          1      Introduction........................................................................................................ 4
          2      Configuration of the S7-1200............................................................................ 6
                 2.1           Configuring Hardware .......................................................................... 6
                 2.2           Creating a User Program ..................................................................... 8
          3      PC Station Configuration ................................................................................ 13
          4      Configuring the S7 Connection...................................................................... 18
                 4.1           Add S7 Connection ............................................................................ 18
                 4.2           Display and Change Properties of the S7 Connection in the
                               Inspector Window............................................................................... 19
          5      Compiling and Downloading the Configuration and User Program of
                 the S7-1200....................................................................................................... 23
          6      Compiling and Downloading the PC Station Configuration........................ 28
          7      OPC Scout V10................................................................................................. 34




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                                                              3


                                            http://eyeteck.vn
1 Introduction



1            Introduction
             This entry shows you how to configure an S7-1200, a PC station and an S7
             connection in STEP 7 (TIA Portal) V11 so that you can exchange data between the
             stations over Industrial Ethernet.

Create project
             In Windows, select the command "Start  Programs  Siemens Automation 
             TIA Portal V11" to start STEP 7 (TIA Portal) V11.
             In the Portal view, select the "Create new project" action.
             Enter the project name in the appropriate field.
Figure 1-1




             Click the "Create" button to create a new project.
Figure 1-2




Switch to Project View
             Use the "Project View" link to switch to the Project View.




                                                        S7 communication between PC station and S7-1200
4                                                                              V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
1 Introduction


Figure 1-3




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                5


                                       http://eyeteck.vn
2 Configuration of the S7-1200



2            Configuration of the S7-1200
             Configure your S7-1200 in STEP 7 (TIA Portal) V11. Then create the user program
             and define which data is to be monitored over the S7 connection of the OPC
             server.

2.1          Configuring Hardware
Add an S7-1200 Station
             In the project tree, double-click the "Add new device" item. The "Add new device"
             dialog opens.
Figure 2-1




             Click the "PLC" button in the working area. Go to "PLC  SIMATIC S7-1200 
             CPU" and select the required controller. Click the "OK" button to add the selected
             S7-1200 CPU to your project.




                                                      S7 communication between PC station and S7-1200
6                                                                            V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
2 Configuration of the S7-1200


Figure 2-2




Add IP address and assign subnet
              In the project tree, double-click the "Devices & networks" item. This opens the
              "Network View" working area of the hardware and network editor.
              Click the PROFINET interface of the S7-1200 CPU.
              In the inspector window you switch to the "Properties" tab. Click the "Ethernet
              addresses" item in the area navigation.
              In this example you enter the IP address 172.16.43.20 and the subnet mask
              255.255.0.0 for the PROFINET interface of the S7-1200 CPU.
              Then assign a subnet to the PROFINET interface. Click the "Add new subnet"
              button to insert a new subnet.
              The connection between the subnet, PN/IE_1, for example, and the S7-1200 is
              now displayed in the "Net View" working area of the hardware and network editor.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                          7


                                       http://eyeteck.vn
2 Configuration of the S7-1200


Figure 2-3




2.2          Creating a User Program
Add data block
             In the project tree, navigate to the device folder of the S7-1200 CPU,
             "PLC_1 [CPU 1212C …]", for example. The device folder contains structured
             objects and actions that belong to the device.
             In the device folder you navigate to the "Program blocks" subfolder and double-
             click the "Add new block" action. The "Add new block" dialog opens.




                                                      S7 communication between PC station and S7-1200
8                                                                            V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
2 Configuration of the S7-1200


Figure 2-4




              Click the "DB Data block" button. Enter the name of the data block and enable the
              "Manual" option to assign the number of the data block manually. If you enable the
              "Automatic" option, the number of the data block is assigned automatically.
              Select the "Standard - compatible with S7-300/400" option for block access.
              Data blocks with standard access have a fixed structure. The data elements in the
              declaration include both symbolic names and a fixed address in the block. The
              address is displayed in the "Offset" column. You can address the tags in this block
              both symbolically and absolutely.
              Apply the settings with "OK".
              The data block DB1 "Data block 1" is used in this example.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                             9


                                       http://eyeteck.vn
2 Configuration of the S7-1200


Figure 2-5




Define static tag in the data block
             Define the static tag "static_01" of the "Bool" data type in the DB1 "Data block 1".
             Click the "Compile" button.




                                                        S7 communication between PC station and S7-1200
10                                                                             V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
2 Configuration of the S7-1200


Figure 2-6




Create Main [OB1]
              In the "Program blocks" folder, you double-click the "Main [OB1]" block to open the
              corresponding dialog window.
Figure 2-7




              Create the program as shown in Fehler! Verweisquelle konnte nicht gefunden
              werden.. The bit links are in the "Instructions" task card under "Basic instructions"
               Bit links".
              Use drag-and-drop to add the Normally open contact, the flip-flop and the
              Assignment to Network 1 of the "Main [OB1]" block.
              Assign the tags below to the flip-flop, to the normally open contact at inputs S and
              R of the flip-flop and to the assignment at output Q of the flip-flop.
Table 2-1
                         Tag                                           Description
 M1.0                                               SR flip-flop input S: NO contact
 M1.1                                               SR flip-flop input R: NO contact
 DB1.DBX0.0                                         SR tag
 M2.0                                               SR flip-flop output Q: Assignment




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                           11


                                       http://eyeteck.vn
2 Configuration of the S7-1200


             Click the "Compile" button.
Figure 2-8




     Notes    The "%" character before the absolute address is added automatically by STEP
              7 (TIA Portal) V11.




                                                    S7 communication between PC station and S7-1200
12                                                                         V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
3 PC Station Configuration



3             PC Station Configuration
              Before you start configuring the PC station in STEP 7 (TIA Portal) V11, determine
              or change the IP address of the network card that you are using in your PC station.
              You enter the IP address and subnet mask of the network card when you configure
              the PC station in STEP 7 (TIA Portal) V11.

Determine and change the IP address and subnet mask of the network card
              In Windows, under Network Connections, you open the Properties dialog of the
              Local Area Network (LAN).
              In this example the network card receives the IP address 172-16.40.11 and subnet
              mask 255.255.0.0.


    Notes       The IP address configured for the PC station in STEP 7 (TIA Portal) V11 must
                match the IP address set in Windows. If you are not using a router, the IP
                addresses of the PC station and the S7-1200 CPU must be in the same subnet.



Figure 3-1




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                        13


                                       http://eyeteck.vn
3 PC Station Configuration



Add a PC Station
             In STEP 7 (TIA Portal) V11 you open the project that contains the configuration for
             the S7-1200 station.
             In the project tree, double-click the "Add new device" item. The "Add new device"
             dialog opens.
Figure 3-2




             Click the "PC systems" button in the working area. Go to "PC systems  PC
             general" and select the "PC station" item.
             Click the "OK" button to add a PC station named "PC-System_1" to your project.




