NATIONAL TRANSMISSION &
DESPATCH COMPANY
MUMMAD DAUD
GENERAL MANAGER PLANNING
NTDC
NTDC’s PRESENT SYSTEM, FUTURE PLANS,
BOTTLENECKS & KPIs
PRESENTATION BY
SEQUENCE OF PRSENTATION
1. General- WAPDA/PEPCO- Structure & Roles
2. NTDC system capacity
3. Future challenges & Target
4. NTDC expansion plan
5. Bottle necks
6. Key performance indicators
3
General- WAPDA/PEPCO- Structure
& Roles
4
Pakistan
Water and Power Development Authority (WAPDA)
WAPDA was formed in 1958. The major responsibilities of
WAPDA were;
– Meet electricity demand of the country (except area of Karachi) by
installing new power plants, transmission lines and distribution
system.
– Develop hydro storage project ( dams) for meeting irrigation and
demand of the country and install hydro plants at dams locations.
WAPDA consisted of two segments :
Power Wing: For meeting electricity demand and responsible for
generation, transmission and distribution.
Water Wing : For developing hydro projects for irrigation
requirements.
5
6
PAKISTAN POWER SECTOR: BACKGROUND
1. The GoP approved Pakistan Power Sector Strategic Plan for
restructuring and reform in 1992, according to which, the power wing of
WAPDA was structured into four (4) Generation Companies (GENCOs),
one (1) National Transmission and Dispatch Company (NTDC) and nine
(9) Distribution Companies (DISCOs).
2. PEPCO was established in 1998 as an independent entity with mandate
to restructure Pakistan Power Sector, corporatise & commercialize the
restructured entities, and to bring about reforms thru introduction of
competition, enhancement of efficiencies and best financial and prudent
utility practices.
3. PEPCO initiated the restructuring and reform process in 1998 with
limited initial success. The reform process was considerably slowed
down beyond 2001 when PEPCO was reduced to a Division in WAPDA.
4. The GoP reactivated the mandate of PEPCO in October 2007 to bridge
the increasing demand supply gap and to reduce the resulting load
shedding in the country.
6
Chairman WAPDAChairman WAPDA MD PEPCOMD PEPCO
PEPCO Management
Team
PEPCO Management
Team
WATER
WING
WATER
WING
FINANCE
WING
FINANCE
WING
POWER
WING
POWER
WING
COMMON
SERVICES
COMMON
SERVICES
RESIDUAL WAPDA
WINGS PART
TRANSITION TO
CORPORATE
ENTITIES
WATERWATER
HYDEL
FINANCE
HYDEL
FINANCE
HYDEL
POWER
HYDEL
POWER
SERVICESSERVICES
RESTRUCTURED POWER
WING
RESTRUCTURED POWER
WING
GENCOsGENCOs NTDCNTDC DISCOsDISCOs
(4) (1) (9)
• HOSPITALS
• ACADEMY
• ETC
AUTONOMOUS COMPANIES WITH
INDEPENDENT COMMERCIAL
OPERATIONS THROUGH BOD
MEMBERS: Hydel power,
Finance, Water
MEMBERS: Hydel power,
Finance, Water
GOP/MW&PGOP/MW&P Chairman PEPCOChairman PEPCO
NEW FACE OF PAKISTAN’S POWER SECTORNEW FACE OF PAKISTAN’S POWER SECTOR
7
National Transmission and Dispatch Company Ltd.
National Transmission & Despatch Company (NTDC)
Limited was incorporated on 6th November, 1998 and
commenced commercial operation on 24th December,
1998. It was organized to take over all the properties,
rights and assets, obligations and liabilities of 220 KV and
500KV Grid Stations and Transmission Lines/Network
owned by Pakistan Water and Power Development
Authority (WAPDA). .
8
NTDC Structure
NTDC segments.
1. Transmission Network Operator (TNO)
2. System Operator (SO)
3. Central Power Purchasing Agency (CPPA)
4. Contract Registrar and Power Exchange
Administrator (CRPEA)
9
NTDC system capacities
10
Length of Transmission Lines
Year 500kV (circuit kM) 220kV (circuit kM)
1980 315 2101
1985 1239 2422
1990 1863 2922
1995 3315 3848
2000 4094 5498
2005 4344 6993
2010 5078 7366
11
Growth in Length of Transmission Lines
(NTDC)
12
No MVA No
1980 0 0 5
1985 2 1350 10
1990 6 4974 14
1995 7 6774 18
2000 9 8274 24
2005 9 8274 26
2010 12 14850 26*
No. & Capacity of Substations (NTDC)
*1 No. 220 KV gird station was added & 1No.
220 KV Grid station was converted to 500 KV 13
500- KV Substations 220- KV Substations
Growth of Transmission System capacity –MVA
(NTDC)
14
Year T&T Losses (%) Remarks
2005 7.63 Includes losses of 132 kV Sys
2006 7.26 Includes losses of 132 kV Sys
2007 3.80 500 & 220 kV only
2008 3.48 500 & 220 kV only
2009 3.58 500 & 220 kV only
2010 3.12 500 & 220 kV only
15
NTDC T&T LOSSES
16
Future challenges & Targets
17
Future Required Generation Capacity
Year
Peak Demand
(MW)
Gen Capacity
Required (MW)
Gen Capacity
Planned (MW)
2010 20101 25126 21388
2011 21705 27131 22697
2012 23441 29301 23788
2013 25306 31633 26279
2014 27438 34298 29405
2015 29463 36829 33630
2016 31672 39950 42530
2017 33154 41443 45338
2018 35568 44460 50034
2019 38557 48196 53284
2020 41783 52229 57470
18
PEPCO System Historical Data / Forecast
Historical PMS
Peak Peak Difference
Years ( MW ) (MW) (%)
1999-00 9289 9311 0.24
2000-01 9718 9736 0.18
2001-02 10922 10243 -6.21
2002-03 10484 10799 3.00
2003-04 11078 11398 2.80
2004-05 12035 12087 0.43
2005-06 13212 12916 -2.20
2006-07 15138 15213 0.50
2007-08 16838 16480 -2.10
2008-09 17252 17867 3.50
2009-10 17847 19451 8.90
19
EXISTING GENERATING CAPACITY (Oct, 2010)
* Hydro availability based on last 5 years average
** Excludes 10% Forced Outages for GENCOs & 6.0% for IPPs & Rental
Type of Generation
Nameplate
/Installed
Capacity
(MW)
Derated/
Dependable
Capacity
(MW)
Availability (MW)
Summer Winter
WAPDA Hydro 6444 6444 6250 2300*
GENCOs 4829 3580 2780 3222**
IPPs (incl Nuclear) 7911 7695 5750 6900**
Rental 62 60 60 60**
Total 19246 17779 14840 12482
20
21
22
FUTURE GENERATION PROJECTS SYSTEM
(Up to Year 2020)
23
NTDC Expansion plan
NTDC ONGOING DEVELOPMENT PROJECT
SR.
