This document summarizes a study to optimize the location of an ex-pit waste dump toe for a coal mine in order to reduce dump truck travel distances. Geotechnical drilling and analysis was conducted to better understand the structural geology and groundwater conditions beneath the dump. This new data allowed the dump toe to be relocated up to 180m closer to the pit crest. Limit equilibrium analysis showed that buttressing and dewatering would be required for the deepest section, but other areas could utilize the new dump toe location without additional stabilization measures. The study resulted in significantly reduced dump truck round trips without compromising slope stability.
Presentation about Ircon's SGEDT project in Malaysia.Hitesh Khanna
This presentation was presented in Indian Railway's IPWE Seminar in January 2013 at Chennai. It depicts the innovations and new Technologies (in the context of Indian Railways) adopted on the project, and the various technical issues, and how they were dealt with.
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014Hitesh Khanna
The presentation covers the basics of Railway tunnel Ventilation and Safety in the context of Pir Panjal Tunnel T-80.
The basic reference document has been UIC Codex 779-9.
Schlumberger - Drilling and Measurement Segment - Internship PresentationZorays Solar Pakistan
I learnt about all the Drilling and Measurement equipment and procedures. During the internship period, I had to survey few technical modules which were specific to Drilling and Measurment segment, which included
• an introduction to Drilling & Measurment segment and its core services
• interpretation of Direction & Inclination terminologies
• learning of Telemetry procedures and working of Measurement While Drilling tools
• understanding of Surface System structure.
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
The said technical paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
Testing for the structural stability of the factors and the over determining limitations can be conducted by choosing the Stability access, under the Examining area.
2BHK Apartments in Bangalore, bangalore5, 2bhk apartments for sale in Bangalore, 2bhk apartment in Bangalore, Bangalore property
More,
<a>Bangalore5</a>
Presentation about Ircon's SGEDT project in Malaysia.Hitesh Khanna
This presentation was presented in Indian Railway's IPWE Seminar in January 2013 at Chennai. It depicts the innovations and new Technologies (in the context of Indian Railways) adopted on the project, and the various technical issues, and how they were dealt with.
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014Hitesh Khanna
The presentation covers the basics of Railway tunnel Ventilation and Safety in the context of Pir Panjal Tunnel T-80.
The basic reference document has been UIC Codex 779-9.
Schlumberger - Drilling and Measurement Segment - Internship PresentationZorays Solar Pakistan
I learnt about all the Drilling and Measurement equipment and procedures. During the internship period, I had to survey few technical modules which were specific to Drilling and Measurment segment, which included
• an introduction to Drilling & Measurment segment and its core services
• interpretation of Direction & Inclination terminologies
• learning of Telemetry procedures and working of Measurement While Drilling tools
• understanding of Surface System structure.
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
The said technical paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
Testing for the structural stability of the factors and the over determining limitations can be conducted by choosing the Stability access, under the Examining area.
2BHK Apartments in Bangalore, bangalore5, 2bhk apartments for sale in Bangalore, 2bhk apartment in Bangalore, Bangalore property
More,
<a>Bangalore5</a>
The lecture is in support of:
(1) The Design of Building Structures (Vol.1, Vol. 2), rev. ed., PDF eBook by Wolfgang Schueller, 2016: chapter 4.
(2) Building Support Structures, Analysis and Design with SAP2000 Software, 2nd ed., eBook by Wolfgang Schueller: chapter 13.
shear walls are vertical elements of the horizontal force resisting system. Shear walls are constructed to counter the effects of lateral load acting on a structure.
CCTV Building, A Structural Design OverviewPeter Bach
The CCTV building is one of the several big Beijing Olympic projects, which houses the headquarters for the Chinese Central Television Network. Its design shows unique style, but great structural engineering challenges to overcome. The following presentation provides an overview of how these challenges were overcome. (Presented at Monash University, Department of Civil Engineering, August 2008).