                                                      S7 communication between PC station and S7-1200
14                                                                           V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
3 PC Station Configuration


Figure 3-3




This opens the "Device View" working area of the hardware and network editor.
              In the project tree, navigate to the device folder of the PC station,
              "PC-System_1 [SIMATIC PC station]", for example. The device folder contains
              structured objects and actions that belong to the device.
              In the device folder double-click the "Device configuration" object to open the
              "Device View" working area of the hardware and network editor.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                         15


                                       http://eyeteck.vn
3 PC Station Configuration


Figure 3-4




Configure user application and communication module of the PC station
             Go to the "Device View" working area of the hardware and network editor and
             configure and parameterize the modules of the PC station.
             The "Hardware catalog" task card contains the user applications and
             communication modules that you can configure in the PC station. Using drag-and-
             drop add the "OPC server" user application to Slot 1 and the "IE general"
             communication module to Slot 2 of the PC station.
Figure 3-5




                                                     S7 communication between PC station and S7-1200
16                                                                          V1.1, Entry ID: 39960679


                                  http://eyeteck.vn
3 PC Station Configuration



Add IP address and assign subnet
              In the project tree, double-click the "Devices & networks" item. This opens the
              "Network View" working area of the hardware and device editor.
              Click the PROFINET interface of the network card in the PC station.
              In the inspector window you switch to the "Properties" tab. In the area navigation
              select the "Ethernet addresses" item.
              In this example you enter the IP address 172.16.40.11 and subnet mask
              255.255.0.0 for the network card.
              Select the subnet that you have already assigned to the S7-1200 CPU and assign
              it also to the network card of the PC station.
              The connection between the subnet, PN/IE_1, for example, and the S7-1200 and
              the PC station is now displayed in the "Net View" working area of the hardware and
              device editor.


   Notes        The IP address configured for the PC station in STEP 7 (TIA Portal) V11 must
                match the IP address set in Windows. If you are not using a router, the IP
                addresses of the PC station and the S7-1200 CPU must be in the same subnet.




Figure 3-6




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                            17


                                       http://eyeteck.vn
4 Configuring the S7 Connection



4            Configuring the S7 Connection
4.1          Add S7 Connection
             In the project tree, double-click the "Devices & networks" item. This opens the
             "Network View" working area of the hardware and network editor.
             In the toolbar of the Net View, click the "Connections" icon to switch to the mode
             for setting the connections.
             In the drop-down list box you select "S7 connection" as connection type.
Figure 4-1




             In the graphical area of the Net View, click the OPC server in the PC station and
             connect it to the S7-1200 CPU.
             In the Net View, the S7 connection is displayed in the graphical area and in the
             "Connections" table in the table area.




                                                       S7 communication between PC station and S7-1200
18                                                                            V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
4 Configuring the S7 Connection


Figure 4-2




4.2           Display and Change Properties of the S7 Connection in
              the Inspector Window
              Proceed as described below to have the properties of the S7 connection displayed
              in the inspector window.
              •   In the table area switch to the "Connections" table and select the configured S7
                  connection.
              •   In the inspector window you switch to the "Properties" tab.

General properties
              In the area navigation select the "General" item to display the connection path.
              The S7 connection is between the OPC server and the S7-1200 CPU.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                          19


                                       http://eyeteck.vn
4 Configuring the S7 Connection


Figure 4-3




             In the area navigation select the "Special connection properties" item.
             Here you see a display of the special connection properties of the local end point,
             "Active connection establishment", for example.
             In this example, the OPC server establishes the S7 connection. The
             communication partner, S7-1200 CPU, is participates passively in establishing the
             connection.




                                                       S7 communication between PC station and S7-1200
20                                                                            V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
4 Configuring the S7 Connection


Figure 4-4




              In the area navigation select the "Address details" item.
              Here you have a display of the local end point, the partner end point and the TSAP
              of both end points.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                       21


                                       http://eyeteck.vn
4 Configuring the S7 Connection


Figure 4-5




                                             S7 communication between PC station and S7-1200
22                                                                  V1.1, Entry ID: 39960679


                                  http://eyeteck.vn
5 Compiling and Downloading the Configuration and User Program of the S7-1200



5             Compiling and Downloading the
              Configuration and User Program of the S7-
              1200
Compile
              To compile the configuration and user program of the S7-1200 you right-click the
              device folder of the S7-1200 CPU in the project navigation. There you select
              "Compile  All".




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                          23


                                       http://eyeteck.vn
5 Compiling and Downloading the Configuration and User Program of the S7-1200


Figure 5-1




Download
             To download the configuration and user program of the S7-1200 you right-click the
             device folder of the S7-1200 CPU in the project navigation. There you select
             "Download to device  All".




                                                     S7 communication between PC station and S7-1200
24                                                                          V1.1, Entry ID: 39960679


                                  http://eyeteck.vn
5 Compiling and Downloading the Configuration and User Program of the S7-1200


Figure 5-2




              The "Extended download to device" dialog opens. Check the settings below:
              •   PG/PC interface type
              •   PG/PC interface
              •   Connection with the subnet
              Under "Accessible devices in subnet" you select the relevant device and click the
              "Load" button.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                           25


                                       http://eyeteck.vn
5 Compiling and Downloading the Configuration and User Program of the S7-1200


Figure 5-3




     Notes    If the project has already been loaded once into the S7-1200 CPU, the "Load
              preview" dialog is opened immediately instead of the "Extended download to
              device" dialog.




             The "Load preview" dialog opens. Click the "Load" button.




                                                     S7 communication between PC station and S7-1200
26                                                                          V1.1, Entry ID: 39960679


                                  http://eyeteck.vn
5 Compiling and Downloading the Configuration and User Program of the S7-1200


Figure 5-4




              The dialog box containing the results of the download procedure opens. If the S7-
              1200 is in "STOP" mode for the download procedure, check the "Start all" check
              box. Click the "Finish" button. The status LED of the S7-1200 CPU indicates the
              "RUN" mode after downloading.
Figure 5-5




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                       27


                                       http://eyeteck.vn
6 Compiling and Downloading the PC Station Configuration



6            Compiling and Downloading the PC
             Station Configuration
Open the Station Configuration Editor
             Open the Component Configuration Editor with the icon in the Windows taskbar.
Figure 6-1




             Insert the modules, namely the OPC server and the network card, in the
             Component Configuration Editor in accordance with the hardware configuration.
             In this example you add the OPC server to Slot 1 and the network card to Slot 2.
             Then change the station name in the Component Configuration Editor. The name
             of the PC station must be identical in STEP 7 (TIA Portal) V11 and in the
             Component Configuration Editor.
             The station name "PC-System_1" is used in this example.




                                                      S7 communication between PC station and S7-1200
28                                                                           V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
6 Compiling and Downloading the PC Station Configuration


Figure 6-2




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                        29


                                       http://eyeteck.vn
6 Compiling and Downloading the PC Station Configuration



Compile
             To compile the configuration of the PC station you right-click the device folder of
             the PC station in the project navigation. There you select "Compile  All".
Figure 6-3




Download
             To download the configuration of the PC station you right-click the device folder of
             the PC station in the project navigation. There you select "Download to device 
             All".




