PATTERN
PRODUCTION
- SPE Team
Definition:
Pattern production is a fixed schedule
production where set of parts are
arranged in a sequence.
Basic Principles:
i) Fixed time variable quantity
ii) Fixed quantity variable time
Basic Principles:
i) Fixed time variable quantity
ii) Fixed quantity variable time
Fixed time variable quantity
09.00
10.00
10.00
11.00
11.00
12.00
12.00
13.00
13.00
14.00
Fixed
Time
Variable
quantity A -90
Fixed quantity variable time
Fixed
quantity
Variable
time
09.00
10.00
10.00
11.00
11.00
12.00
(Kanban A = 90)
A -100
In this case, wait till the
Kanban qty (A) comes
to 100
In this case, regardless of
qty start at 9.00 am
WHY Pattern Production?
1. Capacity without change over is ok
- Pattern Production not required
1. Capacity without change over is ok
- Pattern Production not required
- Our total load time is less than the shift time
WHY Pattern Production?
1. Capacity without change over is ok
- Pattern Production not required
2. Capacity with change over is ok
- Pattern Production not mandatory
2. Capacity with change over is ok
- Pattern Production not mandatory
- Our total load time (With changeover) is less than the shift time
WHY Pattern Production?
1. Capacity without change over is ok
- Pattern Production not required
2. Capacity with change over is ok
- Pattern Production not mandatory
3. Capacity without change over is not ok
- Capacity constraint cannot meet the customer demand
3. Capacity without change over is not ok
- Capacity constraint cannot meet the customer demand
- Our total load time is greater than the shift time (Capacity
constraint)
WHY Pattern Production?
1. Capacity without change over is ok
- Pattern Production not required
2. Capacity with change over is ok
- Pattern Production not mandatory
3. Capacity without change over is not ok
- Capacity constraint cannot meet the customer demand
4. Capacity without change over is ok and capacity with changeover is not ok
- Pattern production is mandatory
4. Capacity without change over is ok and capacity with changeover is not ok
- Pattern production is mandatory
Capacity without
changeover is ok
Capacity with
changeover not ok
We should
go for
pattern
Data required for preparing the Pattern production
1. Number of machines
2. Production capacity (SPM)
3. Volume required per day
4. Dandori time and material loading time (Minutes)
5. Total Avl. working time in a day (minutes)
6. Total Part numbers (Models / Variants)
Pattern production
Example:
Capacity without Changeover is ok Capacity with Changeover is not ok
Lot size calculation:
=Requirement per shift X number of patterns
Lot size calculation:
=Requirement per shift X number of patterns
Example:
Going for 01 pattern, SPM is 6 then
A = 300 X 1 =300/6 = 50min (Load time = 50 +30 (dandori))
Going for 02 pattern, SPM is 6
A = 300 X 2 = 600/6 = 100min (Load time = 100 + 30 (dandori))
Similarly do this calculation for all parts and check on which pattern
the load time is less than the shift time.
.
.
.
E & F
parts Not
able to
complete
Trail 1
Trail 3
Able to
satisfy
customer
requirement
Pattern production
Stop time
(can be used for kaizen
and human devp.)
Deciding the store stock for the above example
For 03 pattern how much stock should we keep.
Store Stock:
= Lot size (Req. per shift x no. of patterns) + Safety stock(01 shift qty)
A = (300*3)+300=1200
Min Max for part number A
Max = 1200 and Min = 300
Benefits of Pattern production
 Effective utilization of all resources.
 Elimination of daily production planning.
 Unplanned O.T is eliminated.
 Variation in production in minimized (helps in
maintaining stock)
Pattern production
Pattern production

More Related Content

What's hot

Cellular layout/Manufacturing
Cellular layout/ManufacturingCellular layout/Manufacturing
Cellular layout/ManufacturingFahad Ali
 
Measurement System Analysis (MSA)
Measurement System Analysis (MSA)Measurement System Analysis (MSA)
Measurement System Analysis (MSA)Ram Kumar
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleFrank-G. Adler
 
Learning to see (VSM)
Learning to see (VSM)Learning to see (VSM)
Learning to see (VSM)Mohamed Effat
 
New Employee Lean Orientation
New Employee Lean OrientationNew Employee Lean Orientation
New Employee Lean Orientationflevko
 
Problem solving techniques
Problem solving techniquesProblem solving techniques
Problem solving techniquesAhsan Saleem
 
7 Quality Control Tools (SQC Model) [MARCH 2009]
7 Quality Control Tools (SQC Model) [MARCH 2009]7 Quality Control Tools (SQC Model) [MARCH 2009]
7 Quality Control Tools (SQC Model) [MARCH 2009]Fahad Mahmud Mirza
 
Ishikawa fishbone diagram
Ishikawa fishbone diagramIshikawa fishbone diagram
Ishikawa fishbone diagramgarvsuthar
 
Timwoods- Lean Manufacturing
Timwoods- Lean ManufacturingTimwoods- Lean Manufacturing
Timwoods- Lean Manufacturinglakshya bhardwaj
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)Inter Alliance Werardt
 
Fishbone analysis
Fishbone analysisFishbone analysis
Fishbone analysisTarun Yadav
 
Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...Sumit Bhattacharya
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basicssarah bridge
 

What's hot (20)

Visual Management by Operational Excellence Consulting
Visual Management by Operational Excellence ConsultingVisual Management by Operational Excellence Consulting
Visual Management by Operational Excellence Consulting
 
Cellular layout/Manufacturing
Cellular layout/ManufacturingCellular layout/Manufacturing
Cellular layout/Manufacturing
 
Qc story
Qc storyQc story
Qc story
 
Measurement System Analysis (MSA)
Measurement System Analysis (MSA)Measurement System Analysis (MSA)
Measurement System Analysis (MSA)
 
implementation of 5s
implementation of 5simplementation of 5s
implementation of 5s
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training Module
 
Learning to see (VSM)
Learning to see (VSM)Learning to see (VSM)
Learning to see (VSM)
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
5 whys
5 whys5 whys
5 whys
 
The Six Big Losses of OEE
The Six Big Losses of OEEThe Six Big Losses of OEE
The Six Big Losses of OEE
 
New Employee Lean Orientation
New Employee Lean OrientationNew Employee Lean Orientation
New Employee Lean Orientation
 
Problem solving techniques
Problem solving techniquesProblem solving techniques
Problem solving techniques
 
Visual Control and Management : Manufacturing Management
Visual Control and Management : Manufacturing ManagementVisual Control and Management : Manufacturing Management
Visual Control and Management : Manufacturing Management
 
7 Quality Control Tools (SQC Model) [MARCH 2009]
7 Quality Control Tools (SQC Model) [MARCH 2009]7 Quality Control Tools (SQC Model) [MARCH 2009]
7 Quality Control Tools (SQC Model) [MARCH 2009]
 
Ishikawa fishbone diagram
Ishikawa fishbone diagramIshikawa fishbone diagram
Ishikawa fishbone diagram
 
Timwoods- Lean Manufacturing
Timwoods- Lean ManufacturingTimwoods- Lean Manufacturing
Timwoods- Lean Manufacturing
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
 
Fishbone analysis
Fishbone analysisFishbone analysis
Fishbone analysis
 
Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...Application of value stream mapping for reduction of cycle time in machining ...
Application of value stream mapping for reduction of cycle time in machining ...
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basics
 

Similar to Pattern production

Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysisvideoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysisvideoaakash15
 
In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)Ankur Shukla
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industryGanesh TN
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxMukhtarMohamedAbdila
 
Balancing exercise for garment industry
Balancing exercise for garment industryBalancing exercise for garment industry
Balancing exercise for garment industryAdithy_Kottangal
 
Motion and time study english
Motion and time study englishMotion and time study english
Motion and time study englishNorhan Abd Elaziz
 
lecture 16 (2).pdfjgbggnygjtnygugjgjybughy
lecture 16 (2).pdfjgbggnygjtnygugjgjybughylecture 16 (2).pdfjgbggnygjtnygugjgjybughy
lecture 16 (2).pdfjgbggnygjtnygugjgjybughyvipulpawar19
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layoutsAkash Bakshi
 
Manufacturing planning and control systems
Manufacturing planning and control systemsManufacturing planning and control systems
Manufacturing planning and control systemshaitham shehata
 

Similar to Pattern production (20)

Line balancing
Line balancing Line balancing
Line balancing
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
 
Test
TestTest
Test
 
OEE
OEEOEE
OEE
 
Line Balancing In Garments Industry
Line Balancing In Garments IndustryLine Balancing In Garments Industry
Line Balancing In Garments Industry
 
Dore Dore case study
Dore Dore case studyDore Dore case study
Dore Dore case study
 
Ct6
Ct6Ct6
Ct6
 
Balancing exercise for garment industry
Balancing exercise for garment industryBalancing exercise for garment industry
Balancing exercise for garment industry
 
Motion and time study english
Motion and time study englishMotion and time study english
Motion and time study english
 
TPM Loss Analysis
TPM  Loss AnalysisTPM  Loss Analysis
TPM Loss Analysis
 
lecture 16 (2).pdfjgbggnygjtnygugjgjybughy
lecture 16 (2).pdfjgbggnygjtnygugjgjybughylecture 16 (2).pdfjgbggnygjtnygugjgjybughy
lecture 16 (2).pdfjgbggnygjtnygugjgjybughy
 
A line in apparel
A line in apparelA line in apparel
A line in apparel
 
Equipment Availability Analysis
Equipment Availability AnalysisEquipment Availability Analysis
Equipment Availability Analysis
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layouts
 
Manufacturing planning and control systems
Manufacturing planning and control systemsManufacturing planning and control systems
Manufacturing planning and control systems
 

More from Jitesh Gaurav (20)

What i es do iie iab v2
What i es do iie iab v2What i es do iie iab v2
What i es do iie iab v2
 
Weld material
Weld materialWeld material
Weld material
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Spi link
Spi linkSpi link
Spi link
 
