SlideShare a Scribd company logo
Overview of Key Terms for a Water Purchase
Agreement between the San Diego County Water
Authority and Poseidon Resources




                             San Diego County Water Authority
                            Water Planning Committee Meeting
                                                          1
                                           September 27, 2012
                                                            1
Proposed WPA Overview
• 50 MGD desalination plant located on the site of the
  Encina Power Station (Poseidon)
• 10 mile 54-inch diameter conveyance pipeline (Poseidon)
• Connection to Water Authority aqueduct Pipeline 3
  (Poseidon)
• Relining of 5.5 mile reach of Pipeline 3 (Water Authority)
• Improvements at the TOVWTP to accommodate
  desalinated water flows (Water Authority)

                                                           3
•   30 years from the date of commercial operation
•   Subject to early buy-out provisions
•   Can be extended for up to 3 years due to Force
    Majeure events




                                                     4
• Water Authority
• Project Company: Poseidon
• EPC Contractor: Kiewit-Shea Joint Venture
• Process Engineering and Equipment:

• IDE Operating Services Provider: IDE




                                              5
 Developer/Owner of the Plant
  Poseidon Resources (Channelside)
  Poseidon to finance through a combination of debt (82%) and
   equity (18%)
     Debt to be provided through tax-exempt Private Activity Bonds (PAB’s)
     Equity to be provided by Stonepeak

 Construction/Operation of the Plant
  Contractor – Joint venture of Kiewit Infrastructure West and
   J.F. Shea Construction
  IDE Technologies is process technology provider
  Plant Operations and Maintenance also to be provided by IDE
                                                                              6
 Owner of the Conveyance Pipeline
  Water Authority will own and maintain the Conveyance Pipeline
    Not subject to franchise fees or possessory interest taxes

  Finance using municipal purpose bonds issued by California
   Pollution Control Financing Authority (CPCFA)
    Bonds maintain risk transfer to Poseidon by insulating the Water
     Authority from financial responsibility if Poseidon is unable to perform
    Exempt from AMT – Lower interest rate




                                                                                7
 Construction of the Conveyance Pipeline
  Design Build Agreement between the Water Authority and
   Poseidon
  Contractor – Kiewit/Shea Joint Venture

 Construction of the P3 Relining and TOVWTP
  Improvements
  Water Authority will be responsible to finance and complete
   these improvements



                                                                 8
• Permit, Design and Build the Desal Plant (WPA)
• Permit, Design and Build the Conveyance Pipeline
  (Design-Build Agreement)
• Operate and Maintain the Desal Plant
• Supply Product Water




                                                     9
• “Take or Pay” for Product Water if it meets
  specifications (minimum of 48,000 AF/Year)
• Timely Construction of TOVWTP
  Improvements and Pipeline 3 Rehabilitation
• Physically be able to receive Product Water
• Operate and Maintain the Conveyance Pipeline, the
  TOVWTP Improvements and Pipeline 3



                                                      10
• Equity Investment: $165 Million
• Project Financing: Non-Performance Risk
  Incentivizes Bondholders to Cure Breaches
• Letter of Credit to Secure Performance

• Letter of Credit to Assure Financing




                                              11
• Product Water Quality Guarantee
   • Compliance with all federal and state drinking water
     regulations
   • Additional standards for certain water quality parameters
• Minimum Product Water Delivery Guarantee
   • Annual supply to meet Water Authority demands (between
     48,000 and 56,000 acre-feet)
• Water Ordering Rights
   • Water Authority rights to adjust delivery orders to reflect
     seasonal and daily demand changes

                                                                   12
• Purchase options at Water Authority sole discretion
• Convenience Termination
   • Early buy-out provision

• End of Term
   • $1 end of 30-year term
• Event of Default
• Unavailability of Financing for Required Improvements



                                                        13
• Poseidon
  • Events include:
    ▪    Failure to pass performance testing by the agreed upon Commercial Operations
         Date
    ▪    Poseidon project company bankruptcy or abandonment of the project
    ▪    Repeated violations of Primary Drinking Water Standards
    ▪    Multiple notices of violation issued by a regulatory agency
    ▪    Deliveries less than 75 percent of the annual amount
    ▪    Failure to make Contracted Shortfall Payments

  • Water Authority has the option to terminate the agreement
• Water Authority
  • Failure to pay undisputed bill amounts owed Poseidon within
        45 days of the due date                                                         14
Proposed WPA
Organization of Agreement
 WPA consists of agreement text and technical appendices
   26 articles (sections)
   18 technical appendices (reviewed at Special Board Meeting of Sept 20, 2012)




 Article 1 – Definitions and Interpretation
   Detailed definitions and interpretations of key terms used in the agreement
    and appendices
       Includes cross references to specific articles within the agreement




                                                                                  16
 Article 2 – Representations and Warranties
   Representations by the Water Authority and Poseidon that the proposed
    WPA is based upon
       Includes statements regarding correctness of information provided,
        sufficiency of financing to build facilities and Poseidon's interest in plant site

 Article 3 – Term
   Agreement start date (contract execution date) and end date
   Provisions that “survive” past the end of the agreement
       E.g. records , property rights




                                                                                             17
 Article 4 – Contract Obligations Generally
   General obligations of the Water Authority and Poseidon during
    construction and operation
   Specifically addresses:
       Poseidon Letter of Credit requirements
       Poseidon responsibility for design, construction and performance
       Cost cap of $21.28 million (adjusted from $20 million in 2010 Term Sheet)
        on Poseidon’s obligation to upgrade the Project intake
           Will occur when the power plant once-through cooling system ceases
            operation




                                                                                    18
 Article 5 – Water Authority Obligations Generally
   Date certain for completion of Water Authority Improvements
       30 months after financial close

   Poseidon obligations regarding testing of Water Authority Improvements

 Article 6 – Project Financing and Refinancing
   Poseidon’s responsibilities to obtain and repay initial and any subsequent
    Project financing without recourse to the Water Authority
   Permitted and non-permitted debt
   50/50 sharing of refinancing gain



                                                                                 19
 Article 7 – Completion and Acceptance of the Plant
   Mechanical completion, commissioning and performance testing of the Plant
       Water Authority approval rights

