Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources - Presentation provided to the Water Planning Committee of the San Diego County Water Authority on September 27.
The document discusses key aspects of EPC contracts and the FIDIC Silver Book for major infrastructure projects. It notes that EPC contracts allocate significant risk to contractors in exchange for price and schedule guarantees. The FIDIC Silver Book is a turnkey contract form that departs from the usual risk allocation. The summary highlights common bankability issues for lenders and key contract clauses around fixed price and schedule, performance guarantees, liability caps, security provisions, and defects liability.
The document shows a schedule diagram comparing the original 514 day contract duration to the actual 698 day completion duration for a project, which resulted in a total delay of 184 days. 61 days of the delay were considered excusable, while 123 days were considered non-excusable according to the analysis, which is illustrated schematically.
Earned schedule role in performance reporting and other important delay indicators.
Video: https://www.youtube.com/watch?v=FbA6RWB1gDM&feature=youtu.be
The full course: https://www.luqmanacademy.com/course?course=project-control-using-evm_399sl6015424f8aba9
Video: https://twitter.com/magedkom/status/1354678096683618305?s=20
P3 Fundamentals Seminar - P3 AgreementsStephanie Kam
The document discusses the typical structure and key agreements in a public-private partnership (P3) project. There is usually a concession agreement between the government and private entity that defines their responsibilities and service delivery requirements. It also addresses the budget, compensation, and expectations over the long-term period. Principal contract terms in the concession agreement cover the project scope and duration, termination conditions, obligations of both parties, provisions for force majeure and changes in law, and dispute resolution process. Additional agreements include a shareholders agreement and financing agreement between the private entity and its investors/lenders.
The contractor can submit a claim to the engineer within 28 days of an event occurring or its effects ending. The contractor must then submit details of the claim within 42 days, or a period agreed with the engineer. If the engineer rejects the claim or does not respond, either party can refer the dispute to the dispute board for resolution.
The document discusses key issues faced in Engineering, Procurement, and Construction (EPC) projects and provides recommendations to address them. It summarizes EPC capabilities, project lifecycle, and common issues around quantity variation, drawings delays, constructability, procurement delays, and monitoring of critical items. Root cause analyses are presented for key issues. Recommendations are provided around talent retention, standardization, coordination, vendor management, approvals processes, and quality assurance to minimize variations and delays.
Slides from Abu Dhabi Prroject Financing Conference (2002) on "Negotiating the Terms & Conditions of the Project Debt and Achieving Financial Close"
The document discusses key aspects of EPC contracts and the FIDIC Silver Book for major infrastructure projects. It notes that EPC contracts allocate significant risk to contractors in exchange for price and schedule guarantees. The FIDIC Silver Book is a turnkey contract form that departs from the usual risk allocation. The summary highlights common bankability issues for lenders and key contract clauses around fixed price and schedule, performance guarantees, liability caps, security provisions, and defects liability.
The document shows a schedule diagram comparing the original 514 day contract duration to the actual 698 day completion duration for a project, which resulted in a total delay of 184 days. 61 days of the delay were considered excusable, while 123 days were considered non-excusable according to the analysis, which is illustrated schematically.
Earned schedule role in performance reporting and other important delay indicators.
Video: https://www.youtube.com/watch?v=FbA6RWB1gDM&feature=youtu.be
The full course: https://www.luqmanacademy.com/course?course=project-control-using-evm_399sl6015424f8aba9
Video: https://twitter.com/magedkom/status/1354678096683618305?s=20
P3 Fundamentals Seminar - P3 AgreementsStephanie Kam
The document discusses the typical structure and key agreements in a public-private partnership (P3) project. There is usually a concession agreement between the government and private entity that defines their responsibilities and service delivery requirements. It also addresses the budget, compensation, and expectations over the long-term period. Principal contract terms in the concession agreement cover the project scope and duration, termination conditions, obligations of both parties, provisions for force majeure and changes in law, and dispute resolution process. Additional agreements include a shareholders agreement and financing agreement between the private entity and its investors/lenders.
The contractor can submit a claim to the engineer within 28 days of an event occurring or its effects ending. The contractor must then submit details of the claim within 42 days, or a period agreed with the engineer. If the engineer rejects the claim or does not respond, either party can refer the dispute to the dispute board for resolution.
The document discusses key issues faced in Engineering, Procurement, and Construction (EPC) projects and provides recommendations to address them. It summarizes EPC capabilities, project lifecycle, and common issues around quantity variation, drawings delays, constructability, procurement delays, and monitoring of critical items. Root cause analyses are presented for key issues. Recommendations are provided around talent retention, standardization, coordination, vendor management, approvals processes, and quality assurance to minimize variations and delays.
Slides from Abu Dhabi Prroject Financing Conference (2002) on "Negotiating the Terms & Conditions of the Project Debt and Achieving Financial Close"
This document outlines the key milestones and deliverables in a process plant design project from conceptual design through detailed design and construction. It includes milestones for various disciplines like process, mechanical, piping, civil/structural, instrumentation and control, and electrical. The milestones range from developing preliminary design criteria and equipment lists to issuing design packages, finalizing vendor data, and completing construction drawings.
This document discusses time-bar clauses in standard construction contracts. It begins with an introduction that defines time-bar clauses and notes their increasing use. It then outlines the purposes of time-bar clauses such as alerting employers to claims and allowing for timely evaluation. The document reviews general legal principles around time-bar clauses from relevant case law. It examines the effectiveness of time-bar clauses in contracts like FIDIC and discusses requirements for notices of claims and record keeping. The role of the quantity surveyor is also mentioned.
110801Proposed Fidic Contract Framework For Complex Epc ProjectsMy own
Structure and Components of a Comprehensive Suite Of Components forming the Level of Contract Documentation Needed for Complex Industrial or Mining Mega Project
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
The document discusses time management under the FIDIC Red Book 2017 construction contract. It outlines the key project parties, including the engineer, employer, and contractor. It then examines various time-related clauses such as the time for completion, commencement and delays, extensions of time, suspension, resumption of work, and delay damages. The payment process and typical payment events are also summarized. Finally, the document reviews FIDIC's dispute resolution provisions, including the process for claims, references to the dispute adjudication board, and potential arbitration.
This document discusses various topics related to procurement including reasons to buy or build, types of procurement analysis, item classification, risks, and configuration management. It provides definitions and examples of key procurement terms and concepts such as:
- Reasons for buying vs building including strategic alignment, control, transparency, and learning curves.
- Types of procurement analysis including payback period and net present value calculations.
- Classification of items, contracts, and services for procurement.
- Risks in procurement processes and methods for mapping and managing risks.
- Configuration management processes like identification, status accounting, and verification.
- Tools for managing changes and issues like change logs and issue logs.
The document discusses FIDIC, an international organization for consulting engineers. It was founded in 1913 and now has over 60 member countries. FIDIC is best known for publishing standard contract conditions used around the world for construction projects. The document discusses the new editions of FIDIC's standard contracts, including the Red Book for construction, Yellow Book for plant design/build, and Silver Book for EPC turnkey projects. It provides details on the applicability of each book under different project delivery systems. The document also discusses improvements made in the new editions to address issues like back payments, financial arrangements, and contractor-financed projects.
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
•Retention money is held as a percentage of interim payments.
•Retention money is returned in parts after issue of taking over certificate and after expiry of defects notification period.
•In lieu of retention as percentage of interim payments, the contractor can issue a retention guarantee as agreed by the parties.
