PETROSYNC’S COST ENGINEERING & PROJECT MANAGEMENT
Your Key To Project Success by Ensuring Project is within Budget and Allocated Time
12 October —15 October 2015
Bangkok, Thailand
AUDITINGPROJECTPERFORMANCE
&PROJECTCONTROL
2
Our Auditing Project Performance & Project Control course is developed to help you learn the
required skillsets to validate your project through auditing the limits of time, human
resources, materials, budget, and specifications to ensure project success.
COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL
How Does This Course Benefits You?
Success Criteria Development
-Do you know how to determine "success criteria" for
project audit?
Pinpoint Critical Criteria in Capital Projects Evaluation
Master the critical criteria in project evaluation by learning the causes of variances & program
evaluation and review technique (PERT) to ensure better evaluation and management in
projects.
Evaluate the Strengths and Weaknesses in Projects
Attain best skills in evaluating strengths and weaknesses in projects by learning the triple
constraints of project performance and effective measures in auditing project performance.
Adopt Consistent Process for Accessing Project Risk
Handle project risk by adopting consistent process by learning the risk analysis approaches to
minimize the risk and to ensure success in project
Master Ways to Recover Troubled Projects
Master the skills in recovering troubled projects by identifying the change within the project
and determining the risk tolerances and learning the alternative constraints in managing.
Gain best-in-industry practices and benchmarks to ensure project success
Learn the best practices and benchmarks in auditing project performance by practising to
measure the triple constraints of project management and risk that ensure project success.
Development of "Lessons Learned" on the project
- Do you know this can help improve project performance?
Effective measures for auditing project performance and controlling projects is the key to
any project’s success. In this course, you will discover proven ways to work within your
identified constraints, without letting predefined limits curtail creativity and innovation.
general@petrosync.com | +65 6451 4500 | www.petrosync.com
Course Overview
Course Design
This course focuses on the hands-on training and experience, practicing art of auditing your
project against the project requirements documents, risk management plans, and budget
estimates.
Includes Specific and Practical Case Studies
You will also learn the best industry practices used to measure the triple constraints of
project management and risk that ensure project success and techniques for estimating and
forecasting future performance of your project.
3
COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL
PetroSync Distinguished Instructor
Who Needs This Program
Practical & Consulting
Over 23 years in project audit and management and was a
Master Business Analyst. His experience includes several multi-
million dollar international projects.
Training
Has delivered this course in several oil & gas companies, and it
has been well-rated from the past attendees.
Regional
Clientele base is from the SEAsian region, as well as in EU, and
AUS
Awards
 PMI Project Management Professional (PMP)
Mr. William H. Volpé III
PMP, CET, GWCPM,
GWCBA.
President & CEO
The Volpe Consortium,
Inc.
 People involved in Project Auditing and Management., Project & Cost Control, Internal
Audit, Risk Management, Project Planning, Project Quality Assurance & Process
Improvement
Job Titles Include:
Project Auditor
Financial Controller
Project Controller
Contract Engineers
Project Planner
Project Manager
Schedule Control Engineers
Project Engineers
PetroSync Inhouse Solutions
PetroSync can tailor our courses to meet your specific
needs at your preferred location and schedule. Contact us
for more information at +65 6415 4500 or email to
general @petrosync.com
PetroSync Quality Assurance
All PetroSync courses are developed with top quality to
address all your training needs and purposes. Our courses
are vetted strictly to ensure that we always deliver the best
courses with the best industry expert.
general@petrosync.com | +65 6451 4500 | www.petrosync.com
08:00—09:00 Registration (Day 1) 13:00—14:00 Lunch
09:00—11:00 Session I 14:00—15:30 Session III
11:00—11.15 Refreshment Session I 15:30—15:45 Refreshment Session II
11:15—13:00 Session II 15:45—17:00 Session Iv (Last Session)
Course Schedule
4
COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL
DAY 1
Assessing Team Health During a Project Audit
Leadership and Management
 What is leadership?
 The difference between leadership and management
 Articulate your leadership vision, in light of the
assessment, and consider the best way(s) to realize it
 Processes for establishing direction, aligning people, and
motivating people to follow your vision
 Identifying different leadership styles
Leading Effective Teams
 What is a team?
 The stages of team development
 Forming/Storming/Norming/Performing/Adjourning
 Leading & maintaining effective, productive teams
DAY 2
Project Management Governance
 Projct management life-cycle and governance
 Reviews vs. Audits
 Planning tools
 The triple constraints and stakeholder management
 Discussion: Project Requirements Document
 Discussion: Work Breakdown Structure (WBS)
Estimating for Scheduling & Cost Control
 Using estimates for scheduling and cost control
 The estimating guideline
 Levels of estimating and estimate types
Top-down vs. bottom-up
Order of magnitude
Budget
Definitive
 Four estimating methodologies
Bottom-up
Parametric
Supplier bids
Analogous
Resource Allocation & Estimating
 Cost types and categories
 Identify controllable costs
Resource
Material
Direct
Indirect
 Program Evaluation and Review Technique (PERT) -
Planning and controlling risk with contingency
 Building the project resource pool
Using resources to build estimates
The responsibility matrix
 Time-controlled estimates
 Resource-limited estimates
Course Agenda — 4 Days
DAY 3
Scheduling - Part 2
 Basic scheduling and network calculations
 Exercises: Build a complex scheduling network
 Advanced precedence relationships and the critical path
 Alternative constraints
 Gantt and milestone charts
The Baseline and Cost Curves
 Establishing baselines
 Understanding types of baselines
 Time-phased distribution of costs
 Cumulative cost curves—Presenting Project Health

