SlideShare a Scribd company logo
PMP® Sample
Questions 4
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the
development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every
attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam.
However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially
published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or
expressed by OSP International LLC.
This presentation will showcase free sample
PMP® questions that will help and guide
you in studying for your PMP® exam
Find more free sample questions when you visit
www.free-pm-exam-questions.com and
free.pm-exam-simulator.com
1. You have just taken over from a project manager who was managing a construction project.
According to the previous project manager, the project team is in the performing stage and
smoothly carrying out the project activities. During your first week on the job you determine
that the project team is actually in serious conflict. Every team member approaches you with a
conflict and a suggestion to resolve that conflict. Almost everyone believes that the approved
Project Management Plan needs to be updated in order to successfully carry out the project.
What is the potential reason for this team behavior and why is it in conflict with the previous
project manager's statement?
A. The previous project manager lied about the team's performance
B. The approved Project Management Plan is faulty
C. You do not have expert power to motivate your project team
D. The replacement of the project manager has moved the project team back to the storming
stage
Hint: Any of the given choices can be true,however,look for sufficient evidence in the given scenario.
Sample PMP® Exam Question
The correct answer is D
Explanation: ChoicesA, B, and C can be real situations,
and if they are occur, they can cause conflicts. However,
as there isn't sufficient evidence given in this scenario,
we can't say for sure that any of these choices are the
potential reason for the team's behavior. In contrast,
whenever there is a significant change in the team
membership the team can move back from performing
to storming or even to the norming stage.As you
replaced the previous project manager, this might have
caused the team to degrade from the performing stage
to the storming stage.
Answer and Explanation
2. You are managing a software development project. One month ago your Software
Development Team Lead resigned and you promoted your star programmer to lead the
development team. This person was a fantastic software coder and you thought the
promotion would mean that he could share his expertise across the development team.
However, you are surprised to learn that the performance of your new team lead in his
new role is not meeting your expectations. Which empirical rule did you forget while
considering the promotion of this person?
A. Peter Principle
B. Murphy Principle
C. Pareto Principle
D. Cornelius Principle
Sample PMP® Exam Question
HINT: The promotion in this case is a classic example of the 'Peter Principle' or 'Halo Effect'.
The correct answer isA
Explanation:The Peter Principle states, "In a hierarchy
every employee tends to rise to his/her level of
incompetence". Most project team members are
motivated by an opportunity to grow, accomplish, and
apply their professional skills to meet new challenges.
Their achievements continuously promote them within
an organization to a certain level until they are unable to
perform.Your team lead might have risen to his
incompetency level.
Answer and Explanation
3. You are managing a construction project. Your civil supervisor is responsible for inspecting
daily operations and communicating his observations to your documentation officer, who then
produces a daily work status report and distributes it to the project stakeholders. Today your
documentation officer is on leave, and you ask your civil supervisor to prepare the status
report. Your civil supervisor does not like your documentation officer and does not want to
perform any of the documentation officer's tasks for him. However, you ask him do this as a
favor to you and in return he can submit one of his own reports that is due today by the end of
the week.Which conflict resolution strategy you have used?
A. Withdrawing
B. Compromising
C. Forcing
D. Confronting
*Hint:You are trying to satisfy your disgruntled employee by offering a compromise.
Sample PMP® Exam Question
The correct answer is B
Compromising means searching for solutions that
bring some degree of satisfaction to all parties. Since
you know that your civil supervisor does not want to
perform the documentation officer's task, you are
asking him to postpone the delivery of some of his
own work until the end of the week so that this task
can be performed. In this case you are both
compromising
Answer and Explanation
4. You have just been appointed as a project manager for a long-term project, which is in
its execution phase. You discover that the project team is not motivated and is not
performing to the standards required. After further investigation, you learn that your
company has been hiring team members on a short-term, contractual basis. As a result,
the project team members are not developing a long-term commitment towards the
project. You have decided to motivate the team members by offering them long-term
positions. Your strategy works and your team members become motivated. Your
motivational strategy is an example of which of the following theories?
A. Theory X
B. TheoryY
C. Theory Z
D. TheoryA
Hint: This theory was developed by Dr.William Ouchi.
Sample PMP® Exam Question
The correct answer is C
Theory Z was developed by Dr.William Ouchi and
concerns increasing employee loyalty to their
organizations. It was developed in Japan in the 1980's
when jobs were often offered for life.This theory has the
following benefits; 1) It results in increased productivity
2) It emphasizes the well-being of the employees both at
work and outside of work 3) It encourages steady
employment and 4) It leads to high employee satisfaction
and morale. On the other hand,Theory X andTheoryY
describe two very different management attitudes toward
workforce motivation in terms of workforce supervision,
which has nothing to do with offering long-term
positions.
Answer and Explanation
5. You have just been hired as the operations manager for a telecommunications company. You
are tasked with improving the company's services and operations and a team of 20 engineers
report to you. During your first week at this company, you found that the engineers spend at
least 80% of their time responding to unexpected requests for information from different
stakeholders. Because of this, your engineers cannot focus on the operations, which is resulting
in frequent network outages. As the project manager, what should you do first to resolve this
problem?
A. Tell the engineers to stop responding to unexpected requests since they are not
covered in the Communications Management Plan
B. Push the engineers to respond to all the requests faster so that they are able to perform
their regular duties
C. Perform all project communications yourself and let the engineers focus on the
operations
D. Analyze the stakeholder requirements and review the Communications Management Plan
Hint: You need to further investigate the problem
Sample PMP® Exam Question
The correct answer is D
Explanation:You are clearly having issues in your
Control Communications process. Control
Communications is the process used to make
relevant information available to project
stakeholders, as planned to ensure the information
needs of the stakeholders are met.The focus here is
mainly in the Controlling process group. However,
since your team is spending 80% of their time
handling unexpected information requests, clearly
something is terribly wrong.You should further
investigate the issue by analyzing stakeholder
requirements and reviewing the Communications
Management Plan.
Answer and Explanation