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Rajesh Prasad
For the construction of Cable Stayed Bridge at Bardhman, a simulation model was made using LARSA 4D and accordingly design were concluded considering all the possible situation. At the execution stage the profile/geometry control is very important. Accordingly construction stage analysis along with geometry control is being done using LUSAS software. These software are 4D and the fourth dimension is Time. The said presentation covers the LARSA, LUSAS and few pictures on execution at site along with sample of documentation.
#تواصل_تطوير
المحاضرة رقم 187
أستاذ دكتور / مدحت كمال عبدالله
عنوان المحاضرة:
تدعيم كباري باستخدام التفاعل المشترك
للمياه - جسم الكوبري
وعرض حالة عملية
Temporary Support Of Existing Bridges Using
Water-Structure Interaction
including case study
يوم الإثنين 26 ديسمبر 2022
الثامنة مساء توقيت القاهرة
التاسعة مساء توقيت مكة المكرمة
و الحضور عبر تطبيق زووم من خلال الرابط
https://us02web.zoom.us/meeting/register/tZModeusrzsoHtbqmSpzcaX1yPR0TmfeoAQl
علما ان هناك بث مباشر للمحاضرة على القنوات الخاصة بجمعية المهندسين المصريين
ونأمل أن نوفق في تقديم ما ينفع المهندس ومهمة الهندسة في عالمنا العربي
والله الموفق
للتواصل مع إدارة المبادرة عبر قناة التليجرام
https://t.me/EEAKSA
ومتابعة المبادرة والبث المباشر عبر نوافذنا المختلفة
رابط اللينكدان والمكتبة الالكترونية
https://www.linkedin.com/company/eeaksa-egyptian-engineers-association/
رابط قناة التويتر
https://twitter.com/eeaksa
رابط قناة الفيسبوك
https://www.facebook.com/EEAKSA
رابط قناة اليوتيوب
https://www.youtube.com/user/EEAchannal
رابط التسجيل العام للمحاضرات
https://forms.gle/vVmw7L187tiATRPw9
ملحوظة : توجد شهادات حضور مجانية لمن يسجل فى رابط التقيم اخر المحاضرة.
Back analysis of high tunnel convergences in clayey marlsSYSTRA
Ganntas Tunnel is part of the modernization project of the
railway between Alger and Oran, in Algeria. In order to double
and rectify the existing line between El Affroun and Khémis
Miliana, the alignment foresees the excavation of a 7km-long
twin tunnel. The excavation works started in June 2011 with
the contractor CCECC, under the supervision of SYSTRA.
Excavation is driven in conventional method by hydraulic
hammer simultaneously on 8 different faces since excavation
was started also from a junction window towards the middle
of the tunnel. The minimum longitudinal distance to be
respected between two contiguous tunnel faces has been set
to 30m. The tunnel cross-section is a 70m² oval shaped profile,
temporary support consists of shotcrete, bolts and steel ribs.
A 30 to 50cm thick cast in situ concrete final lining is provided
as well.
When the tunnel reached a fault zone in soft clayey marls,
extreme squeezing occurred, works were stopped, and reprofiling
operations were carried out along more than 100m
tunnel length. To date, works proceed at slow rate since high
convergences are still monitored and completion of works is
not expected before December 2016.
Written by SYSTRA tunnel experts : MISANO Edoardo, COUBRAY Jean-Louis,
ESPINOZA CARMONA Fabiola
The main outcome of this project is the construction sequence of HMR which primarily starts with excavation, erection of piers, launching girder process and assembling of segments. This project clearly gives a brief knowledge on how the post tensioning and pre stressing works are held at off site and onsite. This project enlightens about the safety requirements and measures taken during the pre-casting works and at on site works.
Structural and stability assessment for ex-pit dump toe (final)
1. Structural and stability
assessment for ex-pit dump toe
locality optimisation: A case study
John Latilla
26 November 2015
BBUGS / BOHOGS Supplier’s day - Moranbah
5. www.amcconsultants.com
Some key facts
• Multiple seams dipping generally 3° to 17° into highwall
• Flanks (endwalls) dipping 5° to 40° out of pit wall
• Terrace mining (truck and excavator)
• Mid volatile hard coking coal with thermal coal by-product
• Ex-pit waste dumping, at least for next 3 to 5 years
• Nameplate capacity of 15 Mtpa ROM coal to CHPP
• Life-of-Mine stripping ratio of 5.6:1
6. www.amcconsultants.com
The challenge
Optimise the locality of the northern ex-pit waste dump on order to
reduce dump truck round trip distances.
