2گزارش ریاست عملیاتی (2)
1. Brief Reports of Operational
Department
Eng. Shikib Ahmad (Nessar)
DABS/Chief of Operation
Date
DA AFGHANISTAN BRESHNA SHERKAT
www.dabs.af 1
2. DA AFGHANISTAN BRESHNA SHERKAT
2
Contents:
Generation
Transmission
Utilization and Maintenance
Projects underway
3. DA AFGHANISTAN BRESHNA SHERKAT
3
.
• Hydro Power Generation
• Thermal Power Generation
• Importing Power
4. DA AFGHANISTAN BRESHNA SHERKAT
4
1388 & 1389 Actual generation, import and plan 1390 in MWH
Generation and Importing
Plan for 1390
MWH %
Hydro Generation 827,525 27.56%
Thermal Generation 38,950 1.30%
Diesel Generator
Generation
60,998 2.03%
Importing 2,075,353 69.11%
Total 3,002,825
MWH
2,332,934
MWH
2,737,407
MWH
3,002,825
17%
10%
5. Generation and Importing Energy
Power for Kabul City84361
81361
85305
93842
95514
90332
117511
100588.
86732
115923
119168.
113310
0
20000
40000
60000
80000
100000
120000
140000
Comparative Graphs of Kabul City
Power Consumption for two
Quarters 1389-1390
1389
1390
5
6. Comparative Graph of Power Generation and Importing for two
Quarters of the year 1389 & 1390
231929
176727
205692
207949
201518
178058
243312
235390
235390
274284
306189
251905
0
50000
100000
150000
200000
250000
300000
350000
Comparative Graph of the Total
Power Generation and Importing
1389
1390
6
Generation
and
Importing
1389
231929
176727
205692
207949
201518
178058
1390
243312
235390
235390
274284
306189
251905
7. Transmission and Distribution
Successful activation of 220 KV of Tajikistan
to Pulkhomri Substations and Nayebabad and
Mazar-e-Sharif Power Supply for 48
hours, and then provision of power supply of
Pulkhomri and Aybak from Tajikistan
Importing Power
7
8. Transmission and Distribution
• Extension of overhead cables of 110KW from
Nayebabad substation to Kholm of 30 km length
• Extension of overhead cables of 20 km from
Kholm Substation to Kholm City of 5km length
• Exchange of the remaining overhead cables
between Aqina, Andkhoi and Faryab provinces
• Connection and activation of Kapisa 20 KV cable
• Extension of overhead cable of 20KV from Sang
Nawishta to Velayati of 6 km length
8
9. Maintenance and Utilization
Repair of Number 1 Turbine of Surbi Hydro Power Station
Activation of Mahipur Hydro Power Station along with
Successful Implementation of Correctional and Repairing
Plan drafted already
Sustainable maintenance of power stations (Hydro and
Thermal Power)
Refinement of the remaining failures of SCADA system with
assistance of OSKAM company in Kabul Substations
Transmission and Installation of 30 pole distribution
transformers with different capacities
9
10. Maintenance and Utilization
Transmission and Installation of two diesel
generators for Khost and Badakhshan provinces
with different capacities
Test and control of protective relays of Nayebabad
and Sur-e-pul
Maintenance of overhead cable works of Kunduz
220 KV
Solution of technical problems and maintenance of
diesel generators for reliable power supply
10
11. Planned Projects
• Financial support and application of 20 KV double circuit from
Chimtala Substation to Junction 9th of Kabul City
• Financial support and application of double circuit from
Chimtala Substation to Dasht-e-Barchi Kabul City
• Financial support and application of Arghandy 1st and 2nd
projects with installation of 34 transformer poles
• Financial support and application of 20 KV extension cables
from east substation to Dasabz district
11
12. Planned Projects
• Financial support and project application of 20 KV from
Chimtala Substation to Mirbachakot district
• Survey and design of distributing network of Samangan to 3
Megawatt capacity
