SlideShare a Scribd company logo
1 of 2
Product/Production Relationships
2.1 The ABC Company is planning a new product line and will build a new plant to manufacture the
parts for a new product line. The product line will include 50 different models. Annual production
of each model is expected to be 1000 units. Each product will be assembled of 400 components.
All processing of parts will be accomplished in one factory. There are an average of 6 processing
steps required to produce each component, and each processing step takes 1.0 minute (includes an
allowance for setup time and part handling). All processing operations are performed at
workstations, each of which includes a production machine and a human worker. If each
workstation requires a floor space of 250 ft2
, and the factory operates one shift (2000 hr/yr),
determine (a) how many production operations, (b) how much floorspace, and (c) how many
workers will be required in the plant.
Solution: This problem neglects the effect of assembly time.
(a) nof = PQnpno = 50(1000)(400)(6) = 120,000,000 operations in the factory per year.
(c) Total operation time = (120 x 106
ops)(1min./(60 min./hr)) = 2,000,000 hr/yr.
At 2000 hours/yr per worker, w =
2 000 000
2000
, , /
/ ker
hr yr
hr wor
= 1000 workers.
(b) Number of workstations n = w = 1000. Total floorspace = (1000 stations)(250 ft2
/station) = 250,000
ft2
2.2 The XYZ Company is planning to introduce a new product line and will build a new factory to
produce the parts and assembly the final products for the product line. The new product line will
include 100 different models. Annual production of each model is expected to be 1000 units. Each
product will be assembled of 600 components. All processing of parts and assembly of products
will be accomplished in one factory. There are an average of 10 processing steps required to
produce each component, and each processing step takes 30 sec. (includes an allowance for setup
time and part handling). Each final unit of product takes 3.0 hours to assemble. All processing
operations are performed at work cells that each includes a production machine and a human
worker. Products are assembled on single workstations consisting of two workers each. If each
work cell and each workstation require 200 ft2
, and the factory operates one shift (2000 hr/yr),
determine: (a) how many production operations, (b) how much floorspace, and (c) how many
workers will be required in the plant.
Solution: (a) Qf = PQ = 100(1000) = 100,000 products/yr
Number of final assembly operations = 100,000 asby ops/yr
Number of processing operations nof = PQnpno = 100(1000)(600)(10) = 600,000,000 proc ops/yr
(c) Total processing operation time = (600 x 106
ops)(0.5 min./(60 min./hr)) = 5,000,000 hr/yr.
Total assembly operation time = (100 x 103
asby ops)(3 hr/product) = 300,000 hr/yr
Total processing and assembly time = 5,300,000 hr/yr
At 2000 hours/yr per worker, w =
5 300 000
2000
, , /
/ ker
hr yr
hr wor
= 2650 workers.
(b) With 2 workers per workstation, n = w/2 = 2650/2 = 1325 workstations.
Total floorspace = (1325 stations)(200 ft2
/station) = 265,000 ft2
2.3 If the company in Problem 2.2 were to operate three shifts (6000 hr/yr) instead of one shift,
determine the answers to (a), (b), and (c).
Solution: (a) Same total number of processing and assembly operations but spread over three
shifts.
Number of final assembly operations = 100,000 asby ops/yr
Number of processing operations nof = PQnpno = 100(1000)(600)(10) = 600,000,000
operations/yr
(c) Same total number of workers required but spread over three shifts.
Total workers w = 2650 workers. Number of workers/shift = w/3 = 883.33 → 884
workers/shift.
(b) Number of workstations = 884/2 = 442 workstations.
Total floorspace = (442 stations)(200 ft2
/station) = 88,400 ft2
Production Concepts and Mathematical Models
2.4 A certain part is routed through six machines in a batch production plant. The setup and operation
times for each machine are given in the table below. The batch size is 100 and the average
nonoperation time per machine is 12 hours. Determine: (a) manufacturing lead time and (b)
production rate for operation 3.