Managing Change Within The Project
 The process of control
 Earned Value Management (EVM) - Objective assessment
of variance and performance
 Identifying sources of change
 Screening change
 Updating the project plan
 Communicating change
Project Evaluation and Forecasting
 Causes of variances
 Establishing the “data date” for evaluation
 Controlling costs late in the project
 Controlling schedule late in the project
Register For This Course Now!
Kindly fill up your particulars in the
registration form placed at the end of this
brochure, and send it to us or email to
registration@petrosync.com
general@petrosync.com | +65 6451 4500 | www.petrosync.com
DAY 2 (Continued)
Scheduling - Part 1
 Scheduling network
 Validating schedules
 Basic project activities relationships—Arrow diagrams
 Exercises: Precedence diagrams process
5
COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL
Project Audit and Earned-Value Forecasting
 Critical components of the project audit
 Sample project audit process
 Considerations in establishing a monitoring system
 Exercises: Earned-value forecasting
 Advanced earned-value forecasting tools
Analysis Fundamentals
 Risk probability and impact
 Presenting risk
 Risk analysis approaches
Qualitative
Quantitative
Descriptive
 Estimating methods and idea-generation tools
Analogy techniques
Checklists, Questionnaires, and Templates
Expert interview
Delphi technique
Brainstorming
Nominal group technique
Crawford slip method
SWOT analysis
Prototyping
Affinity Digramming
Impact Analysis and Risk Assessment
 Determining risk tolerances
 Analyzing risks
 Impact anlaysis
Project cost impacts
Project schedule impacts
Project scope impacts
 Risk assessment matrix
Analyzing and Prioritizing Risk
 Risk-based financial tools and techniques
 Expected-value analysis
 Decision trees
DAY 4
Register For This Course Now!
Kindly fill up your particulars in the
registration form placed at the end of this
brochure, and send it to us or email to
registration@petrosync.com
general@petrosync.com | +65 6451 4500 | www.petrosync.com
You Might Also Be Interested In:
Analysis & Modeling for Cost, Economics & Risk
27-29 July 2015 | Kuala Lumpur, Malaysia
Successful Project Cost Estimation & Control
7-11 September 2015 | Kuala Lumpur, Malaysia
Cost Engineering Intensive
28 Sept-1 Oct 2015 | Kuala Lumpur, Malaysia
6
By Credit Card:
Please debit my credit card: Visa MasterCard AMEX Security Code:
Card Number: Expiry Date:
Name Printed on Card:
By Direct Transfer: Please quote invoice number(s) on remittance advice
PetroSync Global Pte Ltd Bank Details:
Account Name: PetroSync Global Pte Ltd
Bank Name: DBS Bank Ltd
Bank Code: 7171—Bank Swift Code: DBSSSGSGXXX—Branch Code: 288
Account No: SGD: 288-901898-0 USD: 0288-002682-01-6
Bank Address: 12 Marina Boulevard, Level 3. Marina Bay Financial Centre Tower 3. Singapore 018982.
All bank charges to be borne by payer. Please ensure that PetroSync Global Pte Ltd receives the full invoiced
amount.
Title : Auditing Project Performance & Project Control
Date : 12-15 October, 2015
Location : Bangkok, Thailand
COURSE DETAILS
INVESTMENT PACKAGE DATELINE FULL MASTERCLASS
Standard Price 9 October 2015 USD 3,595
Early Bird Offer 17 July 2015 USD 3,395
Group Discount
(3 or more Delegates)
9 October 2015 USD 3,295
INVESTMENT PACKAGES (Please Circle)
Group Discount is based on Standard Price
*To enjoy the promotion & discount offer, payment must be made before dateline
* For 7 or more delegates, please inquire for more attractive package.
* Prices include lunches, refreshments and materials. Promotion & discount cannot be combined with other
promotional offers.
* Important: Please note that registration without payment will incur a SGD 200 administration fee.
COURSE CONSULTANT
Name : Cay Aagen
Email : registration@petrosync.com
Phone : +65 6415 4500
Fax : +65 6415 4322
TERMS AND CONDITIONS
DISCLAIMER
Please note that trainers and topics were confirmed at
the time of publishing; however, PetroSync may
necessitate substitutions, alterations or cancellations
of the trainers or topics. As such, PetroSync reserves
the right to change or cancel any part of its published
courseme due to unforeseen circumstances. Any
substitutions or alterations will be updated on our web
page as soon as possible.
DATA PROTECTION
The information you provide will be safeguarded by
PetroSync that may be used to keep you informed of
relevant products and services. As an international
group we may transfer your data on a global basis for
the purpose indicated above. If you do not want us to
share your information with other reputable
companies, please tick this box
CANCELLATION POLICY
You may substitute delegates at any time as long as
reasonable advance notice is given to PetroSync. For
any cancellation received in writing not less than
fourteen (14) working days prior to the training
course, you will receive credit voucher less a SGD $200
administration fee and any related bank or credit card
charges.
Delegates who cancel less than fourteen (14) working
days of the training course, or who do not attend the
course, are liable to pay the full course fee and no
refunds will be granted.
In the event that PetroSync cancels or postpones an
event for any reason and that the delegate is unable or
unwilling to attend in on the rescheduled date, you will
receive a credit voucher for 100% of the contract fee
paid. You may use this credit voucher for another
PetroSync to be mutually agreed with PetroSync,
which must occur within a year from the date of
postponement.
PetroSync is not responsible for any loss or damage as
a result of the cancellation policy. PetroSync will
assume no liability whatsoever in the event this event
is cancelled, rescheduled or postponed due to any Act
of God, fire, act of government or state, war, civil
commotion, insurrection, embargo, industrial action,
or any other reason beyond management control.
CERTIFICATE OF ATTENDANCE
70% attendance is required for PetroSync’s Certificate
of Attendance
DETAILS
Please accept our apologies for mail or email that is
incorrectly addressed.
Please email us at registration@petrosync.com and
inform us of any incorrect details. We will amend them
accordingly.
CHARGES & FEE(S)
- For Payment by Direct Telegraphic Transfer, client
has to bear both local and oversea bank charges.
- For credit card payment, there is additional 4%
credit card processing fee.
1st Delegate Name:
Direct Line Number: Email:
Job Title: Department:
Head of Department:
Mr Mrs Ms Dr Others
2nd Delegate Name:
Direct Line Number: Email:
Job Title: Department:
Head of Department:
Mr Mrs Ms Dr Others
3rd Delegate Name:
Direct Line Number: Email:
Job Title: Department:
Head of Department:
Mr Mrs Ms Dr Others
Attention Invoice to:
Direct Line Number: Fax:
Company: Industry:
Address: Postcode:
Country: Email:
Please note:
- Indicate if you have already registered by Phone Fax Email Web
- If you have not received an acknowledgement before the training, please call us to confirm your booking.
CONFIRMATION
I agree to PetroSync’s terms & conditions, payment terms and cancellation policy.
Authorized Signature:
PAYMENT TERMS : Payment is due in full at the time of registration. Full payment is mandatory for event attendance.
PAYMENT METHOD
INVOICE DETAILS
DELEGATES DETAILS

