SlideShare a Scribd company logo
Structural and stability
assessment for ex-pit dump toe
locality optimisation: A case study
John Latilla
26 November 2015
BBUGS / BOHOGS Supplier’s day - Moranbah
www.amcconsultants.com
Ukhaa Khudag coal mine, Mongolia
www.amcconsultants.com
Project location
www.amcconsultants.com
Project infrastructure
15 Mtpa CHPP18 MW Power Station
Office and mess hall Mine Workshops
www.amcconsultants.com
Some key facts
• Multiple seams dipping generally 3° to 17° into highwall
• Flanks (endwalls) dipping 5° to 40° out of pit wall
• Terrace mining (truck and excavator)
• Mid volatile hard coking coal with thermal coal by-product
• Ex-pit waste dumping, at least for next 3 to 5 years
• Nameplate capacity of 15 Mtpa ROM coal to CHPP
• Life-of-Mine stripping ratio of 5.6:1
www.amcconsultants.com
The challenge
Optimise the locality of the northern ex-pit waste dump on order to
reduce dump truck round trip distances.
Earlier limit equilibrium analyses of cross-sections for pit walls below
the dump indicated the potential to steepen the OSA by as much as
4° through buffer blasting the entire slope
Insufficient geotechnical and geological data available to properly
identify buffer blasting target zones
The phreatic surface used is based on John Simmons’ work from the
Bowen Basin (far wetter conditions)
www.amcconsultants.com
The challenge in a nutshell
7
Possible structural interp.
with additional data
LOM structural interp.
New “optimised” crest locality
Potential gain
50m stand-off distance
not assessed – remains
constant
www.amcconsultants.com
Plan of action
Drill a series of six geotechnical boreholes sited to maximise data
from the potential buffer blasted endwall area. Boreholes required to
be oriented to enable structural and kinematic analyses
Drill ten percussion holes adjacent to and on top of the waste dump
to determine actual phreatic surface
Review geological structure of the ground containing the final
endwall slope beneath the waste dump
Conduct kinematic and limit equilibrium analyses to design optimal
OSA beneath the waste dump using the updated structural and
phreatic surface data
www.amcconsultants.com
Modifications
No acoustic televiewer available in country. Changed to drilling
oriented cored boreholes
60° inclined core boreholes, oriented by means of Ezy-Mark tool
(Reflex). Relies on leaving a crayon impression and a pin profile of
the bottom of the hole
Soft and friable coal and mudstone areas - too much fine and loose
material at bottom of hole to obtain an impression. Oriented core
data unavoidably biased to the stronger units
Inability to orient core in softer zones judged not to be a show
stopper. Overall structural orientations expected to be similar in hard
and softer rock
www.amcconsultants.com
Modifications continued
Two oriented holes close to the dump toe intersected basement rock
(dolerite and basalt) and “replacement” holes were drilled about
100 m further (South) from the dump toe
Info on the basement contacts and structure was nevertheless very
useful
www.amcconsultants.com
Oriented core drilling
11
www.amcconsultants.com
Coring through the waste dump
Local exploration drilling contractor used for the dump hydrology
holes. Did not have a percussion rig available so drilled the holes
with a coring rig
Core was not boxed or logged but simply laid out on the ground near
the rig. Recovery of core not called for in the work order
With an air drilled hole the expectation was that water level