The document provides an overview of an expediter's role and responsibilities in managing the procurement process from purchase order issuance through delivery and warranty periods. It outlines the typical workflow and key activities an expediter performs, including coordinating engineering documents, monitoring production schedules, arranging inspections, coordinating shipping, and ensuring timely resolution of any issues. Timelines and key documents for each stage of the process are also identified to help expedite execution according to the project plan.
The program shall include:
- The order in which the Contractor proposes to carry out the Works;
- The anticipated timing of each stage of design (if any), procurement, manufacture of Plant, delivery to Site, construction, erection, and testing;
- Each of these stages for work by each Nominated Subcontractor;
- The sequence and timing of inspections and tests specified in the Contract; and
- A supporting report providing a general description of the methods intended to be adopted, and details showing the Contractor's reasonable estimates of personnel and Equipment.
Unless the Engineer has responded with comments within 21 days disapproving the program, the Contractor shall proceed with the Works in
Astonish Expediting managed by professionalsNitin Thakurta
The document discusses expediter services which involve facilitating timely processing and shipment of ordered materials. Expediters monitor order progress, address any issues or delays, and ensure on-time delivery. The goal is to establish an expediter company in India that brings value to customers in industries like oil and gas by continuously improving on-time delivery. The expediter duties involve both desk expediting using communication tools as well as field expediting with on-site status checks. Key performance metrics are also tracked to monitor order status. The company aims to initially operate with a small team serving a few major contract clients to prove its expediter service model.
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
The document provides guidelines for identifying, documenting, and presenting construction claims. It discusses objectives of keeping accurate records to support potential claims related to delays, disruptions or other contract issues. Key points covered include rules of engagement for contractors, identifying claim-worthy events, maintaining thorough documentation, and properly establishing a claim's entitlement and quantum or monetary value. The presentation provided templates for organizing supporting records and a general format for submitting a formal claim, including an executive summary, entitlement and quantum analyses, and factual exhibits.
The document outlines the process for executing a project design from start to finish. It involves creating 3D models for all disciplines, setting up interference management and design reviews. As the design progresses, more elements are added to the models like piping, equipment, ductwork, and architectural details. Reviews are conducted at 25%, 50%, 75% and 90% completion milestones. Deliverables include plots, drawings, specifications and manuals to support construction, commissioning and validation.
Construction Contracts Management based on UK common law using more than 40 cases of law with references from the UK, USA regulations, and international rules plus some examples from standard forms of construction contracts such as JCT, NEC & FIDIC.
Promo_Epc project rule of credit and progress measurement ignitetribes
Project progress monitoring and control is one of the most important tasks of construction project management. Many times planner or project manager not able.The hardest part of project controls is accurate performance measurement of work accomplished.
Taking time out to establish repeatable rules of credit can literally remove 75% of the performance measurement "guessing game" out of the equation.
In this book we don't just explain on what is rule of credit but we also provide tonnes of examples on how to establish the weighted milestone. It's a ready to be plug and plan in your project control measurement.
Log in to ignitetribes.com to purchase the book.
The document discusses project financing and the role of a project finance counsel. It defines project financing as financing development or exploitation of an asset using revenues from the project rather than share capital. The key roles of a project finance counsel are to allocate and mitigate risks through documentation, balance interests of participants, and ensure fulfillment of financing requirements. Requirements include fixed contracts, government support, promoter contributions, and security over key assets and contracts to protect lenders.
The document discusses engineering management in the EPC (engineering, procurement, and construction) industry. It outlines the typical project phases and risks involved in EPC contracts. It also identifies common challenges such as scope changes, commodity price volatility, and ensuring vendor and subcontractor quality. The presentation emphasizes the importance of effective engineering management throughout the project lifecycle from bidding through construction and commissioning. Key focus areas include integrated planning, competency of resources, communication, and change management. Success relies on collaboration, responsiveness, contingency planning, and working as a cohesive team.
Fidic comparison red yellow - silver bookHani Saad
1. The document compares three types of construction contracts - the Red Book, Yellow Book, and Silver Book.
2. The Red Book and Yellow Book contracts allocate some key risks like design errors to the employer. The Silver Book allocates most risks to the contractor.
3. The Red Book and Yellow Book contracts use an engineer appointed by the employer to administer the contract, while the Silver Book does not use an engineer and the employer directly administers the contract.
Project Control Practical Way by Herve Baronignitetribes
Here are some key ways to measure procurement progress:
- % Progress based on weighted value of POs, broken down into steps like PO placement, material receipt, inspection, etc.
- Milestones like:
- % of PO value placed
- % of line items with approved submittals
- % of line items where material is received/inspected
- % of line items fully delivered
Tracking procurement progress through milestones helps ensure critical items are on track and identifies delays early. Milestones should reflect major stages from PO placement through delivery and inspection. This provides a more objective view than % progress alone.
Both % progress and milestone tracking are needed to effectively monitor procurement.
Presentation provided to the Water Planning Committee of the San Diego County Water Authority on September 20. Provides an update on the key terms and a brief overview of the technical appendices for the seawater desalination project in Carlsbad.
Presentation given at the San Diego County Water Authority's Special Board of Directors' Meeting on Nov. 29, 2012. To view agenda visit www.sdcwa.org/meetings-and-documents
This document outlines the key milestones and deliverables in a process plant design project from conceptual design through detailed design and construction. It includes milestones for various disciplines like process, mechanical, piping, civil/structural, instrumentation and control, and electrical. The milestones range from developing preliminary design criteria and equipment lists to issuing design packages, finalizing vendor data, and completing construction drawings.
This document discusses time-bar clauses in standard construction contracts. It begins with an introduction that defines time-bar clauses and notes their increasing use. It then outlines the purposes of time-bar clauses such as alerting employers to claims and allowing for timely evaluation. The document reviews general legal principles around time-bar clauses from relevant case law. It examines the effectiveness of time-bar clauses in contracts like FIDIC and discusses requirements for notices of claims and record keeping. The role of the quantity surveyor is also mentioned.
110801Proposed Fidic Contract Framework For Complex Epc ProjectsMy own
Structure and Components of a Comprehensive Suite Of Components forming the Level of Contract Documentation Needed for Complex Industrial or Mining Mega Project
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
The document discusses time management under the FIDIC Red Book 2017 construction contract. It outlines the key project parties, including the engineer, employer, and contractor. It then examines various time-related clauses such as the time for completion, commencement and delays, extensions of time, suspension, resumption of work, and delay damages. The payment process and typical payment events are also summarized. Finally, the document reviews FIDIC's dispute resolution provisions, including the process for claims, references to the dispute adjudication board, and potential arbitration.
This document discusses various topics related to procurement including reasons to buy or build, types of procurement analysis, item classification, risks, and configuration management. It provides definitions and examples of key procurement terms and concepts such as:
- Reasons for buying vs building including strategic alignment, control, transparency, and learning curves.
- Types of procurement analysis including payback period and net present value calculations.
- Classification of items, contracts, and services for procurement.
- Risks in procurement processes and methods for mapping and managing risks.
- Configuration management processes like identification, status accounting, and verification.
- Tools for managing changes and issues like change logs and issue logs.
The document discusses FIDIC, an international organization for consulting engineers. It was founded in 1913 and now has over 60 member countries. FIDIC is best known for publishing standard contract conditions used around the world for construction projects. The document discusses the new editions of FIDIC's standard contracts, including the Red Book for construction, Yellow Book for plant design/build, and Silver Book for EPC turnkey projects. It provides details on the applicability of each book under different project delivery systems. The document also discusses improvements made in the new editions to address issues like back payments, financial arrangements, and contractor-financed projects.