More Related Content

What's hot

Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
Jamil Faraj , PMP
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
Glen Alleman
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
OSP International LLC
 
Software project management
Software project managementSoftware project management
Software project managementR A Akerkar
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
Jamil Faraj , PMP
 
Pmi rmp
Pmi rmpPmi rmp
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
Joshua Pierce
 
MoV syllabus
MoV syllabusMoV syllabus
MoV syllabus
Matt Trigg
 
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
Intaver Insititute
 
Project planning and control - Nov
Project planning and control - NovProject planning and control - Nov
Project planning and control - Nov
Ifeoma Onyemachi
 
Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Nam Trung
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas Industry
David Pires
 

What's hot (20)

Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Ashwani Profile
Ashwani ProfileAshwani Profile
Ashwani Profile
 
CV ABHI 06-09 - Copy
CV ABHI 06-09 - CopyCV ABHI 06-09 - Copy
CV ABHI 06-09 - Copy
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Software project management
Software project managementSoftware project management
Software project management
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
PPRPreparationGuide
PPRPreparationGuidePPRPreparationGuide
PPRPreparationGuide
 
MoV syllabus
MoV syllabusMoV syllabus
MoV syllabus
 
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
 
CV ABHIJIT 04-03-2015
CV ABHIJIT 04-03-2015CV ABHIJIT 04-03-2015
CV ABHIJIT 04-03-2015
 
Ganesh Ramchandran
Ganesh RamchandranGanesh Ramchandran
Ganesh Ramchandran
 
Project planning and control - Nov
Project planning and control - NovProject planning and control - Nov
Project planning and control - Nov
 
Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas Industry
 

Viewers also liked

PetroSync - Directional Drilling Operation
PetroSync - Directional Drilling OperationPetroSync - Directional Drilling Operation
PetroSync - Directional Drilling Operation
PetroSync
 
PetroSync - Introduction to Oil and Gas Accounting
PetroSync - Introduction to Oil and Gas AccountingPetroSync - Introduction to Oil and Gas Accounting
PetroSync - Introduction to Oil and Gas Accounting
PetroSync
 
PetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & Control
PetroSync
 
PetroSync - Cost Engineering Intensive
PetroSync - Cost Engineering IntensivePetroSync - Cost Engineering Intensive
PetroSync - Cost Engineering Intensive
PetroSync
 
PetroSync - Advanced Financial Modelling for Oil and Gas
PetroSync - Advanced Financial Modelling for Oil and GasPetroSync - Advanced Financial Modelling for Oil and Gas
PetroSync - Advanced Financial Modelling for Oil and Gas
PetroSync
 
PetroSync - Root Cause Analysis
PetroSync - Root Cause AnalysisPetroSync - Root Cause Analysis
PetroSync - Root Cause Analysis
PetroSync
 
PetroSync - Drilling String Design
PetroSync - Drilling String DesignPetroSync - Drilling String Design
PetroSync - Drilling String Design
PetroSync
 
PetroSync - Drilling Engineering for Non-Drilling Engineers
PetroSync - Drilling Engineering for Non-Drilling EngineersPetroSync - Drilling Engineering for Non-Drilling Engineers
PetroSync - Drilling Engineering for Non-Drilling Engineers
PetroSync
 
PetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic Systems
PetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic SystemsPetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic Systems
PetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic Systems
PetroSync
 
PetroSync - Risk and Simulation Modelling for Oil and Gas Applications
PetroSync - Risk and Simulation Modelling for Oil and Gas ApplicationsPetroSync - Risk and Simulation Modelling for Oil and Gas Applications
PetroSync - Risk and Simulation Modelling for Oil and Gas Applications
PetroSync
 
PetroSync - Heat Exchanger Fouling & Mitigation Technology
PetroSync - Heat Exchanger Fouling & Mitigation TechnologyPetroSync - Heat Exchanger Fouling & Mitigation Technology
PetroSync - Heat Exchanger Fouling & Mitigation Technology
PetroSync
 
PetroSync - Integration of Petrophysics and Core Analysis
PetroSync - Integration of Petrophysics and Core AnalysisPetroSync - Integration of Petrophysics and Core Analysis
PetroSync - Integration of Petrophysics and Core Analysis
PetroSync
 
PetroSync - Advanced Petroleum Contract Negotiation
PetroSync - Advanced Petroleum Contract NegotiationPetroSync - Advanced Petroleum Contract Negotiation
PetroSync - Advanced Petroleum Contract Negotiation
PetroSync
 
PetroSync - Advanced Contract Negotiation and Post-Contract Management
PetroSync - Advanced Contract Negotiation and Post-Contract ManagementPetroSync - Advanced Contract Negotiation and Post-Contract Management
PetroSync - Advanced Contract Negotiation and Post-Contract Management
PetroSync
 
PetroSync - Post-Contract Management
PetroSync - Post-Contract ManagementPetroSync - Post-Contract Management
PetroSync - Post-Contract Management
PetroSync
 
PetroSync - Legal Report Writing
PetroSync - Legal Report WritingPetroSync - Legal Report Writing
PetroSync - Legal Report Writing
PetroSync
 
PetroSync - Drilling Contract Negotiation & Management
PetroSync - Drilling Contract Negotiation & ManagementPetroSync - Drilling Contract Negotiation & Management
PetroSync - Drilling Contract Negotiation & Management
PetroSync
 
PetroSync - Exploration & Production Accounting
PetroSync - Exploration & Production AccountingPetroSync - Exploration & Production Accounting
PetroSync - Exploration & Production Accounting
PetroSync
 
