SlideShare a Scribd company logo
High-Fidelity Operator Training Simulator for a
Combined Cycle Plant Implemented Before
Plant Commissioning
info@gses.com
Overview
•  Simulator project goals & objectives
•  North American project schedule
•  Unique challenges
•  Execution strategy
•  Virtual Ovation™ system
•  Third-party virtual turbine controls
•  High-fidelity modeling approach with JADE™
•  Summary
Simulator Project Objective
•  GSE and Emerson provided a high-fidelity simulator
with models and controls indistinguishable from a
real-time running plant.
•  Simulator allows for extensive DCS testing/tuning and
operator training prior to plant commissioning
•  Simulator allows for testing with third-party turbine
controls and Emerson implemented BOP systems
Simulator Project Example
•  North American combined cycle plant
Project Goals
•  Test the distributed control system (DCS) logic
thoroughly ahead of plant commissioning
•  Begin training operators ahead plant
commissioning
•  Configure simulator interface with Emerson
Ovation™ Virtual Controllers
Key Project Stake Holders
•  Coordinated effort between:
–  Simulation vendor (GSE)
–  DCS vendor (Emerson)
–  Burns & McDonnell – Turn key solution
provider
–  Utility company
Project Implementation Challenges
•  Establishing communication with the
simulator software
–  Third-party turbine control software in a
VMware environment
–  Ovation DCS system with the balance of
plant
–  GSE model software
Project Implementation Challenges
– A&E solution from third-party OPC alarm
& event server to Ovation
– Resetting the A&E interface on IC reset
– Turbine control mapper program was
designed for real-time environment, not
simulation
Project Execution Strategy
•  High-resource staffing levels due to compressed
schedule
•  Simulator logistics focused on maximizing
productivity and customer interaction
•  Operator training available ahead of plant startup
•  Simulator retune at site
–  Update the DCS & models with running plant
controls after commissioning is complete
Resource Staffing Levels
•  GSE provides 3 to 4 simulator team engineers.
•  Emerson provides lead project simulation
engineer and one project management lead
engineer.
•  Burns & McDonnell and utility company provide
operators for testing and I&C technicians for the
first initial startup.
•  Third-party turbine control vendor provided
remote and contract support.
Project Schedule
•  Simulator schedule (12 to 14 months)
•  Review external logic outside of the Ovation DCS,
some typical examples include:
–  Smart breakers
–  PLC logic
–  Relay logic
•  Review third-party plant controls (turbines in
VMware environment)
Project Schedule
•  Model acceptance testing (MAT) at GSE proves
the accuracy of models prior to DCS integration.
–  Complete startup with functional controls
–  Reduces schedule risk since models will be fully
tested before linking them to new controls
•  Simulator models interface directly with DCS
controls to verify DCS performance prior to plant
commissioning.
Field Tuning
•  Emerson field service was able to tune the
Ovation BOP logic on the simulator.
•  Drum level controls, steam bypass control loops
and dynamic tuning was completed on the
simulator.
•  Tuning with the real equipment will still be
required, however, the default values have all
been modified and scaling and advanced tuning
has been completed.
Customer Acceptance
•  Factory acceptance testing (FAT) at Emerson
involves Burns & McDonnell and utility plant
operators working directly with the simulation
team to perform startup and shutdown testing.
•  Variances are documented and corrected.
•  Site acceptance testing (SAT) is done at
customer site. This ensures the system performs
the same as it does on the factory floor.
Operator Training and Retune
•  Operator training will begin 4-5 months
ahead of plant startup.
•  Simulator retune will be performed at the
plant site by Emerson and GSE to update
the simulator to the commissioned DCS
controls once the plant has been fully
commissioned.
Simulator System Architecture
•  DCS converted to Ovation virtual controller
drops on a virtual controller host (VCH)
•  DCS application software (control logic,
database, and graphics) is installed on the
simulator
Typical Virtual Ovation Layout 2
Model Server
Workstation
Domain
Controller /
Database Server
Workstation2
Operator
Workstation
Third Party
Turbine
Controls
Ovation
Switch
Emulated Hard
Panel
Workstation
Instructor
Workstation
Virtual
Controller
Host /
Operator
Workstation
Turbine Network
Switch
High-Fidelity Modeling Approach
GSE JADETM software:
High-fidelity models of
plant systems using a two-
phase dynamic solution
based on conservation of
mass, momentum, and
energy
GSE SimExec software:
Controls and monitors the
execution of solutions in
Real-time, interactively via
freeze, run, snap, and
reset
Variance Recording System
•  GSE, Emerson, and utility company
communicate using a discrepancy reporting
database accessible via the web,
called Mantis.
•  Allows quick and efficient documentation
and resolution of data requests, model
discrepancies, and DCS discrepancies
GSE Testing Checkpoints for Model
Readiness Verification
•  Simulator schedule incorporates testing
checkpoints throughout project to ensure
model readiness:
–  System unit test (SUT):
•  Models tested stand-alone
–  Model acceptance test (MAT):
•  Models tested integrated together
–  Factory acceptance test (FAT):
•  Models tested integrated with the DCS
The Advantage of Testing a DCS on a
Simulator Prior to Plant Installation
•  Allows correction of errors in DCS and
ensures the DCS works properly
•  Prevents complications during operation of
the real plant
•  Saves time and money spent on attempting
to debug the DCS while controlling real
equipment
•  Avoids multiple startups/shutdowns needed
to make DCS changes
Other Major Benefits of Simulator
•  Mimics the real plant for life-long testing
and training
•  Allows for first pass at field tuning to be
performed prior to DCS delivery
•  Capable of updating and retuning
simultaneously to real plant
•  Extensive training for emergency scenarios
•  Future DCS logic updates can be tested on
the simulator before the real plant
•  Chiller feedback went to all three chillers and logic
prevented the start of B and C chillers since indications
were fed into the DCS that they were already running once
A was started.
•  TCA cooler – low flow trip. Third-party turbine controls had
trip set points that were too close to control set points after
gain blocks were factored in. The initial design didn’t work
in actual testing and was subsequently modified.
•  Vacuum trip – initial logic only accounted for vacuum
pumps in operation and did not account for the hogger
holding vacuum when the pumps shut off. This would have
caused the vacuum breakers to open as soon as all the
vacuum pumps turned off.
Real-Life Examples of Integration
Benefits
Real-Life Examples of Integration
Benefits
•  Motor macro was modified so a trip needed to be
cleared and reset before it could start again.
The issue was observed during simulator testing.
•  This is the advantage of staging the project at
Emerson so the DCS design team can answer
questions.
Summary
•  Burns & McDonnell, Emerson and GSE have
experience with simulation of a natural gas
fired combined cycle power station.
•  The testing done on the simulator allowed
for training to begin and for startup
procedures to be fine tuned.
Feedback
•  Once plant commissioning is completed
then Burns & McDonnell will advise on
further benefits from having the simulator.
For more information:
Go to: www.GSES.com
Call: 800.638.7912
Email: info@gses.com
Follow us on:
Twitter @GSESystems
Facebook.com/GSESystems