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
•Retention money is held as a percentage of interim payments.
•Retention money is returned in parts after issue of taking over certificate and after expiry of defects notification period.
•In lieu of retention as percentage of interim payments, the contractor can issue a retention guarantee as agreed by the parties.
The document provides an overview of an expediter's role and responsibilities in managing the procurement process from purchase order issuance through delivery and warranty periods. It outlines the typical workflow and key activities an expediter performs, including coordinating engineering documents, monitoring production schedules, arranging inspections, coordinating shipping, and ensuring timely resolution of any issues. Timelines and key documents for each stage of the process are also identified to help expedite execution according to the project plan.
The program shall include:
- The order in which the Contractor proposes to carry out the Works;
- The anticipated timing of each stage of design (if any), procurement, manufacture of Plant, delivery to Site, construction, erection, and testing;
- Each of these stages for work by each Nominated Subcontractor;
- The sequence and timing of inspections and tests specified in the Contract; and
- A supporting report providing a general description of the methods intended to be adopted, and details showing the Contractor's reasonable estimates of personnel and Equipment.
Unless the Engineer has responded with comments within 21 days disapproving the program, the Contractor shall proceed with the Works in
Astonish Expediting managed by professionalsNitin Thakurta
The document discusses expediter services which involve facilitating timely processing and shipment of ordered materials. Expediters monitor order progress, address any issues or delays, and ensure on-time delivery. The goal is to establish an expediter company in India that brings value to customers in industries like oil and gas by continuously improving on-time delivery. The expediter duties involve both desk expediting using communication tools as well as field expediting with on-site status checks. Key performance metrics are also tracked to monitor order status. The company aims to initially operate with a small team serving a few major contract clients to prove its expediter service model.
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
The document provides guidelines for identifying, documenting, and presenting construction claims. It discusses objectives of keeping accurate records to support potential claims related to delays, disruptions or other contract issues. Key points covered include rules of engagement for contractors, identifying claim-worthy events, maintaining thorough documentation, and properly establishing a claim's entitlement and quantum or monetary value. The presentation provided templates for organizing supporting records and a general format for submitting a formal claim, including an executive summary, entitlement and quantum analyses, and factual exhibits.
The document outlines the process for executing a project design from start to finish. It involves creating 3D models for all disciplines, setting up interference management and design reviews. As the design progresses, more elements are added to the models like piping, equipment, ductwork, and architectural details. Reviews are conducted at 25%, 50%, 75% and 90% completion milestones. Deliverables include plots, drawings, specifications and manuals to support construction, commissioning and validation.
Construction Contracts Management based on UK common law using more than 40 cases of law with references from the UK, USA regulations, and international rules plus some examples from standard forms of construction contracts such as JCT, NEC & FIDIC.
Promo_Epc project rule of credit and progress measurement ignitetribes
Project progress monitoring and control is one of the most important tasks of construction project management. Many times planner or project manager not able.The hardest part of project controls is accurate performance measurement of work accomplished.
Taking time out to establish repeatable rules of credit can literally remove 75% of the performance measurement "guessing game" out of the equation.
In this book we don't just explain on what is rule of credit but we also provide tonnes of examples on how to establish the weighted milestone. It's a ready to be plug and plan in your project control measurement.
Log in to ignitetribes.com to purchase the book.
The document discusses project financing and the role of a project finance counsel. It defines project financing as financing development or exploitation of an asset using revenues from the project rather than share capital. The key roles of a project finance counsel are to allocate and mitigate risks through documentation, balance interests of participants, and ensure fulfillment of financing requirements. Requirements include fixed contracts, government support, promoter contributions, and security over key assets and contracts to protect lenders.
The document discusses engineering management in the EPC (engineering, procurement, and construction) industry. It outlines the typical project phases and risks involved in EPC contracts. It also identifies common challenges such as scope changes, commodity price volatility, and ensuring vendor and subcontractor quality. The presentation emphasizes the importance of effective engineering management throughout the project lifecycle from bidding through construction and commissioning. Key focus areas include integrated planning, competency of resources, communication, and change management. Success relies on collaboration, responsiveness, contingency planning, and working as a cohesive team.
Fidic comparison red yellow - silver bookHani Saad
1. The document compares three types of construction contracts - the Red Book, Yellow Book, and Silver Book.
2. The Red Book and Yellow Book contracts allocate some key risks like design errors to the employer. The Silver Book allocates most risks to the contractor.
3. The Red Book and Yellow Book contracts use an engineer appointed by the employer to administer the contract, while the Silver Book does not use an engineer and the employer directly administers the contract.
Project Control Practical Way by Herve Baronignitetribes
Here are some key ways to measure procurement progress:
- % Progress based on weighted value of POs, broken down into steps like PO placement, material receipt, inspection, etc.
- Milestones like:
- % of PO value placed
- % of line items with approved submittals
- % of line items where material is received/inspected
- % of line items fully delivered
Tracking procurement progress through milestones helps ensure critical items are on track and identifies delays early. Milestones should reflect major stages from PO placement through delivery and inspection. This provides a more objective view than % progress alone.
Both % progress and milestone tracking are needed to effectively monitor procurement.
Presentation provided to the Water Planning Committee of the San Diego County Water Authority on September 20. Provides an update on the key terms and a brief overview of the technical appendices for the seawater desalination project in Carlsbad.
Presentation given at the San Diego County Water Authority's Special Board of Directors' Meeting on Nov. 29, 2012. To view agenda visit www.sdcwa.org/meetings-and-documents
The document discusses several actions the San Diego County Water Authority Board will need to take to fully implement the Carlsbad Desalination Project, including: approving a design-build agreement for the product water pipeline, adjusting capital improvement project budgets, amending existing contracts, and approving bond financing agreements. It also notes member agencies will need to finalize contracts to purchase water from the desalination plant.
From the July 12 Special Board meeting of the San Diego County Water Authority. Presentation on potential purchase of Water Authority-owned seawater desalination supplies by local agencies.
Presentation given at the San Diego County Water Authority's Special Board of Directors' Meeting on Nov. 15, 2012. To view agenda visit www.sdcwa.org/meetings-and-documents
Virginia established a nutrient trading program and watershed permit in 2005 to help meet Chesapeake Bay nutrient reduction goals cost effectively. The program allows point sources to purchase credits from other point sources or nonpoint nutrient reduction projects. A 2012 law expanded the program by establishing a framework for certifying and using credits from additional nonpoint source practices. Key aspects include establishing baselines, only allowing use of certified credits listed in a public registry, and requiring local water quality protections are not contravened. The program aims to facilitate cost-effective reductions while maintaining regulatory oversight and permanent water quality benefits.
The City of Alamo Heights is considering authorizing a contract with Vortex Services for $373,215 using the BuyBoard Cooperative Program to rehabilitate a sewer main along Ogden through the nature trails to just below the Olmos Basin Dam. The project would use pipe bursting techniques to replace the existing sewer pipe. Vortex Services was the recommended contractor based on their project history and references.
Presentations from a Water Industry Alliance Market Solution Forum.
Experts say South Australia could encourage much MUCH greater stormwater harvesting, not to mention a broader range of water innovation and services, IF we could enable greater third party access.
Presentation given at the San Diego County Water Authority's Water Planning Meeting on Oct. 25, 2012. To view agenda visit www.sdcwa.org/monthly-board-meeting-20
This document provides a preliminary design report for a proposed water system to service the Upper Fintry, Shalal Road, and Valley of the Sun neighbourhoods. It identifies groundwater from wells located on Lot 19 in the Fintry Delta as the preferred water source. The system will have two pressure zones, with the Valley of the Sun area serviced from a 608m reservoir and Upper Fintry serviced from a 555m pressure reducing valve. The design includes a well pump station, 405m booster station, 608m reservoir, and supply and distribution piping. The preliminary cost estimate and potential for expanding the service area are also discussed.