More Related Content

What's hot

Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
Naseer Muhammud
 
09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
Jamil Faraj , PMP
 
Project management-plan
Project management-planProject management-plan
Project management-plan
Tran Tien
 

What's hot (20)

Exam1
Exam1Exam1
Exam1
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 
09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
 
Mobile Marketing Project Charter
Mobile Marketing Project CharterMobile Marketing Project Charter
Mobile Marketing Project Charter
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
Software Project Management Presentation Final
Software Project Management Presentation FinalSoftware Project Management Presentation Final
Software Project Management Presentation Final
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
Social Media Project Charter Template
Social Media Project Charter TemplateSocial Media Project Charter Template
Social Media Project Charter Template
 
1
11
1
 
Project Management and Project Lifecycle cheatsheet
Project Management and Project Lifecycle cheatsheetProject Management and Project Lifecycle cheatsheet
Project Management and Project Lifecycle cheatsheet
 
Project management-plan
Project management-planProject management-plan
Project management-plan
 
The Project Charter in a Nutshell
The Project Charter in a NutshellThe Project Charter in a Nutshell
The Project Charter in a Nutshell
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
Preparing for pmi ba exam
Preparing for pmi ba examPreparing for pmi ba exam
Preparing for pmi ba exam
 
Activity Duration Estimate - Ready template
Activity Duration Estimate - Ready templateActivity Duration Estimate - Ready template
Activity Duration Estimate - Ready template
 

Viewers also liked

Viewers also liked (19)

PMP® Sample Questions
PMP® Sample QuestionsPMP® Sample Questions
PMP® Sample Questions
 
175 PMP Sample Questions
175 PMP Sample Questions175 PMP Sample Questions
175 PMP Sample Questions
 
PMP Five Sample Questions
PMP Five Sample QuestionsPMP Five Sample Questions
PMP Five Sample Questions
 
PMP® Sample Questions 6
PMP® Sample Questions 6PMP® Sample Questions 6
PMP® Sample Questions 6
 
PMP® Sample Questions and Answers
PMP® Sample Questions and AnswersPMP® Sample Questions and Answers
PMP® Sample Questions and Answers
 
PMP Exam Sample Questions 9
PMP Exam Sample Questions 9PMP Exam Sample Questions 9
PMP Exam Sample Questions 9
 
PMP Five Sample Questions - 3
PMP Five Sample Questions - 3PMP Five Sample Questions - 3
PMP Five Sample Questions - 3
 
PMP® Sample Questions 3
PMP® Sample Questions 3PMP® Sample Questions 3
PMP® Sample Questions 3
 
PMP® Sample Questions Set #2
PMP® Sample Questions Set #2PMP® Sample Questions Set #2
PMP® Sample Questions Set #2
 
PMP Sample Questions Set 5
PMP Sample Questions Set 5PMP Sample Questions Set 5
PMP Sample Questions Set 5
 
Pmp sample questions
Pmp sample questionsPmp sample questions
Pmp sample questions
 
PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6
 
PMP Exam Sample Questions Set 1
PMP Exam Sample Questions Set 1PMP Exam Sample Questions Set 1
PMP Exam Sample Questions Set 1
 
PMP Exam Sample Questions Set 8
PMP Exam Sample Questions Set 8PMP Exam Sample Questions Set 8
PMP Exam Sample Questions Set 8
 
PMP® Sample Questions 5
PMP® Sample Questions 5PMP® Sample Questions 5
PMP® Sample Questions 5
 