   Conditions for Provisional Acceptance (Begin Commercial Operation)
       Water Authority approval rights

   Poseidon time limit to achieve commercial operation
       1,430 days after financial closing (approx. 47 months)




                                                                           20
 Article 8 – Operation and Management of the Plant
  Plant operations coordination with the Water Authority
  Plant operations record keeping and reporting requirements
  Requirement to provide Water Authority administrative space at the Plant
  Water Authority access rights to the Plant, including tours
  Water Authority rights to deal with “unworkable relationship” with Plant
   Chief Operator
  Determination of Annual Management Fee
      $5-10/AF based on performance




                                                                              21
 Article 9 – General Performance Responsibilities
   Poseidon Product Water Quality Guarantee
        Off-Specification Product Water and Unacceptable Water
        Remedies for Breach of Product Water Quality Guarantee
   Annual Supply and Demand Commitments by Poseidon and the
      Water Authority
     Product Water delivery scheduling
     Plant flow rate changes and limitations
     Poseidon requirements to make “shortfall payments” on pipeline
      debt service should Poseidon fail to deliver Product Water ordered
      by the Water Authority
     Drought Shortfall Payments
     Raw seawater quality and Uncontrollable Circumstances
                                                                           22
 Article 10 – Maintenance, Repair and Replacement
  Poseidon requirements to document Maintenance, Repair and
   Replacement Plans and Schedules
  Water Authority rights to inspect the Plant
      Annual maintenance inspection
      Biennial full-scale inspection/review of Plant working condition and
       performance capability
  Poseidon requirements to maintain a Computerized Maintenance
   Management System (CMMS)
  End-of-Term condition and performance requirements



                                                                              23
 Article 11 – Capital Modifications
   Requirements and procedures regarding various types of capital
    modifications:
      Made at Poseidon request
          Capital modification exceeds $10 million
          No increase in the unit price

      Made at Water Authority request
          Potential increase to unit price

      Required due to Compensation Adjustment Event
          Capital modifications arising from uninsurable force majeure (e.g.,war,
           terrorism), change in law (e.g., generally applicable to water treatment
           facilities)
          Potential increase to unit price
                                                                                      24
 Article 12 – Contracting and Labor Practices
   Poseidon use of agreed upon project contractors
   Water Authority access to project contractors
   Poseidon responsibility for project labor relations/disputes


 Article 13 – Insurance, Damage and Destruction
   Requirement for Project insurance and proof of coverage




                                                                   25
 Article 14 – Uncontrollable Circumstance Procedures
   General procedures for claiming an uncontrollable circumstance
       Notice to Water Authority within 10 business days of occurrence
       Requirements for specific relief request and resumption of performance

 Article 15 – Insurable and Uninsurable Force Majeure Events
   Specific Poseidon schedule/performance relief under an insurable Force
    Majeure event (e.g., fire, any peril other than uninsurable FM)
   Specific Poseidon schedule/performance/compensation relief under an
    uninsurable Force Majeure event (e.g., war, terrorism, nuclear explosion)
       Requirements for project reinstatement plans and reconstruction standards


                                                                                    26
 Article 16 – Change In Law Events And Other Uncontrollable
  Circumstances
  Specific schedule, performance and compensation relief (if any) for different
   Change in Law events
  Specific schedule, performance and compensation relief (if any) for other
   uncontrollables
      Those not covered by change in law or Force Majeure




                                                                               27
 Article 17 – Monthly Water Purchase Payments
  Contract definitions of monthly charges
      Capital charges
      Operating charges
      Electricity charges

  Establishment and use of monthly/annual tracking accounts
  Unit price cap for uncontrollable circumstances
      Maximum of 10% annually above CPI
      Cumulative maximum of 30% over CPI for the 30-year term

  Billing and payment provisions


                                                                 28
 Article 18 – Dispute Resolution
   Procedures for non-binding mediation
   Court jurisdiction
       San Diego County

 Article 19 – Remedies of the Parties and Water Authority
  Step-in Rights
   Remedies for breach of contract by either party
   Water Authority temporary step-in rights
       Immediate and serious threat to public health and safety




                                                                   29
 Article 20 – Project Company Events of Default
   Listing of specific events of default and breach of contract including:
      •   Failure to pass performance testing by the agreed upon Commercial
          Operations Date
      •   Poseidon project company bankruptcy or abandonment of the project
      •   Repeated violations of Primary Drinking Water Standards
      •   Multiple notices of violation issued by a regulatory agency
      •   Deliveries less than 75 percent of the annual amount
      •   Failure to make Contracted Shortfall Payments
   Water Authority termination right under an event of default




                                                                              30
 Article 21 – Water Authority Events of Default
   Listing of specific events of default including:
       Failure to pay undisputed bill amounts owed Poseidon within 45 days of
        the due date
       Water Authority breach that materially and adversely affects performance
        of Contract obligations
       Water Authority bankruptcy

   Project Company options

 Article 22 – Termination
   Water Authority termination rights
   Poseidon termination rights
                                                                                   31
 Article 23 – Water Authority Project Assets Purchase Options
   Purchase option during the term
       After 10 years of operation
       Purchase price = outstanding bond indebtedness + discounted NPV of remaining
        equity return + any “breakage” fees associated with O&M agreement
   Purchase option in the event of financing unavailability
   Purchase option upon an event of default
   Purchase option at the end of the term
       Purchase price = $1




                                                                                   32
 Article 24 – Assignment and Change in Control
   Limitations on Poseidon’s future assignment or transfer of interest in the
    WPA to another party
   Limitations on changes in control of Project company

 Article 25 – Indemnification
   Circumstances and procedures for Poseidon indemnification of the
    Water Authority




                                                                                 33
 Article 26 – Miscellaneous Provisions
   Requirement for Water Authority consent for any sale of the Plant
   Procedures for contract administration
   Water Authority and Poseidon confidentiality provisions
   Water Authority license to use intellectual property developed as part
    of the Project