NO.
NAME OF SUBSTATIONS
TRANSFORMER
CAPACITY (MVA)
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
1
Ext. at 500 kV Sheikh
Muhammadi
1x450 - Dec, 2010
2
Ext. at 500 kV
Tarbela.
1x237 - Dec, 2010
3 Ext. at 220 kV Bannu
1x160 -
June, 2011
4 Augmentation of 220
kV at N.K.L.P Lahore
3x250 - T2 & T3
Commissioned
T1: Dec. 2011
5 Upgradation of
existing 132 kV to
new 220 kV GIS
Wapda Town Lahore.
3x160 220 kV Lahore - K.L.P D/C
In/Out at Wapda Town. (10+10
km)
G/station
commissioned
T/Line by Mar.
2011
6 New 220 kV GIS
Bandala
2x160 220 kV Gatti - K.S.K D/C In/Out
at Bandala. (5+5 km) Dec, 2011
7 Installation of SVCs
at 220 kV N.K.L.P.
Lahore.
SVCs Static Var Compensators of
appropriate capacity. Dec, 2011
SR.NO.
NAME OF
SUBSTATIONS
TRANSFORMER
CAPACITY (MVA)
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
8 Looping In/Out of
220 kV G/Barotha-
S/Bagh T/L at
Mardan -
Looping in & out of one circuit
of Ghazi Barotha – Shahi Bagh
at Mardan (30 km)
Mar, 2011
9 Extension/Augmenta
tion at existing
substations:
- Dec, 2011
500 kV Dadu 1x450
1x160
220 kV Burhan 1x160
220 kV Mardan 1x250
500 kV Sheikh
Muhammadi 1x160
500 kV New Rewat 1x250
220 kV Shikarpur
1x160 Commissioned
10 220 kV Okara
3x250
220 kV Yousafwala - Sarfaraz
Nagar D/C In/Out at Okara. (5 +
5km)
Dec, 2011
11 220 kV Toba Tek
Singh/Gojra
3x250 220 kV Faisalabad-Multan D/C
In&Out at T.T.Singh/Gojra.
NTDC ONGOING DEVELOPMENT
PROJECTS
SR.
NO.
NAME OF NEW
SUBSTATIONS
TRANSFORMER
CAPACITY
(MVA)
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
12 Installation of
SVC at Quetta
SVC Static Var Compensators of
appropriate capacity Jun, 2012
13 Ext. at Ghazi
Brotha for
addition of 600
MVA 500/220 kV
T/F.
1x600 -
Jun, 2011
14 220 kV Loralai 2x250 220 kV D.G Khan – Loralai (250 km) Dec, 2012
15 Augmentation of
220 kV Ravi at
Lahore.
3x250
March, 2011
16 500kV D.G Khan
Substation.
2x600
2x250
500kV Guddu-Multan 2nd
cct In/Out
at D.G. Khan substation(20+20) km Dec, 2012
NTDC ONGOING DEVELOPMENT PROJECTS
SR.
NO.
NAME OF NEW
SUBSTATIONS
TRANSFORMER
CAPACITY
(MVA)
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
17 220 kV Rohri
New for
interconnection
of IPPs at Engro
Energy PP and
Mari (Dharki)
CCPP
2x250 220 kV D/C T/L Dharki CCPP–
Rohri New (115 km)
Dec, 2011
132 kV D/C T/L for In/Out of
Rohri-Khairpur/Gambat D/C T/L
at Rohri New (1+1 km)
220kV D/C Rohri New-Shikarpur
T/L (50 km)
220 kV D/C T/L for In/Out of
Dharki -Rohri New at Engro
CCPP (5+5 km)
132 kV Rohri New-Gambat D/C
T/L (53 km)
18 220 kV
Gridstation at
Khuzdar,
2x160
220kV D/C Dadu – Khuzdar
Transmission Line (300 km) Dec, 2011
19 220 kV Grid
Station at Ghazi
Road, Lahore
3x160 220 kV D/C T/L for In&Out of
NKLP – Sarfraz Nagar at Ghazi
Road. (30 km)
Dec, 2012
220 kV D/C T/L for In&Out of
Ravi– KSK at Ghazi Rd. (30 km)
NTDC ONGOING DEVELOPMENT PROJECTS
SR.
NO.
NAME OF NEW
SUBSTATIONS
T/F
CAPACITY
(MVA)
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
20 220 kV Grid Station at
Kassowal along with
associated 220kV D/C
T/Lines.