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync
 
PetroSync - Mastering Production Sharing Contracts
PetroSync - Mastering Production Sharing ContractsPetroSync - Mastering Production Sharing Contracts
PetroSync - Mastering Production Sharing Contracts
PetroSync
 

Viewers also liked (20)

PetroSync - Directional Drilling Operation
PetroSync - Directional Drilling OperationPetroSync - Directional Drilling Operation
PetroSync - Directional Drilling Operation
 
PetroSync - Introduction to Oil and Gas Accounting
PetroSync - Introduction to Oil and Gas AccountingPetroSync - Introduction to Oil and Gas Accounting
PetroSync - Introduction to Oil and Gas Accounting
 
PetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & Control
 
PetroSync - Cost Engineering Intensive
PetroSync - Cost Engineering IntensivePetroSync - Cost Engineering Intensive
PetroSync - Cost Engineering Intensive
 
PetroSync - Advanced Financial Modelling for Oil and Gas
PetroSync - Advanced Financial Modelling for Oil and GasPetroSync - Advanced Financial Modelling for Oil and Gas
PetroSync - Advanced Financial Modelling for Oil and Gas
 
PetroSync - Root Cause Analysis
PetroSync - Root Cause AnalysisPetroSync - Root Cause Analysis
PetroSync - Root Cause Analysis
 
PetroSync - Drilling String Design
PetroSync - Drilling String DesignPetroSync - Drilling String Design
PetroSync - Drilling String Design
 
PetroSync - Drilling Engineering for Non-Drilling Engineers
PetroSync - Drilling Engineering for Non-Drilling EngineersPetroSync - Drilling Engineering for Non-Drilling Engineers
PetroSync - Drilling Engineering for Non-Drilling Engineers
 
PetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic Systems
PetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic SystemsPetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic Systems
PetroSync - Applied Sequence Stratigraphy in Carbonates & Siliciclastic Systems
 
PetroSync - Risk and Simulation Modelling for Oil and Gas Applications
PetroSync - Risk and Simulation Modelling for Oil and Gas ApplicationsPetroSync - Risk and Simulation Modelling for Oil and Gas Applications
PetroSync - Risk and Simulation Modelling for Oil and Gas Applications
 
PetroSync - Heat Exchanger Fouling & Mitigation Technology
PetroSync - Heat Exchanger Fouling & Mitigation TechnologyPetroSync - Heat Exchanger Fouling & Mitigation Technology
PetroSync - Heat Exchanger Fouling & Mitigation Technology
 
PetroSync - Integration of Petrophysics and Core Analysis
PetroSync - Integration of Petrophysics and Core AnalysisPetroSync - Integration of Petrophysics and Core Analysis
PetroSync - Integration of Petrophysics and Core Analysis
 
PetroSync - Advanced Petroleum Contract Negotiation
PetroSync - Advanced Petroleum Contract NegotiationPetroSync - Advanced Petroleum Contract Negotiation
PetroSync - Advanced Petroleum Contract Negotiation
 
PetroSync - Advanced Contract Negotiation and Post-Contract Management
PetroSync - Advanced Contract Negotiation and Post-Contract ManagementPetroSync - Advanced Contract Negotiation and Post-Contract Management
PetroSync - Advanced Contract Negotiation and Post-Contract Management
 
PetroSync - Post-Contract Management
PetroSync - Post-Contract ManagementPetroSync - Post-Contract Management
PetroSync - Post-Contract Management
 
PetroSync - Legal Report Writing
PetroSync - Legal Report WritingPetroSync - Legal Report Writing
PetroSync - Legal Report Writing
 
PetroSync - Drilling Contract Negotiation & Management
PetroSync - Drilling Contract Negotiation & ManagementPetroSync - Drilling Contract Negotiation & Management
PetroSync - Drilling Contract Negotiation & Management
 
PetroSync - Exploration & Production Accounting
PetroSync - Exploration & Production AccountingPetroSync - Exploration & Production Accounting
PetroSync - Exploration & Production Accounting
 
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
PetroSync - IWCF Well Intervention Pressure Control Level 3 & 4
 
PetroSync - Mastering Production Sharing Contracts
PetroSync - Mastering Production Sharing ContractsPetroSync - Mastering Production Sharing Contracts
PetroSync - Mastering Production Sharing Contracts
 

Similar to PetroSync - Auditing Project Performance & Project Control

PetroSync - Cost Engineering Risk Management-Earned Value Management
PetroSync - Cost Engineering Risk Management-Earned Value ManagementPetroSync - Cost Engineering Risk Management-Earned Value Management
PetroSync - Cost Engineering Risk Management-Earned Value Management
PetroSync
 
Pmp Certification
Pmp CertificationPmp Certification
Pmp Certification
turnerwife
 
P3M3 - Discovery Assessment
P3M3 - Discovery AssessmentP3M3 - Discovery Assessment
P3M3 - Discovery Assessment
Profeo
 
Project management professional exam outline
Project management professional exam outlineProject management professional exam outline
Project management professional exam outline
Dadunoor Kamati
 
PetroSync - Project Risk Assessment & Management
PetroSync - Project Risk Assessment & ManagementPetroSync - Project Risk Assessment & Management
PetroSync - Project Risk Assessment & Management
PetroSync
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 
MPM Master Project Manager - contact sysenegacademy@gmail.com
MPM Master Project Manager - contact sysenegacademy@gmail.comMPM Master Project Manager - contact sysenegacademy@gmail.com
MPM Master Project Manager - contact sysenegacademy@gmail.com
GAFM Academy of Project Management ® - ISO 29990 Certified International Board of Standards
 
Suresh kumar j Sr. Project Manager
Suresh kumar j Sr. Project ManagerSuresh kumar j Sr. Project Manager
Suresh kumar j Sr. Project Manager
Suresh Kumar Jettipalle
 
Session 7 Everything You Should Know About PMP & CAPM Certifications
Session 7 Everything You Should Know About PMP & CAPM CertificationsSession 7 Everything You Should Know About PMP & CAPM Certifications
Session 7 Everything You Should Know About PMP & CAPM Certifications
Seshne Govender
 
Suresh kumarj sr.pm
Suresh kumarj sr.pmSuresh kumarj sr.pm
Suresh kumarj sr.pm
Suresh Kumar Jettipalle
 
Suresh kumarj sr.pm
Suresh kumarj sr.pmSuresh kumarj sr.pm
Suresh kumarj sr.pm
Suresh Kumar Jettipalle
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Edureka!
 