monitoring would track the gradual climb of water level back up to
equilibrium. With water flushed coring the opposite was expected
www.amcconsultants.com
Waste dump core
13
www.amcconsultants.com
Structural data collection
Oriented core holes logged and photographed by the site
geotechnical team to CoreLog standard (ACARP 2015)
Individual defects identified and measured using CoreProfiler
(CSIRO). Builds a composite photograph of the core column from
core photographed in trays. From this, dip and dip direction are
determined for each defect and plotted on stereonet. Data was then
exported to Dips6.0 for further manipulation and assessment
CoreProfiler also produces RQD and fracture frequency data
CoreProfiler is still in development but was found to be a useful tool
www.amcconsultants.com
CoreProfiler – core box photo
From this:
15
www.amcconsultants.com
CoreProfiler work page example
To this:
16
www.amcconsultants.com
Structural assessment
Structural data analysed in Dips6.0 as follows:
• All defects in all boreholes, then split per endwall sector (NEW2
and NEW4) and finally split into individual boreholes
• Each of the above were then sub-divided into:
 All structure above the lowermost coal seam (BOC) and that below
BOC – the latter being the key strata for endwall design
 Bedding planes only split as above to determine structural trends in
sedimentary rock
• Shears and possible shears analysed separately – insufficient
numbers to analyse shears on a hole for hole basis.
www.amcconsultants.com
Selected stereonet plots
18
All shears – all b/hs
All defects – all b/hs
www.amcconsultants.com
Structural analysis summary
Description
Dip and Dip direction
(°)
Set 1 Set 2 Set 3
All defects for all boreholes 13/207 50/174 –
All defects above BOC 11/211 50/167 –
All defects below BOC 13/204 49/180 –
Bedding planes only for all
boreholes
13/208 49/179 –
Bedding planes only above BOC 14/213 52/173 –
Bedding planes only below BOC 12/203 47/183 –
All defects for basement rocks 11/214 51/180 –
Shears only for all boreholes
(orientation low to medium
confidence)
64/172 73/193 23/217
www.amcconsultants.com
Kinematic assessment
Critical Surface Limits
• Batters
 Final endwalls – 10%
 Interim endwalls – 15%
 Highwalls – 20%
• Overall slope angles
 Below critical infrastructure – 5%
 All others – 10%
www.amcconsultants.com
Kinematic assessment
Planar and wedge sliding are the most likely, kinematically
admissible, failure types
• Excluding the effect of shears:
 Batters should not be formed steeper than 55° in NEW4 and
70° in NEW2
 Overall slope angle (OSA) should not exceed 47°
• Taking shears into account:
 Batter slope angle drops to 25°. OSA 23° for NEW2 and 30°
for NEW4
• Assuming bedding shears will be buffer blasted:
 Max batter angle 55° and OSA 27° to 34°
www.amcconsultants.com
Selected stereonet plots
22
NEW2 batter scale planar sliding
NEW2 batter scale wedge sliding
www.amcconsultants.com
Kinematic analysis results summary
Slope scale Pit sector
Maximum slope dip angle and percentage of
critical surfaces
Planar sliding
(° / %)
Wedge sliding
(CS Mod)*
(° / %)
Batters
(15% critical
surfaces limit)
NEW2 70/13.7 70/13.2*
NEW4 55/14.9 67/15.0*
NEW2 shears 28/14.3 25/13.2
NEW4 shears 59/7.1 33/13.2
OSA
(10% critical
surfaces limit)
NEW2 49/9.8 47/9.8*
NEW4 47/9.7 49/9.8*
NEW2 shears 27/7.1 23/9.9
NEW4 shears 59/7.1 30/6.6
*The critical surface results for wedge sliding have a correction factor of 0.5 applied to better match site experience.
