Mechanical Completion
Certificate (MCC)
A certificate issued by the Executor to document that his MC scope
has been carried out. The MC certificates shall be used per MC
package.
Mechanical Completion
Check Record (MCCR)
A discipline Check record for the various equipment. These records
form the basis of the MC documentation. MCCRs are prepared for
one or more items for recording of the results from checking and
testing performed during Mechanical completion.Mechanical completion and commissioning Z-007
Rev. 2, Dec. 1999
NORSOK standard Page 4 of 54
Mechanical Completion (MC) The checking and testing of equipment and construction to confirm
that the installation is in accordance with drawings and
specifications and ready for commissioning in a safe manner and in
compliance with project requirements.
Mechanical Completions, Preservation, Pre-
Commissioning & Commissioning
Mechanical Completion (CMS)
Mechanical Completion is an integral process of management verification of approved design
installation. It represents the interface between construction and commissioning group activities and
includes all interface checks between all systems and subsystems whether modular or plant wide.
Mechanical Completion verification confirms that construction and installation of equipment, piping,
instrumentation, cabling, electrical, telecoms and mechanical components are physically complete
and all inspections, testing and documentation requirements have been completed.
Preservation
Preservation covers the method of protection and preventative maintenance carried out on equipment
and systems before and after they are taken into use. The process begins with the application of
preservatives and protection fittings by suppliers/vendors, prior to delivery permitting the
equipment/system to arrive at GPS fabrication yard undamaged.
Pre-Commissioning
Pre-Commissioning (PC) is the stage that involves the verification of functional operability of
elements within the system, by subjecting them to a set of simulated operational conditions, to
achieve a state of readiness for commissioning. Pre-commissioning requires energisation of
equipment and the introduction of the Permit to Work / LOTO systems.
Some examples include the running and entire testing of the power generation systems, testing of
emergency shutdown and control systems and dynamic trials on oil and gas export systems prior to
load out to minimize the offshore or site scope.
Commissioning
GPS’s commissioning capability consists of checking and testing all functions according to their
design parameters in conditions as close as possible to the design conditions, and in bringing them to
the status “Ready for Start-Up / Operations Readiness”.
Start-Up & Commissioning
Late facility design details, accelerated construction schedules, just-
in-time manufacturing of equipment and managed low-levels of
materials inventory at the distributor are the New Normal. As such,
improper attention to systems completion, systems turnover, pre-
commissioning, commissioning and start-up can lead a project further
toward failed economics.
Useful Definitions:
System – A section of the facility or process which is mechanically
continuous, but which can be isolated from other sections of the plant
or process in a way which allows independent turnover, inspection or
confirmation of process function.
Pre-Commissioning – Checking for design conformance, piping
mechanical completion, electrical code compliance and instrumentation installation and process tubing
adequacy. Pre-Commissioning includes equipment run-in, PLC and DCS action checks, and a rotation
check of process equipment which can be isolated from the overall process. Pre-Commissioning
activities overlap with construction activities. The two are isolated from one-another by system
boundaries and a robust system package turnover protocol. LOTO compliance, always a must, takes on
even greater meaning as electrical equipment and circuits become energized and equipment rotation
inspections commence.
Commissioning – The phase of a project where actual process fluids are introduced to process
equipment. Commissioning includes multiple function and process performance checks but precedes
actual Start-Up.
Start-Up – When stable process conditions are established and intentional product making or
manufacturing for sale commences.
As one of the last contractors to have access to the work, Ardent
inherits the lost schedule float of all construction predecessors in the
form of construction acceleration. To help manage ourselves toward
timely and efficient completion we have developed a number of
proprietary databases and work-order progress management tools. These tools blend well with systems
turnover and follow on well into systems pre-commissioning and start-up.
Pre-Commissioning starts when facility systems achieve Mechanical Completion. In today's fast track
world of building while some detailed designs are still in review, the Pre-Commissioning efforts must be
tasked and managed in conjunction with the project's integrated Critical Path schedule. Construction is