2x160 220 kV D/C Transmission Line for
In&Out of Vehari – Yousafwala at
Kassowal. (45+45 km) Jan, 2012
21 220 kV GIS substation
at Gwadar
2x160 220 kV D/C T/L from Pak-Iran
border to Gwadar (100 km) Jun, 2012
22 500 kV R.Y.Khan 2x600
500 kV Guddu - Multan 3rd
Circuit In/Out at R.Y.K (30+30 km) Jun. 2012
23
220 kV GIS Shalamar
(Mehmood Buti)
3x250
220 kV Ravi-KSK D/C In/Out at
Shalamar (9km long overhead
T/L) & (3+3km) cable
Jun.2012
NTDC ONGOING DEVELOPMENT PROJECTS
S.#
Name of
Project
Transfor-
mer
Capacity
(MVA)
ASSOCIATED
TRANSMISSION
LINES
Estimated
Cost
(Rs. in
Million)
Eqt. US$
in Million
Approval
by
ECNEC
Financing
Expected
commissi-
oning
1
220 kV
Gujrat
3x250
220 kV Mangla-
Ghakkar D/C In/Out at
Gujrat (2+2 km)
2805 33 22.10.2007 JICA 2011-12
2
220 kV
Chishtian
2x250
220 kV Vehari -
Chishtian D/C T/Line.
( 65 km)
3740 44 22.10.2007 JICA
2011-12
3 500 kV New
Lahore
2x750 Two 500 kV S/C
T/Lines for In/out of
500 kV Sahiwal –
Lahore S/C at Lahore
New (15+15 km)
12665 149 PC-I
cleared by
CDWP on
18.03.2010
JICA 2012-13
Two 500 kV S/C
T/Lines for In/out of
500 kV Lahore –
Gujranwala S/C at
Lahore New (50+50
km)
220 kV D/C T/Line for In/out
of 220 kV NKLP-Ghazi
Road at Lahore New. (50
km)
220 kV D/C T/Line for In/out
of 220 kV NKLP-Wapda
Town at Lahore New.
(54km)
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
Name of
Project
Transfor-
mer
Capacity
(MVA)
ASSOCIATED
TRANSMISSION
LINES
Estimated
Cost
(Rs. in
Million)
Eqt. US$
in
Million
Approval
by ECNEC
Financing
Expected
Year of
commissi-
oning
4-
500 kV
Shikarpur
2x600
Two 500 kV S/C
T/Lines for In/out of
500 kV Dadu-Guddu
circuit No:1 at
Shikarpur (20+20
km)
8160 96
Pc-I
Cleared
by CDWP
on
18.03.2010
JICA
2012-13
Two 500 kV S/C
T/Lines for In/out of
500 kV Dadu-Guddu
circuit No:2 at
Shikarpur. (22+22
km)
220 kV D/C for
In/Out of 500/220 kV
Guddu – Sibbi S/C
at Shikarpur (50 km)
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
Name of
Project
Transfor-
mer
Capacity
(MVA)
ASSOCIATED
TRANSMISSION
LINES
Estimated
Cost
(Rs. in
Million)
Eqt. US$
in
Million
Approval
by ECNEC
Financing
Expected
Year of
commissi-
oning
5-
2nd
source of
supply to
Islamabad
University
-
220 kV D/C T/L
for In/out of
Manshera-
Islamabad T/L
(40 km)
1105 13
PC-I under
preparatio
n
ADB Tr-IV 2012-13
6-
2nd
Source of
supply to
Hala Road
Grid Station
-
220 kV D/C T/L
from T.M Khan
Road to Hala
Road (30 km)
850 10
PC-I under
preparatio
n
ADB Tr-iV 2012-13
7-
220 kV
Nowshera
2x160 - 850 10 06.02.2008 ADB Tr-iV 2012-13
8-
220 kV
Chakdara
2X250
220 kV Chakdara
– Mardan (85
km)
3230 38
PC-I under
preparatio
n
ADB Tr-iIV 2013-14
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
Name of
Project
Transfor-
mer
Capacity
(MVA)
ASSOCIATED
TRANSMISSI
ON LINES
Estimated
Cost
(Rs. in
Million)
Eqt. US$
in
Million
Approval
by ECNEC
Financing
Expected
Year of
commissi-
oning
9-
Augmentation
of 500 & 220 kV
existing
substations
-
3825 45
PC-I
submitted
to GoP in
Aug,2010
ADB Tr-I
(Ext-II)
2011-12
500 kV Rewat 1x750 -
500 kV Sh.
Muhammadi
4x250 -
220 kV Mardan 2x250 -
220 kV Burhan 4x250 -
220 kV Bund
Rd
4x250 -
220 kV
Bahawalpur
2x250 -
220 kV Quetta
Industrial
2X250 -
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
`
Name of Project
Transfor
-mer
Capacity
(MVA)
ASSOCIATED
TRANSMISSION
LINES
Estimate
d Cost
(Rs.
in
Million)
Eqt.
US$ in
Million
Approval
by ECNEC
Financing
Expected
Year of
commissi
-oning
10-
220 kV Mirpur
Khas
2x160
220 kV D/C T/L from
Hala Rd. to .M.Khan
Rd. (10 km)
In/Out of one
circuit of above
220 kV proposed
T/L at Mirpur Khas
New (70 km).
2975 35
PC-I under
preparation
ADB Tr-IV 2013-14
11- 220 kV Taxila. 2x250
In/Out of 220 kV
Burhan - ISPR S/C
at Taxila. (6 km)
2295 27
PC-I under
preparation
ADB Tr-IV 2013-14
12- 220 kV Manshera 2x160
In/out of 220 kV Alai
Khawar-Sangjani
T/L at Manshera
(0.5+.0.5 km)
1105 13
PC-I under
preparation
Iranian
Loan
2013-14
13-
220 kV D.M
Jamali
1x160
1x100
in/out of 220 kV
Uch-Guddu S/C at
D.M. Jamali (5 km)
850 10
PC-I
submitted
to GoP
PM’s Fund 2013-14
14-
Interconnection
of 1200 MW AES
Imported coal
based Power
Plant near
Karachi (Part-I)
-
500 kV Jamshoro--
R.Y.K (535 km)
500 kV Moro-Dadu
(55 km)
25330 298
PC-I cleared
by CDWP
on
18.03.2010
ADB Tr-III 2015-16
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST*
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
1- 220 kV Chakwal
2x160
In/out of 220 kV Mangla-
Rewat S/C at Chakwal
(50 km)
2890 34 2012-13
2- 220 kV GIS Jhang
Rd. Faisalabad 2x250
220 kV Samundri Rd. –
Jhang Rd. D/C T/L (40 km) 2975 35 2012-13
3- 220 kV Chiniot.