2013 Florida Legislative Summary - Environmental and Water BillsThomas F. Mullin
The document summarizes key bills passed by the 2013 Florida legislature related to water resources, environmental regulation, and land use. Major topics included expanding funding for Everglades restoration, establishing numeric nutrient criteria, regulating onsite sewage systems, facilitating public-private partnerships, and reforming aspects of water management and permitting.
New Construction Stormwater Regulation in MinnesotaDan Schleck
Attorney Dan Schleck makes a presentation to the Builders Association of the Twin Cities (BATC) on new construction stormwater permitting and regulation in Minnesota
Item # 5 - Ogden Pipe Bursting Change Order ahcitycouncil
The City of Alamo Heights is requesting approval for a $57,125 change order to correct deficiencies identified in a recently completed sewer rehabilitation project. Post-construction video identified several areas where the rehabilitated sewer pipe did not meet the required slope standards. The change order would fund excavating these areas to remedy the slope issues. The total project cost remains within the original $535,000 budget. Approval of the change order would allow substantial completion by the end of February 2023.
Cwco Investor Presentation March 13, 2017Jeremy Keyser
Consolidated Water provides water desalination and water distribution services. It operates desalination plants in the Cayman Islands, Bahamas, US, Belize, and BVI. It is developing a large desalination plant project in Rosarito, Mexico. Consolidated Water has a history of stable revenues and earnings and seeks to expand into new markets through projects like the one in Mexico and the acquisition of Aerex Industries, a water treatment equipment manufacturer.
CWCO Investor presentation June 13, 2017Jeremy Keyser
Consolidated Water provides water desalination plants and water distribution systems where freshwater is limited. It operates in several countries including the Cayman Islands and Bahamas. The company is developing a large desalination plant project in Rosarito, Mexico. Consolidated Water has a history of dividend payments and acquired Aerex Industries to expand into water treatment equipment manufacturing and services.
This document provides a summary of guidelines and regulations for plumbers and builders working with the Water Corporation. It covers topics such as connecting to water and sewer mains, backflow prevention, interpreting Water Corporation plans, property sewer connections, and submitting as-constructed plans. The purpose is to assist plumbers and builders to work within regulations while protecting public health and infrastructure assets. Key responsibilities include obtaining approvals before connecting to mains, installing backflow prevention devices, accurately locating sewer connection points, and providing as-built sewer diagrams.
Funding Green Projects - Site, Building, and Communities
A presentation by Diane Alecusan, AICP, LEED AP
Office of Redevelopment, Ohio Department of Development
Presented at Columbus Green Building Forum's 2011 Green Building EXPO
SAWACO es la empresa socialista de Agua de la ciudad Ho Chi Minh, la Hidrocapital de la ciudad capital de la República Socialista de Vietnam. Para prestar un mejor servicio realiza asociación con empresas privadas, PPP. Los amigos de Hidroven deberían viajar a Vietnam y retomar una ruta que abandonaron, hace 15 años.
The document discusses authorizing an amendment to the contract with Vortex Services for a sewer main replacement project. Post-construction evaluation found deficiencies that need to be addressed. The proposed change order would authorize Vortex Services to make repairs at a cost of $57,215, increasing the total contract to $448,950. The project was originally budgeted at $535,000 and the amendment would be covered by remaining funds.
Similar to Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources (20)
This document summarizes the Water Authority's efforts to increase the reliability of the San Diego region's water supply through diversification. It shows that the region relies heavily on imported water supplies, which face uncertainties. To address this, the Authority has pursued a variety of local supply projects including seawater desalination, water transfers, groundwater, and recycled water. Charts depict the region's historical and planned water supply portfolio mix out to 2035 as it diversifies its supplies. The document also discusses drought planning, noting California's variable precipitation and the Authority's approach to coordinating a regional response.
This document provides an update on water supply conditions and drought response activities in California:
- The northern Sierra snowpack is only 64% of normal for this time of year, reducing expected water supplies.
- The State Water Project initial allocation for 2016 is 10%, subject to change based on winter precipitation. Allocations have ranged from 5-65% in recent years.
- Local water storage levels and precipitation in the San Diego region are below normal levels due to ongoing drought conditions.
- Water use reductions under the state's emergency regulation have ranged from 2-13% across different local water agencies from June-October 2015. The state may extend mandatory conservation measures into 2016 if drought persists.
The document provides an update on water supply conditions and drought response activities from Dana Friehauf, Water Resources Manager. It includes information on precipitation levels in the Northern Sierra being at 95% of normal, snowpack levels being at 95% of normal, storage levels in Lake Oroville being at 51% of capacity and 74% of average, cumulative potable water use from June 2015-January 2016 being 23% lower than 2013, the outlook for March-May precipitation, an extension and potential adjustments to the State Water Resources Control Board's emergency regulation requiring at least 8% conservation through October 2016, and a new local drought-resilient supply credit as part of the regulation.
This document provides a summary from Alexi Schnell, a Water Resources Specialist, at the August 27, 2015 Water Planning Committee meeting. It discusses current drought conditions, including a 90% chance of El Niño continuing through the winter and into early spring according to NOAA. Charts show Lake Oroville and San Luis Reservoir storage levels well below average. It also outlines updated conservation standards for member agencies and water use reductions of 29% cumulatively in June-July 2015 compared to 2013.
The presentation provides an update on drought conditions and response activities in California. It discusses declining water usage, hotter temperatures compared to previous years, compliance with mandatory conservation standards requiring a 25% reduction in water use, and updates to the state's model landscape ordinance to increase water efficiency and limit turf areas. Key points include June 2015 water use being 26% lower than June 2013, local reservoir storage being at 36% of capacity, and the updated ordinance expected to reduce water use in new homes by 20% and commercial landscapes by 35%.
The document summarizes a presentation given to the Imported Water Committee about the Bay-Delta and California WaterFix project. It provides background on efforts to address water supply reliability and ecosystem restoration in the Bay-Delta, including the formation of BDCP and transition to California WaterFix. Key differences between the projects are noted. Questions still remaining about project size, costs, financing, and impacts to local agencies like the Water Authority are identified. Next steps in the environmental review process are outlined.
The document summarizes a presentation by Larry Purcell on the Bay Delta Conservation Plan (BDCP) and California WaterFix. Some key points:
- The BDCP aims to modernize water delivery infrastructure in the Delta while restoring habitat through 22 conservation measures. Its goals are water supply reliability and ecosystem restoration.
- The California WaterFix is similar but without long-term permit assurances or a habitat conservation plan. It focuses only on new water delivery infrastructure and required mitigation.
- Without a habitat conservation plan/natural community conservation plan, future permitting for species could be limited and done separately, without comprehensive stabilization of water supply or mitigation costs.
- Key questions remain about how the new permitting
1. The document discusses the history of the Water Authority's involvement with the Bay Delta Conservation Plan/California WaterFix and potential costs to the Water Authority.
2. The preferred project is a large infrastructure project to deliver water through the Delta and costs have increased to an estimated $14.9 billion.