Machine Setup time (hr.) Operation time (min.)
1 4 5.0
2 2 3.5
3 8 10.0
4 3 1.9
5 3 4.1
6 4 2.5
Solution: Average Tsu = (4 + 2 + 8 + 3 + 3 + 4)/6 = 24/6 = 4.0 hr
Average Tc = (5 + 3.5 + 10 + 1.9 + 4.1 + 2.5)/6 = 27/6 = 4.5 min
(a) MLT = 6(4.0 + 100(4.5/60) + 12) = 6(23.5) = 141 hr
(b) Rp for operation 3: Tp = [8.0 + 100(10/60)]/100 = 24.67/100 = 0.2467 hr/pc Rp = 4.05
pc/hr
2.5 Suppose the part in previous Problem 2.5 is made in very large quantities on a production line in
which an automated work handling system is used to transfer parts between machines. Transfer
time between stations = 15 s. The total time required to set up the entire line is 150 hours. Assume
that the operation times at the individual machines remain the same. Determine: (a) manufacturing
lead time for a part coming off the line, (b) production rate for operation 3, (c) theoretical
production rate for the entire production line?
Solution: (a) MLT = 6(10.25) = 61.5 min for a average part
MLT = 61.5/60 + 150 = 151.025 hr for first part including setup
(b) Tp for operation 3 = 10.25 min, Rp = 60/10.25 = 5.8536 pc/hr
(c) Theoretical production rate for line = 5.8536 pc/hr since station 3 is the bottleneck station on
the line.
2.6 The average part produced in a certain batch manufacturing plant must be processed through an
average six machines. Twenty (20) new batches of parts are launched each week. Average
operation time = 6 min., average setup time = 5 hours, average batch size = 25 parts, and average
nonoperation time per batch = 10 hr/machine. There are 18 machines in the plant. The plant
operates an average of 70 production hours per week. Scrap rate is negligible. Determine: (a)
manufacturing lead time for an average part, (b) plant capacity, (c) plant utilization. (d) How
would you expect the nonoperation time to be affected by the plant utilization?
Solution: (a) MLT = 6(5 + 25(0.1) + 10) = 105 hr
(b) Tp = (5 + 25 x 0.1)/25 = 0.30 hr/pc, Rp = 3.333 pc/hr. PC = 70(18)(3.333)/6 = 700 pc/week
(c) Parts launched per week = 20 x 25 = 500 pc/week. Utilization U = 500/700 = 0.7143 =
71.43%
(d) As utilization increases towards 100%, we would expect the nonoperation time to increase.
When the workload in the shop grows, the shop becomes busier, but it usually takes longer to get
the jobs out. As utilization decreases, we would expect the nonoperation time to decrease.
2.7 Based on the data in previous Problem 2.7 and your answers to that problem, determine the
average level of work-in-process (number of parts-in-process) in the plant.
Solution: Refers back to Problem 2.3
WIP =
AU PC MLT
SH
( )( )
=
( . )( . )( / )( )
/
1 0 0 7243 700 105
70
pc wk hr
hr wk
= 750 pc
2.8 An average of 20 new orders are started through a certain factory each month. On average, an
order consists of 50 parts to be processed through 10 machines in the factory. The operation time
per machine for each part = 15 min. The nonoperation time per order at each machine averages 8
hours, and the required setup time per order = 4 hours. There are 25 machines in the factory, 80%
of which are operational at any time (the other 20% are in repair or maintenance). The plant
operates 160 hours per month. However, the plant manager complains that a total of 100 overtime
machine-hours must be authorized each month in order to keep up with the production schedule.
(a) What is the manufacturing lead time for an average order? (b) What is the plant capacity (on a
monthly basis) and why must the overtime be authorized? (c) What is the utilization of the plant
according to the definition given in the text? (d) Determine the average level of work-in-process
(number of parts-in-process) in the plant.
Solution: (a) MLT = 10(4 + 50x0.25 + 8) = 245 hr/order
(b) Tp = (4 + 50x0.25)/50 = 16.5/50 = 0.33 hr/pc, Rp = 3.0303 pc/hr
PC = (25x0.80)(160)(3.0303)/10 = 969.7 pc/month
Parts launched per month = 20x25 = 1000 pc/month
Schedule exceeds plant capacity by 1000 - 969.7 = 30.3 pc. This requires overtime in the amount
= (30.303 pc x 10 machines)/(3.0303 pc/hr) = 100 hr.
(c) Utilization U = (1000 pc)/(969.7 pc) = 1.03125 = 103.125%
(d) WIP = (245 hr)(969.7 pc/mo)(1.03125)/(160 hr/mo) = 1531.25 parts