This is referred to as the modified wedge sliding critical surface value (CS Mod.).
www.amcconsultants.com
Structural interpretation
General trend indicated steeper than originally modelled coal
bearing strata along the northern boundary fault in 3 out of 4
cross-sections (CS 20a, 22 & 23)
The other cross-section (CS 28) indicated steeply dipping boundary
fault cutting off the coal strata
A stronger and less disturbed conglomerate zone was identified
below the BOC
Zone of steeply dipping sedimentary rocks assumed to extend along
the southern face of the northern boundary fault. Based on
previously exposed fault zones at UHG. Width variable
www.amcconsultants.com
Dump toe and borehole locality
25
Cross section lines
Geotech boreholes
Arrow denotes hole azimuth
Hydrology boreholes
www.amcconsultants.com
Structural interp. CS 20a
26
www.amcconsultants.com
Phreatic surface model
Locality
Distance from toe
(m)
Phreatic surface below original
ground surface (m)
Minimum Maximum Minimum Maximum
Generic
model
240 m from dump toe (on pit
side)
– 240 – – 28
~100m from dump toe 50 127 18 29 23
Immediately below dump toe 0 0 13 14 13
~60 from toe under dump 40 92 3 6 3
~180 from toe under dump 151 230 0 0 0
210 m from toe under dump 200 230 – – +2
[1] Note that where the pit crest is closer than 240 m the generic (or specific if known) phreatic surface
model must be merged with this model
www.amcconsultants.com
Phreatic surface interp. CS 28
28
www.amcconsultants.com
Limit equilibrium analyses
Based on oriented borehole data and observations of core recovered
from hydrological drilling the interpreted structure from the 2014
model has been modified
The endwall crest can be located up to 180 m further south
Existing minimum stand-off distance between dump toe and slope
crest of 50m was not investigated or altered in this study
The endwall areas represented by the two eastern most cross
sections (CS 23 & 28) require no additional buttressing or
dewatering
The most westerly, and deepest, endwall slope (as represented by
the two most westerly cross sections, CS 20a & 22) requires
extensive toe stabilisation plus dewatering
www.amcconsultants.com
Cross-section 20a
30
Buffer blast
Waste buttress
www.amcconsultants.com
Cross-section 28
31
GALEN A Version 6.10
Project UHG 2014 Slope Stability Analysis - Cross Section 28
File: C:UsersJlatillaDocumentsNumerical modellingGalenaUHG2015 NEW4 Buffered endwall below dump CS 28 (extended).gmf
Edited:
Processed:
21 Aug 2015
21 Aug 2015AMC ConsultantsLicensed to:
Analysis
Results
4
Multiple Stability Analysis
Method:
Surface:
Spencer-Wright
Circular
Critical Factor of Safety: 1.24
Interslice Force (Final) Angle: 28.9 °
Material K eys
WOB (c:27 ø:22.4 g:22)
MWOB (c:115 ø:31.7 g:23)
FOB (c:358 ø:37.2 g:24.5)
CF (c:40 ø:23 g:14.4)
BPS (c:0 ø:14 g:19.4)
WR (c:27 ø:26.8 g:18.3)
FSZ (c:24 ø:18 g:21.8)
CG (c:785 ø:42.9 g:24.7)
BW (c:612 ø:34.1 g:29)
BF (c:828 ø:41.1 g:29)
800 900 1000 1100 1200 1300
1200
1250
1300
1350
1400
1450
1500
1550
1600
1650
Buttress of flat to
shallow dipping strata
www.amcconsultants.com
Conclusions
This extensive study has resulted in far better understanding of the
structure and strength of critical strata beneath the waste dump toe
This improved knowledge has enabled the dump toe locality to be
moved significantly closer to the pit crest thereby significantly
reducing dump truck round trip distances
Thank you
Energy Resources LLC are thanked for
their assistance in preparing this
presentation and for permission to share
this experience