3. There is uncertainty around supply benefits without an NCCP/HCP and around how costs will be allocated.
This document provides background information on California's efforts to address water supply issues related to the Sacramento-San Joaquin Delta and transport of State Water Project water. It summarizes the history of initiatives including CalFed and the Bay Delta Conservation Plan (BDCP). The document then outlines topics discussed at recent Metropolitan Water District board meetings regarding the BDCP/California WaterFix, including project details, costs, risks and timeline. It concludes by summarizing the key aspects and public review process for the recently released recirculated draft environmental documents.
1) The document discusses the estimated costs of the Delta conveyance facility for urban and agricultural water users in California and their capacity to pay.
2) It analyzes the potential costs to the Metropolitan Water District (MWD) under different scenarios for cost allocation between the State Water Project and Central Valley Project, ranging from $211 million to $546 million.
3) It notes that there are important financing risks still to be resolved, such as construction cost overruns, regulatory uncertainty, and whether habitat funding will be provided, that could jeopardize operating the tunnels or affect the ability to issue bonds.
1) The document discusses the financing issues around building a Delta conveyance facility, known as the BDCP.
2) It analyzes the potential costs to water contractors like MWD under different scenarios, finding their peak annual costs could range from $168 million to $378 million depending on how costs are allocated.
3) It notes a number of important financing risks still need to be resolved, including the revenue stream certainty required to issue bonds and developing credit for CVP contractors to finance their share.
This document discusses a government relations program on imported water and the Bay-Delta Conservation Plan (BDCP). It notes the competing interests in the Delta region involving water supply, ecosystem, and transportation. It outlines the Water Authority's analysis of the BDCP plan and environmental reviews over several years. Key questions are identified regarding project size, costs, water supply benefits for San Diego, and financial obligations. The Water Authority will continue engagement to ensure a cost-effective Delta solution that balances environmental and water supply needs and limits financial obligations proportionate to benefits received.
The document summarizes a presentation made to the Imported Water Committee about the Draft Implementing Agreement for the Bay Delta Conservation Plan (BDCP). The Implementing Agreement describes the roles, responsibilities, and commitments for implementing the BDCP, including regulatory assurances, funding, and governance. It is required for the BDCP to receive permits as a Natural Community Conservation Plan and is a typical agreement for a Habitat Conservation Plan. Key topics covered in the presentation include regulatory assurances, funding obligations of permittees versus state/federal entities, governance structure, and decision making. Areas for public comment on the draft agreement are identified as governance, funding, regulatory assurances, adaptive management and future modifications, and water operations decision trees.
1. The BDCP is a massive infrastructure project that will be difficult to implement and costs are likely to increase.
2. How project costs are allocated among contractors and who will ultimately pay are important issues that could significantly impact water rates.
3. The San Diego County Water Authority's region has explored additional local projects that may help address supply impacts, but would come at a cost and allow more local control compared to relying on the BDCP.
This document provides an overview and agenda for an Imported Water Committee meeting regarding review of the Bay Delta Conservation Plan (BDCP) documents. It summarizes prior board briefings on BDCP issues, the BDCP review process, the environmental review process for BDCP under CEQA and NEPA, and initial subject areas proposed for comment in a letter, such as governance, funding, economic analysis, and project risks. The staff recommendation is to authorize submitting a formal comment letter on the BDCP Draft EIR/EIS.
Update on Supply Conditions and Drought Response Activities
Water Planning Committee - May 28, 2015 Meeting
Presentation by: Dana Friehauf, Water Resources Manager
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks and SWRCB Emergency Regulation
Special Board Meeting, May 14, 2015
Presentation by: Dana Friehauf, Water Resources Manager
In our second session, we shall learn all about the main features and fundamentals of UiPath Studio that enable us to use the building blocks for any automation project.
📕 Detailed agenda:
Variables and Datatypes
Workflow Layouts
Arguments
Control Flows and Loops
Conditional Statements
💻 Extra training through UiPath Academy:
Variables, Constants, and Arguments in Studio
Control Flow in Studio
What is an RPA CoE? Session 1 – CoE VisionDianaGray10
In the first session, we will review the organization's vision and how this has an impact on the COE Structure.
Topics covered:
• The role of a steering committee
• How do the organization’s priorities determine CoE Structure?
Speaker:
Chris Bolin, Senior Intelligent Automation Architect Anika Systems
ScyllaDB is making a major architecture shift. We’re moving from vNode replication to tablets – fragments of tables that are distributed independently, enabling dynamic data distribution and extreme elasticity. In this keynote, ScyllaDB co-founder and CTO Avi Kivity explains the reason for this shift, provides a look at the implementation and roadmap, and shares how this shift benefits ScyllaDB users.
This talk will cover ScyllaDB Architecture from the cluster-level view and zoom in on data distribution and internal node architecture. In the process, we will learn the secret sauce used to get ScyllaDB's high availability and superior performance. We will also touch on the upcoming changes to ScyllaDB architecture, moving to strongly consistent metadata and tablets.
Connector Corner: Seamlessly power UiPath Apps, GenAI with prebuilt connectorsDianaGray10
Join us to learn how UiPath Apps can directly and easily interact with prebuilt connectors via Integration Service--including Salesforce, ServiceNow, Open GenAI, and more.
The best part is you can achieve this without building a custom workflow! Say goodbye to the hassle of using separate automations to call APIs. By seamlessly integrating within App Studio, you can now easily streamline your workflow, while gaining direct access to our Connector Catalog of popular applications.
We’ll discuss and demo the benefits of UiPath Apps and connectors including:
Creating a compelling user experience for any software, without the limitations of APIs.
Accelerating the app creation process, saving time and effort
Enjoying high-performance CRUD (create, read, update, delete) operations, for
seamless data management.
Speakers:
Russell Alfeche, Technology Leader, RPA at qBotic and UiPath MVP
Charlie Greenberg, host
Conversational agents, or chatbots, are increasingly used to access all sorts of services using natural language. While open-domain chatbots - like ChatGPT - can converse on any topic, task-oriented chatbots - the focus of this paper - are designed for specific tasks, like booking a flight, obtaining customer support, or setting an appointment. Like any other software, task-oriented chatbots need to be properly tested, usually by defining and executing test scenarios (i.e., sequences of user-chatbot interactions). However, there is currently a lack of methods to quantify the completeness and strength of such test scenarios, which can lead to low-quality tests, and hence to buggy chatbots.
To fill this gap, we propose adapting mutation testing (MuT) for task-oriented chatbots. To this end, we introduce a set of mutation operators that emulate faults in chatbot designs, an architecture that enables MuT on chatbots built using heterogeneous technologies, and a practical realisation as an Eclipse plugin. Moreover, we evaluate the applicability, effectiveness and efficiency of our approach on open-source chatbots, with promising results.
QA or the Highway - Component Testing: Bridging the gap between frontend appl...zjhamm304
These are the slides for the presentation, "Component Testing: Bridging the gap between frontend applications" that was presented at QA or the Highway 2024 in Columbus, OH by Zachary Hamm.
Must Know Postgres Extension for DBA and Developer during MigrationMydbops
Mydbops Opensource Database Meetup 16
Topic: Must-Know PostgreSQL Extensions for Developers and DBAs During Migration
Speaker: Deepak Mahto, Founder of DataCloudGaze Consulting
Date & Time: 8th June | 10 AM - 1 PM IST
Venue: Bangalore International Centre, Bangalore
Abstract: Discover how PostgreSQL extensions can be your secret weapon! This talk explores how key extensions enhance database capabilities and streamline the migration process for users moving from other relational databases like Oracle.
Key Takeaways:
* Learn about crucial extensions like oracle_fdw, pgtt, and pg_audit that ease migration complexities.
* Gain valuable strategies for implementing these extensions in PostgreSQL to achieve license freedom.