Industrial 2x250
220 kV Gatti - Ludewala
D/C In/Out at Chiniot
Industrial. (2+2 km)
2380 28 2012-13
4- 220 kV Shadman
2x250
220 kV D/C cable from
Shadman to Bund Road
(30 km)
4250 50 2012-13
5- 220 kV D.I Khan 2x250 220 kV D/C T/Line for
In/out of 220 kV Chashma
Nuclear – Ludewala S/C at
D.I Khan (100 km)
3825 45
2012-13
7- 220 kV Gharo
2x250
220 kV Gharo – T.M Khan
Road ((130) 4590 54 2012-13
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRD
YEAR OF
COMMISSIO-
NING
8- 220 kV Jhimpir
2x250
In/Out of 220 kV Gharo – T.M
Khan Road at Jhimpir (65
km)
3230 38 2012-13
9- 220 kV
Mastung 2x250
220 KV Mastung Sibbi (120
km) 4080 48 2013-14
10- 220 kV Jamrud`
2x250
220 kV Jamrud – Sh.
Muhammadi (10 km) 1445 17 2013-14
11- 500 kV
Faisalabad New 2x750
In/out of 500 kV Muzaffargarh
– Gatti 1st
circuit at at
Faisalabad new (1+1 km) 6630 78 2013-14
2x250
220 kV Faisalabad New – T.T
Singh D/C T/Line (70 km)
12- 220 kV M-3
Industrial
Estate
Faisalabad 2x250
220 kV M3 Industrial Estate –
Faisalabad New (70 km)
In/Out of 220 kV Faisalabad
New - M3 Industrial Estate at
220 kV Chinot Industrial New
(30 km)
3570 42 2013-14
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
13- 500 kV
Peshawar New
2x750
In/out of Tarbela – Sh.
Muhammadi at Peshawar
New (2+2 km)
In/Out of 220 kV Sh.
Muhammadi-Shahibagh at
Peshawar New (5 km)
5440 64 2014-15
14- 220 kV Kohat
2x250
220 kV Kohat – Peshawar
New (50 km)
220 kV Kohat – Bannu
(150 km)
5950 70 2014-15
15- 220 kV
Islamabad I-10 2x250
In/Out of 220 kV Rewat –
Islamabad University D/C at
Islamabad I-10 (30+30 km)
2635 31 2014-15
16- Ext. at 220 kV
Gujrat 1x250
-
425 5 2014-15
17- 220 kV
Kamalabad 2x250
In/out of Rewat – Islamabad
Peshawar Rd. at Kamalabad
(5+5 km)
1445 17 2015-16
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
18- Ext. at 500 kV
Gujranwala 1x600
-
1700 20 2015-16
19- Ext. at 500 kV
Lahore New 1x750
-
2040 24 2015-16
20- 220 kV Kamra
2x250
In/out of 220 kV Tarbela –
Taxila at Kamra (5 km) 1275 15 2015-16
21- 220 kV Iqbal
Town 2x250
In/Out of 220 kV Lahore –
Wapda Town D/C at Iqbal
Town (20+20 km)
2125 25 2015-16
22- 220 kV
Gujranwala
New
2x250
In/Out of 220 kV Mangala –
K.S.K at Gujranwala New
(20 km)
220 kV Nokhar - Gujranwala
New (50 kM)
2890 34 2015-16
23- 220 kV Pindi
Bhattian 2x250
220 kV Pindi Bhattian Ind. –
Gujranwala (50 km) 2380 28 2015-16
24- 220 kV Head
Faqirian 2x250
220 kV Head Faqirian –
Ludewala (60 km) 2380
28
2015-16
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
25- 220 kV
Joharabad 2x250
In/out of 220 kV D/C
Ludewala –Chashma at
Jauharabad (5+6 km)
1445 17 2015-16
26- 220 kV Alizai
2x250
220 kV Kohat – Ali zai D/C
(110 km) 3825 45 2015-16
27- 2nd
Source of
supply to 220
kV Chakwal
substation
-
In/out of 220 kV Mangla
-Rewat 2nd
circuit at Chakwal
(60 km) 1530 18 2015-16
28- 2nd
Source of
supply to 220
kV Bhawalpur
substation
-
220 kV R.Y.K – Bahalawlpur
D/C T/L (150 km)
3825 45 2015-16
29- 220 kV Arif
Wala 2x250
In/Out of 220 kV Yousafwala
– Kassowal D/C at Arifwala
(5+5 km)
1445 17 2015-16
Total: 82620 972
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
1-
Power Dispersal
from 747 MW
CCPP at Guddu
-
500 kV Guddu New PP –
M. Garh (256 km)
In/Out of Guddu – Multan
at New Guddu (10+10 km)
7735 91 2012-13
2-
Dispersal of
Power from Uch-2
-
220 kV Uch-II – Sibbi D/C
(125 km)
2975 35 2012-13
3-
UAE Combined
Cycle power plant
at GTPS
Faisalabad
1x160
In/out of existing 220 kV
T/lines at Proposed power
plant
1700 20 2012-13
4-
Interconnection of
1200 MW AES
Imported coal
based power near
Karachi (Part-II)
500 kV
switch
ing
statio
n at
Matiari
500 kV S/C T/Line from
AES Power Plant to
Matiari switching station
(200 km)
In/Out of 500 kV Hub-
Jamshoro S/C T/Line at
AES (45+45 km)
In/out of 500 kV
Jamshoro-R.Y.K at Matiari
(5+5 km)
14450
(PC-I
cleared by
CDWP on
18.3.10)
170 2015-16
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
5-
Interconnection of
1200 MW Engro &
1200 MW PEPCO’s
Thar Coal Based
Power Plants at
Thar
-
500 kV D/C T/L form Thar
coal power plants to
Matiari (275 km)
500 kV HVDC Matiari –
Lahore/ Faisalabad T/L
(1100 km)
