SlideShare a Scribd company logo
Reactive Power Management
- Case study
-- Nandan Pathak (AE)
ICT -1 ICT -2 G-3 G-4 G-5
200 MW
160 MVAR
160 MW
135
MVAR
200 MW
160 MVAR
160 MW
135
MVAR
160 MW
140
MVAR
LOAD LOAD
220 kV
Girwali Bus
220 kV
Parli Bus
~
GENERATION
870 MW
730 MVAR
LOAD:
A ) GENERATORS:
a) High MVAR drawl
b) High excitation current
B) ICT:
a) Overloading due to MVAR
b) Low voltage on 220 kV bus ( 200 kV)
C) LOAD:
11 kV side:
a) Overload tripping
b) Very low voltages
c) Conductor snapping
d) Local load shedding
440 V side:
a) Failure of transformers
b) Conductor snapping
A)High seasonal load especially agriculture
during October to March
B) Failure of reactive compensation
A)Identification of areas
a) Beed district
b) Solapur district
c) Nanded district
d) Pabhani district
e) Latur district
A)Identification of radial feeders
220 kV
Girwali Bus
220 kV Nanded
160 MW 100 MVAR
220 kV Parbhani
100 MW 80 MVAR 132 kV
Parli Bus
132kV Beed
80 MW 60 MVAR
~ ~
132 kV Latur -1
90 MW 75 MVAR
132 kV Latur -2
60 MW 45 MVAR
132 kV
Girwali Bus
On similar lines loaded 11 & 33 feeders were identified.
I) Reactive power compensation available :
i. Substation ----- 164 MVAR
ii. Switched capacitors on 11kV – 240 MVAR (0.6 X405)
II) Focus Area – 11 kV , 0.6 MVAR capacitors
a. Repairs in a central laboratory
b. On site replacement, checking, modification, training
Modifications adopted for
optimum compensation
 1. Cell rating 0.66 Mvar at 12 kV
 2. De-rating at Low Voltage2. De-rating at Low Voltage
 3.3. ModificationModification
 A. Fixed capacitorsA. Fixed capacitors
 B. Addition to basic schemeB. Addition to basic scheme
 4. On site demonstrations
 5. Team visit – Nasik , Pune (R ),
Kolhapur, Sangli,Parbhani
 1. Reduction in overload tripping of 11 kV &
33 kV feeders.
 2. Reduction in blowing of HG fuses at 33/11
kV transformers.
 3. Reduction in conductor snapping.
 4. Improvement in voltage profiles
 LTLT 105 Volts to 190 volts105 Volts to 190 volts
 11kV11kV 7.6 kV to 9.8 kV7.6 kV to 9.8 kV
ICT -1 ICT -2 G-3 G-4 G-5
250 MW (200)
100 MVAR(160)
200 MW(160)
60 MVAR(135)250 MW(200)
100MVAR(160
)
200 MW
60 MVAR
195 MW(150)
80 MVAR(140)
LOAD LOAD
220 kV
Girwali Bus
220 kV
Parli Bus
~
GENERATION
1095 MW (870)
400 MVAR (730)
LOAD:
Voltage changes:
220 kV 215 kV (200 kV)
132 kV 125 kV (106 kV)
33 kV 31 kV (27 kV)
Radial load changes
132 kV
Parli Bus
132kV Beed
95 MW 30 MVAR
(80 MW 60 MVAR)
~ ~
132 kV Latur –1
105 MW 40 MVAR
(90 MW 75 MVAR)
132 kV Latur –2
70 MW 30 MVAR
(60 MW 45 MVAR)
132 kV
Girwali
Bus
MONTH KWH 1998 KWH 1999 KWH 2000 KWH 2001
January 791500 1101100 1014800 401700
February 545000 938100 699100 239400
March 667900 819800 663300* 262200
April 539400 790900 87400* 183400
May 512000 473200 -* 275400
June 164400* 459800 167700* 43800**
July 313900 1170300♣ 442100  
August 310400 948000♣ 490900  
September 330600 630400 342700  
October 500300 706100 350100  
November 530400 854700 626000  
December 307300* 1104100 542000  
•---Load shifted to another feeder ♣--- Load of other feeder taken on this feeder
•** --- kWh meter stopped due to leading PF
Note:
0.6 MVAR capacitor bank recommissioned at village Pandharee on Dt.28.11.2000
0.6 MVAR capacitor bank added at same location on Dt.4.12.2000
  New 0.6 MVAR capacitor bank commissioned at Pokharni Phata on Dt.8.12.2000
KWH recorded on 11kV Matkuli feeder from 132 / 11 kV T/F at 132 kV Ashti
substation
0
200000
400000
600000
800000
1000000
1200000
JanuaryFebruary
March
April
May
June
July
August
Septem
berOctoberNovem
berDecem
ber
1998
1999
2000
2001
Month Forecasted Energy sent
out (kWH)
Actual Energy sent out
(kWH)
Savings
(kWH)
Remark
Dec 2000 689997 542000 147997 21.45 %
Jan 2001 624172 401700 222472 35.60 %
Feb 2001 520905 239400 281505 54.00 %
Mar 2001 562029 265200 296829 52.00 %
Apr 2001 511766 183400 328366 64.10 %
May 2001 451451 275400 176051 39.00 %
Total 3360320 1907100 1453220 43.24 %
Energy savings on 11 kV Matkuli feeder
1.System requires high order reactive compensation.
2.Use of fixed value non switched/seasonal manual switched
capacitors is economical.
3. Complementary switching for optimum compensation.
4. Dedicated setup for overall line loss reduction.