                                                                             34
Proposed WPA
Costs and Water Pricing
1.        The Electricity Charge is                                       3.    The Capital Charge is
          driven by:                                                            driven by:
                                                                                • Poseidon’s Capital
          •        Terms of Poseidon’s O&M
                                                                                  Budget
                   Agreement with IDE
                                                  Electricity                   • Bond Issuance
          •        SDG&E Rates
                                                   Charge                       • Negotiated Equity
          •        Water Authority’s option to                                    Return/Developer Fee
                   select supplier                                              • Development period
          The Electricity Charge will vary
                                                                Capital           costs
          with electricity prices                               Charge         The Capital Charge is fixed
                                                 Operating                     at a pre-established
                                                                               escalation rate
                                                  Charge
     2.        The Operating Charge is
               driven by:
               •     Terms of Poseidon’s O&M
                     Agreement with IDE
               •     Other operating expenses
              The Operating Charge is
              indexed to CPI
                                                                                                        36
   Direct costs
     Capital Costs
      ▪ Desal Plant Related:       $484 Million
        ▪ Includes: planning, permitting, design, construction, and legal costs
      ▪ SDG&E substation:    $20 Million
      ▪ Wetlands Mitigation: $23 Million
        ▪ Includes: design, permitting and construction of 66 acres of wetlands
      ▪ GHG Mitigation:            $1.25 Million
        ▪ Includes: reforestation and one time purchase of mitigation credits
      ▪ Conveyance Pipeline: $163 Million
     Total Capital Costs: $691 Million
     Financing Costs
       Reserves, capitalized interest, etc: $213 Million
                                                                                  37
   Total Capital Costs:    $691 Million
   Financing Costs:        $213 Million
   Total Cost              $904 Million
   Method of Finance
      ▪ 82% funded through Bonds issued by the California
        Pollution Control Financing Authority
      ▪ 18% Cash Equity from Stonepeak Infrastructure

        Bond Financing         Equity Contribution
        $740 Million           $164 Million


                                                            38
   Direct costs
 Operating and Maintenance Costs:
     Fixed O&M costs: $22.7 million annually
      ▪ Non electricity: $19.2 million annually
      ▪ Electricity: $3.5 million annually
     Variable O&M Costs: $26.1 - $30.4 million annually
      ▪ Non electricity: $4.9 – $5.6 million annually
      ▪ Electricity: $21.2 – $24.8 million annually
     Total O&M Costs: $48.8- $53.1 million annually
 Costs reflect a range of 48,000 AFY-56,000 AFY

                                                           39
   Direct Costs associated with WPA
     Payments to Poseidon
      ▪ Capital Charge
      ▪ Operating Charge
     Debt Service on Conveyance Pipeline


    48,ooo acre feet per year   56,000 acre feet per year
              $2,097/AF                   $1,876/AF




                                                            40
   Indirect Costs
     Water Authority costs: Pipeline 3 and Twin Oaks Valley
      WTP improvements; Twin Oaks additional operating costs,
      oversight during project construction

     48,ooo acre feet per year   56,000 acre feet per year
          $96 + $83 = $179/AF          $82 + $71 = $153/AF


     Administrative Costs during operation
    48,ooo acre feet per year    56,000 acre feet per year

                $14/AF                       $12/AF


                                                                41
   Total Unit Cost
     Payments to Poseidon
     Debt Service on Conveyance Pipeline
     Water Authority Improvements and Construction
      Oversight
     Twin Oaks additional Operating Costs
     Water Authority administrative Costs during operations
    48,ooo acre feet per year   56,000 acre feet per year
              $2,290/AF                   $2,041/AF


                                                               42
Finalize Proposed WPA and Technical Appendices
Finalize construction and operating prices
Finalize Design Build Agreement for new pipeline
Finalize Bond and other financing documents
Board incorporates into rate and charge structure
Finalize agreement for Member Agency purchase as local supply
Hold two evening community meetings


                                                          43
   Public Meetings (Two)
     Evening Water Planning Committee Meeting at SDCWA
        ▪ October 2, 2012 - 6:30 pm, SDCWA, 4677 Overland Ave., San Diego

     Evening Water Planning Committee meeting in Carlsbad
        ▪ October 10, 2012 - 6:30 pm, City of Carlsbad Faraday Operations Center


   October Special Board Meeting – Oct. 11, 2012
     Australian Desalination experience
     Detailed discussion on Draft WPA costs and terms
     Continue discussions on financial components
     Continue discussion on rate structure

                                                                                   44
   October Regular Board Meeting – Oct. 25, 2012
     Review actions related to Pipeline 3 rehabilitation, Twin Oaks and
      other distribution system activities

     Continue discussions on financial components and rate structure




                                                                           45
QUESTIONS?

More Related Content

What's hot

Milestone checklist
Milestone checklist   Milestone checklist
time bar clauses
time bar clausestime bar clauses
time bar clauses
AMILA GAYAN
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
My own
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
John Buchovecky
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
Section 01 Procurement Fundamentals
Section 01 Procurement FundamentalsSection 01 Procurement Fundamentals
Section 01 Procurement Fundamentals
Avik Munshi
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
dhiraj.gaur
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Divyanshu Dayal
 
Procurement Expediting Training
Procurement Expediting TrainingProcurement Expediting Training
Procurement Expediting Training
Mohd Ishar Ishak
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
Astonish Expediting managed by professionals
Astonish Expediting managed by professionalsAstonish Expediting managed by professionals
Astonish Expediting managed by professionals
Nitin Thakurta
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
Tahir B Mirza
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
TW Carl
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Presentationon infrastructure project_finance
Presentationon infrastructure project_financePresentationon infrastructure project_finance
Presentationon infrastructure project_finance
sabinji
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
Nam N.N Tran M.Eng, PMP
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
Hani Saad
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
ignitetribes
 

What's hot (20)

Milestone checklist
Milestone checklist   Milestone checklist
Milestone checklist
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Section 01 Procurement Fundamentals
Section 01 Procurement FundamentalsSection 01 Procurement Fundamentals
Section 01 Procurement Fundamentals
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
Procurement Expediting Training
Procurement Expediting TrainingProcurement Expediting Training
Procurement Expediting Training
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Astonish Expediting managed by professionals
Astonish Expediting managed by professionalsAstonish Expediting managed by professionals
Astonish Expediting managed by professionals
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Presentationon infrastructure project_finance
Presentationon infrastructure project_financePresentationon infrastructure project_finance
Presentationon infrastructure project_finance
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 

