2. You are leading a project to design a high-efficiency solar cell. The project needs copper, silver,
and silicon among other materials. You have ordered custom-built manufacturing equipment,
secured permission to install a solar array on the roof for testing, and reserved a conference room
for daily stand-up meetings.
What is the result of your efforts?
A. Resource histogram
B. Resource management plan
C. Resource assignment matrix
D. Physical resource assignments
HINT: What output of the Acquire Resources process describes the physical resources reserved for
the project?
Question
3. The correct answer is D.
It can be inferred from the question that the process of acquiring resources is being performed. One of the
outputs from the Acquire Resources process is physical resource assignments.
Documentation of the physical resource assignments records the material, equipment, supplies, locations,
and other physical resources that will be used during the project. Based on the description provided by
the question, the physical resource assignments is what has been accomplished.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.