More Related Content

What's hot

Electrical Theory Review
Electrical Theory ReviewElectrical Theory Review
Electrical Theory Review
Daniel Gray
 
Giulianno bozzo
Giulianno bozzoGiulianno bozzo
Giulianno bozzo
giuliano45
 
Optimum design and performance for nablus network
Optimum design and performance for nablus networkOptimum design and performance for nablus network
Optimum design and performance for nablus network
slmnsvn
 
Strong Power for Cryptocurrency Mining/HPC/GPGPU Systems
Strong Power for Cryptocurrency Mining/HPC/GPGPU SystemsStrong Power for Cryptocurrency Mining/HPC/GPGPU Systems
Strong Power for Cryptocurrency Mining/HPC/GPGPU Systems
FSP Technology Inc.
 
Danapur Electrical LayOut-Final Model
Danapur Electrical LayOut-Final ModelDanapur Electrical LayOut-Final Model
Danapur Electrical LayOut-Final ModelMd Ishteyaque
 
Original NPN Transistor D468 2SD468 468 TO-92 New
Original NPN Transistor D468 2SD468 468 TO-92 NewOriginal NPN Transistor D468 2SD468 468 TO-92 New
Original NPN Transistor D468 2SD468 468 TO-92 New
AUTHELECTRONIC
 
Occ of dc generator
Occ of dc generatorOcc of dc generator
Occ of dc generator
Jayaraju Gaddala
 
Three phase power measurement
Three phase power measurementThree phase power measurement
Three phase power measurement
Jayaraju Gaddala
 
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Alan Courtay
 
Curva 1 clase 3
Curva 1 clase 3Curva 1 clase 3
Curva 1 clase 3
Daniela Portillo
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCL
surendra rawat
 
220kv substation
220kv substation220kv substation
220kv substation
Anbarasu Balakrishnan
 
Sub station design
Sub station designSub station design
Sub station design
JunaedulIslam
 
Compact nsx dc
Compact nsx dcCompact nsx dc
Compact nsx dc
José Escobar
 
132kv Substation
132kv Substation132kv Substation
132kv Substationguestecdd58
 
132kv Substation demo
132kv Substation demo132kv Substation demo
132kv Substation demo
Pravesh Kafle
 
Practice questions
Practice questionsPractice questions
Practice questions
Abha Tripathi
 

What's hot (19)

Electrical Theory Review
Electrical Theory ReviewElectrical Theory Review
Electrical Theory Review
 
Giulianno bozzo
Giulianno bozzoGiulianno bozzo
Giulianno bozzo
 
Optimum design and performance for nablus network
Optimum design and performance for nablus networkOptimum design and performance for nablus network
Optimum design and performance for nablus network
 