More Related Content

What's hot

INDUSTRIAL ENGINEERING - PLANT LAYOUT
INDUSTRIAL ENGINEERING -  PLANT LAYOUTINDUSTRIAL ENGINEERING -  PLANT LAYOUT
INDUSTRIAL ENGINEERING - PLANT LAYOUTBRS ENGINEERING
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancingRohit Goutam
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems Nityanand Yadav
 
Facility layout ppt
Facility layout pptFacility layout ppt
Facility layout pptAnju Rana
 
Introduction to Group technology
Introduction to Group technologyIntroduction to Group technology
Introduction to Group technologyHashim Hasnain Hadi
 
Flexible manufacturing syatem
Flexible manufacturing syatemFlexible manufacturing syatem
Flexible manufacturing syatemDobariya Gautam
 
79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancingJoseph Konnully
 
Performance Measures of Manufacturing System
Performance Measures of Manufacturing SystemPerformance Measures of Manufacturing System
Performance Measures of Manufacturing SystemDesignage Solutions
 
Lecture 25 flexible manufacturing systems [compatibility mode]
Lecture 25 flexible manufacturing systems [compatibility mode]Lecture 25 flexible manufacturing systems [compatibility mode]
Lecture 25 flexible manufacturing systems [compatibility mode]Dr.Muftooh Ur Rehman Siddiqi
 

What's hot (20)

Fms (1)
Fms (1)Fms (1)
Fms (1)
 
Chapter 6 mfg systems
Chapter 6    mfg systemsChapter 6    mfg systems
Chapter 6 mfg systems
 
INDUSTRIAL ENGINEERING - PLANT LAYOUT
INDUSTRIAL ENGINEERING -  PLANT LAYOUTINDUSTRIAL ENGINEERING -  PLANT LAYOUT
INDUSTRIAL ENGINEERING - PLANT LAYOUT
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems
 
OR 14 15-unit_3
OR 14 15-unit_3OR 14 15-unit_3
OR 14 15-unit_3
 
Facility layout ppt
Facility layout pptFacility layout ppt
Facility layout ppt
 
Method study
Method studyMethod study
Method study
 
Flexible Manufacturing Systems V2 090310
Flexible Manufacturing Systems V2 090310Flexible Manufacturing Systems V2 090310
Flexible Manufacturing Systems V2 090310
 
Introduction to Group technology
Introduction to Group technologyIntroduction to Group technology
Introduction to Group technology
 
Cad, cam, cim
Cad, cam, cimCad, cam, cim
Cad, cam, cim
 
Man and machine chart
Man and machine chartMan and machine chart
Man and machine chart
 
Manufacturing systems
Manufacturing systems Manufacturing systems
Manufacturing systems
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
Flexible manufacturing syatem
Flexible manufacturing syatemFlexible manufacturing syatem
Flexible manufacturing syatem
 
79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancing
 
Performance Measures of Manufacturing System
Performance Measures of Manufacturing SystemPerformance Measures of Manufacturing System
Performance Measures of Manufacturing System
 