More Related Content

What's hot

Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
Andy Lang
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
Personal Secret
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and OperationsAchal Gupta
 
Mechanical completion handbook1
Mechanical completion handbook1Mechanical completion handbook1
Mechanical completion handbook1zulfikar N joel
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
d_mackay
 
Episode 7 : iCON Basic Training
Episode 7 :  iCON Basic Training Episode 7 :  iCON Basic Training
Episode 7 : iCON Basic Training
SAJJAD KHUDHUR ABBAS
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
SAJJAD KHUDHUR ABBAS
 
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Process Safety Management in Design, Construction &  Commissioning | Lalit  K...Process Safety Management in Design, Construction &  Commissioning | Lalit  K...
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Cairn India Limited
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineerankur sood
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
SAJJAD KHUDHUR ABBAS
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1Jahanzeb Khan
 
Saurabh Singh - CV.DOC
Saurabh Singh - CV.DOCSaurabh Singh - CV.DOC
Saurabh Singh - CV.DOCsaurabh singh
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)
SAJJAD KHUDHUR ABBAS
 
Instrumentation Construction Pre- CommnEngineer RESUME
Instrumentation Construction  Pre- CommnEngineer  RESUMEInstrumentation Construction  Pre- CommnEngineer  RESUME
Instrumentation Construction Pre- CommnEngineer RESUMEMohammed Y. Ahmed Nilangakar
 