• Survey and design of distributing network of Laghman
province to 2 megawatt capacity
• Survey and design of distributing network of Baghlan province
to 1 megawatt capacity
• Preparation of documents and put up at auction of one
junction, survey and design of overhead cables 20 KV double
circuit at the length of 15 KM in Herat city
12
13. The Projects underway
• Preparation of documents and put up at auction of
110/220 KW
• 80x2 MV ampere in the proximity of Nooruljahad
substation
• Preparation of documents and put up at auction of
220 KV transmission cable Turkministan in Boghracha
dam in Herat province
• Financial support and application of distributing
network of 0,2 and 0,4 KV of Panjshir province
• Survey and design of distributing network of Gazni
province for 1,5 MV
13
14. Projects underway
• Financial support and application of distributing
network of 0.2, 0.4 KV of Ningahar province
• Financial support and application of distributing
network of 0.2, 0.4 KV of Paktika province
• Financial support and application of distributing
network of 20, 0.4 KV of Logar province
14
15. Projects underway
• Financial support and application of extended
cable of 20 KV from Botkhak substation to
Arzan Qimat Kabul
• Survey and design of distributing network of
Ningahar province with 5 MV capacity
• The total projects funded by DABS will
approximately reach to USD 14 Million
• The total projects of PMO reaches to USD 303
million
15
16. DA AFGHANISTAN BRESHNA SHERKAT
16
2009 & 2010 actual energy import and plan 2011 in MWH
542,288
316,949
314,715
59,746
843,102
381,514 362,090
82,014
1,102,800
449,280 420,650
102,623
I.R. Iran Republic of Turkmenistan Republic of TajikistanRepublic of Uzbekistan
17. DA AFGHANISTAN BRESHNA SHERKAT
17
Timeline for Importing Energy through 220 KV to MW per hour
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
2010
- - -
50,000 60,200 60,200 60,200 111,600 108,000 50,000
- -
500,200
2011
- - -
50,000 92,500 92,500 92,500 111,600 108,000 50,000
- -
597,100
2012
- - -
50,000 104,000 104,000 104,000 111,600 108,000 50,000
- -
631,600
2013
- - -
50,000 111,600 108,000 111,600 111,600 108,000 50,000
- -
650,800
2014
- - -
50,000 111,600 108,000 111,600 111,600 108,000 50,000
- -
650,800
- - -
250,000 479,900 472,700 479,900 558,000 540,000 250,000
- -
3,030,500
18. DA AFGHANISTAN BRESHNA SHERKAT
18
500,200
597,100
631,600
650,800 650,800
-
100,000
200,000
300,000
400,000
500,000
600,000
700,000
2010 2011 2012 2013 2014
Attract price in MV per hour
$18
$21
$22
$23 $23
$-
$5
$10
$15
$20
$25
2010 2011 2012 2013 2014Millions
Price in USD
Timeline for Importing Energy through 220 KV to MW per hour
20. DA AFGHANISTAN BRESHNA SHERKAT
20
DABS – National Load Control Center (NLCC)
DABS National Load Control Center (NLCC) built at
Tarakhil power plant,
Equipped with SCADA system (Supervisory Control
And Data Acquisition).
SCADA Project commissioned on 24 August 2011.
SCADA provides DABS with a vital tool for
operations, energy dispatch and instantaneous
data.
The data from the SCADA system will enable:
- accurate energy balances
- loss quantification.
- determine network
- load Flow
21. DA AFGHANISTAN BRESHNA SHERKAT
21
NEPS Reactive Power Project
• Purpose: to improve the quality of power delivered by the NEPS system
• Project is nearing completion:
− one of three 25MVAR shunt reactors at Naibabad Switching Station has been
energized;
− work continues on the installation of 2 x 25MVAR capacitor banks at Pule
Khomri, Baghlan
− The capacitor banks at Chimtala and North sub-stations (120MVAR and 20MVAR
respectively) were energized in early July 2011