* Discover how these key extensions can empower both developers and DBAs during the migration process.
* Don't miss this chance to gain practical knowledge from an industry expert and stay updated on the latest open-source database trends.
Mydbops Managed Services specializes in taking the pain out of database management while optimizing performance. Since 2015, we have been providing top-notch support and assistance for the top three open-source databases: MySQL, MongoDB, and PostgreSQL.
Our team offers a wide range of services, including assistance, support, consulting, 24/7 operations, and expertise in all relevant technologies. We help organizations improve their database's performance, scalability, efficiency, and availability.
Contact us: info@mydbops.com
Visit: https://www.mydbops.com/
Follow us on LinkedIn: https://in.linkedin.com/company/mydbops
For more details and updates, please follow up the below links.
Meetup Page : https://www.meetup.com/mydbops-databa...
Twitter: https://twitter.com/mydbopsofficial
Blogs: https://www.mydbops.com/blog/
Facebook(Meta): https://www.facebook.com/mydbops/
The Department of Veteran Affairs (VA) invited Taylor Paschal, Knowledge & Information Management Consultant at Enterprise Knowledge, to speak at a Knowledge Management Lunch and Learn hosted on June 12, 2024. All Office of Administration staff were invited to attend and received professional development credit for participating in the voluntary event.
The objectives of the Lunch and Learn presentation were to:
- Review what KM ‘is’ and ‘isn’t’
- Understand the value of KM and the benefits of engaging
- Define and reflect on your “what’s in it for me?”
- Share actionable ways you can participate in Knowledge - - Capture & Transfer
GlobalLogic Java Community Webinar #18 “How to Improve Web Application Perfor...GlobalLogic Ukraine
Під час доповіді відповімо на питання, навіщо потрібно підвищувати продуктивність аплікації і які є найефективніші способи для цього. А також поговоримо про те, що таке кеш, які його види бувають та, основне — як знайти performance bottleneck?
Відео та деталі заходу: https://bit.ly/45tILxj
[OReilly Superstream] Occupy the Space: A grassroots guide to engineering (an...Jason Yip
The typical problem in product engineering is not bad strategy, so much as “no strategy”. This leads to confusion, lack of motivation, and incoherent action. The next time you look for a strategy and find an empty space, instead of waiting for it to be filled, I will show you how to fill it in yourself. If you’re wrong, it forces a correction. If you’re right, it helps create focus. I’ll share how I’ve approached this in the past, both what works and lessons for what didn’t work so well.
From Natural Language to Structured Solr Queries using LLMsSease
This talk draws on experimentation to enable AI applications with Solr. One important use case is to use AI for better accessibility and discoverability of the data: while User eXperience techniques, lexical search improvements, and data harmonization can take organizations to a good level of accessibility, a structural (or “cognitive” gap) remains between the data user needs and the data producer constraints.
That is where AI – and most importantly, Natural Language Processing and Large Language Model techniques – could make a difference. This natural language, conversational engine could facilitate access and usage of the data leveraging the semantics of any data source.
The objective of the presentation is to propose a technical approach and a way forward to achieve this goal.
The key concept is to enable users to express their search queries in natural language, which the LLM then enriches, interprets, and translates into structured queries based on the Solr index’s metadata.
This approach leverages the LLM’s ability to understand the nuances of natural language and the structure of documents within Apache Solr.
The LLM acts as an intermediary agent, offering a transparent experience to users automatically and potentially uncovering relevant documents that conventional search methods might overlook. The presentation will include the results of this experimental work, lessons learned, best practices, and the scope of future work that should improve the approach and make it production-ready.
As AI technology is pushing into IT I was wondering myself, as an “infrastructure container kubernetes guy”, how get this fancy AI technology get managed from an infrastructure operational view? Is it possible to apply our lovely cloud native principals as well? What benefit’s both technologies could bring to each other?
Let me take this questions and provide you a short journey through existing deployment models and use cases for AI software. On practical examples, we discuss what cloud/on-premise strategy we may need for applying it to our own infrastructure to get it to work from an enterprise perspective. I want to give an overview about infrastructure requirements and technologies, what could be beneficial or limiting your AI use cases in an enterprise environment. An interactive Demo will give you some insides, what approaches I got already working for real.
Keywords: AI, Containeres, Kubernetes, Cloud Native
Event Link: https://meine.doag.org/events/cloudland/2024/agenda/#agendaId.4211
In the realm of cybersecurity, offensive security practices act as a critical shield. By simulating real-world attacks in a controlled environment, these techniques expose vulnerabilities before malicious actors can exploit them. This proactive approach allows manufacturers to identify and fix weaknesses, significantly enhancing system security.
This presentation delves into the development of a system designed to mimic Galileo's Open Service signal using software-defined radio (SDR) technology. We'll begin with a foundational overview of both Global Navigation Satellite Systems (GNSS) and the intricacies of digital signal processing.
The presentation culminates in a live demonstration. We'll showcase the manipulation of Galileo's Open Service pilot signal, simulating an attack on various software and hardware systems. This practical demonstration serves to highlight the potential consequences of unaddressed vulnerabilities, emphasizing the importance of offensive security practices in safeguarding critical infrastructure.
AI in the Workplace Reskilling, Upskilling, and Future Work.pptxSunil Jagani
Discover how AI is transforming the workplace and learn strategies for reskilling and upskilling employees to stay ahead. This comprehensive guide covers the impact of AI on jobs, essential skills for the future, and successful case studies from industry leaders. Embrace AI-driven changes, foster continuous learning, and build a future-ready workforce.
Read More - https://bit.ly/3VKly70
MySQL InnoDB Storage Engine: Deep Dive - MydbopsMydbops
This presentation, titled "MySQL - InnoDB" and delivered by Mayank Prasad at the Mydbops Open Source Database Meetup 16 on June 8th, 2024, covers dynamic configuration of REDO logs and instant ADD/DROP columns in InnoDB.
This presentation dives deep into the world of InnoDB, exploring two ground-breaking features introduced in MySQL 8.0:
• Dynamic Configuration of REDO Logs: Enhance your database's performance and flexibility with on-the-fly adjustments to REDO log capacity. Unleash the power of the snake metaphor to visualize how InnoDB manages REDO log files.
• Instant ADD/DROP Columns: Say goodbye to costly table rebuilds! This presentation unveils how InnoDB now enables seamless addition and removal of columns without compromising data integrity or incurring downtime.
Key Learnings:
• Grasp the concept of REDO logs and their significance in InnoDB's transaction management.
• Discover the advantages of dynamic REDO log configuration and how to leverage it for optimal performance.
• Understand the inner workings of instant ADD/DROP columns and their impact on database operations.
• Gain valuable insights into the row versioning mechanism that empowers instant column modifications.
Northern Engraving | Nameplate Manufacturing Process - 2024Northern Engraving
Manufacturing custom quality metal nameplates and badges involves several standard operations. Processes include sheet prep, lithography, screening, coating, punch press and inspection. All decoration is completed in the flat sheet with adhesive and tooling operations following. The possibilities for creating unique durable nameplates are endless. How will you create your brand identity? We can help!