often progressed by area, and by the time erection progress exceeds 70% and/or I&E progress exceeds
50%, it is time to begin turning over systems from construction to the Pre-Commissioning team. Ardent's
system turnover database and protocol helps to define,punchlist and manage inspection and pre-
commissioning efforts. Our experienced instrument technicians and field process techs can inspect,
track and assure systems completion progress is monitored, measured, achieved and reported.
Commissioning and Start-up are a key part of project execution and are the natural outflow of quality
systems completion, turnover and pre-commissioning. Introducing and stabilizing process fluids and
conditions and commencing product export are WHY facilities get built. Ardent's Pre-Commissioning,
Commissioning and Start-up Techs can help lead the way to the ultimate finish line, successful project
completion.
5 MECHANICAL COMPLETION
5.1 Introduction
This chapter forms the basis for the execution and documentation of mechanical completion
activities.
Mechanical completion takes place through all phases of a project, up to the commissioning phase.
• Mechanical completion encompasses all disciplines.
• The detailed responsibilities are described in the contract.
• Executor of MC activities is responsible for establishing and compiling the MC dossiers and
report status into PCS.
5.2 Documentation for a MC Package
The MC package shall consist of an MCC, an MCSI, MCCRs and a PLR printout as described
below.
A Mechanical Completion Certificate (MCC) is a form completed by the Executor after all MC is
carried out. The MCC is the cover sheet for each MC package. An MC package shall when signed,
be ready for handover to commissioning.
The Check Records (MCCR) are the forms on which the Executors record the results of all
checks, inspections and tests carried out for each individual item.
A Punch List (PL) shall be prepared by the Executor along with the package a PL shall be included to
document incomplete work.
A Mechanical Completion Status Index (MCSI) listing the status of all MCCRs for the MC
package shall be included.
5.3 Handover at Mechanical completion
Handover from Mechanical completion to commissioning shall be at commissioning package level,
documented by the ready for commissioning certificate (RFCC).
5.4 Carry Over Work Register (COWR)
The COWR lists all punch items that the Project accepts as cannot be completed during present
phase. The register is used for the release of the work from the Executor and will as such be an input
to the scheduling and planning of outstanding work to be performed during later phases.
The COWR Item number and cross reference to the Punch list/MCCR shall be given. COWR work
shall be marked up on drawings or sketches and be included in the records.
Material Status List (MSL) and marked up drawings/instruction shall contain sufficient information
for job setting in a later phase.
5.5 Typical Mechanical completion activities
Mechanical completion activities includes checking of fabrication and installation work.
Executor shall complete packages related to listed disciplines and as required by the MCSI.
Executor shall complete the check list items as per the MCCRs. (See Annex A for typicals). The
activities shall include but not be limited to:
5.5.1 Mechanical
• Visual inspection for complete and correct installation.
• Internal inspection of tanks and vessels.
• Alignment.
• Load testing of lifting equipment.
• Hot oil flushing.
• Bolt tensioning.
• Dimension control.
• Preservation.
5.5.2 Electrical
• Visual inspection for complete and correct installation.
• Insulation and continuity testing of cables.
• Insulation testing of generator, transformers and motors, panels, distribution board etc.
• Earthing checks.
• Static check of switches and control devices.
• Battery preparations.
• Lighting and socket outlet checks.
• Area completion.
• Heat tracing.
• Preservation.
5.5.3 Instrument/Telecommunication
• Calibration and testing of instruments prior to installation.
• Visual inspection for complete and correct installation.
• Insulation and continuity testing of cables.
• Cleaning, flushing, pressure and leak testing of pneumatic and hydraulic tubing.
• Adjustment of control, alarm and shutdown settings.
• Loop testing.
• Function testing of control systems.
• Function testing of field instruments.
• Hot oil flushing of instrument tubing.
• Area completion.
• Preservation.
5.5.4 Piping
• NDE carried out.
• Welding procedures.
• Removal of all items subject to damage during flushing, cleaning and pressure testing.
• Flushing of pipework.
• Chemical cleaning and testing of pipework.
• Drying of tested pipework.
• Preservation of tested pipework.
• Reinstatement of all items after testing.
• Final inspection of pipework.
• Test ISO's and P&ID's showing the extent of each pressure test.
• Pneumatic and hydraulic tubing.
• Hot oil flushing of pipework.
• Bolt tensioning.
• Pipe supports completed.
• Insulation.
• Flow coding.