                                                       S7 communication between PC station and S7-1200
30                                                                            V1.1, Entry ID: 39960679


                                   http://eyeteck.vn
6 Compiling and Downloading the PC Station Configuration


Figure 6-4




              The "Extended download to device" dialog opens. Check the settings below:
              •   PG/PC interface type
              •   PG/PC interface
              •   Connection with the subnet
              Under "Accessible devices in subnet" you select the relevant device and click the
              "Load" button.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                           31


                                       http://eyeteck.vn
6 Compiling and Downloading the PC Station Configuration


Figure 6-5




     Notes    If the project has already been loaded once into the S7-1200 CPU, the "Load
              preview" dialog is opened immediately instead of the "Extended download to
              device" dialog.




             The "Load preview" dialog opens. Click the "Load" button.




                                                     S7 communication between PC station and S7-1200
32                                                                          V1.1, Entry ID: 39960679


                                  http://eyeteck.vn
6 Compiling and Downloading the PC Station Configuration


Figure 6-6




              Commissioning of the PC station is completed after downloading of the
              configuration.




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                        33


                                       http://eyeteck.vn
7 OPC Scout V10



7            OPC Scout V10
             In this example the OPC Scout V10 is used as OPC client. Using the OPC client
             you can access the data of the S7-1200 CPU over the OPC server.
             Start the OPC Scout V10 by means of the menu "Start  SIMATIC  SIMATIC
             NET  OPC Scout V10".

Establish connection to the OPC server
             In the Server Explorer you double-click the "OPC.SimaticNET" item to establish a
             connection to the OPC server.
Figure 7-1




                                                     S7 communication between PC station and S7-1200
34                                                                          V1.1, Entry ID: 39960679


                                  http://eyeteck.vn
7 OPC Scout V10


              The configured S7 connection named "S7_Verbindung_1" is displayed in the
              Server Explorer under OPC.SimaticNET in the "S7" folder.
Figure 7-2




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                  35


                                       http://eyeteck.vn
7 OPC Scout V10



Create OPC items
             Add the items below to the DA view.
Table 7-1


 S7:[S7_Verbindung_1]MX1.0                         By means of the OPC item you monitor and control
                                                   the marker bit M1.0 in the S7-1200 CPU.
 S7:[S7_Verbindung_1]MX1.1                         By means of the OPC item you monitor and control
                                                   the marker bit M1.1 in the S7-1200 CPU.
 S7:[S7_Verbindung_1]MX2.0                         By means of the OPC item you monitor the marker
                                                   bit M2.0 in the S7-1200 CPU.
 S7:[S7_Verbindung_1]DB1, X0.0                     By means of the OPC item you monitor Bit 0.0 of
                                                   the DB1 data block in the S7-1200 CPU.


Figure 7-3




Monitor OPC items
             Click the "Monitoring ON" button to monitor the values of the OPC items. The
             values of the OPC items are displayed in the "Value" column.
Figure 7-4




                                                       S7 communication between PC station and S7-1200
36                                                                            V1.1, Entry ID: 39960679


                                  http://eyeteck.vn
7 OPC Scout V10



Write values
              In the "New value" column you enter the value that you want to write to the S7-
              1200.
              Enter the values below in the "New value" column (see Table 7-2). Click the "Write"
              button. The marker bit M2.0 and Bit 0 in DB1 are given the value "True".
              The results of the write procedure are displayed in the "Value" column.
Table 7-2
                      OPC item                                       New value
 S7:[S7_Verbindung_1]MX1.0                         True
 S7:[S7_Verbindung_1]MX1.1                         False


Figure 7-5




              Enter the values below in the "New value" column (see Table 7-3). Click the "Write"
              button. The marker bit M2.0 and Bit 0 in DB1 are reset to the value "False".
              The results of the write procedure are displayed in the "Value" column.
Table 7-3
                      OPC item                                       New value
 S7:[S7_Verbindung_1]MX1.0                         False
 S7:[S7_Verbindung_1]MX1.1                         True


Figure 7-6




S7 communication between PC station and S7-1200
V1.1, Item ID: 39960679                                                                         37


                                       http://eyeteck.vn

More Related Content

What's hot

06 binary operations
06 binary operations06 binary operations
06 binary operationsEman Sulaeman
 
Simatic manager siemens S7 guide
Simatic manager  siemens S7 guideSimatic manager  siemens S7 guide
Simatic manager siemens S7 guideRoopesh Matale
 
Ladder logic on Soft-Master Honeywell PLC ML50
Ladder logic on Soft-Master Honeywell PLC ML50Ladder logic on Soft-Master Honeywell PLC ML50
Ladder logic on Soft-Master Honeywell PLC ML50Shivam Singh
 
02 pcs 7 documentation and support v1.00 en
02 pcs 7 documentation and support v1.00 en02 pcs 7 documentation and support v1.00 en
02 pcs 7 documentation and support v1.00 enconfidencial
 
18 syntax rules v1.0
18 syntax rules v1.018 syntax rules v1.0
18 syntax rules v1.0confidencial
 
_PLC and HMI Development with Siemens TIA Portal.pdf
_PLC and HMI Development with Siemens TIA Portal.pdf_PLC and HMI Development with Siemens TIA Portal.pdf
_PLC and HMI Development with Siemens TIA Portal.pdfRafaelRiesgo2
 
Allenbradley Control Logix PLC Network Architecture
Allenbradley Control Logix PLC Network  ArchitectureAllenbradley Control Logix PLC Network  Architecture
Allenbradley Control Logix PLC Network ArchitectureDEEPAK GORAI
 
14 mass data engineering v1.00_en
14 mass data engineering v1.00_en14 mass data engineering v1.00_en
14 mass data engineering v1.00_enconfidencial
 
Simatic s7 200-introduction
Simatic s7 200-introductionSimatic s7 200-introduction
Simatic s7 200-introductionPhan van Tan
 
An overview of siemens plc address mapping
An overview of siemens plc address mappingAn overview of siemens plc address mapping
An overview of siemens plc address mappingJustEngineering
 
Ch4 v70 system_configuration_en
Ch4 v70 system_configuration_enCh4 v70 system_configuration_en
Ch4 v70 system_configuration_enconfidencial
 
Honeywell PLC ML-50 (MLM-DR16S)
Honeywell PLC ML-50 (MLM-DR16S)Honeywell PLC ML-50 (MLM-DR16S)
Honeywell PLC ML-50 (MLM-DR16S)Shivam Singh
 

What's hot (20)

06 binary operations
06 binary operations06 binary operations
06 binary operations
 
Ch5 v70 cfc_en
Ch5 v70 cfc_enCh5 v70 cfc_en
Ch5 v70 cfc_en
 
Simatic manager siemens S7 guide
Simatic manager  siemens S7 guideSimatic manager  siemens S7 guide
Simatic manager siemens S7 guide
 