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor IvaniukFwdays
At this talk we will discuss DDoS protection tools and best practices, discuss network architectures and what AWS has to offer. Also, we will look into one of the largest DDoS attacks on Ukrainian infrastructure that happened in February 2022. We'll see, what techniques helped to keep the web resources available for Ukrainians and how AWS improved DDoS protection for all customers based on Ukraine experience
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources
1. Overview of Key Terms for a Water Purchase
Agreement between the San Diego County Water
Authority and Poseidon Resources
San Diego County Water Authority
Water Planning Committee Meeting
1
September 27, 2012
1
3. • 50 MGD desalination plant located on the site of the
Encina Power Station (Poseidon)
• 10 mile 54-inch diameter conveyance pipeline (Poseidon)
• Connection to Water Authority aqueduct Pipeline 3
(Poseidon)
• Relining of 5.5 mile reach of Pipeline 3 (Water Authority)
• Improvements at the TOVWTP to accommodate
desalinated water flows (Water Authority)
3
4. • 30 years from the date of commercial operation
• Subject to early buy-out provisions
• Can be extended for up to 3 years due to Force
Majeure events
4
5. • Water Authority
• Project Company: Poseidon
• EPC Contractor: Kiewit-Shea Joint Venture
• Process Engineering and Equipment:
• IDE Operating Services Provider: IDE
5
6. Developer/Owner of the Plant
Poseidon Resources (Channelside)
Poseidon to finance through a combination of debt (82%) and
equity (18%)
Debt to be provided through tax-exempt Private Activity Bonds (PAB’s)
Equity to be provided by Stonepeak
Construction/Operation of the Plant
Contractor – Joint venture of Kiewit Infrastructure West and
J.F. Shea Construction
IDE Technologies is process technology provider
Plant Operations and Maintenance also to be provided by IDE
6
7. Owner of the Conveyance Pipeline
Water Authority will own and maintain the Conveyance Pipeline
Not subject to franchise fees or possessory interest taxes
Finance using municipal purpose bonds issued by California
Pollution Control Financing Authority (CPCFA)
Bonds maintain risk transfer to Poseidon by insulating the Water
Authority from financial responsibility if Poseidon is unable to perform
Exempt from AMT – Lower interest rate
7
8. Construction of the Conveyance Pipeline
Design Build Agreement between the Water Authority and
Poseidon
Contractor – Kiewit/Shea Joint Venture
Construction of the P3 Relining and TOVWTP
Improvements
Water Authority will be responsible to finance and complete
these improvements
8
9. • Permit, Design and Build the Desal Plant (WPA)
• Permit, Design and Build the Conveyance Pipeline
(Design-Build Agreement)
• Operate and Maintain the Desal Plant
• Supply Product Water
9
10. • “Take or Pay” for Product Water if it meets
specifications (minimum of 48,000 AF/Year)
• Timely Construction of TOVWTP
Improvements and Pipeline 3 Rehabilitation
• Physically be able to receive Product Water
• Operate and Maintain the Conveyance Pipeline, the
TOVWTP Improvements and Pipeline 3
10
11. • Equity Investment: $165 Million
• Project Financing: Non-Performance Risk
Incentivizes Bondholders to Cure Breaches
• Letter of Credit to Secure Performance
• Letter of Credit to Assure Financing
11
12. • Product Water Quality Guarantee
• Compliance with all federal and state drinking water
regulations
• Additional standards for certain water quality parameters
• Minimum Product Water Delivery Guarantee
• Annual supply to meet Water Authority demands (between
48,000 and 56,000 acre-feet)
• Water Ordering Rights
• Water Authority rights to adjust delivery orders to reflect
seasonal and daily demand changes
12
13. • Purchase options at Water Authority sole discretion
• Convenience Termination
• Early buy-out provision
• End of Term
• $1 end of 30-year term
• Event of Default
• Unavailability of Financing for Required Improvements
13
14. • Poseidon
• Events include:
▪ Failure to pass performance testing by the agreed upon Commercial Operations
Date
▪ Poseidon project company bankruptcy or abandonment of the project
▪ Repeated violations of Primary Drinking Water Standards
▪ Multiple notices of violation issued by a regulatory agency
▪ Deliveries less than 75 percent of the annual amount
▪ Failure to make Contracted Shortfall Payments
• Water Authority has the option to terminate the agreement
• Water Authority
• Failure to pay undisputed bill amounts owed Poseidon within
45 days of the due date 14
16. WPA consists of agreement text and technical appendices
26 articles (sections)
18 technical appendices (reviewed at Special Board Meeting of Sept 20, 2012)
Article 1 – Definitions and Interpretation
Detailed definitions and interpretations of key terms used in the agreement
and appendices
Includes cross references to specific articles within the agreement
16
17. Article 2 – Representations and Warranties
Representations by the Water Authority and Poseidon that the proposed
WPA is based upon
Includes statements regarding correctness of information provided,
sufficiency of financing to build facilities and Poseidon's interest in plant site
Article 3 – Term
Agreement start date (contract execution date) and end date
Provisions that “survive” past the end of the agreement
E.g. records , property rights
17
18. Article 4 – Contract Obligations Generally
General obligations of the Water Authority and Poseidon during
construction and operation
Specifically addresses:
Poseidon Letter of Credit requirements
Poseidon responsibility for design, construction and performance
Cost cap of $21.28 million (adjusted from $20 million in 2010 Term Sheet)
on Poseidon’s obligation to upgrade the Project intake
Will occur when the power plant once-through cooling system ceases
operation
18
19. Article 5 – Water Authority Obligations Generally
Date certain for completion of Water Authority Improvements
30 months after financial close
Poseidon obligations regarding testing of Water Authority Improvements
Article 6 – Project Financing and Refinancing
Poseidon’s responsibilities to obtain and repay initial and any subsequent
Project financing without recourse to the Water Authority
Permitted and non-permitted debt
50/50 sharing of refinancing gain
19
20. Article 7 – Completion and Acceptance of the Plant
Mechanical completion, commissioning and performance testing of the Plant
Water Authority approval rights
Conditions for Provisional Acceptance (Begin Commercial Operation)
Water Authority approval rights
Poseidon time limit to achieve commercial operation
1,430 days after financial closing (approx. 47 months)
20
21. Article 8 – Operation and Management of the Plant
Plant operations coordination with the Water Authority
Plant operations record keeping and reporting requirements
Requirement to provide Water Authority administrative space at the Plant
Water Authority access rights to the Plant, including tours
Water Authority rights to deal with “unworkable relationship” with Plant
Chief Operator
Determination of Annual Management Fee
$5-10/AF based on performance
21
22. Article 9 – General Performance Responsibilities
Poseidon Product Water Quality Guarantee
Off-Specification Product Water and Unacceptable Water
Remedies for Breach of Product Water Quality Guarantee
Annual Supply and Demand Commitments by Poseidon and the
Water Authority
Product Water delivery scheduling
Plant flow rate changes and limitations
Poseidon requirements to make “shortfall payments” on pipeline
debt service should Poseidon fail to deliver Product Water ordered
by the Water Authority
Drought Shortfall Payments
Raw seawater quality and Uncontrollable Circumstances
22
23. Article 10 – Maintenance, Repair and Replacement
Poseidon requirements to document Maintenance, Repair and
Replacement Plans and Schedules
Water Authority rights to inspect the Plant
Annual maintenance inspection
Biennial full-scale inspection/review of Plant working condition and
performance capability
Poseidon requirements to maintain a Computerized Maintenance
Management System (CMMS)
End-of-Term condition and performance requirements
23
24. Article 11 – Capital Modifications