More Related Content

What's hot

Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and CommissioningpetroEDGE
 
Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideChukwuma Anyanwu, PMP, CCP
 
Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)Stephanus Roux C Eng , IntPE(uk) , FIET
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfMDAbdullah621330
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Cross country pipeline _Telecom_Instrumentation and SCADA
Cross country pipeline _Telecom_Instrumentation and SCADACross country pipeline _Telecom_Instrumentation and SCADA
Cross country pipeline _Telecom_Instrumentation and SCADARakesh Ujjawal
 
Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineeringasim569
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installationswan saiful arini
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works Shaik Mohsin
 
Api 570 course material
Api 570 course materialApi 570 course material
Api 570 course materialTASSIO DOURADO
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
what is process piping
what is process pipingwhat is process piping
what is process pipingVarun Patel
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
PIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdfPIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdfMassinissaHamel
 
Heat Exchangers inspection .pdf
Heat Exchangers inspection .pdfHeat Exchangers inspection .pdf
Heat Exchangers inspection .pdfNickeshShah
 
API 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory CourseAPI 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory CoursepetroEDGE
 

What's hot (20)

Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and Commissioning
 
Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guide
 
Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Cross country pipeline _Telecom_Instrumentation and SCADA
Cross country pipeline _Telecom_Instrumentation and SCADACross country pipeline _Telecom_Instrumentation and SCADA
Cross country pipeline _Telecom_Instrumentation and SCADA
 
Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineering
 
Panel check-list
Panel check-listPanel check-list
Panel check-list
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Api 570 course material
Api 570 course materialApi 570 course material
Api 570 course material
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
PIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdfPIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdf
 
Heat Exchangers inspection .pdf
Heat Exchangers inspection .pdfHeat Exchangers inspection .pdf
Heat Exchangers inspection .pdf
 
Dcs operator training
Dcs operator trainingDcs operator training
Dcs operator training
 
Pipeline repair techniques
Pipeline repair techniquesPipeline repair techniques
Pipeline repair techniques
 
API 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory CourseAPI 570 Piping and Pipeline Inspectors Preparatory Course
API 570 Piping and Pipeline Inspectors Preparatory Course
 

Similar to Mechanical completion

110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resumeUmang Tailor
 
Pre commissioning Instrument Engineer
Pre commissioning Instrument EngineerPre commissioning Instrument Engineer
Pre commissioning Instrument EngineerKamran Saeed
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdfharis348605
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editorseldhoev
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxRamkumar906213
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxRamkumar906213
 
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfAPTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfssuser1fc1f0
 
instrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbineinstrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbineKsPuri
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSOlivia Wilson
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSOlivia Wilson
 
Resume_Instrumentation Engineer_9 year experience
Resume_Instrumentation Engineer_9 year experienceResume_Instrumentation Engineer_9 year experience
Resume_Instrumentation Engineer_9 year experienceDHRUVA MISHRA
 

Similar to Mechanical completion (20)

110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resume
 
Pre commissioning Instrument Engineer
Pre commissioning Instrument EngineerPre commissioning Instrument Engineer
Pre commissioning Instrument Engineer
 
019113
019113019113
019113
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
 
CV
CVCV
CV
 
Cv of nilesh rk
Cv of nilesh rkCv of nilesh rk
Cv of nilesh rk
 
commissioning c-3
commissioning c-3commissioning c-3
commissioning c-3
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editors
 
Brij mohan cv
Brij mohan  cvBrij mohan  cv
Brij mohan cv
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptx
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptx
 
Sreekumar_Resume
Sreekumar_ResumeSreekumar_Resume
Sreekumar_Resume
 
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfAPTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
 
instrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbineinstrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbine
 
NY_ CV
NY_ CVNY_ CV
NY_ CV
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
 
Resume_Instrumentation Engineer_9 year experience
Resume_Instrumentation Engineer_9 year experienceResume_Instrumentation Engineer_9 year experience
Resume_Instrumentation Engineer_9 year experience
 