Terminal Stations at both
ends
88400 1040 2015-16
6
Interconnection of
1200 MW Imported
coal based PPIB
and 1000 MW
Imported Coal
based PEPCO’s
power Plants at
Karachi
-
Two 500 kV circuits from
Power Plants to Matiari
(200 km each)
500 kV HVDC Matiari –
Lahore/Faisalabad T/L
(1100 km)
Extension of Terminal
Stations at both ends
85000 1000 2015-16
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
7-
Import of 1000 MW
Power from Iran
-
Two 500 kV HVAC S/C
T/Lines from Zahidan to
Quetta with series
compensation (198 km)
Switching station at
Zahidan, Quetta and
midpoint between Zahidan
& Quetta
40120 472 2015-16
8-
Import of 1000 MW
Power from
Tajikistan (CASA-
1000)
-
500 kV HVDC T/L from
Pak-Afghan Border to
Peshawar (71 km)
500 kV Converter Station
Peshawar
16065 189 2015-16
9-
Dispersal of
Power from 340
MW Chashma-III
-
220 kV Chashma New –
Bannu (125 km)
In/out of 220 kV D.I. Kahan
– Jahurabad S/C at
Chashma New (1 km)
3000 35 2016-17
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
10-
Interconnection of
2x1000 MW
Nuclear Power
Plants at Karachi
-
Three 500 kV Circuits from
Nuclear Plants to Matiari
(200 km each)
25500 300 2018-19
Total 284945 3352
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR
#.
NAME OF NEW
SUBSTATIONS
T/F CAP.
(MVA)
ASSOCIATED
TRANSMISSION
LINES
ESTIMATED
COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
1-
Dispersal of
Power from 969
MW Neelum
Jhelum Hydro
Power Project to
Rawat &
Gujranwala
-
500 kV Neelum
Jhelum – Rawat S/C
T/Line (110 km).
500 kV Neelum
Jhelum – Gujranwala
S/C T/Line (235 km)
19125 225 2015-16
2-
Dispersal of
Power from 720
MW Karot HPP
-
500 kV Karot –
Lahore New (270 km)
In/Out of 500 kV
Neelum Jhelum –
Gujranwala at Karot
(10 km)
13250 156 2015-16
3-
Power Dispersal
of 740 MW
Munda HPP
-
In/Out of 220 kV
Peshawar – Shahi
Bagh at Munda (35
km)
850 10 2016-17
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER
PLANTS
SR
#.
NAME OF NEW
SUBSTATIONS
T/F CAP.
(MVA)
ASSOCIATED
TRANSMISSION
LINES
ESTIMATED
COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
11000
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER
PLANTS
SR
#.
NAME OF NEW
SUBSTATIONS
T/F CAP.
(MVA)
ASSOCIATED
TRANSMISSION
LINES
ESTIMATED
COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIO-
NING
6-
Dispersal of
Power from 4500
MW Diamer
Basha HPP to
Lahore with
interconnection
at Dasu and
Gujar Khan
765 kV
HVAC
substations
at Gujar
Khan &
Lahore with
765/500 kV
3x500 MVA
T/Fs
500 MVAR
SVC at
Gujar Khan
Three 765 kV HVAC
T/Ls from Basha to
Gujar Khan (407 km
long each)
Two 765 kV HVAC
T/Ls from Gujar
Khan to Lahore (260
km long each)
113900 1340 2018-19
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER
PLANTS
SR
#.
NAME OF NEW
SUBSTATIONS
T/F CAP.
(MVA)
ASSOCIATED
TRANSMISSION
LINES
ESTIMATED
COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIREDD
YEAR OF
COMMISSIO-
NING
7-
Dispersal of
Power from 5400
-7000 MW Bunji
Hydro Power
Project to
Lahore with
interconnection
at Gujar Khan
765 kV
HVAC
substatin
extn at:
Basha,
Dasu,
Thakot,
Gujar khan
Lahore
765 kV new
substation
at Bunji. 
2 x 765 kV HVAC 110
km long Bunji -
Basha S/C T/Lines
1x765 kV HVAC 759
km long Bunji –
Dasu-Thakot-Gujar
Khan-Lahore S/C
T/Lines
126225 1485  2019-20
Total 296170 3484
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER
PLANTS
PC-I for dispersal of Power from Neelum Jhelum HPP has been approved by ECNEC
Studies are being carried out to ascertain the interconnection schemes for the
projects at Sr. No: 2 to 7
BOTTLE NECKS
48
Bottle Necks
• At present no major system constraints
• Intermittent over-loading of transformers at
some places being addressed by addition of
following transformation capacities up to
2014-15
– 500/220 KV 11400 MVA
– 220/132 KV 19330 MVA
49
50
• For huge future development the bottle necks
would be
1. Availability of finance
2. Responsibility of dispersal from power plants &
uncertainty of generation project.
• Capacity of
1. Planning department
2. Local Consultant
3. Local contractors
• Inconducive Law & order situation for foreign
consultants and contractors.