Similar to Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources

Seawater Desalination Update - Sept. 20
Seawater Desalination Update - Sept. 20Seawater Desalination Update - Sept. 20
Seawater Desalination Update - Sept. 20
San Diego County Water Authority
 
Carlsbad Desalination Project Water Purchase Agreement and Related Issues
Carlsbad Desalination Project Water Purchase Agreement and Related IssuesCarlsbad Desalination Project Water Purchase Agreement and Related Issues
Carlsbad Desalination Project Water Purchase Agreement and Related Issues
San Diego County Water Authority
 
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
San Diego County Water Authority
 
Member Agency Purchases of Water Authority-owned Supplies - Carlsbad
Member Agency Purchases of Water Authority-owned Supplies - CarlsbadMember Agency Purchases of Water Authority-owned Supplies - Carlsbad
Member Agency Purchases of Water Authority-owned Supplies - Carlsbad
San Diego County Water Authority
 
Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....
Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....
Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....
San Diego County Water Authority
 
The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia
CleanH2O
 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogden
ahcitycouncil
 
Third Party Access for Water - IPART, James Cox
Third Party Access for Water - IPART, James CoxThird Party Access for Water - IPART, James Cox
Third Party Access for Water - IPART, James Cox
Water Industry Alliance
 
Approval of Uniform Contract for Member Agency Purchase of Treated Water from...
Approval of Uniform Contract for Member Agency Purchase of Treated Water from...Approval of Uniform Contract for Member Agency Purchase of Treated Water from...
Approval of Uniform Contract for Member Agency Purchase of Treated Water from...
San Diego County Water Authority
 
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdfPreliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Bappy114
 
Legal Portion Cwa
Legal Portion CwaLegal Portion Cwa
Legal Portion Cwa
dstryker
 
2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water Bills2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water Bills
Thomas F. Mullin
 
New Construction Stormwater Regulation in Minnesota
New Construction Stormwater Regulation in MinnesotaNew Construction Stormwater Regulation in Minnesota
New Construction Stormwater Regulation in Minnesota
Dan Schleck
 
Item # 5 - Ogden Pipe Bursting Change Order
Item # 5 - Ogden Pipe Bursting Change Order Item # 5 - Ogden Pipe Bursting Change Order
Item # 5 - Ogden Pipe Bursting Change Order
ahcitycouncil
 
Cwco Investor Presentation March 13, 2017
Cwco Investor Presentation  March 13, 2017Cwco Investor Presentation  March 13, 2017
Cwco Investor Presentation March 13, 2017
Jeremy Keyser
 
CWCO Investor presentation June 13, 2017
CWCO Investor presentation June 13, 2017CWCO Investor presentation June 13, 2017
CWCO Investor presentation June 13, 2017
Jeremy Keyser
 
Plumbing handbook
Plumbing handbookPlumbing handbook
Plumbing handbook
Raees Nk
 
2011 expo-asilp-presentation cgbf
2011 expo-asilp-presentation cgbf2011 expo-asilp-presentation cgbf
2011 expo-asilp-presentation cgbf
EllieNowels
 
Sawaco Ho Chi-Minh ppp para lograr eficiencia
Sawaco Ho Chi-Minh ppp para lograr eficienciaSawaco Ho Chi-Minh ppp para lograr eficiencia
Sawaco Ho Chi-Minh ppp para lograr eficiencia
Jose María De Viana
 
Item # 5 - PPT Ogden Pipebursting Amendment
Item # 5 - PPT Ogden Pipebursting AmendmentItem # 5 - PPT Ogden Pipebursting Amendment
Item # 5 - PPT Ogden Pipebursting Amendment
ahcitycouncil
 

Similar to Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources (20)

Seawater Desalination Update - Sept. 20
Seawater Desalination Update - Sept. 20Seawater Desalination Update - Sept. 20
Seawater Desalination Update - Sept. 20
 
Carlsbad Desalination Project Water Purchase Agreement and Related Issues
Carlsbad Desalination Project Water Purchase Agreement and Related IssuesCarlsbad Desalination Project Water Purchase Agreement and Related Issues
Carlsbad Desalination Project Water Purchase Agreement and Related Issues
 
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
 
Member Agency Purchases of Water Authority-owned Supplies - Carlsbad
Member Agency Purchases of Water Authority-owned Supplies - CarlsbadMember Agency Purchases of Water Authority-owned Supplies - Carlsbad
Member Agency Purchases of Water Authority-owned Supplies - Carlsbad
 
Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....
Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....
Carlsbad Deslation Project Water Purchase Agreement and Related Issues - Nov....
 
The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia
 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogden
 
Third Party Access for Water - IPART, James Cox
Third Party Access for Water - IPART, James CoxThird Party Access for Water - IPART, James Cox
Third Party Access for Water - IPART, James Cox
 
Approval of Uniform Contract for Member Agency Purchase of Treated Water from...
Approval of Uniform Contract for Member Agency Purchase of Treated Water from...Approval of Uniform Contract for Member Agency Purchase of Treated Water from...
Approval of Uniform Contract for Member Agency Purchase of Treated Water from...
 
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdfPreliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
 
Legal Portion Cwa
Legal Portion CwaLegal Portion Cwa
Legal Portion Cwa
 
2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water Bills2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water Bills
 
New Construction Stormwater Regulation in Minnesota
New Construction Stormwater Regulation in MinnesotaNew Construction Stormwater Regulation in Minnesota
New Construction Stormwater Regulation in Minnesota
 
Item # 5 - Ogden Pipe Bursting Change Order
Item # 5 - Ogden Pipe Bursting Change Order Item # 5 - Ogden Pipe Bursting Change Order
Item # 5 - Ogden Pipe Bursting Change Order
 
Cwco Investor Presentation March 13, 2017
Cwco Investor Presentation  March 13, 2017Cwco Investor Presentation  March 13, 2017
Cwco Investor Presentation March 13, 2017
 
CWCO Investor presentation June 13, 2017
CWCO Investor presentation June 13, 2017CWCO Investor presentation June 13, 2017
CWCO Investor presentation June 13, 2017
 
Plumbing handbook
Plumbing handbookPlumbing handbook
Plumbing handbook
 
2011 expo-asilp-presentation cgbf
2011 expo-asilp-presentation cgbf2011 expo-asilp-presentation cgbf
2011 expo-asilp-presentation cgbf
 