My ppt
My pptMy ppt
My ppt
 
Strong Power for Cryptocurrency Mining/HPC/GPGPU Systems
Strong Power for Cryptocurrency Mining/HPC/GPGPU SystemsStrong Power for Cryptocurrency Mining/HPC/GPGPU Systems
Strong Power for Cryptocurrency Mining/HPC/GPGPU Systems
 
dn542fa_web
dn542fa_webdn542fa_web
dn542fa_web
 
Danapur Electrical LayOut-Final Model
Danapur Electrical LayOut-Final ModelDanapur Electrical LayOut-Final Model
Danapur Electrical LayOut-Final Model
 
Original NPN Transistor D468 2SD468 468 TO-92 New
Original NPN Transistor D468 2SD468 468 TO-92 NewOriginal NPN Transistor D468 2SD468 468 TO-92 New
Original NPN Transistor D468 2SD468 468 TO-92 New
 
Occ of dc generator
Occ of dc generatorOcc of dc generator
Occ of dc generator
 
Three phase power measurement
Three phase power measurementThree phase power measurement
Three phase power measurement
 
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
Quasi-resonant Flyback Converter Simulations with Saber - APEC 2016
 
Curva 1 clase 3
Curva 1 clase 3Curva 1 clase 3
Curva 1 clase 3
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCL
 
220kv substation
220kv substation220kv substation
220kv substation
 
Sub station design
Sub station designSub station design
Sub station design
 
Compact nsx dc
Compact nsx dcCompact nsx dc
Compact nsx dc
 
132kv Substation
132kv Substation132kv Substation
132kv Substation
 
132kv Substation demo
132kv Substation demo132kv Substation demo
132kv Substation demo
 
Practice questions
Practice questionsPractice questions
Practice questions
 

Similar to Mvar management

Presentation Fatehpur Substation TL Final 22.09.2021.pptx
Presentation Fatehpur Substation  TL Final 22.09.2021.pptxPresentation Fatehpur Substation  TL Final 22.09.2021.pptx
Presentation Fatehpur Substation TL Final 22.09.2021.pptx
abhishek357916
 
1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_india
ganesh g
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
Vaibhav Jain
 
National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)
Aneel-k Suthar
 
Industrial Training Presentation
Industrial Training PresentationIndustrial Training Presentation
Industrial Training Presentation
kumarmayursinha
 
southern grid
southern grid southern grid
southern grid
Molla Morshad
 
220 kv training by saurabh chauhan
 220 kv training by saurabh chauhan 220 kv training by saurabh chauhan
220 kv training by saurabh chauhan
saurabh chauhan
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
Prannay Kumar Giri
 
A brief about Jeypore Sub-station Presentation
A brief about Jeypore Sub-station PresentationA brief about Jeypore Sub-station Presentation
A brief about Jeypore Sub-station Presentation
Jeyporess2021
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report
imkanhaiyalal
 
Ht and lt scheme dc system
Ht and lt scheme dc systemHt and lt scheme dc system
Ht and lt scheme dc system
Shashi Katiyar
 
04_KAYAH.pptx
04_KAYAH.pptx04_KAYAH.pptx
04_KAYAH.pptx
MahmoudAli386741
 
Industrial summer training
Industrial summer trainingIndustrial summer training
Industrial summer training
Shubham Patel
 
2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)hekmatjoo
 
Training report on DVC
Training report on DVCTraining report on DVC
Training report on DVC
Linkon Khan
 
Hydro POWER PLANT
Hydro POWER PLANTHydro POWER PLANT
Hydro POWER PLANT
soprajap
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
Avirup Ghosh
 
Power Transmission & Distribution in India
Power Transmission & Distribution in IndiaPower Transmission & Distribution in India
Power Transmission & Distribution in India
Indian Energy Sector
 
Sor
SorSor
Ac supply system
Ac supply systemAc supply system
Ac supply systemankitankesh
 

Similar to Mvar management (20)

Presentation Fatehpur Substation TL Final 22.09.2021.pptx
Presentation Fatehpur Substation  TL Final 22.09.2021.pptxPresentation Fatehpur Substation  TL Final 22.09.2021.pptx
Presentation Fatehpur Substation TL Final 22.09.2021.pptx
 