More Related Content

What's hot

Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
Hitesh Khanna
 
Horizontal drilling
Horizontal drillingHorizontal drilling
Horizontal drilling
Mubarik Rao
 
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
Hitesh Khanna
 
Schlumberger - Drilling and Measurement Segment - Internship Presentation
Schlumberger - Drilling and Measurement Segment - Internship PresentationSchlumberger - Drilling and Measurement Segment - Internship Presentation
Schlumberger - Drilling and Measurement Segment - Internship Presentation
Zorays Solar Pakistan
 
Reducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast FanReducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast Fanharlandmachacon
 
Report steffones
Report steffonesReport steffones
Report steffones
Steffones K
 
The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
Alaa Metwally
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
Vehicle load transfer part II 2021
Vehicle load transfer part II 2021Vehicle load transfer part II 2021
Vehicle load transfer part II 2021
William Harbin
 
Vehicle load transfer part III 2021
Vehicle load transfer part III 2021Vehicle load transfer part III 2021
Vehicle load transfer part III 2021
William Harbin
 
Vehicle load transfer part I 2021
Vehicle load transfer part I 2021Vehicle load transfer part I 2021
Vehicle load transfer part I 2021
William Harbin
 
C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021
William Harbin
 
SUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUESSUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUES
R821992
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...Benoit Latapie
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
Himanshu Gupta
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)coderweb
 
Design of openpit mining
Design of openpit miningDesign of openpit mining
Design of openpit miningSATYANARAYANA I
 

What's hot (20)

Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
Screw piles
Screw pilesScrew piles
Screw piles
 
Horizontal drilling
Horizontal drillingHorizontal drilling
Horizontal drilling
 
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
 
Schlumberger - Drilling and Measurement Segment - Internship Presentation
Schlumberger - Drilling and Measurement Segment - Internship PresentationSchlumberger - Drilling and Measurement Segment - Internship Presentation
Schlumberger - Drilling and Measurement Segment - Internship Presentation
 
Reducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast FanReducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast Fan
 
CTA - LST - AZIMUTH SYSTEM 20160607
CTA - LST - AZIMUTH SYSTEM 20160607CTA - LST - AZIMUTH SYSTEM 20160607
CTA - LST - AZIMUTH SYSTEM 20160607
 
Report steffones
Report steffonesReport steffones
Report steffones
 
The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Vehicle load transfer part II 2021
Vehicle load transfer part II 2021Vehicle load transfer part II 2021
Vehicle load transfer part II 2021
 
Vehicle load transfer part III 2021
Vehicle load transfer part III 2021Vehicle load transfer part III 2021
Vehicle load transfer part III 2021
 
Vehicle load transfer part I 2021
Vehicle load transfer part I 2021Vehicle load transfer part I 2021
Vehicle load transfer part I 2021
 
C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021
 
SUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUESSUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUES
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
Design of openpit mining
Design of openpit miningDesign of openpit mining
Design of openpit mining
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 

Viewers also liked

Structural stability testing
Structural stability testingStructural stability testing
Structural stability testing
abhishekabhi123
 
Structural stability
Structural stabilityStructural stability
Structural stability
Bangalore Property
 
Topic%20 compression
Topic%20 compressionTopic%20 compression
Topic%20 compressionSaleem Malik
 
Design 3 2011 - Design Lecture Structures
Design 3 2011 - Design Lecture  StructuresDesign 3 2011 - Design Lecture  Structures
Design 3 2011 - Design Lecture Structures
Galala University
 
Stability of High-Rise Buildings
Stability of High-Rise BuildingsStability of High-Rise Buildings
Stability of High-Rise Buildings
Akash Waghani
 
Lateral stability of building structures
Lateral stability of building structuresLateral stability of building structures
Lateral stability of building structures
Wolfgang Schueller
 
Shear wall
Shear wallShear wall
CCTV Building, A Structural Design Overview
CCTV Building, A Structural Design OverviewCCTV Building, A Structural Design Overview
CCTV Building, A Structural Design Overview
Peter Bach
 

Viewers also liked (9)

Structural stability testing
Structural stability testingStructural stability testing
Structural stability testing
 
Structural stability
Structural stabilityStructural stability
Structural stability
 
Topic%20 compression
Topic%20 compressionTopic%20 compression
Topic%20 compression
 
Design 3 2011 - Design Lecture Structures
Design 3 2011 - Design Lecture  StructuresDesign 3 2011 - Design Lecture  Structures
Design 3 2011 - Design Lecture Structures
 
Stability of High-Rise Buildings
Stability of High-Rise BuildingsStability of High-Rise Buildings
Stability of High-Rise Buildings
 
Lateral stability of building structures
Lateral stability of building structuresLateral stability of building structures
Lateral stability of building structures
 
Shear wall
Shear wallShear wall
Shear wall
 
Bracing connections
Bracing connectionsBracing connections
Bracing connections
 
CCTV Building, A Structural Design Overview
CCTV Building, A Structural Design OverviewCCTV Building, A Structural Design Overview
CCTV Building, A Structural Design Overview
 

Similar to Structural and stability assessment for ex-pit dump toe (final)