KEY PERFORMANCE INDICATORS
51
Reference documents
• NTDC GRID CODE (JUNE 2005)
• NEPRA PERFORMANCE STANDARDS
(TRANSMISSION) RULES (NOV. 2005)
52
KEY PERFORMANCE INDICATORS
1.System Reliability
• Transmission System incl. Tie Lines
a) System Duration of Interruption
= A/N
where
A= sum of the total outage hours recorded at all the interconnection
points (other than 132 kV line tripping) in a period
N = Number of monitoring points (Interconnection Point)
Tie lines means interconnection facility for the transfer of electric power
between the licensee and other utilities not governed by the Act.
53
KEY PERFORMANCE INDICATORS
1. System Reliability
b)System Frequency Interruption
= A/N
Where
A= sum of the total outage hours recorded at all the interconnection
points (other than 132 kV line tripping) in a period
N= Number of circuits
54
KEY PERFORMANCE INDICATORS
2. System Security
(Energy not served)
= ∑ Pi x T
Where
Pi = Power interrupted in MW in a circuit
T = Time Duration in Hours
55
KEY PERFORMANCE INDICATORS
3. Quality of Supply
A) System Voltage Variation Grid
Performance
Code Standard
-500 kV
Under Normal Conditions -5 +8% -+ 5%
Under N-1 Conditions -+10% -+ 10%
-220 kV
Under Normal Conditions -5 +8% -+ 5%
Under N-1 Conditions -+10% -+ 10%
-132 kV
Under Normal Conditions -5 +8% -+
5%
Under N-1 Conditions -+10% -+56
THANKS
57

National Transmission And Dispatch Company (NTDC)

  • 2.
    NATIONAL TRANSMISSION & DESPATCHCOMPANY MUMMAD DAUD GENERAL MANAGER PLANNING NTDC NTDC’s PRESENT SYSTEM, FUTURE PLANS, BOTTLENECKS & KPIs PRESENTATION BY
  • 3.
    SEQUENCE OF PRSENTATION 1.General- WAPDA/PEPCO- Structure & Roles 2. NTDC system capacity 3. Future challenges & Target 4. NTDC expansion plan 5. Bottle necks 6. Key performance indicators 3
  • 4.
  • 5.
    Pakistan Water and PowerDevelopment Authority (WAPDA) WAPDA was formed in 1958. The major responsibilities of WAPDA were; – Meet electricity demand of the country (except area of Karachi) by installing new power plants, transmission lines and distribution system. – Develop hydro storage project ( dams) for meeting irrigation and demand of the country and install hydro plants at dams locations. WAPDA consisted of two segments : Power Wing: For meeting electricity demand and responsible for generation, transmission and distribution. Water Wing : For developing hydro projects for irrigation requirements. 5
  • 6.
    6 PAKISTAN POWER SECTOR:BACKGROUND 1. The GoP approved Pakistan Power Sector Strategic Plan for restructuring and reform in 1992, according to which, the power wing of WAPDA was structured into four (4) Generation Companies (GENCOs), one (1) National Transmission and Dispatch Company (NTDC) and nine (9) Distribution Companies (DISCOs). 2. PEPCO was established in 1998 as an independent entity with mandate to restructure Pakistan Power Sector, corporatise & commercialize the restructured entities, and to bring about reforms thru introduction of competition, enhancement of efficiencies and best financial and prudent utility practices. 3. PEPCO initiated the restructuring and reform process in 1998 with limited initial success. The reform process was considerably slowed down beyond 2001 when PEPCO was reduced to a Division in WAPDA. 4. The GoP reactivated the mandate of PEPCO in October 2007 to bridge the increasing demand supply gap and to reduce the resulting load shedding in the country. 6
  • 7.
    Chairman WAPDAChairman WAPDAMD PEPCOMD PEPCO PEPCO Management Team PEPCO Management Team WATER WING WATER WING FINANCE WING FINANCE WING POWER WING POWER WING COMMON SERVICES COMMON SERVICES RESIDUAL WAPDA WINGS PART TRANSITION TO CORPORATE ENTITIES WATERWATER HYDEL FINANCE HYDEL FINANCE HYDEL POWER HYDEL POWER SERVICESSERVICES RESTRUCTURED POWER WING RESTRUCTURED POWER WING GENCOsGENCOs NTDCNTDC DISCOsDISCOs (4) (1) (9) • HOSPITALS • ACADEMY • ETC AUTONOMOUS COMPANIES WITH INDEPENDENT COMMERCIAL OPERATIONS THROUGH BOD MEMBERS: Hydel power, Finance, Water MEMBERS: Hydel power, Finance, Water GOP/MW&PGOP/MW&P Chairman PEPCOChairman PEPCO NEW FACE OF PAKISTAN’S POWER SECTORNEW FACE OF PAKISTAN’S POWER SECTOR 7
  • 8.
    National Transmission andDispatch Company Ltd. National Transmission & Despatch Company (NTDC) Limited was incorporated on 6th November, 1998 and commenced commercial operation on 24th December, 1998. It was organized to take over all the properties, rights and assets, obligations and liabilities of 220 KV and 500KV Grid Stations and Transmission Lines/Network owned by Pakistan Water and Power Development Authority (WAPDA). . 8
  • 9.
    NTDC Structure NTDC segments. 1.Transmission Network Operator (TNO) 2. System Operator (SO) 3. Central Power Purchasing Agency (CPPA) 4. Contract Registrar and Power Exchange Administrator (CRPEA) 9
  • 10.
  • 11.
    Length of TransmissionLines Year 500kV (circuit kM) 220kV (circuit kM) 1980 315 2101 1985 1239 2422 1990 1863 2922 1995 3315 3848 2000 4094 5498 2005 4344 6993 2010 5078 7366 11
  • 12.
    Growth in Lengthof Transmission Lines (NTDC) 12
  • 13.
    No MVA No 19800 0 5 1985 2 1350 10 1990 6 4974 14 1995 7 6774 18 2000 9 8274 24 2005 9 8274 26 2010 12 14850 26* No. & Capacity of Substations (NTDC) *1 No. 220 KV gird station was added & 1No. 220 KV Grid station was converted to 500 KV 13 500- KV Substations 220- KV Substations
  • 14.