1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_india
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
 
National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)
 
Industrial Training Presentation
Industrial Training PresentationIndustrial Training Presentation
Industrial Training Presentation
 
southern grid
southern grid southern grid
southern grid
 
220 kv training by saurabh chauhan
 220 kv training by saurabh chauhan 220 kv training by saurabh chauhan
220 kv training by saurabh chauhan
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
 
A brief about Jeypore Sub-station Presentation
A brief about Jeypore Sub-station PresentationA brief about Jeypore Sub-station Presentation
A brief about Jeypore Sub-station Presentation
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report
 
Ht and lt scheme dc system
Ht and lt scheme dc systemHt and lt scheme dc system
Ht and lt scheme dc system
 
04_KAYAH.pptx
04_KAYAH.pptx04_KAYAH.pptx
04_KAYAH.pptx
 
Industrial summer training
Industrial summer trainingIndustrial summer training
Industrial summer training
 
2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)
 
Training report on DVC
Training report on DVCTraining report on DVC
Training report on DVC
 
Hydro POWER PLANT
Hydro POWER PLANTHydro POWER PLANT
Hydro POWER PLANT
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
 
Power Transmission & Distribution in India
Power Transmission & Distribution in IndiaPower Transmission & Distribution in India
Power Transmission & Distribution in India
 
Sor
SorSor
Sor
 
Ac supply system
Ac supply systemAc supply system
Ac supply system
 

More from vishal laddha

Case study on EHTC.pdf
Case study on EHTC.pdfCase study on EHTC.pdf
Case study on EHTC.pdf
vishal laddha
 
Super critcal_sub critical_higher capacity sets - Copy.pdf
Super critcal_sub critical_higher capacity sets - Copy.pdfSuper critcal_sub critical_higher capacity sets - Copy.pdf
Super critcal_sub critical_higher capacity sets - Copy.pdf
vishal laddha
 
CMC.pptx
CMC.pptxCMC.pptx
CMC.pptx
vishal laddha
 
Gun Kaizen.pptx
Gun Kaizen.pptxGun Kaizen.pptx
Gun Kaizen.pptx
vishal laddha
 
MAR,23.pptx
MAR,23.pptxMAR,23.pptx
MAR,23.pptx
vishal laddha
 
Real Python 🐍👨_💻-1.pdf
Real Python 🐍👨_💻-1.pdfReal Python 🐍👨_💻-1.pdf
Real Python 🐍👨_💻-1.pdf
vishal laddha
 
Brief Writeup on BCVMS.pdf
Brief Writeup on BCVMS.pdfBrief Writeup on BCVMS.pdf
Brief Writeup on BCVMS.pdf
vishal laddha
 
BASICS OF VIBRATION.ppt
BASICS OF VIBRATION.pptBASICS OF VIBRATION.ppt
BASICS OF VIBRATION.ppt
vishal laddha
 
Flame Scanner.ppt
Flame Scanner.pptFlame Scanner.ppt
Flame Scanner.ppt
vishal laddha
 
EXCITATION SYSTEM.ppt
EXCITATION SYSTEM.pptEXCITATION SYSTEM.ppt
EXCITATION SYSTEM.ppt
vishal laddha
 
HR.pptx
HR.pptxHR.pptx
HR.pptx
vishal laddha
 
battery.ppt
battery.pptbattery.ppt
battery.ppt
vishal laddha
 
December'2022 Maintenance review1.pptx
December'2022 Maintenance review1.pptxDecember'2022 Maintenance review1.pptx
December'2022 Maintenance review1.pptx
vishal laddha
 
Case Studies on Vibrations.ppt
Case Studies on Vibrations.pptCase Studies on Vibrations.ppt
Case Studies on Vibrations.ppt
vishal laddha
 
Assignment business comm
Assignment business commAssignment business comm
Assignment business comm
vishal laddha
 
Assignment accounts
Assignment  accountsAssignment  accounts
Assignment accounts
vishal laddha
 
Assignment hrm
Assignment hrmAssignment hrm
Assignment hrm
vishal laddha
 
Plant operation manual
Plant operation manualPlant operation manual
Plant operation manual
vishal laddha
 