Final Presentation
Final PresentationFinal Presentation
Final PresentationMonique F M
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
Loay Ghazaleh MBA, BSc Civil Eng.
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Rajesh Prasad
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
Dr Mazin Alhamrany
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
VR M
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Audubon Engineering Company
 
Rocker bogie mechanism
Rocker bogie mechanismRocker bogie mechanism
Rocker bogie mechanism
dinesh rajeswari
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportJoshua Yu
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
Egyptian Engineers Association
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
Sandia 2014 Wind Turbine Blade Workshop- Van Dam
Sandia 2014 Wind Turbine Blade Workshop- Van DamSandia 2014 Wind Turbine Blade Workshop- Van Dam
Sandia 2014 Wind Turbine Blade Workshop- Van Dam
Sandia National Laboratories: Energy & Climate: Renewables
 
Back analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marlsBack analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marls
SYSTRA
 
Metroppt
MetropptMetroppt
Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1John Latilla
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
Shashank Gaurav
 
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design NoteAuber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Hoa Nguyen
 
Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
Anjani Shukla
 

Similar to Structural and stability assessment for ex-pit dump toe (final) (20)

Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Paper
PaperPaper
Paper
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
 
Rocker bogie mechanism
Rocker bogie mechanismRocker bogie mechanism
Rocker bogie mechanism
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering Report
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Sandia 2014 Wind Turbine Blade Workshop- Van Dam
Sandia 2014 Wind Turbine Blade Workshop- Van DamSandia 2014 Wind Turbine Blade Workshop- Van Dam
Sandia 2014 Wind Turbine Blade Workshop- Van Dam
 
Back analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marlsBack analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marls
 
Metroppt
MetropptMetroppt
Metroppt
 
Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
IPTC_12_2015
IPTC_12_2015IPTC_12_2015
IPTC_12_2015
 
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design NoteAuber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
 
ISEE_CJP_2016_Version FINAL_Return
ISEE_CJP_2016_Version FINAL_ReturnISEE_CJP_2016_Version FINAL_Return
ISEE_CJP_2016_Version FINAL_Return
 
Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
 

Structural and stability assessment for ex-pit dump toe (final)

