SlideShare a Scribd company logo
OPTIMIZATION OF WASTE HANDLING
IN SURFACE MINES
INTRODUCTION
๏ƒ˜ The prime objective of waste dump planning is to minimize the vertical
and horizontal distance between source and disposal area.
๏ƒ˜ Other factors like stability, availability of dumping area,
environmental hazards, types of equipments used etc. usually act
counter to above objective.
๏ƒ˜ Therefore, it is necessary to determine basic factors governing the
waste dump plan for an opencast mine
OBJECTIVE
(1) To study factors governing waste handling in
opencast mines.
(2) To optimize the waste handling capacity of an
opencast mine.
PARAMETERS AFFECTING WASTE HANDLING
CAPACITY OF A MINE
ECONOMIC PARAMETERS
1) Minimize the horizontal and vertical distance
of the source to disposal area ,
2) Deciding type of dumping ( in-pit or ex-pit)
3) cost of establishing a safe dump.
DESIGN PARAMETERS
๏ƒ’ (1) Economic :-
I. Minimize vertical and horizontal distance,
II. Minimize the current haulage cost versus the
discounted future re-handling cost of in-pit dumps.
๏ƒ’ (2) Non-economic:-
i. Stability,
ii. Political or surface rights,
iii. Environmental considerations,
iv. Physical configuration of dumps,
v. Method of placement,
vi. The planned development schedule.
GENERAL ENGINEERING
1) Swell factor of the run-of-mine,
2) Compaction ratio,
3) Angle of repose of the dump material,
4) Supportive surface strength of dump material,
5) Other factors
OTHER FACTORS
๏ƒ˜ Distribution at the time of a new dump,
๏ƒ˜ Notching of low levels of the dump,
๏ƒ˜ Removal of vegetation and other unconsolidated
material for obtaining a stable base,
๏ƒ˜ End dump from pit head for good draining pattern,
๏ƒ˜ Properly placing the drainage structures like culvert
pipes etc.
OPERATING CONSIDERATIONS
1) A slight positive gradient should be maintained at
the dump to ensure that the run off will drain away
from crest to natural ground.
2) Positive gradient is also good as the haul trucks
will have to power back to dump rather than roll
back.
3) In cases where the dump failure is serious, then
an alternative dump location will have to be used
until the situation is corrected.
4) For stabilizing dump failure we can put a layer of
lower dump on the toe of the failure
CASE STUDY
๏ƒผ Preparing a case study on the waste dumping
management of a mine having both in-pit and ex-pit
dumps.
๏ƒผ Finding sites for in-pit and ex- pit dumping in the
mine.
PROBLEM STATEMENT
Previously the mine had 2 box cuts, one in A block
and another one was in B block to reach the
requirement of 8Mtpa. Ex-Pit dump was placed in
North-West side of A block. With changes in mine
sequence (i.e. start of mine from B block with
5.0mtpa capacity) we need to find place of dumping
overburden.
INTRODUCTI
ON
๏ƒ’ The combined area of the blocks is 7.81km2 .
๏ƒ’ The topography over the coal bearing area is gently undulating ,
but rises steeply to the north from the block boundary.
๏ƒ’ The coal seams are steeply dipping and the blocks are
intersected by several faults.
๏ƒ’ There is total of over 20 named seams varying in thickness up
to 7 m, but generally 1 to 2 meters.
๏ƒ’ Strip ratio is 5.16 bcm/t (bank cubic meters per tonnes)
๏ƒ’ A and B blocks contain 2 blocks
๏ƒ‰ 1) West block (A block)
๏ƒ‰ 2) East block (pachmo)
INTRODUCTION OF KBP BLOCK
A- Block
B Block
Bโ€™s Nallah
A Block
B Block
Area - 865.63
Area -1065.89
STUDY OF TOPOGRAPHY OF KBP
BLOCK
B-Block
Rl-330
Rl-360
Rl-330
Rl-350
Rl-370
Rl-370
1. General Topography of Block is dipping down from West to east and North to South. RL
is varying fro n 330 min to 380 maximum.
2. There is no perennial nala within Pachmo block bout water may ingress from Northern
STUDY OF COAL BEARING AREA IN AND AROUND BLOCK
B-Block
Non Coal Bearing
area within block
Coal Bearing area
Coal Bearing area
of other mine
๏ƒ’ EX-PIT DUMP
30M
30M 30M
30M30M
37.5หš
37.5หš
90
M28หš
โ€ข IN-PIT DUMP
30M
30M
30M
10M
37.5หš
40M
28หš
STUDY OF RULES AND
REGULATIONS
- EC condition
- Mining Plan
- By-Laws
Conceptual dump configuration