Sawaco Ho Chi-Minh ppp para lograr eficiencia
Sawaco Ho Chi-Minh ppp para lograr eficienciaSawaco Ho Chi-Minh ppp para lograr eficiencia
Sawaco Ho Chi-Minh ppp para lograr eficiencia
 
Item # 5 - PPT Ogden Pipebursting Amendment
Item # 5 - PPT Ogden Pipebursting AmendmentItem # 5 - PPT Ogden Pipebursting Amendment
Item # 5 - PPT Ogden Pipebursting Amendment
 

More from San Diego County Water Authority

Session 2 presentation
Session 2 presentationSession 2 presentation
Session 2 presentation
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015
San Diego County Water Authority
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
San Diego County Water Authority
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
San Diego County Water Authority
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
San Diego County Water Authority
 
Bay-Delta Activities Update
Bay-Delta Activities UpdateBay-Delta Activities Update
Bay-Delta Activities Update
San Diego County Water Authority
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
San Diego County Water Authority
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
San Diego County Water Authority
 
2015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 20152015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 2015
San Diego County Water Authority
 
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
San Diego County Water Authority
 
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
San Diego County Water Authority
 
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response Activities
San Diego County Water Authority
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
San Diego County Water Authority
 

More from San Diego County Water Authority (20)

Session 2 presentation
Session 2 presentationSession 2 presentation
Session 2 presentation
 
Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015
 
Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015
 
Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
 
Bay-Delta Activities Update
Bay-Delta Activities UpdateBay-Delta Activities Update
Bay-Delta Activities Update
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
2015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 20152015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 2015
 
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
 
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
 
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response Activities
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
 

Recently uploaded

Day 2 - Intro to UiPath Studio Fundamentals
Day 2 - Intro to UiPath Studio FundamentalsDay 2 - Intro to UiPath Studio Fundamentals
Day 2 - Intro to UiPath Studio Fundamentals
UiPathCommunity
 
What is an RPA CoE? Session 1 – CoE Vision
What is an RPA CoE?  Session 1 – CoE VisionWhat is an RPA CoE?  Session 1 – CoE Vision
What is an RPA CoE? Session 1 – CoE Vision
DianaGray10
 
ScyllaDB Tablets: Rethinking Replication
ScyllaDB Tablets: Rethinking ReplicationScyllaDB Tablets: Rethinking Replication
ScyllaDB Tablets: Rethinking Replication
ScyllaDB
 
A Deep Dive into ScyllaDB's Architecture
A Deep Dive into ScyllaDB's ArchitectureA Deep Dive into ScyllaDB's Architecture
A Deep Dive into ScyllaDB's Architecture
ScyllaDB
 
Christine's Product Research Presentation.pptx
Christine's Product Research Presentation.pptxChristine's Product Research Presentation.pptx
Christine's Product Research Presentation.pptx
christinelarrosa
 
Connector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectors
Connector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectorsConnector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectors
Connector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectors
DianaGray10
 
Mutation Testing for Task-Oriented Chatbots
Mutation Testing for Task-Oriented ChatbotsMutation Testing for Task-Oriented Chatbots
Mutation Testing for Task-Oriented Chatbots
Pablo Gómez Abajo
 
QA or the Highway - Component Testing: Bridging the gap between frontend appl...
QA or the Highway - Component Testing: Bridging the gap between frontend appl...QA or the Highway - Component Testing: Bridging the gap between frontend appl...
QA or the Highway - Component Testing: Bridging the gap between frontend appl...
zjhamm304
 
Must Know Postgres Extension for DBA and Developer during Migration
Must Know Postgres Extension for DBA and Developer during MigrationMust Know Postgres Extension for DBA and Developer during Migration
Must Know Postgres Extension for DBA and Developer during Migration
Mydbops
 
AWS Certified Solutions Architect Associate (SAA-C03)
AWS Certified Solutions Architect Associate (SAA-C03)AWS Certified Solutions Architect Associate (SAA-C03)
AWS Certified Solutions Architect Associate (SAA-C03)
HarpalGohil4
 
Demystifying Knowledge Management through Storytelling
Demystifying Knowledge Management through StorytellingDemystifying Knowledge Management through Storytelling
Demystifying Knowledge Management through Storytelling
Enterprise Knowledge
 
GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...
GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...
GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...
GlobalLogic Ukraine
 
[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...
[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...
[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...
Jason Yip
 
From Natural Language to Structured Solr Queries using LLMs
From Natural Language to Structured Solr Queries using LLMsFrom Natural Language to Structured Solr Queries using LLMs
From Natural Language to Structured Solr Queries using LLMs
Sease
 
Containers & AI - Beauty and the Beast!?!
Containers & AI - Beauty and the Beast!?!Containers & AI - Beauty and the Beast!?!
Containers & AI - Beauty and the Beast!?!
Tobias Schneck
 
GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)
Javier Junquera
 
AI in the Workplace Reskilling, Upskilling, and Future Work.pptx
AI in the Workplace Reskilling, Upskilling, and Future Work.pptxAI in the Workplace Reskilling, Upskilling, and Future Work.pptx
AI in the Workplace Reskilling, Upskilling, and Future Work.pptx
Sunil Jagani
 
MySQL InnoDB Storage Engine: Deep Dive - Mydbops
MySQL InnoDB Storage Engine: Deep Dive - MydbopsMySQL InnoDB Storage Engine: Deep Dive - Mydbops
MySQL InnoDB Storage Engine: Deep Dive - Mydbops
Mydbops
 
Northern Engraving | Nameplate Manufacturing Process - 2024
Northern Engraving | Nameplate Manufacturing Process - 2024Northern Engraving | Nameplate Manufacturing Process - 2024
Northern Engraving | Nameplate Manufacturing Process - 2024
Northern Engraving
 
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
Fwdays
 

Recently uploaded (20)

Day 2 - Intro to UiPath Studio Fundamentals
Day 2 - Intro to UiPath Studio FundamentalsDay 2 - Intro to UiPath Studio Fundamentals
Day 2 - Intro to UiPath Studio Fundamentals
 