  • 1. Structural and stability assessment for ex-pit dump toe locality optimisation: A case study John Latilla 26 November 2015 BBUGS / BOHOGS Supplier’s day - Moranbah
  • 4. www.amcconsultants.com Project infrastructure 15 Mtpa CHPP18 MW Power Station Office and mess hall Mine Workshops
  • 5. www.amcconsultants.com Some key facts • Multiple seams dipping generally 3° to 17° into highwall • Flanks (endwalls) dipping 5° to 40° out of pit wall • Terrace mining (truck and excavator) • Mid volatile hard coking coal with thermal coal by-product • Ex-pit waste dumping, at least for next 3 to 5 years • Nameplate capacity of 15 Mtpa ROM coal to CHPP • Life-of-Mine stripping ratio of 5.6:1
  • 6. www.amcconsultants.com The challenge Optimise the locality of the northern ex-pit waste dump on order to reduce dump truck round trip distances. Earlier limit equilibrium analyses of cross-sections for pit walls below the dump indicated the potential to steepen the OSA by as much as 4° through buffer blasting the entire slope Insufficient geotechnical and geological data available to properly identify buffer blasting target zones The phreatic surface used is based on John Simmons’ work from the Bowen Basin (far wetter conditions)
  • 7. www.amcconsultants.com The challenge in a nutshell 7 Possible structural interp. with additional data LOM structural interp. New “optimised” crest locality Potential gain 50m stand-off distance not assessed – remains constant
  • 8. www.amcconsultants.com Plan of action Drill a series of six geotechnical boreholes sited to maximise data from the potential buffer blasted endwall area. Boreholes required to be oriented to enable structural and kinematic analyses Drill ten percussion holes adjacent to and on top of the waste dump to determine actual phreatic surface Review geological structure of the ground containing the final endwall slope beneath the waste dump Conduct kinematic and limit equilibrium analyses to design optimal OSA beneath the waste dump using the updated structural and phreatic surface data
  • 9. www.amcconsultants.com Modifications No acoustic televiewer available in country. Changed to drilling oriented cored boreholes 60° inclined core boreholes, oriented by means of Ezy-Mark tool (Reflex). Relies on leaving a crayon impression and a pin profile of the bottom of the hole Soft and friable coal and mudstone areas - too much fine and loose material at bottom of hole to obtain an impression. Oriented core data unavoidably biased to the stronger units Inability to orient core in softer zones judged not to be a show stopper. Overall structural orientations expected to be similar in hard and softer rock
  • 10. www.amcconsultants.com Modifications continued Two oriented holes close to the dump toe intersected basement rock (dolerite and basalt) and “replacement” holes were drilled about 100 m further (South) from the dump toe Info on the basement contacts and structure was nevertheless very useful
  • 12. www.amcconsultants.com Coring through the waste dump Local exploration drilling contractor used for the dump hydrology holes. Did not have a percussion rig available so drilled the holes with a coring rig Core was not boxed or logged but simply laid out on the ground near the rig. Recovery of core not called for in the work order With an air drilled hole the expectation was that water level monitoring would track the gradual climb of water level back up to equilibrium. With water flushed coring the opposite was expected
  • 14. www.amcconsultants.com Structural data collection Oriented core holes logged and photographed by the site geotechnical team to CoreLog standard (ACARP 2015) Individual defects identified and measured using CoreProfiler (CSIRO). Builds a composite photograph of the core column from core photographed in trays. From this, dip and dip direction are determined for each defect and plotted on stereonet. Data was then exported to Dips6.0 for further manipulation and assessment CoreProfiler also produces RQD and fracture frequency data CoreProfiler is still in development but was found to be a useful tool
  • 17. www.amcconsultants.com Structural assessment Structural data analysed in Dips6.0 as follows: • All defects in all boreholes, then split per endwall sector (NEW2 and NEW4) and finally split into individual boreholes • Each of the above were then sub-divided into:  All structure above the lowermost coal seam (BOC) and that below BOC – the latter being the key strata for endwall design  Bedding planes only split as above to determine structural trends in sedimentary rock • Shears and possible shears analysed separately – insufficient numbers to analyse shears on a hole for hole basis.
  • 18. www.amcconsultants.com Selected stereonet plots 18 All shears – all b/hs All defects – all b/hs
  • 19. www.amcconsultants.com Structural analysis summary Description Dip and Dip direction (°) Set 1 Set 2 Set 3 All defects for all boreholes 13/207 50/174 – All defects above BOC 11/211 50/167 – All defects below BOC 13/204 49/180 – Bedding planes only for all boreholes 13/208 49/179 – Bedding planes only above BOC 14/213 52/173 – Bedding planes only below BOC 12/203 47/183 – All defects for basement rocks 11/214 51/180 – Shears only for all boreholes (orientation low to medium confidence) 64/172 73/193 23/217
