You have finished estimating costs for your project. What is your next activity with regard to
managing the costs?
A. Develop Cost Performance Baseline
B. Develop Work Performance Measurements
C. Develop Budget Forecasts
D. Plan Quality Management
HINT: Determine Budget is the process after the Estimate Costs process.
Question
The correct answer is A.
The immediate activity following estimation of costs is determining the budget. The output of the
Determine Budget process is the development of a Cost Performance Baseline.
Answer
All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.


Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.


We are a trusted and experienced education provider.

Free PMP Sample Q & A

  • 1.
  • 2.
    You have finishedestimating costs for your project. What is your next activity with regard to managing the costs? A. Develop Cost Performance Baseline B. Develop Work Performance Measurements C. Develop Budget Forecasts D. Plan Quality Management HINT: Determine Budget is the process after the Estimate Costs process. Question
  • 3.
    The correct answeris A. The immediate activity following estimation of costs is determining the budget. The output of the Determine Budget process is the development of a Cost Performance Baseline. Answer
  • 4.
    All our questionsare updated to the latest  A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.