CAD/CAM/CIM ( Lecture 2 model construction and product design)
CAD/CAM/CIM ( Lecture 2 model construction and product design)CAD/CAM/CIM ( Lecture 2 model construction and product design)
CAD/CAM/CIM ( Lecture 2 model construction and product design)
 
Lecture 25 flexible manufacturing systems [compatibility mode]
Lecture 25 flexible manufacturing systems [compatibility mode]Lecture 25 flexible manufacturing systems [compatibility mode]
Lecture 25 flexible manufacturing systems [compatibility mode]
 
Line balancing
Line balancingLine balancing
Line balancing
 

Similar to Test

Contoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturContoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturMahros Darsin
 
Chapter 4 product layout - 1st (3)
Chapter 4  product layout - 1st (3)Chapter 4  product layout - 1st (3)
Chapter 4 product layout - 1st (3)Shadina Shah
 
Decision policies for production networks
Decision policies for production networksDecision policies for production networks
Decision policies for production networksSpringer
 
Problem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docxProblem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docxsleeperharwell
 
Operational Research
Operational ResearchOperational Research
Operational ResearchBrendaGaytan6
 
CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
Examination paper of materials management
Examination paper of materials managementExamination paper of materials management
Examination paper of materials managementNMIMS ASSIGNMENTS HELP
 
Departmental Rate and Plantwide Rate
Departmental Rate and Plantwide RateDepartmental Rate and Plantwide Rate
Departmental Rate and Plantwide RateMaryhope Salili
 
flexible-manufacturing-systems
 flexible-manufacturing-systems flexible-manufacturing-systems
flexible-manufacturing-systemssabry said
 

Similar to Test (20)

Contoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturContoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas Manufaktur
 
8th Semester Mechanical Engineering (June/July-2015) Question Papers
8th Semester Mechanical Engineering  (June/July-2015) Question Papers8th Semester Mechanical Engineering  (June/July-2015) Question Papers
8th Semester Mechanical Engineering (June/July-2015) Question Papers
 
Chapter 4 product layout - 1st (3)
Chapter 4  product layout - 1st (3)Chapter 4  product layout - 1st (3)
Chapter 4 product layout - 1st (3)
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 
5271197.ppt
5271197.ppt5271197.ppt
5271197.ppt
 
Decision policies for production networks
Decision policies for production networksDecision policies for production networks
Decision policies for production networks
 
Problem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docxProblem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docx
 
5case
5case5case
5case
 
Operational Research
Operational ResearchOperational Research
Operational Research
 
Line balancing
Line balancing Line balancing
Line balancing
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
Line Balancing In Garments Industry
Line Balancing In Garments IndustryLine Balancing In Garments Industry
Line Balancing In Garments Industry
 
Examination paper of materials management
Examination paper of materials managementExamination paper of materials management
Examination paper of materials management
 
Departmental Rate and Plantwide Rate
Departmental Rate and Plantwide RateDepartmental Rate and Plantwide Rate
Departmental Rate and Plantwide Rate
 
Productivity
ProductivityProductivity
Productivity
 
flexible-manufacturing-systems
 flexible-manufacturing-systems flexible-manufacturing-systems
flexible-manufacturing-systems
 
Productivity.ppt
Productivity.pptProductivity.ppt
Productivity.ppt
 
Productivity (1)
 Productivity (1) Productivity (1)
Productivity (1)
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 

Recently uploaded (20)

Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 

Test

  • 1. Product/Production Relationships 2.1 The ABC Company is planning a new product line and will build a new plant to manufacture the parts for a new product line. The product line will include 50 different models. Annual production of each model is expected to be 1000 units. Each product will be assembled of 400 components. All processing of parts will be accomplished in one factory. There are an average of 6 processing steps required to produce each component, and each processing step takes 1.0 minute (includes an allowance for setup time and part handling). All processing operations are performed at workstations, each of which includes a production machine and a human worker. If each workstation requires a floor space of 250 ft2 , and the factory operates one shift (2000 hr/yr), determine (a) how many production operations, (b) how much floorspace, and (c) how many workers will be required in the plant. Solution: This problem neglects the effect of assembly time. (a) nof = PQnpno = 50(1000)(400)(6) = 120,000,000 operations in the factory per year. (c) Total operation time = (120 x 106 ops)(1min./(60 min./hr)) = 2,000,000 hr/yr. At 2000 hours/yr per worker, w = 2 000 000 2000 , , / / ker hr yr hr wor = 1000 workers. (b) Number of workstations n = w = 1000. Total floorspace = (1000 stations)(250 ft2 /station) = 250,000 ft2 2.2 The XYZ Company is planning to introduce a new product line and will build a new factory to produce the parts and assembly the final products for the product line. The new product line will include 100 different models. Annual production of each model is expected to be 1000 units. Each product will be assembled of 600 components. All processing of parts and assembly of products will be accomplished in one factory. There are an average of 10 processing steps required to produce each component, and each processing step takes 30 sec. (includes an allowance for setup time and part handling). Each final unit of product takes 3.0 hours to assemble. All processing operations are performed at work cells that each includes a production machine and a human worker. Products are assembled on single workstations consisting of two workers each. If each work cell and each workstation require 200 ft2 , and the factory operates one shift (2000 hr/yr), determine: (a) how many production operations, (b) how much floorspace, and (c) how many workers will be required in the plant. Solution: (a) Qf = PQ = 100(1000) = 100,000 products/yr Number of final assembly operations = 100,000 asby ops/yr Number of processing operations nof = PQnpno = 100(1000)(600)(10) = 600,000,000 proc ops/yr (c) Total processing operation time = (600 x 106 ops)(0.5 min./(60 min./hr)) = 5,000,000 hr/yr. Total assembly operation time = (100 x 103 asby ops)(3 hr/product) = 300,000 hr/yr Total processing and assembly time = 5,300,000 hr/yr At 2000 hours/yr per worker, w = 5 300 000 2000 , , / / ker hr yr hr wor = 2650 workers. (b) With 2 workers per workstation, n = w/2 = 2650/2 = 1325 workstations. Total floorspace = (1325 stations)(200 ft2 /station) = 265,000 ft2 2.3 If the company in Problem 2.2 were to operate three shifts (6000 hr/yr) instead of one shift, determine the answers to (a), (b), and (c). Solution: (a) Same total number of processing and assembly operations but spread over three shifts. Number of final assembly operations = 100,000 asby ops/yr Number of processing operations nof = PQnpno = 100(1000)(600)(10) = 600,000,000 operations/yr (c) Same total number of workers required but spread over three shifts. Total workers w = 2650 workers. Number of workers/shift = w/3 = 883.33 → 884 workers/shift. (b) Number of workstations = 884/2 = 442 workstations. Total floorspace = (442 stations)(200 ft2 /station) = 88,400 ft2 Production Concepts and Mathematical Models 2.4 A certain part is routed through six machines in a batch production plant. The setup and operation times for each machine are given in the table below. The batch size is 100 and the average