Ladder logic on Soft-Master Honeywell PLC ML50
Ladder logic on Soft-Master Honeywell PLC ML50Ladder logic on Soft-Master Honeywell PLC ML50
Ladder logic on Soft-Master Honeywell PLC ML50
 
02 pcs 7 documentation and support v1.00 en
02 pcs 7 documentation and support v1.00 en02 pcs 7 documentation and support v1.00 en
02 pcs 7 documentation and support v1.00 en
 
18 syntax rules v1.0
18 syntax rules v1.018 syntax rules v1.0
18 syntax rules v1.0
 
_PLC and HMI Development with Siemens TIA Portal.pdf
_PLC and HMI Development with Siemens TIA Portal.pdf_PLC and HMI Development with Siemens TIA Portal.pdf
_PLC and HMI Development with Siemens TIA Portal.pdf
 
Allenbradley Control Logix PLC Network Architecture
Allenbradley Control Logix PLC Network  ArchitectureAllenbradley Control Logix PLC Network  Architecture
Allenbradley Control Logix PLC Network Architecture
 
14 mass data engineering v1.00_en
14 mass data engineering v1.00_en14 mass data engineering v1.00_en
14 mass data engineering v1.00_en
 
Simatic s7 200-introduction
Simatic s7 200-introductionSimatic s7 200-introduction
Simatic s7 200-introduction
 
An overview of siemens plc address mapping
An overview of siemens plc address mappingAn overview of siemens plc address mapping
An overview of siemens plc address mapping
 
plc introduction
plc introductionplc introduction
plc introduction
 
Temarios automatizacion
Temarios automatizacionTemarios automatizacion
Temarios automatizacion
 
Ch4 v70 system_configuration_en
Ch4 v70 system_configuration_enCh4 v70 system_configuration_en
Ch4 v70 system_configuration_en
 
Honeywell PLC ML-50 (MLM-DR16S)
Honeywell PLC ML-50 (MLM-DR16S)Honeywell PLC ML-50 (MLM-DR16S)
Honeywell PLC ML-50 (MLM-DR16S)
 
Tia portal v14_en
Tia portal v14_enTia portal v14_en
Tia portal v14_en
 
Ch6 v70 sfc_en
Ch6 v70 sfc_enCh6 v70 sfc_en
Ch6 v70 sfc_en
 
Ch8 v70 os_en
Ch8 v70 os_enCh8 v70 os_en
Ch8 v70 os_en
 
Siemens-S7-1200-PLC
Siemens-S7-1200-PLCSiemens-S7-1200-PLC
Siemens-S7-1200-PLC
 
Delta v emerson_getting_started
Delta v emerson_getting_startedDelta v emerson_getting_started
Delta v emerson_getting_started
 

Viewers also liked

1 sinamics components
1 sinamics components1 sinamics components
1 sinamics componentsconfidencial
 
2 s120 commissioning
2 s120 commissioning2 s120 commissioning
2 s120 commissioningconfidencial
 
Appron feeder common ckt-diagram
Appron feeder common ckt-diagramAppron feeder common ckt-diagram
Appron feeder common ckt-diagramyogagivananda
 
Siemens micromaster-440-manual
Siemens micromaster-440-manualSiemens micromaster-440-manual
Siemens micromaster-440-manualAshok Kumar
 
Asi : Actuator Sensor Interface
Asi : Actuator Sensor InterfaceAsi : Actuator Sensor Interface
Asi : Actuator Sensor Interfaceprashob7
 
Energy savings using ac drives [autosaved]
Energy savings using ac drives [autosaved]Energy savings using ac drives [autosaved]
Energy savings using ac drives [autosaved]prashob7
 
Sce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesSce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesCharles Santos
 
Phan mem plc s7 1200 opc simatic-net-e
Phan mem plc s7 1200 opc simatic-net-ePhan mem plc s7 1200 opc simatic-net-e
Phan mem plc s7 1200 opc simatic-net-eBùi Thể
 
Siemens simatic step_7_programmers_handbook
Siemens simatic step_7_programmers_handbookSiemens simatic step_7_programmers_handbook
Siemens simatic step_7_programmers_handbookvannghiatdh
 
Industrial Networking - Profibus
Industrial Networking - ProfibusIndustrial Networking - Profibus
Industrial Networking - ProfibusYogesh Kumar
 
Manejo de avisos y alarmas en HMI
Manejo de avisos y alarmas en HMIManejo de avisos y alarmas en HMI
Manejo de avisos y alarmas en HMIjohn piñeros
 
1317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten1
1317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten11317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten1
1317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten1Cecilia Noboa
 

Viewers also liked (20)

1 sinamics components
1 sinamics components1 sinamics components
1 sinamics components
 
2 s120 commissioning
2 s120 commissioning2 s120 commissioning
2 s120 commissioning
 
Appron feeder common ckt-diagram
Appron feeder common ckt-diagramAppron feeder common ckt-diagram
Appron feeder common ckt-diagram
 
Siemens micromaster-440-manual
Siemens micromaster-440-manualSiemens micromaster-440-manual
Siemens micromaster-440-manual
 
Asi : Actuator Sensor Interface
Asi : Actuator Sensor InterfaceAsi : Actuator Sensor Interface
Asi : Actuator Sensor Interface
 
Energy savings using ac drives [autosaved]
Energy savings using ac drives [autosaved]Energy savings using ac drives [autosaved]
Energy savings using ac drives [autosaved]
 
Sce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesSce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_prices
 
Ko 7 kdp-06
Ko 7 kdp-06Ko 7 kdp-06
Ko 7 kdp-06
 
Phan mem plc s7 1200 opc simatic-net-e
Phan mem plc s7 1200 opc simatic-net-ePhan mem plc s7 1200 opc simatic-net-e
Phan mem plc s7 1200 opc simatic-net-e
 
W04 Profinet in process automation - Pete Brown, Siemens
W04   Profinet in process automation - Pete Brown, SiemensW04   Profinet in process automation - Pete Brown, Siemens
W04 Profinet in process automation - Pete Brown, Siemens
 
Sinamics g120 treinamento (en)
Sinamics g120 treinamento (en)Sinamics g120 treinamento (en)
Sinamics g120 treinamento (en)
 
Siemens simatic step_7_programmers_handbook
Siemens simatic step_7_programmers_handbookSiemens simatic step_7_programmers_handbook
Siemens simatic step_7_programmers_handbook
 
Profibus, Profinet and IO-Link seminar update - Bob Squirrell
Profibus, Profinet and IO-Link seminar update - Bob SquirrellProfibus, Profinet and IO-Link seminar update - Bob Squirrell
Profibus, Profinet and IO-Link seminar update - Bob Squirrell
 