SSCG Project Management Services
SSCG Project Management ServicesSSCG Project Management Services
SSCG Project Management Services
SSCG Consulting
 
REQB® - Advanced Level Requirements Manager
REQB® - Advanced Level Requirements ManagerREQB® - Advanced Level Requirements Manager
CAPM Exam Prep Course Preview
CAPM Exam Prep Course PreviewCAPM Exam Prep Course Preview
CAPM Exam Prep Course Preview
Invensis Learning
 
Introduction to-project-management
Introduction to-project-managementIntroduction to-project-management
Introduction to-project-managementPinta Florin
 

Similar to PetroSync - Auditing Project Performance & Project Control (20)

PetroSync - Cost Engineering Risk Management-Earned Value Management
PetroSync - Cost Engineering Risk Management-Earned Value ManagementPetroSync - Cost Engineering Risk Management-Earned Value Management
PetroSync - Cost Engineering Risk Management-Earned Value Management
 
Project Management brochure
Project Management brochureProject Management brochure
Project Management brochure
 
Pmp Certification
Pmp CertificationPmp Certification
Pmp Certification
 
P3M3 - Discovery Assessment
P3M3 - Discovery AssessmentP3M3 - Discovery Assessment
P3M3 - Discovery Assessment
 
Project management professional exam outline
Project management professional exam outlineProject management professional exam outline
Project management professional exam outline
 
Shibumon Manaveettil CV
Shibumon Manaveettil CVShibumon Manaveettil CV
Shibumon Manaveettil CV
 
PetroSync - Project Risk Assessment & Management
PetroSync - Project Risk Assessment & ManagementPetroSync - Project Risk Assessment & Management
PetroSync - Project Risk Assessment & Management
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
Pmp
PmpPmp
Pmp
 
MPM Master Project Manager - contact sysenegacademy@gmail.com
MPM Master Project Manager - contact sysenegacademy@gmail.comMPM Master Project Manager - contact sysenegacademy@gmail.com
MPM Master Project Manager - contact sysenegacademy@gmail.com
 
Suresh kumar j Sr. Project Manager
Suresh kumar j Sr. Project ManagerSuresh kumar j Sr. Project Manager
Suresh kumar j Sr. Project Manager
 
Session 7 Everything You Should Know About PMP & CAPM Certifications
Session 7 Everything You Should Know About PMP & CAPM CertificationsSession 7 Everything You Should Know About PMP & CAPM Certifications
Session 7 Everything You Should Know About PMP & CAPM Certifications
 
SureshKumarJ-Sr.PM
SureshKumarJ-Sr.PMSureshKumarJ-Sr.PM
SureshKumarJ-Sr.PM
 
Suresh kumarj sr.pm
Suresh kumarj sr.pmSuresh kumarj sr.pm
Suresh kumarj sr.pm
 
Suresh kumarj sr.pm
Suresh kumarj sr.pmSuresh kumarj sr.pm
Suresh kumarj sr.pm
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
 
SSCG Project Management Services
SSCG Project Management ServicesSSCG Project Management Services
SSCG Project Management Services
 
REQB® - Advanced Level Requirements Manager
REQB® - Advanced Level Requirements ManagerREQB® - Advanced Level Requirements Manager
REQB® - Advanced Level Requirements Manager
 
CAPM Exam Prep Course Preview
CAPM Exam Prep Course PreviewCAPM Exam Prep Course Preview
CAPM Exam Prep Course Preview
 
Introduction to-project-management
Introduction to-project-managementIntroduction to-project-management
Introduction to-project-management
 

More from PetroSync

PetroSync - API Specification Q1 9th Edition Quality Management System Traini...
PetroSync - API Specification Q1 9th Edition Quality Management System Traini...PetroSync - API Specification Q1 9th Edition Quality Management System Traini...
PetroSync - API Specification Q1 9th Edition Quality Management System Traini...
PetroSync
 
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource DocumentPetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync
 
PetroSync - Surface Geochemical Exploration for Oil and Gas
PetroSync - Surface Geochemical Exploration for Oil and GasPetroSync - Surface Geochemical Exploration for Oil and Gas
PetroSync - Surface Geochemical Exploration for Oil and Gas
PetroSync
 
PetroSync - Geological Interpretation of Well Logs
PetroSync - Geological Interpretation of Well LogsPetroSync - Geological Interpretation of Well Logs
PetroSync - Geological Interpretation of Well Logs
PetroSync
 
PetroSync - Chemically Enhanced Water Alternating Gas
PetroSync - Chemically Enhanced Water Alternating GasPetroSync - Chemically Enhanced Water Alternating Gas
PetroSync - Chemically Enhanced Water Alternating Gas
PetroSync
 
PetroSync - Budgeting and Forecasting in Oil & Gas Industry
PetroSync - Budgeting and Forecasting in Oil & Gas IndustryPetroSync - Budgeting and Forecasting in Oil & Gas Industry
PetroSync - Budgeting and Forecasting in Oil & Gas Industry
PetroSync
 
PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...
PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...
PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...
PetroSync
 
PetroSync - Drilling Engineering for Non-Drilling Engineer
PetroSync - Drilling Engineering for Non-Drilling EngineerPetroSync - Drilling Engineering for Non-Drilling Engineer
PetroSync - Drilling Engineering for Non-Drilling Engineer
PetroSync
 
PetroSync - Gas Turbine Failure Analysis
PetroSync - Gas Turbine Failure AnalysisPetroSync - Gas Turbine Failure Analysis
PetroSync - Gas Turbine Failure Analysis
PetroSync
 
PetroSync - Acoustic and Flow Induced Vibration
PetroSync - Acoustic and Flow Induced VibrationPetroSync - Acoustic and Flow Induced Vibration
PetroSync - Acoustic and Flow Induced Vibration
PetroSync
 