Terrace angle- 37.5
deg
Aver all dump Slopes-
28deg
PRODCUTION SCHEDULE FOR 5.0 MTPA COAL FROM
PACHMOY1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total
Coal -mt 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0
OB -
mbCuM 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 5.0 245.0
Terrace wise ROM Coal -MT
EBC 0.3 1.0 2.3 1.9 5.5
ET1 0.6 0.6 1.6 2.0 2.0 2.0 0.8 9.5
ET2 0.6 1.6 2.0 1.6 1.6 1.6 0.6 9.6
ET3 1.0 1.4 1.4 1.4 2.7 2.7 2.7 1.1 14.2
WT6 1.3 1.3 1.3 1.3 1.5 0.4 7.0
WT5 0.5 1.0 1.0 0.6 3.1
Total 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0
Terrace wise OB-Mbcum
EBC 1.5 5.0 11.5 9.5 28.0
ET1 3.0 3.0 7.8 10.0 10.0 10.0 3.8 48.0
ET2 3.0 7.8 10.0 8.1 8.1 8.1 2.9 48.0
ET3 5.0 6.9 6.9 6.9 13.4 13.4 13.4 5.3 71.0
WT6 6.3 6.3 6.6 6.6 7.3 2.0 35.0
WT5 2.5 5.0 5.0 2.8 15.0
Total OB 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 4.8 244.0
โ€ขTotal OB Generation will be 245 mbcum. ( 342 Loose MCuM )
โ€ขThe overburden generated needs to be disposed either In-Pit or Ex-Pit
โ€ข Effort should be there to minimize ex-pit dumping and maximize in-pit
dumping
STUDY OF ULTIMATE PIT OF PACHMO
+10m
+190m
+280m
+330m
Non Coal Bearing Area=60
ha
Depth of Mine 290mtra
Width- NS 1.3 KM
Width EW- 2.4 KM
Rom reserves- 48 mt
+100m
Bโ€™s Nallah
Pit advance direction (East to West
A
B
Section Along - AB
Bโ€™s Nallah
EBC 5.5
ET1 9.5
ET2 9.6
ET3 14.2
WT6 7
WT5 3.05
Total 48.85
ROM reserves
STUDY OF TERRACE SEQUENCING
BCET
1
ET
2
WT-6
ET
3
WT-5
Pit advance direction (East to West
POSSIBLE LOCATIONS OF DUMPING WASTE
Dump-1: Dumping over coal bearing area located towards end of pit
Dump-2: Dumping over non-coal bearing area in North- East Part.
Dump-3: Dumping Ex-Pit along northern boundary.
Dump-4: In-Pit Dumping along with mining.
Dump-1
Dump-2
Dump-3
Dump-4
CRITERIA FOR IN-PIT DUMP
SEQUENCING
๏ƒ‰ 1st In โ€“Pit dumping can be done after the completion of Box-
Cut.
๏ƒ‰ Subsequent in-pit dumping is only possible after completion of
each terrace.
๏ƒ‰ There should be space of around 200mtrs from the toe of In
pit dump and bottom of pit
๏ƒ‰ Ultimate pit Geometry should be favorable for in-Pit Dumping.
45
deg
BC
T1T2
T3T4
200mtrs
DUMP SPACE AVAILABLE
Dump-1: 12.4 M CuM ( to be re-handled)
Dump-2: 16.8 M CuM
Dump-3: 202 MCuM + 12.4 MCuM
Dump-4: In- Pit Dump -1: 12.5 MCuM
In-Pit Dump-2 : 35.4 MCuM
In โ€“Pit Dump-3 : 57 .6 MCuM
Dump-1
Dump-2
Dump-3
Dump-4
OVER BURDEN DUMPING
SEQUANCE
Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total
Total Loose OB Mbcum 2.1 11.2 24.5 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 17.5 6.7 342.0
AVAILABLE DUMP SPACE IN MBCUM
Dump-I 12.4
Dump-2 16.8 16.8
In-Pit BC dump 12.5 12.5
In-Pit T1 dump 35.4 35.4
In-Pit T1 dump 57.6 57.6
Total 29.1 12.5 35.4 57.6 122.2
Internal dumping-MCuM 2.1 11.2 15.8 12.5 35.0 35.0 27.5 139.1
External Dumping -
MCuM 8.7 35.0 22.5 35.0 35.0 35.0 7.5 17.5 6.7 202.8
PIT POSITION AT END OF BOX CUT ( Year -4
Dump-1 Completed
12.4 mCuM
Dump-2
Completed
16.2 mCuM
End of Box Cut
T-1, T2 & T3 in
operation
Ex-Pit Dump in
operation
44 mCuM
IN PIT DUMP-1 AFTER COMPLETION OF BOX
CUT
( Year -5)
T-1, T2 & T3 in
operation
Ex-Pit Dump in
operation
In Pit Dump-1
12.5 MCum
IN PIT DUMP-2 AFTER COMPLETION OF
TERRACE T-1 (Year -9)
T-2, T3 & WT6
in operation
Ex-Pit Dump in
operation
In Pit Dump-2
35.4 MCum
Dump-1 has
been re-handled
IN PIT DUMP-3 AFTER COMPLETION OF
TERRACE
T-2 (Year -10)
T-3, WT-6 & WT5
in operation
Ex-Pit Dump in
operation
In Pit Dump-3
57.57 MCum
ULTIMATE VOID AFTER -13 YEARS ( END OF LIFE OF
MINE)
T-3, WT-6 & WT5
in operation
Ex-Pit Dump in
operation
( 296 HA)
212 MCuM
In Pit Dump-1 ,2
,3
105 MCum
Total Void โ€“ 173
MCuM
CONCLUSIONS
1. Ex-Pit dumping space is essential for 5.0mtpa within 2
& ยฝ year.
2. Ex-Pit dump space should be acquired within 2 &1/2
year for sustaining production level.
2. The area required for ex-pit dumping space is 296
hector.
3. Due to faster rate of production big ultimate void is
formed.
2. However, ultimate void can be used if we continue
mining in KB Block.