Step7 200 completo
Step7 200 completoStep7 200 completo
Step7 200 completo
 
Practical steps to a successful PROFIBUS project - Richard Needham and Xiu Ji
Practical steps to a successful PROFIBUS project - Richard Needham and Xiu JiPractical steps to a successful PROFIBUS project - Richard Needham and Xiu Ji
Practical steps to a successful PROFIBUS project - Richard Needham and Xiu Ji
 
03 profibus design_good_practices
03 profibus design_good_practices03 profibus design_good_practices
03 profibus design_good_practices
 
Rede profibus
Rede profibusRede profibus
Rede profibus
 
Industrial Networking - Profibus
Industrial Networking - ProfibusIndustrial Networking - Profibus
Industrial Networking - Profibus
 
Manejo de avisos y alarmas en HMI
Manejo de avisos y alarmas en HMIManejo de avisos y alarmas en HMI
Manejo de avisos y alarmas en HMI
 
1317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten1
1317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten11317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten1
1317747663 n 031-norma-y-protocolo-para-la-prevencion-deteccion-y-aten1
 

Similar to Plc-s7-1200-opc-to-pc-connection-guide

Plc s7-1200-opc-to-pc-connection-guide
Plc s7-1200-opc-to-pc-connection-guidePlc s7-1200-opc-to-pc-connection-guide
Plc s7-1200-opc-to-pc-connection-guideTrung Le
 
Plc s7-300-special-communication1
Plc s7-300-special-communication1Plc s7-300-special-communication1
Plc s7-300-special-communication1Bùi Thể
 
08 comunicação logo! com s7 1200
08 comunicação logo! com s7 120008 comunicação logo! com s7 1200
08 comunicação logo! com s7 1200Marcio Miranda
 
procedure_to_config_OSS_over_IP (2).ppt
procedure_to_config_OSS_over_IP (2).pptprocedure_to_config_OSS_over_IP (2).ppt
procedure_to_config_OSS_over_IP (2).pptArbab Husain
 
Manual del sistema del controlador programable S7-200 CPU21x
Manual del sistema del controlador programable S7-200 CPU21xManual del sistema del controlador programable S7-200 CPU21x
Manual del sistema del controlador programable S7-200 CPU21xSANTIAGO PABLO ALBERTO
 
Chapter 2_Architecture_edited_SDT
Chapter 2_Architecture_edited_SDTChapter 2_Architecture_edited_SDT
Chapter 2_Architecture_edited_SDTStephanie Stribling
 
Siemens cp 242-8 as-interface master profibus-dp slave
Siemens cp 242-8 as-interface master  profibus-dp slaveSiemens cp 242-8 as-interface master  profibus-dp slave
Siemens cp 242-8 as-interface master profibus-dp slaveDien Ha The
 
Manual HUB SERIAL EQUINOX
Manual HUB SERIAL EQUINOXManual HUB SERIAL EQUINOX
Manual HUB SERIAL EQUINOXPablo Vera
 
hmi_time_sync_how_to_e
hmi_time_sync_how_to_ehmi_time_sync_how_to_e
hmi_time_sync_how_to_eEcuador
 
61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdf
61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdf61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdf
61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdfmohamedhayballa1
 
smartlock_final_report
smartlock_final_reportsmartlock_final_report
smartlock_final_reportElliot Barer
 
Esm rel notes_v5.2
Esm rel notes_v5.2Esm rel notes_v5.2
Esm rel notes_v5.2Protect724
 
Quadcept v10.2.0 Released
Quadcept v10.2.0 ReleasedQuadcept v10.2.0 Released
Quadcept v10.2.0 ReleasedQuadcept
 
2017 10-oow-fma-application-containers-v01-final
2017 10-oow-fma-application-containers-v01-final2017 10-oow-fma-application-containers-v01-final
2017 10-oow-fma-application-containers-v01-finalMarkus Flechtner
 

Similar to Plc-s7-1200-opc-to-pc-connection-guide (20)

Plc s7-1200-opc-to-pc-connection-guide
Plc s7-1200-opc-to-pc-connection-guidePlc s7-1200-opc-to-pc-connection-guide
Plc s7-1200-opc-to-pc-connection-guide
 
Plc s7-300-special-communication1
Plc s7-300-special-communication1Plc s7-300-special-communication1
Plc s7-300-special-communication1
 
08 comunicação logo! com s7 1200
08 comunicação logo! com s7 120008 comunicação logo! com s7 1200
08 comunicação logo! com s7 1200
 
procedure_to_config_OSS_over_IP (2).ppt
procedure_to_config_OSS_over_IP (2).pptprocedure_to_config_OSS_over_IP (2).ppt
procedure_to_config_OSS_over_IP (2).ppt
 
Manual del sistema del controlador programable S7-200 CPU21x
Manual del sistema del controlador programable S7-200 CPU21xManual del sistema del controlador programable S7-200 CPU21x
Manual del sistema del controlador programable S7-200 CPU21x
 
Chapter 2_Architecture_edited_SDT
Chapter 2_Architecture_edited_SDTChapter 2_Architecture_edited_SDT
Chapter 2_Architecture_edited_SDT
 
Ies5000 usg
Ies5000 usgIes5000 usg
Ies5000 usg
 
Siemens cp 242-8 as-interface master profibus-dp slave
Siemens cp 242-8 as-interface master  profibus-dp slaveSiemens cp 242-8 as-interface master  profibus-dp slave
Siemens cp 242-8 as-interface master profibus-dp slave
 
Manual HUB SERIAL EQUINOX
Manual HUB SERIAL EQUINOXManual HUB SERIAL EQUINOX
Manual HUB SERIAL EQUINOX
 
hmi_time_sync_how_to_e
hmi_time_sync_how_to_ehmi_time_sync_how_to_e
hmi_time_sync_how_to_e
 
61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdf
61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdf61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdf
61883659_WinCC_RuntimeAdv_access_SQL_via_script_DOCU_en (1).pdf
 
Simens plc training. simatic working-with-step-7
Simens  plc  training. simatic working-with-step-7Simens  plc  training. simatic working-with-step-7
Simens plc training. simatic working-with-step-7
 
Ae13 system komm_hb
Ae13 system komm_hbAe13 system komm_hb
Ae13 system komm_hb
 
Plc operation part 2
Plc operation part 2Plc operation part 2
Plc operation part 2
 
smartlock_final_report
smartlock_final_reportsmartlock_final_report
smartlock_final_report
 
Esm rel notes_v5.2
Esm rel notes_v5.2Esm rel notes_v5.2
Esm rel notes_v5.2
 
Quadcept v10.2.0 Released
Quadcept v10.2.0 ReleasedQuadcept v10.2.0 Released
Quadcept v10.2.0 Released
 
2017 10-oow-fma-application-containers-v01-final
2017 10-oow-fma-application-containers-v01-final2017 10-oow-fma-application-containers-v01-final
2017 10-oow-fma-application-containers-v01-final
 