PetroSync - Carbonate Reservoir Characterization
PetroSync - Carbonate Reservoir CharacterizationPetroSync - Carbonate Reservoir Characterization
PetroSync - Carbonate Reservoir Characterization
PetroSync
 
PetroSync - Well Completion and Workover
PetroSync - Well Completion and WorkoverPetroSync - Well Completion and Workover
PetroSync - Well Completion and Workover
PetroSync
 
PetroSync - Offshore Marine Operation
PetroSync - Offshore Marine OperationPetroSync - Offshore Marine Operation
PetroSync - Offshore Marine Operation
PetroSync
 
PetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling OptimisationPetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling Optimisation
PetroSync
 
PetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving Management
PetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving ManagementPetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving Management
PetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving Management
PetroSync
 
PetroSync - API 579 Fitness for Service
PetroSync - API 579 Fitness for ServicePetroSync - API 579 Fitness for Service
PetroSync - API 579 Fitness for Service
PetroSync
 
PetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded Formations
PetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded FormationsPetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded Formations
PetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded Formations
PetroSync
 
PetroSync - Applied Reservoir Engineering
PetroSync - Applied Reservoir EngineeringPetroSync - Applied Reservoir Engineering
PetroSync - Applied Reservoir Engineering
PetroSync
 
PetroSync - Fractured Reservoir Modeling with Application to Fractured Basement
PetroSync - Fractured Reservoir Modeling with Application to Fractured BasementPetroSync - Fractured Reservoir Modeling with Application to Fractured Basement
PetroSync - Fractured Reservoir Modeling with Application to Fractured Basement
PetroSync
 
PetroSync - Financial Assets Valuation for Oil & Gas
PetroSync - Financial Assets Valuation for Oil & GasPetroSync - Financial Assets Valuation for Oil & Gas
PetroSync - Financial Assets Valuation for Oil & Gas
PetroSync
 

More from PetroSync (20)

PetroSync - API Specification Q1 9th Edition Quality Management System Traini...
PetroSync - API Specification Q1 9th Edition Quality Management System Traini...PetroSync - API Specification Q1 9th Edition Quality Management System Traini...
PetroSync - API Specification Q1 9th Edition Quality Management System Traini...
 
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource DocumentPetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
 
PetroSync - Surface Geochemical Exploration for Oil and Gas
PetroSync - Surface Geochemical Exploration for Oil and GasPetroSync - Surface Geochemical Exploration for Oil and Gas
PetroSync - Surface Geochemical Exploration for Oil and Gas
 
PetroSync - Geological Interpretation of Well Logs
PetroSync - Geological Interpretation of Well LogsPetroSync - Geological Interpretation of Well Logs
PetroSync - Geological Interpretation of Well Logs
 
PetroSync - Chemically Enhanced Water Alternating Gas
PetroSync - Chemically Enhanced Water Alternating GasPetroSync - Chemically Enhanced Water Alternating Gas
PetroSync - Chemically Enhanced Water Alternating Gas
 
PetroSync - Budgeting and Forecasting in Oil & Gas Industry
PetroSync - Budgeting and Forecasting in Oil & Gas IndustryPetroSync - Budgeting and Forecasting in Oil & Gas Industry
PetroSync - Budgeting and Forecasting in Oil & Gas Industry
 
PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...
PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...
PetroSync - Practical Accounting in Joint Ventures & Production Sharing Contr...
 
PetroSync - Drilling Engineering for Non-Drilling Engineer
PetroSync - Drilling Engineering for Non-Drilling EngineerPetroSync - Drilling Engineering for Non-Drilling Engineer
PetroSync - Drilling Engineering for Non-Drilling Engineer
 
PetroSync - Gas Turbine Failure Analysis
PetroSync - Gas Turbine Failure AnalysisPetroSync - Gas Turbine Failure Analysis
PetroSync - Gas Turbine Failure Analysis
 
PetroSync - Acoustic and Flow Induced Vibration
PetroSync - Acoustic and Flow Induced VibrationPetroSync - Acoustic and Flow Induced Vibration
PetroSync - Acoustic and Flow Induced Vibration
 
PetroSync - Carbonate Reservoir Characterization
PetroSync - Carbonate Reservoir CharacterizationPetroSync - Carbonate Reservoir Characterization
PetroSync - Carbonate Reservoir Characterization
 
PetroSync - Well Completion and Workover
PetroSync - Well Completion and WorkoverPetroSync - Well Completion and Workover
PetroSync - Well Completion and Workover
 
PetroSync - Offshore Marine Operation
PetroSync - Offshore Marine OperationPetroSync - Offshore Marine Operation
PetroSync - Offshore Marine Operation
 
PetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling OptimisationPetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling Optimisation
 
PetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving Management
PetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving ManagementPetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving Management
PetroSync - TEMA & HTRI-Heat Exchanger Design & Cost Saving Management
 
PetroSync - API 579 Fitness for Service
PetroSync - API 579 Fitness for ServicePetroSync - API 579 Fitness for Service
PetroSync - API 579 Fitness for Service
 
PetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded Formations
PetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded FormationsPetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded Formations
PetroSync - Applied Petrophysics for Low Resistivity Thin-Bedded Formations
 
PetroSync - Applied Reservoir Engineering
PetroSync - Applied Reservoir EngineeringPetroSync - Applied Reservoir Engineering
PetroSync - Applied Reservoir Engineering
 
PetroSync - Fractured Reservoir Modeling with Application to Fractured Basement
PetroSync - Fractured Reservoir Modeling with Application to Fractured BasementPetroSync - Fractured Reservoir Modeling with Application to Fractured Basement
PetroSync - Fractured Reservoir Modeling with Application to Fractured Basement
 
PetroSync - Financial Assets Valuation for Oil & Gas
PetroSync - Financial Assets Valuation for Oil & GasPetroSync - Financial Assets Valuation for Oil & Gas
PetroSync - Financial Assets Valuation for Oil & Gas
 

Recently uploaded

SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
ssuserf63bd7
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
CIOWomenMagazine
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 

Recently uploaded (9)

SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 

PetroSync - Auditing Project Performance & Project Control

  • 1. Supported By PETROSYNC’S COST ENGINEERING & PROJECT MANAGEMENT Your Key To Project Success by Ensuring Project is within Budget and Allocated Time 12 October —15 October 2015 Bangkok, Thailand AUDITINGPROJECTPERFORMANCE &PROJECTCONTROL
  • 2. 2 Our Auditing Project Performance & Project Control course is developed to help you learn the required skillsets to validate your project through auditing the limits of time, human resources, materials, budget, and specifications to ensure project success. COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL How Does This Course Benefits You? Success Criteria Development -Do you know how to determine "success criteria" for project audit? Pinpoint Critical Criteria in Capital Projects Evaluation Master the critical criteria in project evaluation by learning the causes of variances & program evaluation and review technique (PERT) to ensure better evaluation and management in projects. Evaluate the Strengths and Weaknesses in Projects Attain best skills in evaluating strengths and weaknesses in projects by learning the triple constraints of project performance and effective measures in auditing project performance. Adopt Consistent Process for Accessing Project Risk Handle project risk by adopting consistent process by learning the risk analysis approaches to minimize the risk and to ensure success in project Master Ways to Recover Troubled Projects Master the skills in recovering troubled projects by identifying the change within the project and determining the risk tolerances and learning the alternative constraints in managing. Gain best-in-industry practices and benchmarks to ensure project success Learn the best practices and benchmarks in auditing project performance by practising to measure the triple constraints of project management and risk that ensure project success. Development of "Lessons Learned" on the project - Do you know this can help improve project performance? Effective measures for auditing project performance and controlling projects is the key to any project’s success. In this course, you will discover proven ways to work within your identified constraints, without letting predefined limits curtail creativity and innovation. general@petrosync.com | +65 6451 4500 | www.petrosync.com Course Overview Course Design This course focuses on the hands-on training and experience, practicing art of auditing your project against the project requirements documents, risk management plans, and budget estimates. Includes Specific and Practical Case Studies You will also learn the best industry practices used to measure the triple constraints of project management and risk that ensure project success and techniques for estimating and forecasting future performance of your project.
  • 3. 3 COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL PetroSync Distinguished Instructor Who Needs This Program Practical & Consulting Over 23 years in project audit and management and was a Master Business Analyst. His experience includes several multi- million dollar international projects. Training Has delivered this course in several oil & gas companies, and it has been well-rated from the past attendees. Regional Clientele base is from the SEAsian region, as well as in EU, and AUS Awards  PMI Project Management Professional (PMP) Mr. William H. Volpé III PMP, CET, GWCPM, GWCBA. President & CEO The Volpe Consortium, Inc.  People involved in Project Auditing and Management., Project & Cost Control, Internal Audit, Risk Management, Project Planning, Project Quality Assurance & Process Improvement Job Titles Include: Project Auditor Financial Controller Project Controller Contract Engineers Project Planner Project Manager Schedule Control Engineers Project Engineers PetroSync Inhouse Solutions PetroSync can tailor our courses to meet your specific needs at your preferred location and schedule. Contact us for more information at +65 6415 4500 or email to general @petrosync.com PetroSync Quality Assurance All PetroSync courses are developed with top quality to address all your training needs and purposes. Our courses are vetted strictly to ensure that we always deliver the best courses with the best industry expert. general@petrosync.com | +65 6451 4500 | www.petrosync.com 08:00—09:00 Registration (Day 1) 13:00—14:00 Lunch 09:00—11:00 Session I 14:00—15:30 Session III 11:00—11.15 Refreshment Session I 15:30—15:45 Refreshment Session II 11:15—13:00 Session II 15:45—17:00 Session Iv (Last Session) Course Schedule
  • 4. 4 COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL DAY 1 Assessing Team Health During a Project Audit Leadership and Management  What is leadership?  The difference between leadership and management  Articulate your leadership vision, in light of the assessment, and consider the best way(s) to realize it  Processes for establishing direction, aligning people, and motivating people to follow your vision  Identifying different leadership styles Leading Effective Teams  What is a team?  The stages of team development  Forming/Storming/Norming/Performing/Adjourning  Leading & maintaining effective, productive teams DAY 2 Project Management Governance  Projct management life-cycle and governance  Reviews vs. Audits  Planning tools  The triple constraints and stakeholder management  Discussion: Project Requirements Document  Discussion: Work Breakdown Structure (WBS) Estimating for Scheduling & Cost Control  Using estimates for scheduling and cost control  The estimating guideline  Levels of estimating and estimate types Top-down vs. bottom-up Order of magnitude Budget Definitive  Four estimating methodologies Bottom-up Parametric Supplier bids Analogous Resource Allocation & Estimating  Cost types and categories  Identify controllable costs Resource Material Direct Indirect  Program Evaluation and Review Technique (PERT) - Planning and controlling risk with contingency  Building the project resource pool Using resources to build estimates The responsibility matrix  Time-controlled estimates  Resource-limited estimates Course Agenda — 4 Days DAY 3 Scheduling - Part 2  Basic scheduling and network calculations  Exercises: Build a complex scheduling network  Advanced precedence relationships and the critical path  Alternative constraints  Gantt and milestone charts The Baseline and Cost Curves  Establishing baselines  Understanding types of baselines  Time-phased distribution of costs  Cumulative cost curves—Presenting Project Health  Managing Change Within The Project  The process of control  Earned Value Management (EVM) - Objective assessment of variance and performance  Identifying sources of change  Screening change  Updating the project plan  Communicating change Project Evaluation and Forecasting  Causes of variances  Establishing the “data date” for evaluation  Controlling costs late in the project  Controlling schedule late in the project Register For This Course Now! Kindly fill up your particulars in the registration form placed at the end of this brochure, and send it to us or email to registration@petrosync.com general@petrosync.com | +65 6451 4500 | www.petrosync.com DAY 2 (Continued) Scheduling - Part 1  Scheduling network  Validating schedules  Basic project activities relationships—Arrow diagrams  Exercises: Precedence diagrams process