More Related Content

What's hot

Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
SATYANARAYANA I
ย 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
Infocengrs63
ย 
Utah
UtahUtah
Utah
Jim Werner
ย 
Tipong report
Tipong report Tipong report
Tipong report
sanjay kumar choudhary
ย 
Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016
Company Spotlight
ย 
Crescent Power Point
Crescent Power PointCrescent Power Point
Crescent Power Point
Kurt Hoffman
ย 
Coal Sccl
Coal ScclCoal Sccl
Coal Sccl
VR M
ย 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
sou_suk_sou
ย 
HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)
John Coughlan
ย 
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Marcellus Drilling News
ย 
New Pacific Metals Corporate Presentation
New Pacific Metals Corporate PresentationNew Pacific Metals Corporate Presentation
New Pacific Metals Corporate Presentation
newpacific
ย 
Presentation - July 4, 2011
Presentation - July 4, 2011Presentation - July 4, 2011
Presentation - July 4, 2011
newpacificmetals
ย 
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
AMIT SAHU
ย 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
John Latilla
ย 
Kombat Copper Corporate Presentation
Kombat Copper Corporate PresentationKombat Copper Corporate Presentation
Kombat Copper Corporate Presentation
kombatcopper
ย 
TriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentationTriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentation
Chris Helweg
ย 
Barapukuria
Barapukuria Barapukuria
Barapukuria
redwanislam14
ย 