Earlier limit equilibrium analyses of cross-sections for pit walls below
the dump indicated the potential to steepen the OSA by as much as
4° through buffer blasting the entire slope
Insufficient geotechnical and geological data available to properly
identify buffer blasting target zones
The phreatic surface used is based on John Simmons’ work from the
Bowen Basin (far wetter conditions)
7. www.amcconsultants.com
The challenge in a nutshell
7
Possible structural interp.
with additional data
LOM structural interp.
New “optimised” crest locality
Potential gain
50m stand-off distance
not assessed – remains
constant
8. www.amcconsultants.com
Plan of action
Drill a series of six geotechnical boreholes sited to maximise data
from the potential buffer blasted endwall area. Boreholes required to
be oriented to enable structural and kinematic analyses
Drill ten percussion holes adjacent to and on top of the waste dump
to determine actual phreatic surface
Review geological structure of the ground containing the final
endwall slope beneath the waste dump
Conduct kinematic and limit equilibrium analyses to design optimal
OSA beneath the waste dump using the updated structural and
phreatic surface data
9. www.amcconsultants.com
Modifications
No acoustic televiewer available in country. Changed to drilling
oriented cored boreholes
60° inclined core boreholes, oriented by means of Ezy-Mark tool
(Reflex). Relies on leaving a crayon impression and a pin profile of
the bottom of the hole
Soft and friable coal and mudstone areas - too much fine and loose
material at bottom of hole to obtain an impression. Oriented core
data unavoidably biased to the stronger units
Inability to orient core in softer zones judged not to be a show
stopper. Overall structural orientations expected to be similar in hard
and softer rock
10. www.amcconsultants.com
Modifications continued
Two oriented holes close to the dump toe intersected basement rock
(dolerite and basalt) and “replacement” holes were drilled about
100 m further (South) from the dump toe
Info on the basement contacts and structure was nevertheless very
useful
12. www.amcconsultants.com
Coring through the waste dump
Local exploration drilling contractor used for the dump hydrology
holes. Did not have a percussion rig available so drilled the holes
with a coring rig
Core was not boxed or logged but simply laid out on the ground near
the rig. Recovery of core not called for in the work order
With an air drilled hole the expectation was that water level
monitoring would track the gradual climb of water level back up to
equilibrium. With water flushed coring the opposite was expected
14. www.amcconsultants.com
Structural data collection
Oriented core holes logged and photographed by the site
geotechnical team to CoreLog standard (ACARP 2015)
Individual defects identified and measured using CoreProfiler
(CSIRO). Builds a composite photograph of the core column from
core photographed in trays. From this, dip and dip direction are
determined for each defect and plotted on stereonet. Data was then
exported to Dips6.0 for further manipulation and assessment
CoreProfiler also produces RQD and fracture frequency data
CoreProfiler is still in development but was found to be a useful tool
17. www.amcconsultants.com
Structural assessment
Structural data analysed in Dips6.0 as follows:
• All defects in all boreholes, then split per endwall sector (NEW2
and NEW4) and finally split into individual boreholes
• Each of the above were then sub-divided into:
All structure above the lowermost coal seam (BOC) and that below
BOC – the latter being the key strata for endwall design
Bedding planes only split as above to determine structural trends in
sedimentary rock
• Shears and possible shears analysed separately – insufficient
numbers to analyse shears on a hole for hole basis.