What is an RPA CoE? Session 1 – CoE Vision
What is an RPA CoE?  Session 1 – CoE VisionWhat is an RPA CoE?  Session 1 – CoE Vision
What is an RPA CoE? Session 1 – CoE Vision
 
ScyllaDB Tablets: Rethinking Replication
ScyllaDB Tablets: Rethinking ReplicationScyllaDB Tablets: Rethinking Replication
ScyllaDB Tablets: Rethinking Replication
 
A Deep Dive into ScyllaDB's Architecture
A Deep Dive into ScyllaDB's ArchitectureA Deep Dive into ScyllaDB's Architecture
A Deep Dive into ScyllaDB's Architecture
 
Christine's Product Research Presentation.pptx
Christine's Product Research Presentation.pptxChristine's Product Research Presentation.pptx
Christine's Product Research Presentation.pptx
 
Connector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectors
Connector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectorsConnector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectors
Connector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectors
 
Mutation Testing for Task-Oriented Chatbots
Mutation Testing for Task-Oriented ChatbotsMutation Testing for Task-Oriented Chatbots
Mutation Testing for Task-Oriented Chatbots
 
QA or the Highway - Component Testing: Bridging the gap between frontend appl...
QA or the Highway - Component Testing: Bridging the gap between frontend appl...QA or the Highway - Component Testing: Bridging the gap between frontend appl...
QA or the Highway - Component Testing: Bridging the gap between frontend appl...
 
Must Know Postgres Extension for DBA and Developer during Migration
Must Know Postgres Extension for DBA and Developer during MigrationMust Know Postgres Extension for DBA and Developer during Migration
Must Know Postgres Extension for DBA and Developer during Migration
 
AWS Certified Solutions Architect Associate (SAA-C03)
AWS Certified Solutions Architect Associate (SAA-C03)AWS Certified Solutions Architect Associate (SAA-C03)
AWS Certified Solutions Architect Associate (SAA-C03)
 
Demystifying Knowledge Management through Storytelling
Demystifying Knowledge Management through StorytellingDemystifying Knowledge Management through Storytelling
Demystifying Knowledge Management through Storytelling
 
GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...
GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...
GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...
 
[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...
[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...
[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...
 
From Natural Language to Structured Solr Queries using LLMs
From Natural Language to Structured Solr Queries using LLMsFrom Natural Language to Structured Solr Queries using LLMs
From Natural Language to Structured Solr Queries using LLMs
 
Containers & AI - Beauty and the Beast!?!
Containers & AI - Beauty and the Beast!?!Containers & AI - Beauty and the Beast!?!
Containers & AI - Beauty and the Beast!?!
 
GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)
 
AI in the Workplace Reskilling, Upskilling, and Future Work.pptx
AI in the Workplace Reskilling, Upskilling, and Future Work.pptxAI in the Workplace Reskilling, Upskilling, and Future Work.pptx
AI in the Workplace Reskilling, Upskilling, and Future Work.pptx
 
MySQL InnoDB Storage Engine: Deep Dive - Mydbops
MySQL InnoDB Storage Engine: Deep Dive - MydbopsMySQL InnoDB Storage Engine: Deep Dive - Mydbops
MySQL InnoDB Storage Engine: Deep Dive - Mydbops
 
Northern Engraving | Nameplate Manufacturing Process - 2024
Northern Engraving | Nameplate Manufacturing Process - 2024Northern Engraving | Nameplate Manufacturing Process - 2024
Northern Engraving | Nameplate Manufacturing Process - 2024
 