What's hot (20)

Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and Operations
 
MS CV May 2016
MS CV May 2016MS CV May 2016
MS CV May 2016
 
Mechanical completion handbook1
Mechanical completion handbook1Mechanical completion handbook1
Mechanical completion handbook1
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
Episode 7 : iCON Basic Training
Episode 7 :  iCON Basic Training Episode 7 :  iCON Basic Training
Episode 7 : iCON Basic Training
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Process Safety Management in Design, Construction &  Commissioning | Lalit  K...Process Safety Management in Design, Construction &  Commissioning | Lalit  K...
Process Safety Management in Design, Construction & Commissioning | Lalit K...
 
parveer
parveerparveer
parveer
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Matt Instr CV
Matt Instr CVMatt Instr CV
Matt Instr CV
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1
 
Saurabh Singh - CV.DOC
Saurabh Singh - CV.DOCSaurabh Singh - CV.DOC
Saurabh Singh - CV.DOC
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)
 
CV
CVCV
CV
 
Instrumentation Construction Pre- CommnEngineer RESUME
Instrumentation Construction  Pre- CommnEngineer  RESUMEInstrumentation Construction  Pre- CommnEngineer  RESUME
Instrumentation Construction Pre- CommnEngineer RESUME
 
Sr.Inst Tech
Sr.Inst TechSr.Inst Tech
Sr.Inst Tech
 

Viewers also liked

Dcs operator training
Dcs operator trainingDcs operator training
Arsalan curriculum vitae
Arsalan curriculum vitae Arsalan curriculum vitae
Arsalan curriculum vitae
Arsalan Ali
 
Resume Rakesh Naik
Resume Rakesh NaikResume Rakesh Naik
Resume Rakesh NaikRakesh Naik
 
SEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCE
SEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCESEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCE
SEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCESEBTAIN ABID
 
Bansil Resume field operator
Bansil Resume field operatorBansil Resume field operator
Bansil Resume field operatorBansil Gandhi
 
Operation Refinery - Mayur resume
Operation Refinery - Mayur resumeOperation Refinery - Mayur resume
Operation Refinery - Mayur resumeMayur Amin
 
Plant commissioning
Plant commissioningPlant commissioning
Plant commissioningViljoen (Bp)
 
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectPaul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Global CCS Institute
 
Rahal e-Gas Simplified - Lubna Al Muhairi | Insight Magazine
Rahal e-Gas Simplified - Lubna Al Muhairi | Insight MagazineRahal e-Gas Simplified - Lubna Al Muhairi | Insight Magazine
Rahal e-Gas Simplified - Lubna Al Muhairi | Insight MagazineHeba Hashem
 
Working of DCS systems
Working of DCS systemsWorking of DCS systems
Working of DCS systems
hameedakhtar155
 

Viewers also liked (19)

Dcs operator training
Dcs operator trainingDcs operator training
Dcs operator training
 
Resume
ResumeResume
Resume
 
Prasanna resume
Prasanna resumePrasanna resume
Prasanna resume
 
Arsalan curriculum vitae
Arsalan curriculum vitae Arsalan curriculum vitae
Arsalan curriculum vitae
 
Ravindra CV
Ravindra CVRavindra CV
Ravindra CV
 
Resume Rakesh Naik
Resume Rakesh NaikResume Rakesh Naik
Resume Rakesh Naik
 
SEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCE
SEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCESEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCE
SEEKING FOR JOB WITH 5 YEARS PETROCHEMICAL INDUSTRIAL EXPERIENCE
 
Bansil Resume field operator
Bansil Resume field operatorBansil Resume field operator
Bansil Resume field operator
 
Kannan resume
Kannan resumeKannan resume
Kannan resume
 
R Rao CV update
R Rao CV updateR Rao CV update
R Rao CV update
 
chinna terminal operator.
chinna terminal operator.chinna terminal operator.
chinna terminal operator.
 