  • 2. nonoperation time per machine is 12 hours. Determine: (a) manufacturing lead time and (b) production rate for operation 3. Machine Setup time (hr.) Operation time (min.) 1 4 5.0 2 2 3.5 3 8 10.0 4 3 1.9 5 3 4.1 6 4 2.5 Solution: Average Tsu = (4 + 2 + 8 + 3 + 3 + 4)/6 = 24/6 = 4.0 hr Average Tc = (5 + 3.5 + 10 + 1.9 + 4.1 + 2.5)/6 = 27/6 = 4.5 min (a) MLT = 6(4.0 + 100(4.5/60) + 12) = 6(23.5) = 141 hr (b) Rp for operation 3: Tp = [8.0 + 100(10/60)]/100 = 24.67/100 = 0.2467 hr/pc Rp = 4.05 pc/hr 2.5 Suppose the part in previous Problem 2.5 is made in very large quantities on a production line in which an automated work handling system is used to transfer parts between machines. Transfer time between stations = 15 s. The total time required to set up the entire line is 150 hours. Assume that the operation times at the individual machines remain the same. Determine: (a) manufacturing lead time for a part coming off the line, (b) production rate for operation 3, (c) theoretical production rate for the entire production line? Solution: (a) MLT = 6(10.25) = 61.5 min for a average part MLT = 61.5/60 + 150 = 151.025 hr for first part including setup (b) Tp for operation 3 = 10.25 min, Rp = 60/10.25 = 5.8536 pc/hr (c) Theoretical production rate for line = 5.8536 pc/hr since station 3 is the bottleneck station on the line. 2.6 The average part produced in a certain batch manufacturing plant must be processed through an average six machines. Twenty (20) new batches of parts are launched each week. Average operation time = 6 min., average setup time = 5 hours, average batch size = 25 parts, and average nonoperation time per batch = 10 hr/machine. There are 18 machines in the plant. The plant operates an average of 70 production hours per week. Scrap rate is negligible. Determine: (a) manufacturing lead time for an average part, (b) plant capacity, (c) plant utilization. (d) How would you expect the nonoperation time to be affected by the plant utilization? Solution: (a) MLT = 6(5 + 25(0.1) + 10) = 105 hr (b) Tp = (5 + 25 x 0.1)/25 = 0.30 hr/pc, Rp = 3.333 pc/hr. PC = 70(18)(3.333)/6 = 700 pc/week (c) Parts launched per week = 20 x 25 = 500 pc/week. Utilization U = 500/700 = 0.7143 = 71.43% (d) As utilization increases towards 100%, we would expect the nonoperation time to increase. When the workload in the shop grows, the shop becomes busier, but it usually takes longer to get the jobs out. As utilization decreases, we would expect the nonoperation time to decrease. 2.7 Based on the data in previous Problem 2.7 and your answers to that problem, determine the average level of work-in-process (number of parts-in-process) in the plant. Solution: Refers back to Problem 2.3 WIP = AU PC MLT SH ( )( ) = ( . )( . )( / )( ) / 1 0 0 7243 700 105 70 pc wk hr hr wk = 750 pc 2.8 An average of 20 new orders are started through a certain factory each month. On average, an order consists of 50 parts to be processed through 10 machines in the factory. The operation time per machine for each part = 15 min. The nonoperation time per order at each machine averages 8 hours, and the required setup time per order = 4 hours. There are 25 machines in the factory, 80% of which are operational at any time (the other 20% are in repair or maintenance). The plant operates 160 hours per month. However, the plant manager complains that a total of 100 overtime machine-hours must be authorized each month in order to keep up with the production schedule. (a) What is the manufacturing lead time for an average order? (b) What is the plant capacity (on a monthly basis) and why must the overtime be authorized? (c) What is the utilization of the plant according to the definition given in the text? (d) Determine the average level of work-in-process (number of parts-in-process) in the plant. Solution: (a) MLT = 10(4 + 50x0.25 + 8) = 245 hr/order (b) Tp = (4 + 50x0.25)/50 = 16.5/50 = 0.33 hr/pc, Rp = 3.0303 pc/hr PC = (25x0.80)(160)(3.0303)/10 = 969.7 pc/month Parts launched per month = 20x25 = 1000 pc/month Schedule exceeds plant capacity by 1000 - 969.7 = 30.3 pc. This requires overtime in the amount = (30.303 pc x 10 machines)/(3.0303 pc/hr) = 100 hr. (c) Utilization U = (1000 pc)/(969.7 pc) = 1.03125 = 103.125% (d) WIP = (245 hr)(969.7 pc/mo)(1.03125)/(160 hr/mo) = 1531.25 parts