What's hot (17)

Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
ย 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
ย 
Utah
UtahUtah
Utah
ย 
Tipong report
Tipong report Tipong report
Tipong report
ย 
Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016Terra X Minerals Presentation March 2016
Terra X Minerals Presentation March 2016
ย 
Crescent Power Point
Crescent Power PointCrescent Power Point
Crescent Power Point
ย 
Coal Sccl
Coal ScclCoal Sccl
Coal Sccl
ย 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
ย 
HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)HCK AJM Paper May 03 (Double Space)
HCK AJM Paper May 03 (Double Space)
ย 
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
Portion of Gastar Investor Presentation for August 2015 Focused on Marcellus/...
ย 
New Pacific Metals Corporate Presentation
New Pacific Metals Corporate PresentationNew Pacific Metals Corporate Presentation
New Pacific Metals Corporate Presentation
ย 
Presentation - July 4, 2011
Presentation - July 4, 2011Presentation - July 4, 2011
Presentation - July 4, 2011
ย 
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
ย 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
ย 
Kombat Copper Corporate Presentation
Kombat Copper Corporate PresentationKombat Copper Corporate Presentation
Kombat Copper Corporate Presentation
ย 
TriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentationTriMetals Mining Inc. april-2017-corporate-presentation
TriMetals Mining Inc. april-2017-corporate-presentation
ย 
Barapukuria
Barapukuria Barapukuria
Barapukuria
ย 

Similar to Optimization of waste handling in surface mines

Conversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineConversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast Mine
Abdul Mujeeb
ย 
Group 3 Presentation
Group 3 PresentationGroup 3 Presentation
Group 3 Presentation
Mark Whitfield
ย 
Pillar design
Pillar designPillar design
Pillar design
Pillar designPillar design
ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...
ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...
ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...
Egyptian Engineers Association
ย 
Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015
Terry Butler-Blaxell
ย 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)
Gautam Sharma
ย 
Pillar design
Pillar designPillar design
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case study
TIKESHWAR MAHTO
ย 
African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006
James AH Campbell
ย 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
AGNIVORAY1
ย 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
SATYANARAYANA I
ย 
Internship report
Internship reportInternship report
Internship report
Ghulam Mehdi
ย 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
Jill Reeves
ย 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
Jill Reeves
ย 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
MD.Suresh Kumar
ย 
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenpark
Greenbridge nv
ย 
Mahadevpuri ug mine
Mahadevpuri ug mineMahadevpuri ug mine
Mahadevpuri ug mine
Shivam Bambhaniya
ย 
326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptx326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptx
mohdsuriamohdsuhaimi
ย 
Extraction of developed pillars by opencast mine: acase study
Extraction of developed pillars by opencast mine:   acase studyExtraction of developed pillars by opencast mine:   acase study
Extraction of developed pillars by opencast mine: acase study
DGMS, Ministry of Labour & Employment, New Delhi
ย 

Similar to Optimization of waste handling in surface mines (20)

Conversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineConversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast Mine
ย 
Group 3 Presentation
Group 3 PresentationGroup 3 Presentation
Group 3 Presentation
ย 
Pillar design
Pillar designPillar design
Pillar design
ย 
Pillar design
Pillar designPillar design
Pillar design
ย 
ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...
ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...
ilovepdf_#ุชูˆุงุตู„_ุชุทูˆูŠุฑ ุงู„ู…ุญุงุถุฑุฉ ุฑู‚ู… 187 ุฃุณุชุงุฐ ุฏูƒุชูˆุฑ / ู…ุฏุญุช ูƒู…ุงู„ ุนุจุฏุงู„ู„ู‡ ุนู†ูˆุงู† ...
ย 
Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015Bandalup Magnesite Overview Public_jun 2015
Bandalup Magnesite Overview Public_jun 2015
ย 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)
ย 
Pillar design
Pillar designPillar design
Pillar design
ย 
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case study
ย 
African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006
ย 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
ย 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
ย 
Internship report
Internship reportInternship report
Internship report
ย 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
ย 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
ย 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
ย 
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenpark
ย 
Mahadevpuri ug mine
Mahadevpuri ug mineMahadevpuri ug mine
Mahadevpuri ug mine
ย 
326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptx326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptx
ย 
Extraction of developed pillars by opencast mine: acase study
Extraction of developed pillars by opencast mine:   acase studyExtraction of developed pillars by opencast mine:   acase study
Extraction of developed pillars by opencast mine: acase study
ย 

More from Safdar Ali

Safety in mines
Safety in minesSafety in mines
Safety in mines
Safdar Ali
ย 
Tunneling
TunnelingTunneling
Tunneling
Safdar Ali
ย 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
Safdar Ali
ย 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.
Safdar Ali
ย 
Basting
BastingBasting
Basting
Safdar Ali
ย 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operations
Safdar Ali
ย 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for mining
Safdar Ali
ย 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floor
Safdar Ali
ย 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stability
Safdar Ali
ย 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
Safdar Ali
ย 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their units
Safdar Ali
ย 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mine
Safdar Ali
ย 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezing
Safdar Ali
ย 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
Safdar Ali
ย 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second schedule
Safdar Ali
ย 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sections
Safdar Ali
ย 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveying
Safdar Ali
ย 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applications
Safdar Ali
ย 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
Gyrotheodolite
Safdar Ali
ย 
Gps2
Gps2Gps2
Gps2
Safdar Ali
ย 

More from Safdar Ali (20)

Safety in mines
Safety in minesSafety in mines
Safety in mines
ย 
Tunneling
TunnelingTunneling
Tunneling
ย 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
ย 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.
ย 
Basting
BastingBasting
Basting
ย 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operations
ย 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for mining
ย 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floor
ย 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stability
ย 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
ย 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their units
ย 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mine
ย 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezing
ย 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
ย 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second schedule
ย 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sections
ย 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveying
ย 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applications
ย 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
Gyrotheodolite
ย 
Gps2
Gps2Gps2
Gps2
ย 

Recently uploaded

Bossa Nโ€™ Roll Records by Ismael Vazquez.
Bossa Nโ€™ Roll Records by Ismael Vazquez.Bossa Nโ€™ Roll Records by Ismael Vazquez.
Bossa Nโ€™ Roll Records by Ismael Vazquez.
IsmaelVazquez38
ย 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
zuzanka
ย 
Accounting for Restricted Grants When and How To Record Properly
Accounting for Restricted Grants  When and How To Record ProperlyAccounting for Restricted Grants  When and How To Record Properly
Accounting for Restricted Grants When and How To Record Properly
TechSoup
ย 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
ย 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
ย 
How to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in useHow to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in use
Celine George
ย 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
ย 
Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
nitinpv4ai
ย 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
zuzanka
ย 
Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
nitinpv4ai
ย 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
nitinpv4ai
ย 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
EduSkills OECD
ย 
How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17
Celine George
ย 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
David Douglas School District
ย 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
Krassimira Luka
ย 
How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17
Celine George
ย 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
PsychoTech Services
ย 
skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)
Mohammad Al-Dhahabi
ย 
How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17
Celine George
ย 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
nitinpv4ai
ย 

Recently uploaded (20)