Operation Refinery - Mayur resume
Operation Refinery - Mayur resumeOperation Refinery - Mayur resume
Operation Refinery - Mayur resume
 
Plant commissioning
Plant commissioningPlant commissioning
Plant commissioning
 
Previous projects
Previous projectsPrevious projects
Previous projects
 
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectPaul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
 
339 solar power plant deepak
339 solar power plant deepak339 solar power plant deepak
339 solar power plant deepak
 
Rahal e-Gas Simplified - Lubna Al Muhairi | Insight Magazine
Rahal e-Gas Simplified - Lubna Al Muhairi | Insight MagazineRahal e-Gas Simplified - Lubna Al Muhairi | Insight Magazine
Rahal e-Gas Simplified - Lubna Al Muhairi | Insight Magazine
 
Working of DCS systems
Working of DCS systemsWorking of DCS systems
Working of DCS systems
 
ADNOC Ppt
ADNOC PptADNOC Ppt
ADNOC Ppt
 

Similar to High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant Commissioning

Dynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationDynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design Validation
GSE Systems, Inc.
 
The Benefits of using Dynamic Simulation and Training Systems
The Benefits of using Dynamic Simulation and Training SystemsThe Benefits of using Dynamic Simulation and Training Systems
The Benefits of using Dynamic Simulation and Training Systems
Risman Hatibi
 
Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes
Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and SuccessesMochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes
Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes
GSE Systems, Inc.
 
Modelon Modelica executable requirements Ansys Conference 2016
Modelon Modelica executable requirements Ansys Conference 2016Modelon Modelica executable requirements Ansys Conference 2016
Modelon Modelica executable requirements Ansys Conference 2016
Modelon
 
MCS2SIM - Method Allowing Application of PSA Results in Simulators
MCS2SIM - Method Allowing Application of PSA Results in SimulatorsMCS2SIM - Method Allowing Application of PSA Results in Simulators
MCS2SIM - Method Allowing Application of PSA Results in Simulators
GSE Systems, Inc.
 
James Goss - Motor Design Limited
James Goss - Motor Design Limited James Goss - Motor Design Limited
James Goss - Motor Design Limited
cwiemeexpo
 
Real-Time Engineering Simulators
Real-Time Engineering SimulatorsReal-Time Engineering Simulators
Real-Time Engineering Simulators
GSE Systems, Inc.
 
Jason Lowe I_C HMI Devloper
Jason Lowe I_C HMI DevloperJason Lowe I_C HMI Devloper
Jason Lowe I_C HMI DevloperJerome Lowe
 
Implementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsImplementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human Factors
GSE Systems, Inc.
 
Virtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing PerformanceVirtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing Performance
GSE Systems, Inc.
 
DCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdf
DCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdfDCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdf
DCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdf
Okeke Livinus
 
Innovation in Nuclear Simulation
Innovation in Nuclear SimulationInnovation in Nuclear Simulation
Innovation in Nuclear Simulation
GSE Systems, Inc.
 
Resume - Jason Lewis
Resume - Jason LewisResume - Jason Lewis
Resume - Jason LewisJason Lewis
 
Fontys Driving Simulator for Fontys
Fontys Driving Simulator for FontysFontys Driving Simulator for Fontys
Fontys Driving Simulator for FontysBen Pyman
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017Czero
 
GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Systems, Inc.
 
It‘s Math That Drives Things – Simulink as Simulation and Modeling Environment
It‘s Math That Drives Things – Simulink as Simulation and Modeling EnvironmentIt‘s Math That Drives Things – Simulink as Simulation and Modeling Environment
It‘s Math That Drives Things – Simulink as Simulation and Modeling Environment
Joachim Schlosser
 
POWID P031-OTSforCOSdesignFinal
POWID P031-OTSforCOSdesignFinalPOWID P031-OTSforCOSdesignFinal
POWID P031-OTSforCOSdesignFinalMarlina Lukman
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)Vijayakumar Kumar
 

Similar to High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant Commissioning (20)

Dynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationDynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design Validation
 
The Benefits of using Dynamic Simulation and Training Systems
The Benefits of using Dynamic Simulation and Training SystemsThe Benefits of using Dynamic Simulation and Training Systems
The Benefits of using Dynamic Simulation and Training Systems
 
Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes
Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and SuccessesMochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes
Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes
 