Cable fault-finding-guide
Cable fault-finding-guideCable fault-finding-guide
Cable fault-finding-guide
vishal laddha
 

More from vishal laddha (20)

Case study on EHTC.pdf
Case study on EHTC.pdfCase study on EHTC.pdf
Case study on EHTC.pdf
 
Super critcal_sub critical_higher capacity sets - Copy.pdf
Super critcal_sub critical_higher capacity sets - Copy.pdfSuper critcal_sub critical_higher capacity sets - Copy.pdf
Super critcal_sub critical_higher capacity sets - Copy.pdf
 
CMC.pptx
CMC.pptxCMC.pptx
CMC.pptx
 
Gun Kaizen.pptx
Gun Kaizen.pptxGun Kaizen.pptx
Gun Kaizen.pptx
 
MAR,23.pptx
MAR,23.pptxMAR,23.pptx
MAR,23.pptx
 
Real Python 🐍👨_💻-1.pdf
Real Python 🐍👨_💻-1.pdfReal Python 🐍👨_💻-1.pdf
Real Python 🐍👨_💻-1.pdf
 
Brief Writeup on BCVMS.pdf
Brief Writeup on BCVMS.pdfBrief Writeup on BCVMS.pdf
Brief Writeup on BCVMS.pdf
 
BASICS OF VIBRATION.ppt
BASICS OF VIBRATION.pptBASICS OF VIBRATION.ppt
BASICS OF VIBRATION.ppt
 
Flame Scanner.ppt
Flame Scanner.pptFlame Scanner.ppt
Flame Scanner.ppt
 
EXCITATION SYSTEM.ppt
EXCITATION SYSTEM.pptEXCITATION SYSTEM.ppt
EXCITATION SYSTEM.ppt
 
HR.pptx
HR.pptxHR.pptx
HR.pptx
 
battery.ppt
battery.pptbattery.ppt
battery.ppt
 
December'2022 Maintenance review1.pptx
December'2022 Maintenance review1.pptxDecember'2022 Maintenance review1.pptx
December'2022 Maintenance review1.pptx
 
Case Studies on Vibrations.ppt
Case Studies on Vibrations.pptCase Studies on Vibrations.ppt
Case Studies on Vibrations.ppt
 
Assignment business comm
Assignment business commAssignment business comm
Assignment business comm
 
Assignment accounts
Assignment  accountsAssignment  accounts
Assignment accounts
 
Assignment hrm
Assignment hrmAssignment hrm
Assignment hrm
 
Plant operation manual
Plant operation manualPlant operation manual
Plant operation manual
 
Hplpbp
HplpbpHplpbp
Hplpbp
 
Cable fault-finding-guide
Cable fault-finding-guideCable fault-finding-guide
Cable fault-finding-guide
 

Recently uploaded

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 

Recently uploaded (20)