Stone i tech
Stone i techStone i tech
Stone i tech
 
CCNA Icnd110 s02l05
CCNA Icnd110 s02l05CCNA Icnd110 s02l05
CCNA Icnd110 s02l05
 

More from Bùi Thể

Cảm biến áp suất MPS
Cảm biến áp suất MPSCảm biến áp suất MPS
Cảm biến áp suất MPSBùi Thể
 
Cảm biến áp suất P250
Cảm biến áp suất P250Cảm biến áp suất P250
Cảm biến áp suất P250Bùi Thể
 
Cảm biến mức LR400
Cảm biến mức LR400Cảm biến mức LR400
Cảm biến mức LR400Bùi Thể
 
Cảm biến áp suất-sitrans p250
Cảm biến áp suất-sitrans p250Cảm biến áp suất-sitrans p250
Cảm biến áp suất-sitrans p250Bùi Thể
 
Cảm biến áp suất-sitranspz
Cảm biến áp suất-sitranspzCảm biến áp suất-sitranspz
Cảm biến áp suất-sitranspzBùi Thể
 
Cam bien-ap-suat-phan2
Cam bien-ap-suat-phan2Cam bien-ap-suat-phan2
Cam bien-ap-suat-phan2Bùi Thể
 
cảm biến áp suất -phan1
cảm biến áp suất -phan1cảm biến áp suất -phan1
cảm biến áp suất -phan1Bùi Thể
 
PLC S7- 300 module data_manual_en-us_en-us
PLC S7- 300 module data_manual_en-us_en-usPLC S7- 300 module data_manual_en-us_en-us
PLC S7- 300 module data_manual_en-us_en-usBùi Thể
 
Giao trinh-plc-s7-1200-easy book
Giao trinh-plc-s7-1200-easy bookGiao trinh-plc-s7-1200-easy book
Giao trinh-plc-s7-1200-easy bookBùi Thể
 
Tai lieu plc s7 200
Tai lieu plc s7 200Tai lieu plc s7 200
Tai lieu plc s7 200Bùi Thể
 
Tai lieu plc s7 1200
Tai lieu plc s7 1200Tai lieu plc s7 1200
Tai lieu plc s7 1200Bùi Thể
 
Tai lieu plc s7 300
Tai lieu plc s7 300Tai lieu plc s7 300
Tai lieu plc s7 300Bùi Thể
 
Tai lieu plc s7 300
Tai lieu plc s7 300Tai lieu plc s7 300
Tai lieu plc s7 300Bùi Thể
 

More from Bùi Thể (13)

Cảm biến áp suất MPS
Cảm biến áp suất MPSCảm biến áp suất MPS
Cảm biến áp suất MPS
 
Cảm biến áp suất P250
Cảm biến áp suất P250Cảm biến áp suất P250
Cảm biến áp suất P250
 
Cảm biến mức LR400
Cảm biến mức LR400Cảm biến mức LR400
Cảm biến mức LR400
 
Cảm biến áp suất-sitrans p250
Cảm biến áp suất-sitrans p250Cảm biến áp suất-sitrans p250
Cảm biến áp suất-sitrans p250
 
Cảm biến áp suất-sitranspz
Cảm biến áp suất-sitranspzCảm biến áp suất-sitranspz
Cảm biến áp suất-sitranspz
 
Cam bien-ap-suat-phan2
Cam bien-ap-suat-phan2Cam bien-ap-suat-phan2
Cam bien-ap-suat-phan2
 
cảm biến áp suất -phan1
cảm biến áp suất -phan1cảm biến áp suất -phan1
cảm biến áp suất -phan1
 
PLC S7- 300 module data_manual_en-us_en-us
PLC S7- 300 module data_manual_en-us_en-usPLC S7- 300 module data_manual_en-us_en-us
PLC S7- 300 module data_manual_en-us_en-us
 
Giao trinh-plc-s7-1200-easy book
Giao trinh-plc-s7-1200-easy bookGiao trinh-plc-s7-1200-easy book
Giao trinh-plc-s7-1200-easy book
 
Tai lieu plc s7 200
Tai lieu plc s7 200Tai lieu plc s7 200
Tai lieu plc s7 200
 
Tai lieu plc s7 1200
Tai lieu plc s7 1200Tai lieu plc s7 1200
Tai lieu plc s7 1200
 