Matt Instr CV
Matt Instr CVMatt Instr CV
Matt Instr CV
 

Recently uploaded

Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 

Recently uploaded (20)

Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

Mechanical completion

  • 1. Mechanical Completion Certificate (MCC) A certificate issued by the Executor to document that his MC scope has been carried out. The MC certificates shall be used per MC package. Mechanical Completion Check Record (MCCR) A discipline Check record for the various equipment. These records form the basis of the MC documentation. MCCRs are prepared for one or more items for recording of the results from checking and testing performed during Mechanical completion.Mechanical completion and commissioning Z-007 Rev. 2, Dec. 1999 NORSOK standard Page 4 of 54 Mechanical Completion (MC) The checking and testing of equipment and construction to confirm that the installation is in accordance with drawings and specifications and ready for commissioning in a safe manner and in compliance with project requirements. Mechanical Completions, Preservation, Pre- Commissioning & Commissioning Mechanical Completion (CMS) Mechanical Completion is an integral process of management verification of approved design installation. It represents the interface between construction and commissioning group activities and includes all interface checks between all systems and subsystems whether modular or plant wide. Mechanical Completion verification confirms that construction and installation of equipment, piping, instrumentation, cabling, electrical, telecoms and mechanical components are physically complete and all inspections, testing and documentation requirements have been completed. Preservation Preservation covers the method of protection and preventative maintenance carried out on equipment and systems before and after they are taken into use. The process begins with the application of preservatives and protection fittings by suppliers/vendors, prior to delivery permitting the equipment/system to arrive at GPS fabrication yard undamaged. Pre-Commissioning Pre-Commissioning (PC) is the stage that involves the verification of functional operability of elements within the system, by subjecting them to a set of simulated operational conditions, to achieve a state of readiness for commissioning. Pre-commissioning requires energisation of equipment and the introduction of the Permit to Work / LOTO systems.
  • 2. Some examples include the running and entire testing of the power generation systems, testing of emergency shutdown and control systems and dynamic trials on oil and gas export systems prior to load out to minimize the offshore or site scope. Commissioning GPS’s commissioning capability consists of checking and testing all functions according to their design parameters in conditions as close as possible to the design conditions, and in bringing them to the status “Ready for Start-Up / Operations Readiness”. Start-Up & Commissioning Late facility design details, accelerated construction schedules, just- in-time manufacturing of equipment and managed low-levels of materials inventory at the distributor are the New Normal. As such, improper attention to systems completion, systems turnover, pre- commissioning, commissioning and start-up can lead a project further toward failed economics. Useful Definitions: System – A section of the facility or process which is mechanically continuous, but which can be isolated from other sections of the plant or process in a way which allows independent turnover, inspection or confirmation of process function. Pre-Commissioning – Checking for design conformance, piping mechanical completion, electrical code compliance and instrumentation installation and process tubing adequacy. Pre-Commissioning includes equipment run-in, PLC and DCS action checks, and a rotation check of process equipment which can be isolated from the overall process. Pre-Commissioning activities overlap with construction activities. The two are isolated from one-another by system boundaries and a robust system package turnover protocol. LOTO compliance, always a must, takes on even greater meaning as electrical equipment and circuits become energized and equipment rotation inspections commence. Commissioning – The phase of a project where actual process fluids are introduced to process equipment. Commissioning includes multiple function and process performance checks but precedes actual Start-Up. Start-Up – When stable process conditions are established and intentional product making or manufacturing for sale commences. As one of the last contractors to have access to the work, Ardent inherits the lost schedule float of all construction predecessors in the form of construction acceleration. To help manage ourselves toward timely and efficient completion we have developed a number of