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 

Mvar management

  • 1. Reactive Power Management - Case study -- Nandan Pathak (AE)
  • 2. ICT -1 ICT -2 G-3 G-4 G-5 200 MW 160 MVAR 160 MW 135 MVAR 200 MW 160 MVAR 160 MW 135 MVAR 160 MW 140 MVAR LOAD LOAD 220 kV Girwali Bus 220 kV Parli Bus
  • 3. ~ GENERATION 870 MW 730 MVAR LOAD: A ) GENERATORS: a) High MVAR drawl b) High excitation current B) ICT: a) Overloading due to MVAR b) Low voltage on 220 kV bus ( 200 kV)
  • 4. C) LOAD: 11 kV side: a) Overload tripping b) Very low voltages c) Conductor snapping d) Local load shedding 440 V side: a) Failure of transformers b) Conductor snapping
  • 5. A)High seasonal load especially agriculture during October to March B) Failure of reactive compensation
  • 6. A)Identification of areas a) Beed district b) Solapur district c) Nanded district d) Pabhani district e) Latur district
  • 7. A)Identification of radial feeders 220 kV Girwali Bus 220 kV Nanded 160 MW 100 MVAR 220 kV Parbhani 100 MW 80 MVAR 132 kV Parli Bus 132kV Beed 80 MW 60 MVAR ~ ~ 132 kV Latur -1 90 MW 75 MVAR 132 kV Latur -2 60 MW 45 MVAR 132 kV Girwali Bus On similar lines loaded 11 & 33 feeders were identified.
  • 8. I) Reactive power compensation available : i. Substation ----- 164 MVAR ii. Switched capacitors on 11kV – 240 MVAR (0.6 X405) II) Focus Area – 11 kV , 0.6 MVAR capacitors a. Repairs in a central laboratory b. On site replacement, checking, modification, training
  • 9. Modifications adopted for optimum compensation  1. Cell rating 0.66 Mvar at 12 kV  2. De-rating at Low Voltage2. De-rating at Low Voltage  3.3. ModificationModification  A. Fixed capacitorsA. Fixed capacitors  B. Addition to basic schemeB. Addition to basic scheme
  • 10.
  • 11.
  • 12.  4. On site demonstrations  5. Team visit – Nasik , Pune (R ), Kolhapur, Sangli,Parbhani
  • 13.  1. Reduction in overload tripping of 11 kV & 33 kV feeders.  2. Reduction in blowing of HG fuses at 33/11 kV transformers.  3. Reduction in conductor snapping.  4. Improvement in voltage profiles  LTLT 105 Volts to 190 volts105 Volts to 190 volts  11kV11kV 7.6 kV to 9.8 kV7.6 kV to 9.8 kV
  • 14. ICT -1 ICT -2 G-3 G-4 G-5 250 MW (200) 100 MVAR(160) 200 MW(160) 60 MVAR(135)250 MW(200) 100MVAR(160 ) 200 MW 60 MVAR 195 MW(150) 80 MVAR(140) LOAD LOAD 220 kV Girwali Bus 220 kV Parli Bus
  • 15. ~ GENERATION 1095 MW (870) 400 MVAR (730) LOAD: Voltage changes: 220 kV 215 kV (200 kV) 132 kV 125 kV (106 kV) 33 kV 31 kV (27 kV)
  • 16. Radial load changes 132 kV Parli Bus 132kV Beed 95 MW 30 MVAR (80 MW 60 MVAR) ~ ~ 132 kV Latur –1 105 MW 40 MVAR (90 MW 75 MVAR) 132 kV Latur –2 70 MW 30 MVAR (60 MW 45 MVAR) 132 kV Girwali Bus
  • 17. MONTH KWH 1998 KWH 1999 KWH 2000 KWH 2001 January 791500 1101100 1014800 401700 February 545000 938100 699100 239400 March 667900 819800 663300* 262200 April 539400 790900 87400* 183400 May 512000 473200 -* 275400 June 164400* 459800 167700* 43800** July 313900 1170300♣ 442100   August 310400 948000♣ 490900   September 330600 630400 342700   October 500300 706100 350100   November 530400 854700 626000   December 307300* 1104100 542000   •---Load shifted to another feeder ♣--- Load of other feeder taken on this feeder •** --- kWh meter stopped due to leading PF Note: 0.6 MVAR capacitor bank recommissioned at village Pandharee on Dt.28.11.2000 0.6 MVAR capacitor bank added at same location on Dt.4.12.2000   New 0.6 MVAR capacitor bank commissioned at Pokharni Phata on Dt.8.12.2000 KWH recorded on 11kV Matkuli feeder from 132 / 11 kV T/F at 132 kV Ashti substation
  • 19. Month Forecasted Energy sent out (kWH) Actual Energy sent out (kWH) Savings (kWH) Remark Dec 2000 689997 542000 147997 21.45 % Jan 2001 624172 401700 222472 35.60 % Feb 2001 520905 239400 281505 54.00 % Mar 2001 562029 265200 296829 52.00 % Apr 2001 511766 183400 328366 64.10 % May 2001 451451 275400 176051 39.00 % Total 3360320 1907100 1453220 43.24 % Energy savings on 11 kV Matkuli feeder
  • 20. 1.System requires high order reactive compensation. 2.Use of fixed value non switched/seasonal manual switched capacitors is economical. 3. Complementary switching for optimum compensation. 4. Dedicated setup for overall line loss reduction.