PMP Exam Sample Questions Set 7
PMP Exam Sample Questions Set 7PMP Exam Sample Questions Set 7
PMP Exam Sample Questions Set 7
 
PMP Sample Questions Set 3
PMP Sample Questions Set 3PMP Sample Questions Set 3
PMP Sample Questions Set 3
 
PMP Sample Questions Set 2
PMP Sample Questions Set 2PMP Sample Questions Set 2
PMP Sample Questions Set 2
 
Sample PMP Exam Questions
Sample PMP Exam QuestionsSample PMP Exam Questions
Sample PMP Exam Questions
 

Similar to PMP Exam Sample Questions 4

Similar to PMP Exam Sample Questions 4 (20)

PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Com 140 check point different kinds of messages
Com 140 check point different kinds of messagesCom 140 check point different kinds of messages
Com 140 check point different kinds of messages
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
PMP Sample Questions Set3
PMP Sample Questions Set3PMP Sample Questions Set3
PMP Sample Questions Set3
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Improving project handover webinar, Question responses, 12 April 2018
Improving project handover webinar, Question responses, 12 April 2018Improving project handover webinar, Question responses, 12 April 2018
Improving project handover webinar, Question responses, 12 April 2018
 
PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4
 
Performance Management - Herman Augnis
Performance Management - Herman Augnis Performance Management - Herman Augnis
Performance Management - Herman Augnis
 
Pmp sample questions set2
Pmp sample questions set2Pmp sample questions set2
Pmp sample questions set2
 
Performance phrases examples
Performance phrases examplesPerformance phrases examples
Performance phrases examples
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Session 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM CertificationsSession 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM Certifications
 

More from OSP International LLC

More from OSP International LLC (20)

Free CAPM Exam Sample Question for the Week
Free CAPM Exam Sample Question for the WeekFree CAPM Exam Sample Question for the Week
Free CAPM Exam Sample Question for the Week
 
Free PMP Exam Sample Question for the Week
Free PMP Exam Sample Question for the WeekFree PMP Exam Sample Question for the Week
Free PMP Exam Sample Question for the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 

Recently uploaded

chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 

Recently uploaded (20)

Cracking the Change Management Code Main New.pptx
Cracking the Change Management Code Main New.pptxCracking the Change Management Code Main New.pptx
Cracking the Change Management Code Main New.pptx
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
State of D2C in India: A Logistics Update
State of D2C in India: A Logistics UpdateState of D2C in India: A Logistics Update
State of D2C in India: A Logistics Update
 
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Using Generative AI for Content Marketing
Using Generative AI for Content MarketingUsing Generative AI for Content Marketing
Using Generative AI for Content Marketing
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
Hyundai capital 2024 1quarter Earnings release
Hyundai capital 2024 1quarter Earnings releaseHyundai capital 2024 1quarter Earnings release
Hyundai capital 2024 1quarter Earnings release
 
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | ShajaraLuxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
 
Evolution and Growth of Supply chain.pdf
Evolution and Growth of Supply chain.pdfEvolution and Growth of Supply chain.pdf
Evolution and Growth of Supply chain.pdf
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
Event Report - IBM Think 2024 - It is all about AI and hybrid
Event Report - IBM Think 2024 - It is all about AI and hybridEvent Report - IBM Think 2024 - It is all about AI and hybrid
Event Report - IBM Think 2024 - It is all about AI and hybrid
 
Transforming Max Life Insurance with PMaps Job-Fit Assessments- Case Study
Transforming Max Life Insurance with PMaps Job-Fit Assessments- Case StudyTransforming Max Life Insurance with PMaps Job-Fit Assessments- Case Study
Transforming Max Life Insurance with PMaps Job-Fit Assessments- Case Study
 
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
 
Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024
 
sales plan presentation by mckinsey alum
sales plan presentation by mckinsey alumsales plan presentation by mckinsey alum
sales plan presentation by mckinsey alum
 