Tai lieu plc s7 300
Tai lieu plc s7 300Tai lieu plc s7 300
Tai lieu plc s7 300
 
Tai lieu plc s7 300
Tai lieu plc s7 300Tai lieu plc s7 300
Tai lieu plc s7 300
 

Recently uploaded

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

Plc-s7-1200-opc-to-pc-connection-guide

  • 1. Table of Contents Table of Contents 1 Introduction........................................................................................................ 4 2 Configuration of the S7-1200............................................................................ 6 2.1 Configuring Hardware .......................................................................... 6 2.2 Creating a User Program ..................................................................... 8 3 PC Station Configuration ................................................................................ 13 4 Configuring the S7 Connection...................................................................... 18 4.1 Add S7 Connection ............................................................................ 18 4.2 Display and Change Properties of the S7 Connection in the Inspector Window............................................................................... 19 5 Compiling and Downloading the Configuration and User Program of the S7-1200....................................................................................................... 23 6 Compiling and Downloading the PC Station Configuration........................ 28 7 OPC Scout V10................................................................................................. 34 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 3 http://eyeteck.vn
  • 2. 1 Introduction 1 Introduction This entry shows you how to configure an S7-1200, a PC station and an S7 connection in STEP 7 (TIA Portal) V11 so that you can exchange data between the stations over Industrial Ethernet. Create project In Windows, select the command "Start  Programs  Siemens Automation  TIA Portal V11" to start STEP 7 (TIA Portal) V11. In the Portal view, select the "Create new project" action. Enter the project name in the appropriate field. Figure 1-1 Click the "Create" button to create a new project. Figure 1-2 Switch to Project View Use the "Project View" link to switch to the Project View. S7 communication between PC station and S7-1200 4 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 3. 1 Introduction Figure 1-3 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 5 http://eyeteck.vn
  • 4. 2 Configuration of the S7-1200 2 Configuration of the S7-1200 Configure your S7-1200 in STEP 7 (TIA Portal) V11. Then create the user program and define which data is to be monitored over the S7 connection of the OPC server. 2.1 Configuring Hardware Add an S7-1200 Station In the project tree, double-click the "Add new device" item. The "Add new device" dialog opens. Figure 2-1 Click the "PLC" button in the working area. Go to "PLC  SIMATIC S7-1200  CPU" and select the required controller. Click the "OK" button to add the selected S7-1200 CPU to your project. S7 communication between PC station and S7-1200 6 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 5. 2 Configuration of the S7-1200 Figure 2-2 Add IP address and assign subnet In the project tree, double-click the "Devices & networks" item. This opens the "Network View" working area of the hardware and network editor. Click the PROFINET interface of the S7-1200 CPU. In the inspector window you switch to the "Properties" tab. Click the "Ethernet addresses" item in the area navigation. In this example you enter the IP address 172.16.43.20 and the subnet mask 255.255.0.0 for the PROFINET interface of the S7-1200 CPU. Then assign a subnet to the PROFINET interface. Click the "Add new subnet" button to insert a new subnet. The connection between the subnet, PN/IE_1, for example, and the S7-1200 is now displayed in the "Net View" working area of the hardware and network editor. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 7 http://eyeteck.vn
  • 6. 2 Configuration of the S7-1200 Figure 2-3 2.2 Creating a User Program Add data block In the project tree, navigate to the device folder of the S7-1200 CPU, "PLC_1 [CPU 1212C …]", for example. The device folder contains structured objects and actions that belong to the device. In the device folder you navigate to the "Program blocks" subfolder and double- click the "Add new block" action. The "Add new block" dialog opens. S7 communication between PC station and S7-1200 8 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 7. 2 Configuration of the S7-1200 Figure 2-4 Click the "DB Data block" button. Enter the name of the data block and enable the "Manual" option to assign the number of the data block manually. If you enable the "Automatic" option, the number of the data block is assigned automatically. Select the "Standard - compatible with S7-300/400" option for block access. Data blocks with standard access have a fixed structure. The data elements in the declaration include both symbolic names and a fixed address in the block. The address is displayed in the "Offset" column. You can address the tags in this block both symbolically and absolutely. Apply the settings with "OK". The data block DB1 "Data block 1" is used in this example. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 9 http://eyeteck.vn
  • 8. 2 Configuration of the S7-1200 Figure 2-5 Define static tag in the data block Define the static tag "static_01" of the "Bool" data type in the DB1 "Data block 1". Click the "Compile" button. S7 communication between PC station and S7-1200 10 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 9. 2 Configuration of the S7-1200 Figure 2-6 Create Main [OB1] In the "Program blocks" folder, you double-click the "Main [OB1]" block to open the corresponding dialog window. Figure 2-7 Create the program as shown in Fehler! Verweisquelle konnte nicht gefunden werden.. The bit links are in the "Instructions" task card under "Basic instructions"  Bit links". Use drag-and-drop to add the Normally open contact, the flip-flop and the Assignment to Network 1 of the "Main [OB1]" block. Assign the tags below to the flip-flop, to the normally open contact at inputs S and R of the flip-flop and to the assignment at output Q of the flip-flop. Table 2-1 Tag Description M1.0 SR flip-flop input S: NO contact M1.1 SR flip-flop input R: NO contact DB1.DBX0.0 SR tag M2.0 SR flip-flop output Q: Assignment S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 11 http://eyeteck.vn
  • 10. 2 Configuration of the S7-1200 Click the "Compile" button. Figure 2-8 Notes The "%" character before the absolute address is added automatically by STEP 7 (TIA Portal) V11. S7 communication between PC station and S7-1200 12 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 11. 3 PC Station Configuration 3 PC Station Configuration Before you start configuring the PC station in STEP 7 (TIA Portal) V11, determine or change the IP address of the network card that you are using in your PC station. You enter the IP address and subnet mask of the network card when you configure the PC station in STEP 7 (TIA Portal) V11. Determine and change the IP address and subnet mask of the network card In Windows, under Network Connections, you open the Properties dialog of the Local Area Network (LAN). In this example the network card receives the IP address 172-16.40.11 and subnet mask 255.255.0.0. Notes The IP address configured for the PC station in STEP 7 (TIA Portal) V11 must match the IP address set in Windows. If you are not using a router, the IP addresses of the PC station and the S7-1200 CPU must be in the same subnet. Figure 3-1 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 13 http://eyeteck.vn
  • 12. 3 PC Station Configuration Add a PC Station In STEP 7 (TIA Portal) V11 you open the project that contains the configuration for the S7-1200 station. In the project tree, double-click the "Add new device" item. The "Add new device" dialog opens. Figure 3-2 Click the "PC systems" button in the working area. Go to "PC systems  PC general" and select the "PC station" item. Click the "OK" button to add a PC station named "PC-System_1" to your project. S7 communication between PC station and S7-1200 14 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 13. 3 PC Station Configuration Figure 3-3 This opens the "Device View" working area of the hardware and network editor. In the project tree, navigate to the device folder of the PC station, "PC-System_1 [SIMATIC PC station]", for example. The device folder contains structured objects and actions that belong to the device. In the device folder double-click the "Device configuration" object to open the "Device View" working area of the hardware and network editor. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 15 http://eyeteck.vn
  • 14. 3 PC Station Configuration Figure 3-4 Configure user application and communication module of the PC station Go to the "Device View" working area of the hardware and network editor and configure and parameterize the modules of the PC station. The "Hardware catalog" task card contains the user applications and communication modules that you can configure in the PC station. Using drag-and- drop add the "OPC server" user application to Slot 1 and the "IE general" communication module to Slot 2 of the PC station. Figure 3-5 S7 communication between PC station and S7-1200 16 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 15. 3 PC Station Configuration Add IP address and assign subnet In the project tree, double-click the "Devices & networks" item. This opens the "Network View" working area of the hardware and device editor. Click the PROFINET interface of the network card in the PC station. In the inspector window you switch to the "Properties" tab. In the area navigation select the "Ethernet addresses" item. In this example you enter the IP address 172.16.40.11 and subnet mask 255.255.0.0 for the network card. Select the subnet that you have already assigned to the S7-1200 CPU and assign it also to the network card of the PC station. The connection between the subnet, PN/IE_1, for example, and the S7-1200 and the PC station is now displayed in the "Net View" working area of the hardware and device editor. Notes The IP address configured for the PC station in STEP 7 (TIA Portal) V11 must match the IP address set in Windows. If you are not using a router, the IP addresses of the PC station and the S7-1200 CPU must be in the same subnet. Figure 3-6 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 17 http://eyeteck.vn