    Growth of TransmissionSystem capacity –MVA (NTDC) 14
  • 15.
    Year T&T Losses(%) Remarks 2005 7.63 Includes losses of 132 kV Sys 2006 7.26 Includes losses of 132 kV Sys 2007 3.80 500 & 220 kV only 2008 3.48 500 & 220 kV only 2009 3.58 500 & 220 kV only 2010 3.12 500 & 220 kV only 15 NTDC T&T LOSSES
  • 16.
  • 17.
  • 18.
    Future Required GenerationCapacity Year Peak Demand (MW) Gen Capacity Required (MW) Gen Capacity Planned (MW) 2010 20101 25126 21388 2011 21705 27131 22697 2012 23441 29301 23788 2013 25306 31633 26279 2014 27438 34298 29405 2015 29463 36829 33630 2016 31672 39950 42530 2017 33154 41443 45338 2018 35568 44460 50034 2019 38557 48196 53284 2020 41783 52229 57470 18
  • 19.
    PEPCO System HistoricalData / Forecast Historical PMS Peak Peak Difference Years ( MW ) (MW) (%) 1999-00 9289 9311 0.24 2000-01 9718 9736 0.18 2001-02 10922 10243 -6.21 2002-03 10484 10799 3.00 2003-04 11078 11398 2.80 2004-05 12035 12087 0.43 2005-06 13212 12916 -2.20 2006-07 15138 15213 0.50 2007-08 16838 16480 -2.10 2008-09 17252 17867 3.50 2009-10 17847 19451 8.90 19
  • 20.
    EXISTING GENERATING CAPACITY(Oct, 2010) * Hydro availability based on last 5 years average ** Excludes 10% Forced Outages for GENCOs & 6.0% for IPPs & Rental Type of Generation Nameplate /Installed Capacity (MW) Derated/ Dependable Capacity (MW) Availability (MW) Summer Winter WAPDA Hydro 6444 6444 6250 2300* GENCOs 4829 3580 2780 3222** IPPs (incl Nuclear) 7911 7695 5750 6900** Rental 62 60 60 60** Total 19246 17779 14840 12482 20
  • 21.
  • 22.
  • 23.
    FUTURE GENERATION PROJECTSSYSTEM (Up to Year 2020) 23
  • 24.
  • 25.
    NTDC ONGOING DEVELOPMENTPROJECT SR. NO. NAME OF SUBSTATIONS TRANSFORMER CAPACITY (MVA) ASSOCIATED TRANSMISSION LINES EXPECTED COMMISSIONING 1 Ext. at 500 kV Sheikh Muhammadi 1x450 - Dec, 2010 2 Ext. at 500 kV Tarbela. 1x237 - Dec, 2010 3 Ext. at 220 kV Bannu 1x160 - June, 2011 4 Augmentation of 220 kV at N.K.L.P Lahore 3x250 - T2 & T3 Commissioned T1: Dec. 2011 5 Upgradation of existing 132 kV to new 220 kV GIS Wapda Town Lahore. 3x160 220 kV Lahore - K.L.P D/C In/Out at Wapda Town. (10+10 km) G/station commissioned T/Line by Mar. 2011 6 New 220 kV GIS Bandala 2x160 220 kV Gatti - K.S.K D/C In/Out at Bandala. (5+5 km) Dec, 2011 7 Installation of SVCs at 220 kV N.K.L.P. Lahore. SVCs Static Var Compensators of appropriate capacity. Dec, 2011
  • 26.
    SR.NO. NAME OF SUBSTATIONS TRANSFORMER CAPACITY (MVA) ASSOCIATEDTRANSMISSION LINES EXPECTED COMMISSIONING 8 Looping In/Out of 220 kV G/Barotha- S/Bagh T/L at Mardan - Looping in & out of one circuit of Ghazi Barotha – Shahi Bagh at Mardan (30 km) Mar, 2011 9 Extension/Augmenta tion at existing substations: - Dec, 2011 500 kV Dadu 1x450 1x160 220 kV Burhan 1x160 220 kV Mardan 1x250 500 kV Sheikh Muhammadi 1x160 500 kV New Rewat 1x250 220 kV Shikarpur 1x160 Commissioned 10 220 kV Okara 3x250 220 kV Yousafwala - Sarfaraz Nagar D/C In/Out at Okara. (5 + 5km) Dec, 2011 11 220 kV Toba Tek Singh/Gojra 3x250 220 kV Faisalabad-Multan D/C In&Out at T.T.Singh/Gojra. NTDC ONGOING DEVELOPMENT PROJECTS
  • 27.
    SR. NO. NAME OF NEW SUBSTATIONS TRANSFORMER CAPACITY (MVA) ASSOCIATEDTRANSMISSION LINES EXPECTED COMMISSIONING 12 Installation of SVC at Quetta SVC Static Var Compensators of appropriate capacity Jun, 2012 13 Ext. at Ghazi Brotha for addition of 600 MVA 500/220 kV T/F. 1x600 - Jun, 2011 14 220 kV Loralai 2x250 220 kV D.G Khan – Loralai (250 km) Dec, 2012 15 Augmentation of 220 kV Ravi at Lahore. 3x250 March, 2011 16 500kV D.G Khan Substation. 2x600 2x250 500kV Guddu-Multan 2nd cct In/Out at D.G. Khan substation(20+20) km Dec, 2012 NTDC ONGOING DEVELOPMENT PROJECTS
  • 28.