Bossa Nโ€™ Roll Records by Ismael Vazquez.
Bossa Nโ€™ Roll Records by Ismael Vazquez.Bossa Nโ€™ Roll Records by Ismael Vazquez.
Bossa Nโ€™ Roll Records by Ismael Vazquez.
ย 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
ย 
Accounting for Restricted Grants When and How To Record Properly
Accounting for Restricted Grants  When and How To Record ProperlyAccounting for Restricted Grants  When and How To Record Properly
Accounting for Restricted Grants When and How To Record Properly
ย 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
ย 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
ย 
How to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in useHow to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in use
ย 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
ย 
Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
ย 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
ย 
Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
ย 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
ย 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
ย 
How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17
ย 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
ย 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
ย 
How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17
ย 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
ย 
skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)
ย 
How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17
ย 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
ย 

Optimization of waste handling in surface mines

  • 1.
  • 2. OPTIMIZATION OF WASTE HANDLING IN SURFACE MINES
  • 3. INTRODUCTION ๏ƒ˜ The prime objective of waste dump planning is to minimize the vertical and horizontal distance between source and disposal area. ๏ƒ˜ Other factors like stability, availability of dumping area, environmental hazards, types of equipments used etc. usually act counter to above objective. ๏ƒ˜ Therefore, it is necessary to determine basic factors governing the waste dump plan for an opencast mine
  • 4. OBJECTIVE (1) To study factors governing waste handling in opencast mines. (2) To optimize the waste handling capacity of an opencast mine.
  • 5. PARAMETERS AFFECTING WASTE HANDLING CAPACITY OF A MINE
  • 6. ECONOMIC PARAMETERS 1) Minimize the horizontal and vertical distance of the source to disposal area , 2) Deciding type of dumping ( in-pit or ex-pit) 3) cost of establishing a safe dump.
  • 7. DESIGN PARAMETERS ๏ƒ’ (1) Economic :- I. Minimize vertical and horizontal distance, II. Minimize the current haulage cost versus the discounted future re-handling cost of in-pit dumps.
  • 8. ๏ƒ’ (2) Non-economic:- i. Stability, ii. Political or surface rights, iii. Environmental considerations, iv. Physical configuration of dumps, v. Method of placement, vi. The planned development schedule.
  • 9. GENERAL ENGINEERING 1) Swell factor of the run-of-mine, 2) Compaction ratio, 3) Angle of repose of the dump material, 4) Supportive surface strength of dump material, 5) Other factors
  • 10. OTHER FACTORS ๏ƒ˜ Distribution at the time of a new dump, ๏ƒ˜ Notching of low levels of the dump, ๏ƒ˜ Removal of vegetation and other unconsolidated material for obtaining a stable base, ๏ƒ˜ End dump from pit head for good draining pattern, ๏ƒ˜ Properly placing the drainage structures like culvert pipes etc.