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
 

Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources

  • 1. Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources San Diego County Water Authority Water Planning Committee Meeting 1 September 27, 2012 1
  • 3. • 50 MGD desalination plant located on the site of the Encina Power Station (Poseidon) • 10 mile 54-inch diameter conveyance pipeline (Poseidon) • Connection to Water Authority aqueduct Pipeline 3 (Poseidon) • Relining of 5.5 mile reach of Pipeline 3 (Water Authority) • Improvements at the TOVWTP to accommodate desalinated water flows (Water Authority) 3
  • 4. 30 years from the date of commercial operation • Subject to early buy-out provisions • Can be extended for up to 3 years due to Force Majeure events 4
  • 5. • Water Authority • Project Company: Poseidon • EPC Contractor: Kiewit-Shea Joint Venture • Process Engineering and Equipment: • IDE Operating Services Provider: IDE 5
  • 6.  Developer/Owner of the Plant  Poseidon Resources (Channelside)  Poseidon to finance through a combination of debt (82%) and equity (18%)  Debt to be provided through tax-exempt Private Activity Bonds (PAB’s)  Equity to be provided by Stonepeak  Construction/Operation of the Plant  Contractor – Joint venture of Kiewit Infrastructure West and J.F. Shea Construction  IDE Technologies is process technology provider  Plant Operations and Maintenance also to be provided by IDE 6
  • 7.  Owner of the Conveyance Pipeline  Water Authority will own and maintain the Conveyance Pipeline  Not subject to franchise fees or possessory interest taxes  Finance using municipal purpose bonds issued by California Pollution Control Financing Authority (CPCFA)  Bonds maintain risk transfer to Poseidon by insulating the Water Authority from financial responsibility if Poseidon is unable to perform  Exempt from AMT – Lower interest rate 7
  • 8.  Construction of the Conveyance Pipeline  Design Build Agreement between the Water Authority and Poseidon  Contractor – Kiewit/Shea Joint Venture  Construction of the P3 Relining and TOVWTP Improvements  Water Authority will be responsible to finance and complete these improvements 8
  • 9. • Permit, Design and Build the Desal Plant (WPA) • Permit, Design and Build the Conveyance Pipeline (Design-Build Agreement) • Operate and Maintain the Desal Plant • Supply Product Water 9
  • 10. • “Take or Pay” for Product Water if it meets specifications (minimum of 48,000 AF/Year) • Timely Construction of TOVWTP Improvements and Pipeline 3 Rehabilitation • Physically be able to receive Product Water • Operate and Maintain the Conveyance Pipeline, the TOVWTP Improvements and Pipeline 3 10
  • 11. • Equity Investment: $165 Million • Project Financing: Non-Performance Risk Incentivizes Bondholders to Cure Breaches • Letter of Credit to Secure Performance • Letter of Credit to Assure Financing 11
  • 12. • Product Water Quality Guarantee • Compliance with all federal and state drinking water regulations • Additional standards for certain water quality parameters • Minimum Product Water Delivery Guarantee • Annual supply to meet Water Authority demands (between 48,000 and 56,000 acre-feet) • Water Ordering Rights • Water Authority rights to adjust delivery orders to reflect seasonal and daily demand changes 12
  • 13. • Purchase options at Water Authority sole discretion • Convenience Termination • Early buy-out provision • End of Term • $1 end of 30-year term • Event of Default • Unavailability of Financing for Required Improvements 13
  • 14. • Poseidon • Events include: ▪ Failure to pass performance testing by the agreed upon Commercial Operations Date ▪ Poseidon project company bankruptcy or abandonment of the project ▪ Repeated violations of Primary Drinking Water Standards ▪ Multiple notices of violation issued by a regulatory agency ▪ Deliveries less than 75 percent of the annual amount ▪ Failure to make Contracted Shortfall Payments • Water Authority has the option to terminate the agreement • Water Authority • Failure to pay undisputed bill amounts owed Poseidon within 45 days of the due date 14
  • 16.  WPA consists of agreement text and technical appendices  26 articles (sections)  18 technical appendices (reviewed at Special Board Meeting of Sept 20, 2012)  Article 1 – Definitions and Interpretation  Detailed definitions and interpretations of key terms used in the agreement and appendices  Includes cross references to specific articles within the agreement 16
  • 17.  Article 2 – Representations and Warranties  Representations by the Water Authority and Poseidon that the proposed WPA is based upon  Includes statements regarding correctness of information provided, sufficiency of financing to build facilities and Poseidon's interest in plant site  Article 3 – Term  Agreement start date (contract execution date) and end date  Provisions that “survive” past the end of the agreement  E.g. records , property rights 17
  • 18.  Article 4 – Contract Obligations Generally  General obligations of the Water Authority and Poseidon during construction and operation  Specifically addresses:  Poseidon Letter of Credit requirements  Poseidon responsibility for design, construction and performance  Cost cap of $21.28 million (adjusted from $20 million in 2010 Term Sheet) on Poseidon’s obligation to upgrade the Project intake  Will occur when the power plant once-through cooling system ceases operation 18
  • 19.  Article 5 – Water Authority Obligations Generally  Date certain for completion of Water Authority Improvements  30 months after financial close  Poseidon obligations regarding testing of Water Authority Improvements  Article 6 – Project Financing and Refinancing  Poseidon’s responsibilities to obtain and repay initial and any subsequent Project financing without recourse to the Water Authority  Permitted and non-permitted debt  50/50 sharing of refinancing gain 19
  • 20.  Article 7 – Completion and Acceptance of the Plant  Mechanical completion, commissioning and performance testing of the Plant  Water Authority approval rights  Conditions for Provisional Acceptance (Begin Commercial Operation)  Water Authority approval rights  Poseidon time limit to achieve commercial operation  1,430 days after financial closing (approx. 47 months) 20
  • 21.  Article 8 – Operation and Management of the Plant  Plant operations coordination with the Water Authority  Plant operations record keeping and reporting requirements  Requirement to provide Water Authority administrative space at the Plant  Water Authority access rights to the Plant, including tours  Water Authority rights to deal with “unworkable relationship” with Plant Chief Operator  Determination of Annual Management Fee  $5-10/AF based on performance 21
  • 22.  Article 9 – General Performance Responsibilities  Poseidon Product Water Quality Guarantee  Off-Specification Product Water and Unacceptable Water  Remedies for Breach of Product Water Quality Guarantee  Annual Supply and Demand Commitments by Poseidon and the Water Authority  Product Water delivery scheduling  Plant flow rate changes and limitations  Poseidon requirements to make “shortfall payments” on pipeline debt service should Poseidon fail to deliver Product Water ordered by the Water Authority  Drought Shortfall Payments  Raw seawater quality and Uncontrollable Circumstances 22
  • 23.  Article 10 – Maintenance, Repair and Replacement  Poseidon requirements to document Maintenance, Repair and Replacement Plans and Schedules  Water Authority rights to inspect the Plant  Annual maintenance inspection  Biennial full-scale inspection/review of Plant working condition and performance capability  Poseidon requirements to maintain a Computerized Maintenance Management System (CMMS)  End-of-Term condition and performance requirements 23
  • 24.  Article 11 – Capital Modifications  Requirements and procedures regarding various types of capital modifications:  Made at Poseidon request  Capital modification exceeds $10 million  No increase in the unit price  Made at Water Authority request  Potential increase to unit price  Required due to Compensation Adjustment Event  Capital modifications arising from uninsurable force majeure (e.g.,war, terrorism), change in law (e.g., generally applicable to water treatment facilities)  Potential increase to unit price 24