19. www.amcconsultants.com
Structural analysis summary
Description
Dip and Dip direction
(°)
Set 1 Set 2 Set 3
All defects for all boreholes 13/207 50/174 –
All defects above BOC 11/211 50/167 –
All defects below BOC 13/204 49/180 –
Bedding planes only for all
boreholes
13/208 49/179 –
Bedding planes only above BOC 14/213 52/173 –
Bedding planes only below BOC 12/203 47/183 –
All defects for basement rocks 11/214 51/180 –
Shears only for all boreholes
(orientation low to medium
confidence)
64/172 73/193 23/217
21. www.amcconsultants.com
Kinematic assessment
Planar and wedge sliding are the most likely, kinematically
admissible, failure types
• Excluding the effect of shears:
Batters should not be formed steeper than 55° in NEW4 and
70° in NEW2
Overall slope angle (OSA) should not exceed 47°
• Taking shears into account:
Batter slope angle drops to 25°. OSA 23° for NEW2 and 30°
for NEW4
• Assuming bedding shears will be buffer blasted:
Max batter angle 55° and OSA 27° to 34°
23. www.amcconsultants.com
Kinematic analysis results summary
Slope scale Pit sector
Maximum slope dip angle and percentage of
critical surfaces
Planar sliding
(° / %)
Wedge sliding
(CS Mod)*
(° / %)
Batters
(15% critical
surfaces limit)
NEW2 70/13.7 70/13.2*
NEW4 55/14.9 67/15.0*
NEW2 shears 28/14.3 25/13.2
NEW4 shears 59/7.1 33/13.2
OSA
(10% critical
surfaces limit)
NEW2 49/9.8 47/9.8*
NEW4 47/9.7 49/9.8*
NEW2 shears 27/7.1 23/9.9
NEW4 shears 59/7.1 30/6.6
*The critical surface results for wedge sliding have a correction factor of 0.5 applied to better match site experience.
This is referred to as the modified wedge sliding critical surface value (CS Mod.).
24. www.amcconsultants.com
Structural interpretation
General trend indicated steeper than originally modelled coal
bearing strata along the northern boundary fault in 3 out of 4
cross-sections (CS 20a, 22 & 23)
The other cross-section (CS 28) indicated steeply dipping boundary
fault cutting off the coal strata
A stronger and less disturbed conglomerate zone was identified
below the BOC
Zone of steeply dipping sedimentary rocks assumed to extend along
the southern face of the northern boundary fault. Based on
previously exposed fault zones at UHG. Width variable
25. www.amcconsultants.com
Dump toe and borehole locality
25
Cross section lines
Geotech boreholes
Arrow denotes hole azimuth
Hydrology boreholes
27. www.amcconsultants.com
Phreatic surface model
Locality
Distance from toe
(m)
Phreatic surface below original
ground surface (m)
Minimum Maximum Minimum Maximum
Generic
model
240 m from dump toe (on pit
side)
– 240 – – 28
~100m from dump toe 50 127 18 29 23
Immediately below dump toe 0 0 13 14 13
~60 from toe under dump 40 92 3 6 3
~180 from toe under dump 151 230 0 0 0
210 m from toe under dump 200 230 – – +2
[1] Note that where the pit crest is closer than 240 m the generic (or specific if known) phreatic surface
model must be merged with this model
29. www.amcconsultants.com
Limit equilibrium analyses
Based on oriented borehole data and observations of core recovered
from hydrological drilling the interpreted structure from the 2014
model has been modified
The endwall crest can be located up to 180 m further south
Existing minimum stand-off distance between dump toe and slope
crest of 50m was not investigated or altered in this study
The endwall areas represented by the two eastern most cross
sections (CS 23 & 28) require no additional buttressing or
dewatering
The most westerly, and deepest, endwall slope (as represented by
the two most westerly cross sections, CS 20a & 22) requires
extensive toe stabilisation plus dewatering
32. www.amcconsultants.com
Conclusions
This extensive study has resulted in far better understanding of the
structure and strength of critical strata beneath the waste dump toe
This improved knowledge has enabled the dump toe locality to be
moved significantly closer to the pit crest thereby significantly
reducing dump truck round trip distances
33. Thank you
Energy Resources LLC are thanked for
their assistance in preparing this
presentation and for permission to share
this experience