Requirements and procedures regarding various types of capital
modifications:
Made at Poseidon request
Capital modification exceeds $10 million
No increase in the unit price
Made at Water Authority request
Potential increase to unit price
Required due to Compensation Adjustment Event
Capital modifications arising from uninsurable force majeure (e.g.,war,
terrorism), change in law (e.g., generally applicable to water treatment
facilities)
Potential increase to unit price
24
25. Article 12 – Contracting and Labor Practices
Poseidon use of agreed upon project contractors
Water Authority access to project contractors
Poseidon responsibility for project labor relations/disputes
Article 13 – Insurance, Damage and Destruction
Requirement for Project insurance and proof of coverage
25
26. Article 14 – Uncontrollable Circumstance Procedures
General procedures for claiming an uncontrollable circumstance
Notice to Water Authority within 10 business days of occurrence
Requirements for specific relief request and resumption of performance
Article 15 – Insurable and Uninsurable Force Majeure Events
Specific Poseidon schedule/performance relief under an insurable Force
Majeure event (e.g., fire, any peril other than uninsurable FM)
Specific Poseidon schedule/performance/compensation relief under an
uninsurable Force Majeure event (e.g., war, terrorism, nuclear explosion)
Requirements for project reinstatement plans and reconstruction standards
26
27. Article 16 – Change In Law Events And Other Uncontrollable
Circumstances
Specific schedule, performance and compensation relief (if any) for different
Change in Law events
Specific schedule, performance and compensation relief (if any) for other
uncontrollables
Those not covered by change in law or Force Majeure
27
28. Article 17 – Monthly Water Purchase Payments
Contract definitions of monthly charges
Capital charges
Operating charges
Electricity charges
Establishment and use of monthly/annual tracking accounts
Unit price cap for uncontrollable circumstances
Maximum of 10% annually above CPI
Cumulative maximum of 30% over CPI for the 30-year term
Billing and payment provisions
28
29. Article 18 – Dispute Resolution
Procedures for non-binding mediation
Court jurisdiction
San Diego County
Article 19 – Remedies of the Parties and Water Authority
Step-in Rights
Remedies for breach of contract by either party
Water Authority temporary step-in rights
Immediate and serious threat to public health and safety
29
30. Article 20 – Project Company Events of Default
Listing of specific events of default and breach of contract including:
• Failure to pass performance testing by the agreed upon Commercial
Operations Date
• Poseidon project company bankruptcy or abandonment of the project
• Repeated violations of Primary Drinking Water Standards
• Multiple notices of violation issued by a regulatory agency
• Deliveries less than 75 percent of the annual amount
• Failure to make Contracted Shortfall Payments
Water Authority termination right under an event of default
30
31. Article 21 – Water Authority Events of Default
Listing of specific events of default including:
Failure to pay undisputed bill amounts owed Poseidon within 45 days of
the due date
Water Authority breach that materially and adversely affects performance
of Contract obligations
Water Authority bankruptcy
Project Company options
Article 22 – Termination
Water Authority termination rights
Poseidon termination rights
31
32. Article 23 – Water Authority Project Assets Purchase Options
Purchase option during the term
After 10 years of operation
Purchase price = outstanding bond indebtedness + discounted NPV of remaining
equity return + any “breakage” fees associated with O&M agreement
Purchase option in the event of financing unavailability
Purchase option upon an event of default
Purchase option at the end of the term
Purchase price = $1
32
33. Article 24 – Assignment and Change in Control
Limitations on Poseidon’s future assignment or transfer of interest in the
WPA to another party
Limitations on changes in control of Project company
Article 25 – Indemnification
Circumstances and procedures for Poseidon indemnification of the
Water Authority
33
34. Article 26 – Miscellaneous Provisions
Requirement for Water Authority consent for any sale of the Plant
Procedures for contract administration
Water Authority and Poseidon confidentiality provisions
Water Authority license to use intellectual property developed as part
of the Project
34
36. 1. The Electricity Charge is 3. The Capital Charge is
driven by: driven by:
• Poseidon’s Capital
• Terms of Poseidon’s O&M
Budget
Agreement with IDE
Electricity • Bond Issuance
• SDG&E Rates
Charge • Negotiated Equity
• Water Authority’s option to Return/Developer Fee
select supplier • Development period
The Electricity Charge will vary
Capital costs
with electricity prices Charge The Capital Charge is fixed
Operating at a pre-established
escalation rate
Charge
2. The Operating Charge is
driven by:
• Terms of Poseidon’s O&M
Agreement with IDE
• Other operating expenses
The Operating Charge is
indexed to CPI
36
37. Direct costs
Capital Costs
▪ Desal Plant Related: $484 Million
▪ Includes: planning, permitting, design, construction, and legal costs
▪ SDG&E substation: $20 Million
▪ Wetlands Mitigation: $23 Million
▪ Includes: design, permitting and construction of 66 acres of wetlands
▪ GHG Mitigation: $1.25 Million
▪ Includes: reforestation and one time purchase of mitigation credits
▪ Conveyance Pipeline: $163 Million
Total Capital Costs: $691 Million
Financing Costs
Reserves, capitalized interest, etc: $213 Million
37
38. Total Capital Costs: $691 Million
Financing Costs: $213 Million
Total Cost $904 Million
Method of Finance
▪ 82% funded through Bonds issued by the California
Pollution Control Financing Authority
▪ 18% Cash Equity from Stonepeak Infrastructure
Bond Financing Equity Contribution
$740 Million $164 Million
38
39. Direct costs
Operating and Maintenance Costs:
Fixed O&M costs: $22.7 million annually
▪ Non electricity: $19.2 million annually
▪ Electricity: $3.5 million annually
Variable O&M Costs: $26.1 - $30.4 million annually
▪ Non electricity: $4.9 – $5.6 million annually
▪ Electricity: $21.2 – $24.8 million annually
Total O&M Costs: $48.8- $53.1 million annually
Costs reflect a range of 48,000 AFY-56,000 AFY
39
40. Direct Costs associated with WPA
Payments to Poseidon
▪ Capital Charge
▪ Operating Charge
Debt Service on Conveyance Pipeline
48,ooo acre feet per year 56,000 acre feet per year
$2,097/AF $1,876/AF
40
41. Indirect Costs
Water Authority costs: Pipeline 3 and Twin Oaks Valley
WTP improvements; Twin Oaks additional operating costs,
oversight during project construction
48,ooo acre feet per year 56,000 acre feet per year
$96 + $83 = $179/AF $82 + $71 = $153/AF
Administrative Costs during operation
48,ooo acre feet per year 56,000 acre feet per year
$14/AF $12/AF
41
42. Total Unit Cost
Payments to Poseidon
Debt Service on Conveyance Pipeline
Water Authority Improvements and Construction
Oversight
Twin Oaks additional Operating Costs
Water Authority administrative Costs during operations
48,ooo acre feet per year 56,000 acre feet per year
$2,290/AF $2,041/AF
42
43. Finalize Proposed WPA and Technical Appendices
Finalize construction and operating prices
Finalize Design Build Agreement for new pipeline
Finalize Bond and other financing documents
Board incorporates into rate and charge structure
Finalize agreement for Member Agency purchase as local supply
Hold two evening community meetings
43
44. Public Meetings (Two)
Evening Water Planning Committee Meeting at SDCWA
▪ October 2, 2012 - 6:30 pm, SDCWA, 4677 Overland Ave., San Diego
Evening Water Planning Committee meeting in Carlsbad
▪ October 10, 2012 - 6:30 pm, City of Carlsbad Faraday Operations Center
October Special Board Meeting – Oct. 11, 2012
Australian Desalination experience
Detailed discussion on Draft WPA costs and terms
Continue discussions on financial components
Continue discussion on rate structure
44
45. October Regular Board Meeting – Oct. 25, 2012
Review actions related to Pipeline 3 rehabilitation, Twin Oaks and
other distribution system activities
Continue discussions on financial components and rate structure
45