Projects
handled
Project : Rabab Haeweel Integrated Project (RHIP)
Client : PDO
67 PAR Modules (10,000 MT)
139,550 Inch Dia Piping
Project : UZ 750 K
Client : ZADCO
Scope : 15 PAM + 18 PAR modules (13,400 MT + 254,000 Inch Dia Piping)
Fab. Period: Nov 2014 To Aug 2016
Project : MHN RD III
Client : ONGC
Scope : 2 Jackets (5000MT )
Fab. Period: Mar 2015 To Jan 2016
Project : Umm Lulu and Nasr Phase 1 Project
Client : ADMA OPCO
Scope : Fabrication of 5 Topsides, 5 Jackets & 1 Bridge (18,650 MT)
Fab. Period: Jun 2012- March 2014
Project : Heera Re-development Project- II
Client : ONGC
Scope : 3 Jackets (7500 MT )
Fab. Period: June 2013- Feb 2014
7
Project : Zawtika Phase 1A Field Development
Client : PTTEPI
Scope : 3 Topsides & 3 Jackets (28,000 MT)
Fab. Period: Sep 2011 – Feb 2013
Project : Sagar Uday
Client : ONGC
Scope : Refurbishment
Fab. Period: Sep 2011 – Feb 2013

Previous projects

  • 1.
  • 2.
    Project : RababHaeweel Integrated Project (RHIP) Client : PDO 67 PAR Modules (10,000 MT) 139,550 Inch Dia Piping
  • 3.
    Project : UZ750 K Client : ZADCO Scope : 15 PAM + 18 PAR modules (13,400 MT + 254,000 Inch Dia Piping) Fab. Period: Nov 2014 To Aug 2016
  • 4.
    Project : MHNRD III Client : ONGC Scope : 2 Jackets (5000MT ) Fab. Period: Mar 2015 To Jan 2016
  • 5.
    Project : UmmLulu and Nasr Phase 1 Project Client : ADMA OPCO Scope : Fabrication of 5 Topsides, 5 Jackets & 1 Bridge (18,650 MT) Fab. Period: Jun 2012- March 2014
  • 6.
    Project : HeeraRe-development Project- II Client : ONGC Scope : 3 Jackets (7500 MT ) Fab. Period: June 2013- Feb 2014
  • 7.
    7 Project : ZawtikaPhase 1A Field Development Client : PTTEPI Scope : 3 Topsides & 3 Jackets (28,000 MT) Fab. Period: Sep 2011 – Feb 2013
  • 8.
    Project : SagarUday Client : ONGC Scope : Refurbishment Fab. Period: Sep 2011 – Feb 2013