Modelon Modelica executable requirements Ansys Conference 2016
Modelon Modelica executable requirements Ansys Conference 2016Modelon Modelica executable requirements Ansys Conference 2016
Modelon Modelica executable requirements Ansys Conference 2016
 
MCS2SIM - Method Allowing Application of PSA Results in Simulators
MCS2SIM - Method Allowing Application of PSA Results in SimulatorsMCS2SIM - Method Allowing Application of PSA Results in Simulators
MCS2SIM - Method Allowing Application of PSA Results in Simulators
 
James Goss - Motor Design Limited
James Goss - Motor Design Limited James Goss - Motor Design Limited
James Goss - Motor Design Limited
 
Real-Time Engineering Simulators
Real-Time Engineering SimulatorsReal-Time Engineering Simulators
Real-Time Engineering Simulators
 
Jason Lowe I_C HMI Devloper
Jason Lowe I_C HMI DevloperJason Lowe I_C HMI Devloper
Jason Lowe I_C HMI Devloper
 
Implementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsImplementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human Factors
 
Virtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing PerformanceVirtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing Performance
 
DCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdf
DCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdfDCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdf
DCS_Check-Out_and_Operator_Training_with_HYSYS_Dynamics_White_v1.3.pdf
 
TechComp_overview_brief
TechComp_overview_briefTechComp_overview_brief
TechComp_overview_brief
 
Innovation in Nuclear Simulation
Innovation in Nuclear SimulationInnovation in Nuclear Simulation
Innovation in Nuclear Simulation
 
Resume - Jason Lewis
Resume - Jason LewisResume - Jason Lewis
Resume - Jason Lewis
 
Fontys Driving Simulator for Fontys
Fontys Driving Simulator for FontysFontys Driving Simulator for Fontys
Fontys Driving Simulator for Fontys
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017
 
GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019
 
It‘s Math That Drives Things – Simulink as Simulation and Modeling Environment
It‘s Math That Drives Things – Simulink as Simulation and Modeling EnvironmentIt‘s Math That Drives Things – Simulink as Simulation and Modeling Environment
It‘s Math That Drives Things – Simulink as Simulation and Modeling Environment
 
POWID P031-OTSforCOSdesignFinal
POWID P031-OTSforCOSdesignFinalPOWID P031-OTSforCOSdesignFinal
POWID P031-OTSforCOSdesignFinal
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)
 

More from GSE Systems, Inc.

Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
GSE Systems, Inc.
 
GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Systems, Inc.
 
Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019
GSE Systems, Inc.
 
Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'
GSE Systems, Inc.
 
Control & HMI Emulation Project
Control & HMI Emulation ProjectControl & HMI Emulation Project
Control & HMI Emulation Project
GSE Systems, Inc.
 
Multi-Unit Severe Accident Simulation
Multi-Unit Severe Accident SimulationMulti-Unit Severe Accident Simulation
Multi-Unit Severe Accident Simulation
GSE Systems, Inc.
 
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce ProcessApplying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
GSE Systems, Inc.
 
Investigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashInvestigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc Flash
GSE Systems, Inc.
 
Total Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertTotal Training Solution - Entry2Expert
Total Training Solution - Entry2Expert
GSE Systems, Inc.
 
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
GSE Systems, Inc.
 
ANS-3.5 Overview
ANS-3.5 OverviewANS-3.5 Overview
ANS-3.5 Overview
GSE Systems, Inc.
 
VIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingVIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation Training
GSE Systems, Inc.
 
Human Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorHuman Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy Sector
GSE Systems, Inc.
 
Proposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityProposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue University
GSE Systems, Inc.
 
How to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionHow to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & Selection
GSE Systems, Inc.
 
Are Your Employees Playing Games?
Are Your Employees Playing Games?Are Your Employees Playing Games?
Are Your Employees Playing Games?
GSE Systems, Inc.
 
Simulation Training Post Fukushima
Simulation Training Post FukushimaSimulation Training Post Fukushima
Simulation Training Post Fukushima
GSE Systems, Inc.
 
GSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Performance Improvement Solutions
GSE Performance Improvement Solutions
GSE Systems, Inc.
 
Improving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsImproving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training Programs
GSE Systems, Inc.
 
Simulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowSimulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and Tomorrow
GSE Systems, Inc.
 