  • 16. 4 Configuring the S7 Connection 4 Configuring the S7 Connection 4.1 Add S7 Connection In the project tree, double-click the "Devices & networks" item. This opens the "Network View" working area of the hardware and network editor. In the toolbar of the Net View, click the "Connections" icon to switch to the mode for setting the connections. In the drop-down list box you select "S7 connection" as connection type. Figure 4-1 In the graphical area of the Net View, click the OPC server in the PC station and connect it to the S7-1200 CPU. In the Net View, the S7 connection is displayed in the graphical area and in the "Connections" table in the table area. S7 communication between PC station and S7-1200 18 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 17. 4 Configuring the S7 Connection Figure 4-2 4.2 Display and Change Properties of the S7 Connection in the Inspector Window Proceed as described below to have the properties of the S7 connection displayed in the inspector window. • In the table area switch to the "Connections" table and select the configured S7 connection. • In the inspector window you switch to the "Properties" tab. General properties In the area navigation select the "General" item to display the connection path. The S7 connection is between the OPC server and the S7-1200 CPU. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 19 http://eyeteck.vn
  • 18. 4 Configuring the S7 Connection Figure 4-3 In the area navigation select the "Special connection properties" item. Here you see a display of the special connection properties of the local end point, "Active connection establishment", for example. In this example, the OPC server establishes the S7 connection. The communication partner, S7-1200 CPU, is participates passively in establishing the connection. S7 communication between PC station and S7-1200 20 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 19. 4 Configuring the S7 Connection Figure 4-4 In the area navigation select the "Address details" item. Here you have a display of the local end point, the partner end point and the TSAP of both end points. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 21 http://eyeteck.vn
  • 20. 4 Configuring the S7 Connection Figure 4-5 S7 communication between PC station and S7-1200 22 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 21. 5 Compiling and Downloading the Configuration and User Program of the S7-1200 5 Compiling and Downloading the Configuration and User Program of the S7- 1200 Compile To compile the configuration and user program of the S7-1200 you right-click the device folder of the S7-1200 CPU in the project navigation. There you select "Compile  All". S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 23 http://eyeteck.vn
  • 22. 5 Compiling and Downloading the Configuration and User Program of the S7-1200 Figure 5-1 Download To download the configuration and user program of the S7-1200 you right-click the device folder of the S7-1200 CPU in the project navigation. There you select "Download to device  All". S7 communication between PC station and S7-1200 24 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 23. 5 Compiling and Downloading the Configuration and User Program of the S7-1200 Figure 5-2 The "Extended download to device" dialog opens. Check the settings below: • PG/PC interface type • PG/PC interface • Connection with the subnet Under "Accessible devices in subnet" you select the relevant device and click the "Load" button. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 25 http://eyeteck.vn
  • 24. 5 Compiling and Downloading the Configuration and User Program of the S7-1200 Figure 5-3 Notes If the project has already been loaded once into the S7-1200 CPU, the "Load preview" dialog is opened immediately instead of the "Extended download to device" dialog. The "Load preview" dialog opens. Click the "Load" button. S7 communication between PC station and S7-1200 26 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 25. 5 Compiling and Downloading the Configuration and User Program of the S7-1200 Figure 5-4 The dialog box containing the results of the download procedure opens. If the S7- 1200 is in "STOP" mode for the download procedure, check the "Start all" check box. Click the "Finish" button. The status LED of the S7-1200 CPU indicates the "RUN" mode after downloading. Figure 5-5 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 27 http://eyeteck.vn
  • 26. 6 Compiling and Downloading the PC Station Configuration 6 Compiling and Downloading the PC Station Configuration Open the Station Configuration Editor Open the Component Configuration Editor with the icon in the Windows taskbar. Figure 6-1 Insert the modules, namely the OPC server and the network card, in the Component Configuration Editor in accordance with the hardware configuration. In this example you add the OPC server to Slot 1 and the network card to Slot 2. Then change the station name in the Component Configuration Editor. The name of the PC station must be identical in STEP 7 (TIA Portal) V11 and in the Component Configuration Editor. The station name "PC-System_1" is used in this example. S7 communication between PC station and S7-1200 28 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 27. 6 Compiling and Downloading the PC Station Configuration Figure 6-2 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 29 http://eyeteck.vn
  • 28. 6 Compiling and Downloading the PC Station Configuration Compile To compile the configuration of the PC station you right-click the device folder of the PC station in the project navigation. There you select "Compile  All". Figure 6-3 Download To download the configuration of the PC station you right-click the device folder of the PC station in the project navigation. There you select "Download to device  All". S7 communication between PC station and S7-1200 30 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 29. 6 Compiling and Downloading the PC Station Configuration Figure 6-4 The "Extended download to device" dialog opens. Check the settings below: • PG/PC interface type • PG/PC interface • Connection with the subnet Under "Accessible devices in subnet" you select the relevant device and click the "Load" button. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 31 http://eyeteck.vn
  • 30. 6 Compiling and Downloading the PC Station Configuration Figure 6-5 Notes If the project has already been loaded once into the S7-1200 CPU, the "Load preview" dialog is opened immediately instead of the "Extended download to device" dialog. The "Load preview" dialog opens. Click the "Load" button. S7 communication between PC station and S7-1200 32 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 31. 6 Compiling and Downloading the PC Station Configuration Figure 6-6 Commissioning of the PC station is completed after downloading of the configuration. S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 33 http://eyeteck.vn
  • 32. 7 OPC Scout V10 7 OPC Scout V10 In this example the OPC Scout V10 is used as OPC client. Using the OPC client you can access the data of the S7-1200 CPU over the OPC server. Start the OPC Scout V10 by means of the menu "Start  SIMATIC  SIMATIC NET  OPC Scout V10". Establish connection to the OPC server In the Server Explorer you double-click the "OPC.SimaticNET" item to establish a connection to the OPC server. Figure 7-1 S7 communication between PC station and S7-1200 34 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 33. 7 OPC Scout V10 The configured S7 connection named "S7_Verbindung_1" is displayed in the Server Explorer under OPC.SimaticNET in the "S7" folder. Figure 7-2 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 35 http://eyeteck.vn
  • 34. 7 OPC Scout V10 Create OPC items Add the items below to the DA view. Table 7-1 S7:[S7_Verbindung_1]MX1.0 By means of the OPC item you monitor and control the marker bit M1.0 in the S7-1200 CPU. S7:[S7_Verbindung_1]MX1.1 By means of the OPC item you monitor and control the marker bit M1.1 in the S7-1200 CPU. S7:[S7_Verbindung_1]MX2.0 By means of the OPC item you monitor the marker bit M2.0 in the S7-1200 CPU. S7:[S7_Verbindung_1]DB1, X0.0 By means of the OPC item you monitor Bit 0.0 of the DB1 data block in the S7-1200 CPU. Figure 7-3 Monitor OPC items Click the "Monitoring ON" button to monitor the values of the OPC items. The values of the OPC items are displayed in the "Value" column. Figure 7-4 S7 communication between PC station and S7-1200 36 V1.1, Entry ID: 39960679 http://eyeteck.vn
  • 35. 7 OPC Scout V10 Write values In the "New value" column you enter the value that you want to write to the S7- 1200. Enter the values below in the "New value" column (see Table 7-2). Click the "Write" button. The marker bit M2.0 and Bit 0 in DB1 are given the value "True". The results of the write procedure are displayed in the "Value" column. Table 7-2 OPC item New value S7:[S7_Verbindung_1]MX1.0 True S7:[S7_Verbindung_1]MX1.1 False Figure 7-5 Enter the values below in the "New value" column (see Table 7-3). Click the "Write" button. The marker bit M2.0 and Bit 0 in DB1 are reset to the value "False". The results of the write procedure are displayed in the "Value" column. Table 7-3 OPC item New value S7:[S7_Verbindung_1]MX1.0 False S7:[S7_Verbindung_1]MX1.1 True Figure 7-6 S7 communication between PC station and S7-1200 V1.1, Item ID: 39960679 37 http://eyeteck.vn