  • 11. OPERATING CONSIDERATIONS 1) A slight positive gradient should be maintained at the dump to ensure that the run off will drain away from crest to natural ground. 2) Positive gradient is also good as the haul trucks will have to power back to dump rather than roll back. 3) In cases where the dump failure is serious, then an alternative dump location will have to be used until the situation is corrected. 4) For stabilizing dump failure we can put a layer of lower dump on the toe of the failure
  • 12. CASE STUDY ๏ƒผ Preparing a case study on the waste dumping management of a mine having both in-pit and ex-pit dumps. ๏ƒผ Finding sites for in-pit and ex- pit dumping in the mine.
  • 13. PROBLEM STATEMENT Previously the mine had 2 box cuts, one in A block and another one was in B block to reach the requirement of 8Mtpa. Ex-Pit dump was placed in North-West side of A block. With changes in mine sequence (i.e. start of mine from B block with 5.0mtpa capacity) we need to find place of dumping overburden.
  • 14. INTRODUCTI ON ๏ƒ’ The combined area of the blocks is 7.81km2 . ๏ƒ’ The topography over the coal bearing area is gently undulating , but rises steeply to the north from the block boundary. ๏ƒ’ The coal seams are steeply dipping and the blocks are intersected by several faults. ๏ƒ’ There is total of over 20 named seams varying in thickness up to 7 m, but generally 1 to 2 meters. ๏ƒ’ Strip ratio is 5.16 bcm/t (bank cubic meters per tonnes) ๏ƒ’ A and B blocks contain 2 blocks ๏ƒ‰ 1) West block (A block) ๏ƒ‰ 2) East block (pachmo)
  • 15. INTRODUCTION OF KBP BLOCK A- Block B Block Bโ€™s Nallah A Block B Block Area - 865.63 Area -1065.89
  • 16. STUDY OF TOPOGRAPHY OF KBP BLOCK B-Block Rl-330 Rl-360 Rl-330 Rl-350 Rl-370 Rl-370 1. General Topography of Block is dipping down from West to east and North to South. RL is varying fro n 330 min to 380 maximum. 2. There is no perennial nala within Pachmo block bout water may ingress from Northern
  • 17. STUDY OF COAL BEARING AREA IN AND AROUND BLOCK B-Block Non Coal Bearing area within block Coal Bearing area Coal Bearing area of other mine
  • 18. ๏ƒ’ EX-PIT DUMP 30M 30M 30M 30M30M 37.5หš 37.5หš 90 M28หš โ€ข IN-PIT DUMP 30M 30M 30M 10M 37.5หš 40M 28หš STUDY OF RULES AND REGULATIONS - EC condition - Mining Plan - By-Laws Conceptual dump configuration Terrace angle- 37.5 deg Aver all dump Slopes- 28deg
  • 19. PRODCUTION SCHEDULE FOR 5.0 MTPA COAL FROM PACHMOY1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total Coal -mt 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0 OB - mbCuM 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 5.0 245.0 Terrace wise ROM Coal -MT EBC 0.3 1.0 2.3 1.9 5.5 ET1 0.6 0.6 1.6 2.0 2.0 2.0 0.8 9.5 ET2 0.6 1.6 2.0 1.6 1.6 1.6 0.6 9.6 ET3 1.0 1.4 1.4 1.4 2.7 2.7 2.7 1.1 14.2 WT6 1.3 1.3 1.3 1.3 1.5 0.4 7.0 WT5 0.5 1.0 1.0 0.6 3.1 Total 0.3 1.6 3.5 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 2.5 1.0 49.0 Terrace wise OB-Mbcum EBC 1.5 5.0 11.5 9.5 28.0 ET1 3.0 3.0 7.8 10.0 10.0 10.0 3.8 48.0 ET2 3.0 7.8 10.0 8.1 8.1 8.1 2.9 48.0 ET3 5.0 6.9 6.9 6.9 13.4 13.4 13.4 5.3 71.0 WT6 6.3 6.3 6.6 6.6 7.3 2.0 35.0 WT5 2.5 5.0 5.0 2.8 15.0 Total OB 1.5 8.0 17.5 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 12.5 4.8 244.0 โ€ขTotal OB Generation will be 245 mbcum. ( 342 Loose MCuM ) โ€ขThe overburden generated needs to be disposed either In-Pit or Ex-Pit โ€ข Effort should be there to minimize ex-pit dumping and maximize in-pit dumping