  • 5. 5 COST ENGINEERING & PROJECT MANAGEMENT | AUDITING PROJECT PERFORMANCE & PROJECT CONTROL Project Audit and Earned-Value Forecasting  Critical components of the project audit  Sample project audit process  Considerations in establishing a monitoring system  Exercises: Earned-value forecasting  Advanced earned-value forecasting tools Analysis Fundamentals  Risk probability and impact  Presenting risk  Risk analysis approaches Qualitative Quantitative Descriptive  Estimating methods and idea-generation tools Analogy techniques Checklists, Questionnaires, and Templates Expert interview Delphi technique Brainstorming Nominal group technique Crawford slip method SWOT analysis Prototyping Affinity Digramming Impact Analysis and Risk Assessment  Determining risk tolerances  Analyzing risks  Impact anlaysis Project cost impacts Project schedule impacts Project scope impacts  Risk assessment matrix Analyzing and Prioritizing Risk  Risk-based financial tools and techniques  Expected-value analysis  Decision trees DAY 4 Register For This Course Now! Kindly fill up your particulars in the registration form placed at the end of this brochure, and send it to us or email to registration@petrosync.com general@petrosync.com | +65 6451 4500 | www.petrosync.com You Might Also Be Interested In: Analysis & Modeling for Cost, Economics & Risk 27-29 July 2015 | Kuala Lumpur, Malaysia Successful Project Cost Estimation & Control 7-11 September 2015 | Kuala Lumpur, Malaysia Cost Engineering Intensive 28 Sept-1 Oct 2015 | Kuala Lumpur, Malaysia
  • 6. 6 By Credit Card: Please debit my credit card: Visa MasterCard AMEX Security Code: Card Number: Expiry Date: Name Printed on Card: By Direct Transfer: Please quote invoice number(s) on remittance advice PetroSync Global Pte Ltd Bank Details: Account Name: PetroSync Global Pte Ltd Bank Name: DBS Bank Ltd Bank Code: 7171—Bank Swift Code: DBSSSGSGXXX—Branch Code: 288 Account No: SGD: 288-901898-0 USD: 0288-002682-01-6 Bank Address: 12 Marina Boulevard, Level 3. Marina Bay Financial Centre Tower 3. Singapore 018982. All bank charges to be borne by payer. Please ensure that PetroSync Global Pte Ltd receives the full invoiced amount. Title : Auditing Project Performance & Project Control Date : 12-15 October, 2015 Location : Bangkok, Thailand COURSE DETAILS INVESTMENT PACKAGE DATELINE FULL MASTERCLASS Standard Price 9 October 2015 USD 3,595 Early Bird Offer 17 July 2015 USD 3,395 Group Discount (3 or more Delegates) 9 October 2015 USD 3,295 INVESTMENT PACKAGES (Please Circle) Group Discount is based on Standard Price *To enjoy the promotion & discount offer, payment must be made before dateline * For 7 or more delegates, please inquire for more attractive package. * Prices include lunches, refreshments and materials. Promotion & discount cannot be combined with other promotional offers. * Important: Please note that registration without payment will incur a SGD 200 administration fee. COURSE CONSULTANT Name : Cay Aagen Email : registration@petrosync.com Phone : +65 6415 4500 Fax : +65 6415 4322 TERMS AND CONDITIONS DISCLAIMER Please note that trainers and topics were confirmed at the time of publishing; however, PetroSync may necessitate substitutions, alterations or cancellations of the trainers or topics. As such, PetroSync reserves the right to change or cancel any part of its published courseme due to unforeseen circumstances. Any substitutions or alterations will be updated on our web page as soon as possible. DATA PROTECTION The information you provide will be safeguarded by PetroSync that may be used to keep you informed of relevant products and services. As an international group we may transfer your data on a global basis for the purpose indicated above. If you do not want us to share your information with other reputable companies, please tick this box CANCELLATION POLICY You may substitute delegates at any time as long as reasonable advance notice is given to PetroSync. For any cancellation received in writing not less than fourteen (14) working days prior to the training course, you will receive credit voucher less a SGD $200 administration fee and any related bank or credit card charges. Delegates who cancel less than fourteen (14) working days of the training course, or who do not attend the course, are liable to pay the full course fee and no refunds will be granted. In the event that PetroSync cancels or postpones an event for any reason and that the delegate is unable or unwilling to attend in on the rescheduled date, you will receive a credit voucher for 100% of the contract fee paid. You may use this credit voucher for another PetroSync to be mutually agreed with PetroSync, which must occur within a year from the date of postponement. PetroSync is not responsible for any loss or damage as a result of the cancellation policy. PetroSync will assume no liability whatsoever in the event this event is cancelled, rescheduled or postponed due to any Act of God, fire, act of government or state, war, civil commotion, insurrection, embargo, industrial action, or any other reason beyond management control. CERTIFICATE OF ATTENDANCE 70% attendance is required for PetroSync’s Certificate of Attendance DETAILS Please accept our apologies for mail or email that is incorrectly addressed. Please email us at registration@petrosync.com and inform us of any incorrect details. We will amend them accordingly. CHARGES & FEE(S) - For Payment by Direct Telegraphic Transfer, client has to bear both local and oversea bank charges. - For credit card payment, there is additional 4% credit card processing fee. 1st Delegate Name: Direct Line Number: Email: Job Title: Department: Head of Department: Mr Mrs Ms Dr Others 2nd Delegate Name: Direct Line Number: Email: Job Title: Department: Head of Department: Mr Mrs Ms Dr Others 3rd Delegate Name: Direct Line Number: Email: Job Title: Department: Head of Department: Mr Mrs Ms Dr Others Attention Invoice to: Direct Line Number: Fax: Company: Industry: Address: Postcode: Country: Email: Please note: - Indicate if you have already registered by Phone Fax Email Web - If you have not received an acknowledgement before the training, please call us to confirm your booking. CONFIRMATION I agree to PetroSync’s terms & conditions, payment terms and cancellation policy. Authorized Signature: PAYMENT TERMS : Payment is due in full at the time of registration. Full payment is mandatory for event attendance. PAYMENT METHOD INVOICE DETAILS DELEGATES DETAILS