  • 20. www.amcconsultants.com Kinematic assessment Critical Surface Limits • Batters  Final endwalls – 10%  Interim endwalls – 15%  Highwalls – 20% • Overall slope angles  Below critical infrastructure – 5%  All others – 10%
  • 21. www.amcconsultants.com Kinematic assessment Planar and wedge sliding are the most likely, kinematically admissible, failure types • Excluding the effect of shears:  Batters should not be formed steeper than 55° in NEW4 and 70° in NEW2  Overall slope angle (OSA) should not exceed 47° • Taking shears into account:  Batter slope angle drops to 25°. OSA 23° for NEW2 and 30° for NEW4 • Assuming bedding shears will be buffer blasted:  Max batter angle 55° and OSA 27° to 34°
  • 22. www.amcconsultants.com Selected stereonet plots 22 NEW2 batter scale planar sliding NEW2 batter scale wedge sliding
  • 23. www.amcconsultants.com Kinematic analysis results summary Slope scale Pit sector Maximum slope dip angle and percentage of critical surfaces Planar sliding (° / %) Wedge sliding (CS Mod)* (° / %) Batters (15% critical surfaces limit) NEW2 70/13.7 70/13.2* NEW4 55/14.9 67/15.0* NEW2 shears 28/14.3 25/13.2 NEW4 shears 59/7.1 33/13.2 OSA (10% critical surfaces limit) NEW2 49/9.8 47/9.8* NEW4 47/9.7 49/9.8* NEW2 shears 27/7.1 23/9.9 NEW4 shears 59/7.1 30/6.6 *The critical surface results for wedge sliding have a correction factor of 0.5 applied to better match site experience. This is referred to as the modified wedge sliding critical surface value (CS Mod.).
  • 24. www.amcconsultants.com Structural interpretation General trend indicated steeper than originally modelled coal bearing strata along the northern boundary fault in 3 out of 4 cross-sections (CS 20a, 22 & 23) The other cross-section (CS 28) indicated steeply dipping boundary fault cutting off the coal strata A stronger and less disturbed conglomerate zone was identified below the BOC Zone of steeply dipping sedimentary rocks assumed to extend along the southern face of the northern boundary fault. Based on previously exposed fault zones at UHG. Width variable
  • 25. www.amcconsultants.com Dump toe and borehole locality 25 Cross section lines Geotech boreholes Arrow denotes hole azimuth Hydrology boreholes
  • 27. www.amcconsultants.com Phreatic surface model Locality Distance from toe (m) Phreatic surface below original ground surface (m) Minimum Maximum Minimum Maximum Generic model 240 m from dump toe (on pit side) – 240 – – 28 ~100m from dump toe 50 127 18 29 23 Immediately below dump toe 0 0 13 14 13 ~60 from toe under dump 40 92 3 6 3 ~180 from toe under dump 151 230 0 0 0 210 m from toe under dump 200 230 – – +2 [1] Note that where the pit crest is closer than 240 m the generic (or specific if known) phreatic surface model must be merged with this model
  • 29. www.amcconsultants.com Limit equilibrium analyses Based on oriented borehole data and observations of core recovered from hydrological drilling the interpreted structure from the 2014 model has been modified The endwall crest can be located up to 180 m further south Existing minimum stand-off distance between dump toe and slope crest of 50m was not investigated or altered in this study The endwall areas represented by the two eastern most cross sections (CS 23 & 28) require no additional buttressing or dewatering The most westerly, and deepest, endwall slope (as represented by the two most westerly cross sections, CS 20a & 22) requires extensive toe stabilisation plus dewatering
  • 31. www.amcconsultants.com Cross-section 28 31 GALEN A Version 6.10 Project UHG 2014 Slope Stability Analysis - Cross Section 28 File: C:UsersJlatillaDocumentsNumerical modellingGalenaUHG2015 NEW4 Buffered endwall below dump CS 28 (extended).gmf Edited: Processed: 21 Aug 2015 21 Aug 2015AMC ConsultantsLicensed to: Analysis Results 4 Multiple Stability Analysis Method: Surface: Spencer-Wright Circular Critical Factor of Safety: 1.24 Interslice Force (Final) Angle: 28.9 ° Material K eys WOB (c:27 ø:22.4 g:22) MWOB (c:115 ø:31.7 g:23) FOB (c:358 ø:37.2 g:24.5) CF (c:40 ø:23 g:14.4) BPS (c:0 ø:14 g:19.4) WR (c:27 ø:26.8 g:18.3) FSZ (c:24 ø:18 g:21.8) CG (c:785 ø:42.9 g:24.7) BW (c:612 ø:34.1 g:29) BF (c:828 ø:41.1 g:29) 800 900 1000 1100 1200 1300 1200 1250 1300 1350 1400 1450 1500 1550 1600 1650 Buttress of flat to shallow dipping strata
  • 32. www.amcconsultants.com Conclusions This extensive study has resulted in far better understanding of the structure and strength of critical strata beneath the waste dump toe This improved knowledge has enabled the dump toe locality to be moved significantly closer to the pit crest thereby significantly reducing dump truck round trip distances
  • 33. Thank you Energy Resources LLC are thanked for their assistance in preparing this presentation and for permission to share this experience