  • 3. proprietary databases and work-order progress management tools. These tools blend well with systems turnover and follow on well into systems pre-commissioning and start-up. Pre-Commissioning starts when facility systems achieve Mechanical Completion. In today's fast track world of building while some detailed designs are still in review, the Pre-Commissioning efforts must be tasked and managed in conjunction with the project's integrated Critical Path schedule. Construction is often progressed by area, and by the time erection progress exceeds 70% and/or I&E progress exceeds 50%, it is time to begin turning over systems from construction to the Pre-Commissioning team. Ardent's system turnover database and protocol helps to define,punchlist and manage inspection and pre- commissioning efforts. Our experienced instrument technicians and field process techs can inspect, track and assure systems completion progress is monitored, measured, achieved and reported. Commissioning and Start-up are a key part of project execution and are the natural outflow of quality systems completion, turnover and pre-commissioning. Introducing and stabilizing process fluids and conditions and commencing product export are WHY facilities get built. Ardent's Pre-Commissioning, Commissioning and Start-up Techs can help lead the way to the ultimate finish line, successful project completion. 5 MECHANICAL COMPLETION 5.1 Introduction This chapter forms the basis for the execution and documentation of mechanical completion activities. Mechanical completion takes place through all phases of a project, up to the commissioning phase. • Mechanical completion encompasses all disciplines. • The detailed responsibilities are described in the contract. • Executor of MC activities is responsible for establishing and compiling the MC dossiers and report status into PCS. 5.2 Documentation for a MC Package The MC package shall consist of an MCC, an MCSI, MCCRs and a PLR printout as described below. A Mechanical Completion Certificate (MCC) is a form completed by the Executor after all MC is carried out. The MCC is the cover sheet for each MC package. An MC package shall when signed, be ready for handover to commissioning. The Check Records (MCCR) are the forms on which the Executors record the results of all checks, inspections and tests carried out for each individual item. A Punch List (PL) shall be prepared by the Executor along with the package a PL shall be included to document incomplete work. A Mechanical Completion Status Index (MCSI) listing the status of all MCCRs for the MC package shall be included. 5.3 Handover at Mechanical completion Handover from Mechanical completion to commissioning shall be at commissioning package level,
  • 4. documented by the ready for commissioning certificate (RFCC). 5.4 Carry Over Work Register (COWR) The COWR lists all punch items that the Project accepts as cannot be completed during present phase. The register is used for the release of the work from the Executor and will as such be an input to the scheduling and planning of outstanding work to be performed during later phases. The COWR Item number and cross reference to the Punch list/MCCR shall be given. COWR work shall be marked up on drawings or sketches and be included in the records. Material Status List (MSL) and marked up drawings/instruction shall contain sufficient information for job setting in a later phase. 5.5 Typical Mechanical completion activities Mechanical completion activities includes checking of fabrication and installation work. Executor shall complete packages related to listed disciplines and as required by the MCSI. Executor shall complete the check list items as per the MCCRs. (See Annex A for typicals). The activities shall include but not be limited to: 5.5.1 Mechanical • Visual inspection for complete and correct installation. • Internal inspection of tanks and vessels. • Alignment. • Load testing of lifting equipment. • Hot oil flushing. • Bolt tensioning. • Dimension control. • Preservation. 5.5.2 Electrical • Visual inspection for complete and correct installation. • Insulation and continuity testing of cables. • Insulation testing of generator, transformers and motors, panels, distribution board etc. • Earthing checks. • Static check of switches and control devices. • Battery preparations. • Lighting and socket outlet checks. • Area completion. • Heat tracing. • Preservation. 5.5.3 Instrument/Telecommunication
  • 5. • Calibration and testing of instruments prior to installation. • Visual inspection for complete and correct installation. • Insulation and continuity testing of cables. • Cleaning, flushing, pressure and leak testing of pneumatic and hydraulic tubing. • Adjustment of control, alarm and shutdown settings. • Loop testing. • Function testing of control systems. • Function testing of field instruments. • Hot oil flushing of instrument tubing. • Area completion. • Preservation. 5.5.4 Piping • NDE carried out. • Welding procedures. • Removal of all items subject to damage during flushing, cleaning and pressure testing. • Flushing of pipework. • Chemical cleaning and testing of pipework. • Drying of tested pipework. • Preservation of tested pipework. • Reinstatement of all items after testing. • Final inspection of pipework. • Test ISO's and P&ID's showing the extent of each pressure test. • Pneumatic and hydraulic tubing. • Hot oil flushing of pipework. • Bolt tensioning. • Pipe supports completed. • Insulation. • Flow coding.