More from GSE Systems, Inc. (20)

Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
 
GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019
 
Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019
 
Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'
 
Control & HMI Emulation Project
Control & HMI Emulation ProjectControl & HMI Emulation Project
Control & HMI Emulation Project
 
Multi-Unit Severe Accident Simulation
Multi-Unit Severe Accident SimulationMulti-Unit Severe Accident Simulation
Multi-Unit Severe Accident Simulation
 
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce ProcessApplying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
 
Investigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashInvestigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc Flash
 
Total Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertTotal Training Solution - Entry2Expert
Total Training Solution - Entry2Expert
 
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
 
ANS-3.5 Overview
ANS-3.5 OverviewANS-3.5 Overview
ANS-3.5 Overview
 
VIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingVIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation Training
 
Human Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorHuman Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy Sector
 
Proposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityProposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue University
 
How to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionHow to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & Selection
 
Are Your Employees Playing Games?
Are Your Employees Playing Games?Are Your Employees Playing Games?
Are Your Employees Playing Games?
 
Simulation Training Post Fukushima
Simulation Training Post FukushimaSimulation Training Post Fukushima
Simulation Training Post Fukushima
 
GSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Performance Improvement Solutions
GSE Performance Improvement Solutions
 
Improving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsImproving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training Programs
 
Simulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowSimulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and Tomorrow
 

Recently uploaded

Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
RinaMondal9
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Nexer Digital
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
UiPathCommunity
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024
Pierluigi Pugliese
 

Recently uploaded (20)

Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024
 

High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant Commissioning

  • 1. High-Fidelity Operator Training Simulator for a Combined Cycle Plant Implemented Before Plant Commissioning info@gses.com
  • 2. Overview •  Simulator project goals & objectives •  North American project schedule •  Unique challenges •  Execution strategy •  Virtual Ovation™ system •  Third-party virtual turbine controls •  High-fidelity modeling approach with JADE™ •  Summary
  • 3. Simulator Project Objective •  GSE and Emerson provided a high-fidelity simulator with models and controls indistinguishable from a real-time running plant. •  Simulator allows for extensive DCS testing/tuning and operator training prior to plant commissioning •  Simulator allows for testing with third-party turbine controls and Emerson implemented BOP systems
  • 4. Simulator Project Example •  North American combined cycle plant
  • 5. Project Goals •  Test the distributed control system (DCS) logic thoroughly ahead of plant commissioning •  Begin training operators ahead plant commissioning •  Configure simulator interface with Emerson Ovation™ Virtual Controllers
  • 6. Key Project Stake Holders •  Coordinated effort between: –  Simulation vendor (GSE) –  DCS vendor (Emerson) –  Burns & McDonnell – Turn key solution provider –  Utility company
  • 7. Project Implementation Challenges •  Establishing communication with the simulator software –  Third-party turbine control software in a VMware environment –  Ovation DCS system with the balance of plant –  GSE model software
  • 8. Project Implementation Challenges – A&E solution from third-party OPC alarm & event server to Ovation – Resetting the A&E interface on IC reset – Turbine control mapper program was designed for real-time environment, not simulation
  • 9. Project Execution Strategy •  High-resource staffing levels due to compressed schedule •  Simulator logistics focused on maximizing productivity and customer interaction •  Operator training available ahead of plant startup •  Simulator retune at site –  Update the DCS & models with running plant controls after commissioning is complete
  • 10. Resource Staffing Levels •  GSE provides 3 to 4 simulator team engineers. •  Emerson provides lead project simulation engineer and one project management lead engineer. •  Burns & McDonnell and utility company provide operators for testing and I&C technicians for the first initial startup. •  Third-party turbine control vendor provided remote and contract support.
  • 11. Project Schedule •  Simulator schedule (12 to 14 months) •  Review external logic outside of the Ovation DCS, some typical examples include: –  Smart breakers –  PLC logic –  Relay logic •  Review third-party plant controls (turbines in VMware environment)
  • 12. Project Schedule •  Model acceptance testing (MAT) at GSE proves the accuracy of models prior to DCS integration. –  Complete startup with functional controls –  Reduces schedule risk since models will be fully tested before linking them to new controls •  Simulator models interface directly with DCS controls to verify DCS performance prior to plant commissioning.
  • 13. Field Tuning •  Emerson field service was able to tune the Ovation BOP logic on the simulator. •  Drum level controls, steam bypass control loops and dynamic tuning was completed on the simulator. •  Tuning with the real equipment will still be required, however, the default values have all been modified and scaling and advanced tuning has been completed.
  • 14. Customer Acceptance •  Factory acceptance testing (FAT) at Emerson involves Burns & McDonnell and utility plant operators working directly with the simulation team to perform startup and shutdown testing. •  Variances are documented and corrected. •  Site acceptance testing (SAT) is done at customer site. This ensures the system performs the same as it does on the factory floor.
  • 15. Operator Training and Retune •  Operator training will begin 4-5 months ahead of plant startup. •  Simulator retune will be performed at the plant site by Emerson and GSE to update the simulator to the commissioned DCS controls once the plant has been fully commissioned.
  • 16. Simulator System Architecture •  DCS converted to Ovation virtual controller drops on a virtual controller host (VCH) •  DCS application software (control logic, database, and graphics) is installed on the simulator
  • 17. Typical Virtual Ovation Layout 2 Model Server Workstation Domain Controller / Database Server Workstation2 Operator Workstation Third Party Turbine Controls Ovation Switch Emulated Hard Panel Workstation Instructor Workstation Virtual Controller Host / Operator Workstation Turbine Network Switch
  • 18. High-Fidelity Modeling Approach GSE JADETM software: High-fidelity models of plant systems using a two- phase dynamic solution based on conservation of mass, momentum, and energy GSE SimExec software: Controls and monitors the execution of solutions in Real-time, interactively via freeze, run, snap, and reset
  • 19. Variance Recording System •  GSE, Emerson, and utility company communicate using a discrepancy reporting database accessible via the web, called Mantis. •  Allows quick and efficient documentation and resolution of data requests, model discrepancies, and DCS discrepancies
  • 20. GSE Testing Checkpoints for Model Readiness Verification •  Simulator schedule incorporates testing checkpoints throughout project to ensure model readiness: –  System unit test (SUT): •  Models tested stand-alone –  Model acceptance test (MAT): •  Models tested integrated together –  Factory acceptance test (FAT): •  Models tested integrated with the DCS
  • 21. The Advantage of Testing a DCS on a Simulator Prior to Plant Installation •  Allows correction of errors in DCS and ensures the DCS works properly •  Prevents complications during operation of the real plant •  Saves time and money spent on attempting to debug the DCS while controlling real equipment •  Avoids multiple startups/shutdowns needed to make DCS changes
  • 22. Other Major Benefits of Simulator •  Mimics the real plant for life-long testing and training •  Allows for first pass at field tuning to be performed prior to DCS delivery •  Capable of updating and retuning simultaneously to real plant •  Extensive training for emergency scenarios •  Future DCS logic updates can be tested on the simulator before the real plant
  • 23. •  Chiller feedback went to all three chillers and logic prevented the start of B and C chillers since indications were fed into the DCS that they were already running once A was started. •  TCA cooler – low flow trip. Third-party turbine controls had trip set points that were too close to control set points after gain blocks were factored in. The initial design didn’t work in actual testing and was subsequently modified. •  Vacuum trip – initial logic only accounted for vacuum pumps in operation and did not account for the hogger holding vacuum when the pumps shut off. This would have caused the vacuum breakers to open as soon as all the vacuum pumps turned off. Real-Life Examples of Integration Benefits
  • 24. Real-Life Examples of Integration Benefits •  Motor macro was modified so a trip needed to be cleared and reset before it could start again. The issue was observed during simulator testing. •  This is the advantage of staging the project at Emerson so the DCS design team can answer questions.
  • 25. Summary •  Burns & McDonnell, Emerson and GSE have experience with simulation of a natural gas fired combined cycle power station. •  The testing done on the simulator allowed for training to begin and for startup procedures to be fine tuned.
  • 26. Feedback •  Once plant commissioning is completed then Burns & McDonnell will advise on further benefits from having the simulator.
  • 27. For more information: Go to: www.GSES.com Call: 800.638.7912 Email: info@gses.com Follow us on: Twitter @GSESystems Facebook.com/GSESystems