by OSP International LLC.
2. This presentation will showcase free sample
PMP® questions that will help and guide
you in studying for your PMP® exam
Find more free sample questions when you visit
www.free-pm-exam-questions.com and
free.pm-exam-simulator.com
3. 1. You are considering using WBS templates to create your project's WBS.
Where would you most likely find these templates?
A. Enterprise Environmental Factors
B. Requirements Documentation
C. Project Management Plan
D. Organizational Process Assets
Hint: Get your mind out of the PMBOK Guide and think freely for this question.
Sample PMP® Exam Question
4. The correct answer is D
Explanation:This question isn't asking about "inputs"
to the CreateWBS process.The question is simply
asking:Where could you find templates to help you
build aWBS? Organizational Process Assets contain
WBS templates.
Answer and Explanation
5. 2. You are managing a water supply network deployment project. During project
planning you are considering two approaches to lay the pipe network. Approach A will
most likely cost $50,000 (+/-5%). Approach B will most likely cost $25,000 (+/-
40%). Which approach will you select if your project stakeholders' risk tolerances are
low and if you want to select the less risky approach?
A. Neither approach since they are not definitive estimates
B. Approach B since it ranges from $15,000 to $35,000
C. Approach A since it ranges from $47,500 to $52,500
D. A combination of approach A and B
Hint:Estimates are never definitive.
Sample PMP® Exam Question
6. The correct answer is C
Explanation: Please note that the question doesn't ask for
the approach that is more financially feasible. Instead, the
question asks you to identify the approach that has the
lower risk.The larger the range of an estimate, the larger
the risk. Since approach B is a wide range estimate, it is
more risky.Approach C has a narrow estimate, which
makes this approach less risky.
Answer and Explanation
7. 3. An element of a Work Breakdown Structure that can be viewed at the lowest level
of each branch is referred to as which of the following?
A. ControlAccount
B. Work Breakdown Structure Component"
C. Work Package
D. Task
Hint: A work package is at the lowest level of aWBS.
Sample PMP® Exam Question
8. The correct answer is C
Explanation:A control account is a management control
point where scope, budget, resources, actual cost and
schedule are integrated and compared to earned value
for performance measurement. Control accounts are
placed at selected management points (specific
components at selected levels) of theWork Breakdown
Structure.A work package is a deliverable or project
work component at the lowest level of each branch of
theWork Breakdown Structure.Tasks are the results of
further decomposition of work packages.
Answer and Explanation
9. 4. Sensitivity analysis has strong similarities to which of the following?
A. Probability Distributions
B. Risk Identification
C. Tornado Diagram
D. Statistical Sampling
Hint: Sensitivity analysis is a risk analysis technique,not a risk identification technique.
Sample PMP® Exam Question
10. The correct answer is C
Explanation: Sensitivity analysis is a risk analysis technique,
not a risk identification technique. It is not a sampling
technique or a distribution. In Sensitivity analysis one looks
at the effect of varying the inputs of a mathematical model on
the output of the model itself.TheTornado Diagram is an
example for sensitivity analysis.
Answer and Explanation
11. 5. You are managing a nationwide telecom network deployment project. You learned
that you are unable to start any civil works before obtaining a government agency's
permit, which could take months. The project deadlines are aggressive and you might
face penalties if you don't meet them. Obtaining the government agency's permit
prior to civil works on any site is an example of which of the following?
A. Mandatory Dependency
B. External Dependency
C. Project Constraint
D. Project Requirement
Hint:All of the choices are correct in a way but considering the relationship of the permit to the
civil work will yield only one correct choice.
Sample PMP® Exam Question
12. The correct answer is B
Explanation:The question asked you about the relationship
between civil works and the government agency permit to
perform these works.When we are talking about relationships
between activities we are talking about dependencies between
the tasks. Obtaining the permits will definitely be in your
project's scope of work and will also be a part of your contract.
Therefore, it is considered a mandatory dependency. Similarly,
as you have to fulfil this requirement it is both a project
constraint and a project requirement. Most importantly, as
obtaining the permit and the lead time to do so is beyond your
control, it is an external dependency, which is the best answer
to this question given the scenario.
Answer and Explanation