  • 25.  Article 12 – Contracting and Labor Practices  Poseidon use of agreed upon project contractors  Water Authority access to project contractors  Poseidon responsibility for project labor relations/disputes  Article 13 – Insurance, Damage and Destruction  Requirement for Project insurance and proof of coverage 25
  • 26.  Article 14 – Uncontrollable Circumstance Procedures  General procedures for claiming an uncontrollable circumstance  Notice to Water Authority within 10 business days of occurrence  Requirements for specific relief request and resumption of performance  Article 15 – Insurable and Uninsurable Force Majeure Events  Specific Poseidon schedule/performance relief under an insurable Force Majeure event (e.g., fire, any peril other than uninsurable FM)  Specific Poseidon schedule/performance/compensation relief under an uninsurable Force Majeure event (e.g., war, terrorism, nuclear explosion)  Requirements for project reinstatement plans and reconstruction standards 26
  • 27.  Article 16 – Change In Law Events And Other Uncontrollable Circumstances  Specific schedule, performance and compensation relief (if any) for different Change in Law events  Specific schedule, performance and compensation relief (if any) for other uncontrollables  Those not covered by change in law or Force Majeure 27
  • 28.  Article 17 – Monthly Water Purchase Payments  Contract definitions of monthly charges  Capital charges  Operating charges  Electricity charges  Establishment and use of monthly/annual tracking accounts  Unit price cap for uncontrollable circumstances  Maximum of 10% annually above CPI  Cumulative maximum of 30% over CPI for the 30-year term  Billing and payment provisions 28
  • 29.  Article 18 – Dispute Resolution  Procedures for non-binding mediation  Court jurisdiction  San Diego County  Article 19 – Remedies of the Parties and Water Authority Step-in Rights  Remedies for breach of contract by either party  Water Authority temporary step-in rights  Immediate and serious threat to public health and safety 29
  • 30.  Article 20 – Project Company Events of Default  Listing of specific events of default and breach of contract including: • Failure to pass performance testing by the agreed upon Commercial Operations Date • Poseidon project company bankruptcy or abandonment of the project • Repeated violations of Primary Drinking Water Standards • Multiple notices of violation issued by a regulatory agency • Deliveries less than 75 percent of the annual amount • Failure to make Contracted Shortfall Payments  Water Authority termination right under an event of default 30
  • 31.  Article 21 – Water Authority Events of Default  Listing of specific events of default including:  Failure to pay undisputed bill amounts owed Poseidon within 45 days of the due date  Water Authority breach that materially and adversely affects performance of Contract obligations  Water Authority bankruptcy  Project Company options  Article 22 – Termination  Water Authority termination rights  Poseidon termination rights 31
  • 32.  Article 23 – Water Authority Project Assets Purchase Options  Purchase option during the term  After 10 years of operation  Purchase price = outstanding bond indebtedness + discounted NPV of remaining equity return + any “breakage” fees associated with O&M agreement  Purchase option in the event of financing unavailability  Purchase option upon an event of default  Purchase option at the end of the term  Purchase price = $1 32
  • 33.  Article 24 – Assignment and Change in Control  Limitations on Poseidon’s future assignment or transfer of interest in the WPA to another party  Limitations on changes in control of Project company  Article 25 – Indemnification  Circumstances and procedures for Poseidon indemnification of the Water Authority 33
  • 34.  Article 26 – Miscellaneous Provisions  Requirement for Water Authority consent for any sale of the Plant  Procedures for contract administration  Water Authority and Poseidon confidentiality provisions  Water Authority license to use intellectual property developed as part of the Project 34
  • 35. Proposed WPA Costs and Water Pricing
  • 36. 1. The Electricity Charge is 3. The Capital Charge is driven by: driven by: • Poseidon’s Capital • Terms of Poseidon’s O&M Budget Agreement with IDE Electricity • Bond Issuance • SDG&E Rates Charge • Negotiated Equity • Water Authority’s option to Return/Developer Fee select supplier • Development period The Electricity Charge will vary Capital costs with electricity prices Charge The Capital Charge is fixed Operating at a pre-established escalation rate Charge 2. The Operating Charge is driven by: • Terms of Poseidon’s O&M Agreement with IDE • Other operating expenses The Operating Charge is indexed to CPI 36
  • 37. Direct costs  Capital Costs ▪ Desal Plant Related: $484 Million ▪ Includes: planning, permitting, design, construction, and legal costs ▪ SDG&E substation: $20 Million ▪ Wetlands Mitigation: $23 Million ▪ Includes: design, permitting and construction of 66 acres of wetlands ▪ GHG Mitigation: $1.25 Million ▪ Includes: reforestation and one time purchase of mitigation credits ▪ Conveyance Pipeline: $163 Million  Total Capital Costs: $691 Million  Financing Costs Reserves, capitalized interest, etc: $213 Million 37
  • 38. Total Capital Costs: $691 Million  Financing Costs: $213 Million  Total Cost $904 Million  Method of Finance ▪ 82% funded through Bonds issued by the California Pollution Control Financing Authority ▪ 18% Cash Equity from Stonepeak Infrastructure Bond Financing Equity Contribution $740 Million $164 Million 38
  • 39. Direct costs  Operating and Maintenance Costs:  Fixed O&M costs: $22.7 million annually ▪ Non electricity: $19.2 million annually ▪ Electricity: $3.5 million annually  Variable O&M Costs: $26.1 - $30.4 million annually ▪ Non electricity: $4.9 – $5.6 million annually ▪ Electricity: $21.2 – $24.8 million annually  Total O&M Costs: $48.8- $53.1 million annually  Costs reflect a range of 48,000 AFY-56,000 AFY 39
  • 40. Direct Costs associated with WPA  Payments to Poseidon ▪ Capital Charge ▪ Operating Charge  Debt Service on Conveyance Pipeline 48,ooo acre feet per year 56,000 acre feet per year $2,097/AF $1,876/AF 40
  • 41. Indirect Costs  Water Authority costs: Pipeline 3 and Twin Oaks Valley WTP improvements; Twin Oaks additional operating costs, oversight during project construction 48,ooo acre feet per year 56,000 acre feet per year $96 + $83 = $179/AF $82 + $71 = $153/AF  Administrative Costs during operation 48,ooo acre feet per year 56,000 acre feet per year $14/AF $12/AF 41
  • 42. Total Unit Cost  Payments to Poseidon  Debt Service on Conveyance Pipeline  Water Authority Improvements and Construction Oversight  Twin Oaks additional Operating Costs  Water Authority administrative Costs during operations 48,ooo acre feet per year 56,000 acre feet per year $2,290/AF $2,041/AF 42
  • 43. Finalize Proposed WPA and Technical Appendices Finalize construction and operating prices Finalize Design Build Agreement for new pipeline Finalize Bond and other financing documents Board incorporates into rate and charge structure Finalize agreement for Member Agency purchase as local supply Hold two evening community meetings 43
  • 44. Public Meetings (Two)  Evening Water Planning Committee Meeting at SDCWA ▪ October 2, 2012 - 6:30 pm, SDCWA, 4677 Overland Ave., San Diego  Evening Water Planning Committee meeting in Carlsbad ▪ October 10, 2012 - 6:30 pm, City of Carlsbad Faraday Operations Center  October Special Board Meeting – Oct. 11, 2012  Australian Desalination experience  Detailed discussion on Draft WPA costs and terms  Continue discussions on financial components  Continue discussion on rate structure 44
  • 45. October Regular Board Meeting – Oct. 25, 2012  Review actions related to Pipeline 3 rehabilitation, Twin Oaks and other distribution system activities  Continue discussions on financial components and rate structure 45