6 Sigma - Chapter3
6 Sigma - Chapter36 Sigma - Chapter3
6 Sigma - Chapter3
 
6 Sigma - Chapter2
6 Sigma - Chapter26 Sigma - Chapter2
6 Sigma - Chapter2
 
6 Sigma - Chapter1
6 Sigma - Chapter16 Sigma - Chapter1
6 Sigma - Chapter1
 
6 Sigma - Chapter8
6 Sigma - Chapter86 Sigma - Chapter8
6 Sigma - Chapter8
 
6 Sigma - Chapter7
6 Sigma - Chapter76 Sigma - Chapter7
6 Sigma - Chapter7
 
6 Sigma - Chapter6
6 Sigma - Chapter66 Sigma - Chapter6
6 Sigma - Chapter6
 
6 Sigma - Chapter5
6 Sigma - Chapter56 Sigma - Chapter5
6 Sigma - Chapter5
 
6 Sigma - Chapter4
6 Sigma - Chapter46 Sigma - Chapter4
6 Sigma - Chapter4
 
Pattern production
Pattern productionPattern production
Pattern production
 
smed
smedsmed
smed
 
Methods of kaizen
Methods of kaizenMethods of kaizen
Methods of kaizen
 
Dfmea rating
Dfmea ratingDfmea rating
Dfmea rating
 
Qip
QipQip
Qip
 
Rodebaugh sixsigma[1]
Rodebaugh sixsigma[1]Rodebaugh sixsigma[1]
Rodebaugh sixsigma[1]
 
Tqm
TqmTqm
Tqm
 
Tpm+basics
Tpm+basicsTpm+basics
Tpm+basics
 

Recently uploaded

Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...vershagrag
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 

Recently uploaded (20)

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 

Pattern production

  • 2. Definition: Pattern production is a fixed schedule production where set of parts are arranged in a sequence. Basic Principles: i) Fixed time variable quantity ii) Fixed quantity variable time Basic Principles: i) Fixed time variable quantity ii) Fixed quantity variable time
  • 3. Fixed time variable quantity 09.00 10.00 10.00 11.00 11.00 12.00 12.00 13.00 13.00 14.00 Fixed Time Variable quantity A -90 Fixed quantity variable time Fixed quantity Variable time 09.00 10.00 10.00 11.00 11.00 12.00 (Kanban A = 90) A -100 In this case, wait till the Kanban qty (A) comes to 100 In this case, regardless of qty start at 9.00 am
  • 4. WHY Pattern Production? 1. Capacity without change over is ok - Pattern Production not required
  • 5. 1. Capacity without change over is ok - Pattern Production not required - Our total load time is less than the shift time
  • 6. WHY Pattern Production? 1. Capacity without change over is ok - Pattern Production not required 2. Capacity with change over is ok - Pattern Production not mandatory
  • 7. 2. Capacity with change over is ok - Pattern Production not mandatory - Our total load time (With changeover) is less than the shift time
  • 8. WHY Pattern Production? 1. Capacity without change over is ok - Pattern Production not required 2. Capacity with change over is ok - Pattern Production not mandatory 3. Capacity without change over is not ok - Capacity constraint cannot meet the customer demand
  • 9. 3. Capacity without change over is not ok - Capacity constraint cannot meet the customer demand - Our total load time is greater than the shift time (Capacity constraint)
  • 10. WHY Pattern Production? 1. Capacity without change over is ok - Pattern Production not required 2. Capacity with change over is ok - Pattern Production not mandatory 3. Capacity without change over is not ok - Capacity constraint cannot meet the customer demand 4. Capacity without change over is ok and capacity with changeover is not ok - Pattern production is mandatory
  • 11. 4. Capacity without change over is ok and capacity with changeover is not ok - Pattern production is mandatory Capacity without changeover is ok Capacity with changeover not ok We should go for pattern
  • 12. Data required for preparing the Pattern production 1. Number of machines 2. Production capacity (SPM) 3. Volume required per day 4. Dandori time and material loading time (Minutes) 5. Total Avl. working time in a day (minutes) 6. Total Part numbers (Models / Variants)
  • 13. Pattern production Example: Capacity without Changeover is ok Capacity with Changeover is not ok Lot size calculation: =Requirement per shift X number of patterns
  • 14. Lot size calculation: =Requirement per shift X number of patterns Example: Going for 01 pattern, SPM is 6 then A = 300 X 1 =300/6 = 50min (Load time = 50 +30 (dandori)) Going for 02 pattern, SPM is 6 A = 300 X 2 = 600/6 = 100min (Load time = 100 + 30 (dandori)) Similarly do this calculation for all parts and check on which pattern the load time is less than the shift time.
  • 15. . . . E & F parts Not able to complete Trail 1 Trail 3 Able to satisfy customer requirement Pattern production Stop time (can be used for kaizen and human devp.)
  • 16. Deciding the store stock for the above example For 03 pattern how much stock should we keep. Store Stock: = Lot size (Req. per shift x no. of patterns) + Safety stock(01 shift qty) A = (300*3)+300=1200 Min Max for part number A Max = 1200 and Min = 300
  • 17. Benefits of Pattern production  Effective utilization of all resources.  Elimination of daily production planning.  Unplanned O.T is eliminated.  Variation in production in minimized (helps in maintaining stock)