PMP Exam Sample Questions 4

  • 1. PMP® Sample Questions 4 PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
  • 2. This presentation will showcase free sample PMP® questions that will help and guide you in studying for your PMP® exam Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  • 3. 1. You have just taken over from a project manager who was managing a construction project. According to the previous project manager, the project team is in the performing stage and smoothly carrying out the project activities. During your first week on the job you determine that the project team is actually in serious conflict. Every team member approaches you with a conflict and a suggestion to resolve that conflict. Almost everyone believes that the approved Project Management Plan needs to be updated in order to successfully carry out the project. What is the potential reason for this team behavior and why is it in conflict with the previous project manager's statement? A. The previous project manager lied about the team's performance B. The approved Project Management Plan is faulty C. You do not have expert power to motivate your project team D. The replacement of the project manager has moved the project team back to the storming stage Hint: Any of the given choices can be true,however,look for sufficient evidence in the given scenario. Sample PMP® Exam Question
  • 4. The correct answer is D Explanation: ChoicesA, B, and C can be real situations, and if they are occur, they can cause conflicts. However, as there isn't sufficient evidence given in this scenario, we can't say for sure that any of these choices are the potential reason for the team's behavior. In contrast, whenever there is a significant change in the team membership the team can move back from performing to storming or even to the norming stage.As you replaced the previous project manager, this might have caused the team to degrade from the performing stage to the storming stage. Answer and Explanation
  • 5. 2. You are managing a software development project. One month ago your Software Development Team Lead resigned and you promoted your star programmer to lead the development team. This person was a fantastic software coder and you thought the promotion would mean that he could share his expertise across the development team. However, you are surprised to learn that the performance of your new team lead in his new role is not meeting your expectations. Which empirical rule did you forget while considering the promotion of this person? A. Peter Principle B. Murphy Principle C. Pareto Principle D. Cornelius Principle Sample PMP® Exam Question HINT: The promotion in this case is a classic example of the 'Peter Principle' or 'Halo Effect'.
  • 6. The correct answer isA Explanation:The Peter Principle states, "In a hierarchy every employee tends to rise to his/her level of incompetence". Most project team members are motivated by an opportunity to grow, accomplish, and apply their professional skills to meet new challenges. Their achievements continuously promote them within an organization to a certain level until they are unable to perform.Your team lead might have risen to his incompetency level. Answer and Explanation
  • 7. 3. You are managing a construction project. Your civil supervisor is responsible for inspecting daily operations and communicating his observations to your documentation officer, who then produces a daily work status report and distributes it to the project stakeholders. Today your documentation officer is on leave, and you ask your civil supervisor to prepare the status report. Your civil supervisor does not like your documentation officer and does not want to perform any of the documentation officer's tasks for him. However, you ask him do this as a favor to you and in return he can submit one of his own reports that is due today by the end of the week.Which conflict resolution strategy you have used? A. Withdrawing B. Compromising C. Forcing D. Confronting *Hint:You are trying to satisfy your disgruntled employee by offering a compromise. Sample PMP® Exam Question
  • 8. The correct answer is B Compromising means searching for solutions that bring some degree of satisfaction to all parties. Since you know that your civil supervisor does not want to perform the documentation officer's task, you are asking him to postpone the delivery of some of his own work until the end of the week so that this task can be performed. In this case you are both compromising Answer and Explanation
  • 9. 4. You have just been appointed as a project manager for a long-term project, which is in its execution phase. You discover that the project team is not motivated and is not performing to the standards required. After further investigation, you learn that your company has been hiring team members on a short-term, contractual basis. As a result, the project team members are not developing a long-term commitment towards the project. You have decided to motivate the team members by offering them long-term positions. Your strategy works and your team members become motivated. Your motivational strategy is an example of which of the following theories? A. Theory X B. TheoryY C. Theory Z D. TheoryA Hint: This theory was developed by Dr.William Ouchi. Sample PMP® Exam Question
  • 10. The correct answer is C Theory Z was developed by Dr.William Ouchi and concerns increasing employee loyalty to their organizations. It was developed in Japan in the 1980's when jobs were often offered for life.This theory has the following benefits; 1) It results in increased productivity 2) It emphasizes the well-being of the employees both at work and outside of work 3) It encourages steady employment and 4) It leads to high employee satisfaction and morale. On the other hand,Theory X andTheoryY describe two very different management attitudes toward workforce motivation in terms of workforce supervision, which has nothing to do with offering long-term positions. Answer and Explanation
  • 11. 5. You have just been hired as the operations manager for a telecommunications company. You are tasked with improving the company's services and operations and a team of 20 engineers report to you. During your first week at this company, you found that the engineers spend at least 80% of their time responding to unexpected requests for information from different stakeholders. Because of this, your engineers cannot focus on the operations, which is resulting in frequent network outages. As the project manager, what should you do first to resolve this problem? A. Tell the engineers to stop responding to unexpected requests since they are not covered in the Communications Management Plan B. Push the engineers to respond to all the requests faster so that they are able to perform their regular duties C. Perform all project communications yourself and let the engineers focus on the operations D. Analyze the stakeholder requirements and review the Communications Management Plan Hint: You need to further investigate the problem Sample PMP® Exam Question
  • 12. The correct answer is D Explanation:You are clearly having issues in your Control Communications process. Control Communications is the process used to make relevant information available to project stakeholders, as planned to ensure the information needs of the stakeholders are met.The focus here is mainly in the Controlling process group. However, since your team is spending 80% of their time handling unexpected information requests, clearly something is terribly wrong.You should further investigate the issue by analyzing stakeholder requirements and reviewing the Communications Management Plan. Answer and Explanation