  • 20. STUDY OF ULTIMATE PIT OF PACHMO +10m +190m +280m +330m Non Coal Bearing Area=60 ha Depth of Mine 290mtra Width- NS 1.3 KM Width EW- 2.4 KM Rom reserves- 48 mt +100m Bโ€™s Nallah Pit advance direction (East to West
  • 21. A B Section Along - AB Bโ€™s Nallah EBC 5.5 ET1 9.5 ET2 9.6 ET3 14.2 WT6 7 WT5 3.05 Total 48.85 ROM reserves STUDY OF TERRACE SEQUENCING BCET 1 ET 2 WT-6 ET 3 WT-5 Pit advance direction (East to West
  • 22. POSSIBLE LOCATIONS OF DUMPING WASTE Dump-1: Dumping over coal bearing area located towards end of pit Dump-2: Dumping over non-coal bearing area in North- East Part. Dump-3: Dumping Ex-Pit along northern boundary. Dump-4: In-Pit Dumping along with mining. Dump-1 Dump-2 Dump-3 Dump-4
  • 23. CRITERIA FOR IN-PIT DUMP SEQUENCING ๏ƒ‰ 1st In โ€“Pit dumping can be done after the completion of Box- Cut. ๏ƒ‰ Subsequent in-pit dumping is only possible after completion of each terrace. ๏ƒ‰ There should be space of around 200mtrs from the toe of In pit dump and bottom of pit ๏ƒ‰ Ultimate pit Geometry should be favorable for in-Pit Dumping. 45 deg BC T1T2 T3T4 200mtrs
  • 24. DUMP SPACE AVAILABLE Dump-1: 12.4 M CuM ( to be re-handled) Dump-2: 16.8 M CuM Dump-3: 202 MCuM + 12.4 MCuM Dump-4: In- Pit Dump -1: 12.5 MCuM In-Pit Dump-2 : 35.4 MCuM In โ€“Pit Dump-3 : 57 .6 MCuM Dump-1 Dump-2 Dump-3 Dump-4
  • 25. OVER BURDEN DUMPING SEQUANCE Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Y13 Total Total Loose OB Mbcum 2.1 11.2 24.5 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 17.5 6.7 342.0 AVAILABLE DUMP SPACE IN MBCUM Dump-I 12.4 Dump-2 16.8 16.8 In-Pit BC dump 12.5 12.5 In-Pit T1 dump 35.4 35.4 In-Pit T1 dump 57.6 57.6 Total 29.1 12.5 35.4 57.6 122.2 Internal dumping-MCuM 2.1 11.2 15.8 12.5 35.0 35.0 27.5 139.1 External Dumping - MCuM 8.7 35.0 22.5 35.0 35.0 35.0 7.5 17.5 6.7 202.8
  • 26. PIT POSITION AT END OF BOX CUT ( Year -4 Dump-1 Completed 12.4 mCuM Dump-2 Completed 16.2 mCuM End of Box Cut T-1, T2 & T3 in operation Ex-Pit Dump in operation 44 mCuM
  • 27. IN PIT DUMP-1 AFTER COMPLETION OF BOX CUT ( Year -5) T-1, T2 & T3 in operation Ex-Pit Dump in operation In Pit Dump-1 12.5 MCum
  • 28. IN PIT DUMP-2 AFTER COMPLETION OF TERRACE T-1 (Year -9) T-2, T3 & WT6 in operation Ex-Pit Dump in operation In Pit Dump-2 35.4 MCum Dump-1 has been re-handled
  • 29. IN PIT DUMP-3 AFTER COMPLETION OF TERRACE T-2 (Year -10) T-3, WT-6 & WT5 in operation Ex-Pit Dump in operation In Pit Dump-3 57.57 MCum
  • 30. ULTIMATE VOID AFTER -13 YEARS ( END OF LIFE OF MINE) T-3, WT-6 & WT5 in operation Ex-Pit Dump in operation ( 296 HA) 212 MCuM In Pit Dump-1 ,2 ,3 105 MCum Total Void โ€“ 173 MCuM
  • 31. CONCLUSIONS 1. Ex-Pit dumping space is essential for 5.0mtpa within 2 & ยฝ year. 2. Ex-Pit dump space should be acquired within 2 &1/2 year for sustaining production level. 2. The area required for ex-pit dumping space is 296 hector. 3. Due to faster rate of production big ultimate void is formed. 2. However, ultimate void can be used if we continue mining in KB Block.