    SR. NO. NAME OF NEW SUBSTATIONS TRANSFORMER CAPACITY (MVA) ASSOCIATEDTRANSMISSION LINES EXPECTED COMMISSIONING 17 220 kV Rohri New for interconnection of IPPs at Engro Energy PP and Mari (Dharki) CCPP 2x250 220 kV D/C T/L Dharki CCPP– Rohri New (115 km) Dec, 2011 132 kV D/C T/L for In/Out of Rohri-Khairpur/Gambat D/C T/L at Rohri New (1+1 km) 220kV D/C Rohri New-Shikarpur T/L (50 km) 220 kV D/C T/L for In/Out of Dharki -Rohri New at Engro CCPP (5+5 km) 132 kV Rohri New-Gambat D/C T/L (53 km) 18 220 kV Gridstation at Khuzdar, 2x160 220kV D/C Dadu – Khuzdar Transmission Line (300 km) Dec, 2011 19 220 kV Grid Station at Ghazi Road, Lahore 3x160 220 kV D/C T/L for In&Out of NKLP – Sarfraz Nagar at Ghazi Road. (30 km) Dec, 2012 220 kV D/C T/L for In&Out of Ravi– KSK at Ghazi Rd. (30 km) NTDC ONGOING DEVELOPMENT PROJECTS
  • 29.
    SR. NO. NAME OF NEW SUBSTATIONS T/F CAPACITY (MVA) ASSOCIATEDTRANSMISSION LINES EXPECTED COMMISSIONING 20 220 kV Grid Station at Kassowal along with associated 220kV D/C T/Lines. 2x160 220 kV D/C Transmission Line for In&Out of Vehari – Yousafwala at Kassowal. (45+45 km) Jan, 2012 21 220 kV GIS substation at Gwadar 2x160 220 kV D/C T/L from Pak-Iran border to Gwadar (100 km) Jun, 2012 22 500 kV R.Y.Khan 2x600 500 kV Guddu - Multan 3rd Circuit In/Out at R.Y.K (30+30 km) Jun. 2012 23 220 kV GIS Shalamar (Mehmood Buti) 3x250 220 kV Ravi-KSK D/C In/Out at Shalamar (9km long overhead T/L) & (3+3km) cable Jun.2012 NTDC ONGOING DEVELOPMENT PROJECTS
  • 30.
    S.# Name of Project Transfor- mer Capacity (MVA) ASSOCIATED TRANSMISSION LINES Estimated Cost (Rs. in Million) Eqt.US$ in Million Approval by ECNEC Financing Expected commissi- oning 1 220 kV Gujrat 3x250 220 kV Mangla- Ghakkar D/C In/Out at Gujrat (2+2 km) 2805 33 22.10.2007 JICA 2011-12 2 220 kV Chishtian 2x250 220 kV Vehari - Chishtian D/C T/Line. ( 65 km) 3740 44 22.10.2007 JICA 2011-12 3 500 kV New Lahore 2x750 Two 500 kV S/C T/Lines for In/out of 500 kV Sahiwal – Lahore S/C at Lahore New (15+15 km) 12665 149 PC-I cleared by CDWP on 18.03.2010 JICA 2012-13 Two 500 kV S/C T/Lines for In/out of 500 kV Lahore – Gujranwala S/C at Lahore New (50+50 km) 220 kV D/C T/Line for In/out of 220 kV NKLP-Ghazi Road at Lahore New. (50 km) 220 kV D/C T/Line for In/out of 220 kV NKLP-Wapda Town at Lahore New. (54km) NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
  • 31.
    S.# Name of Project Transfor- mer Capacity (MVA) ASSOCIATED TRANSMISSION LINES Estimated Cost (Rs. in Million) Eqt.US$ in Million Approval by ECNEC Financing Expected Year of commissi- oning 4- 500 kV Shikarpur 2x600 Two 500 kV S/C T/Lines for In/out of 500 kV Dadu-Guddu circuit No:1 at Shikarpur (20+20 km) 8160 96 Pc-I Cleared by CDWP on 18.03.2010 JICA 2012-13 Two 500 kV S/C T/Lines for In/out of 500 kV Dadu-Guddu circuit No:2 at Shikarpur. (22+22 km) 220 kV D/C for In/Out of 500/220 kV Guddu – Sibbi S/C at Shikarpur (50 km) NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
  • 32.
    S.# Name of Project Transfor- mer Capacity (MVA) ASSOCIATED TRANSMISSION LINES Estimated Cost (Rs. in Million) Eqt.US$ in Million Approval by ECNEC Financing Expected Year of commissi- oning 5- 2nd source of supply to Islamabad University - 220 kV D/C T/L for In/out of Manshera- Islamabad T/L (40 km) 1105 13 PC-I under preparatio n ADB Tr-IV 2012-13 6- 2nd Source of supply to Hala Road Grid Station - 220 kV D/C T/L from T.M Khan Road to Hala Road (30 km) 850 10 PC-I under preparatio n ADB Tr-iV 2012-13 7- 220 kV Nowshera 2x160 - 850 10 06.02.2008 ADB Tr-iV 2012-13 8- 220 kV Chakdara 2X250 220 kV Chakdara – Mardan (85 km) 3230 38 PC-I under preparatio n ADB Tr-iIV 2013-14 NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
  • 33.
    S.# Name of Project Transfor- mer Capacity (MVA) ASSOCIATED TRANSMISSI ON LINES Estimated Cost (Rs.in Million) Eqt. US$ in Million Approval by ECNEC Financing Expected Year of commissi- oning 9- Augmentation of 500 & 220 kV existing substations - 3825 45 PC-I submitted to GoP in Aug,2010 ADB Tr-I (Ext-II) 2011-12 500 kV Rewat 1x750 - 500 kV Sh. Muhammadi 4x250 - 220 kV Mardan 2x250 - 220 kV Burhan 4x250 - 220 kV Bund Rd 4x250 - 220 kV Bahawalpur 2x250 - 220 kV Quetta Industrial 2X250 - NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
  • 34.
    S.# ` Name of Project Transfor -mer Capacity (MVA) ASSOCIATED TRANSMISSION LINES Estimate dCost (Rs. in Million) Eqt. US$ in Million Approval by ECNEC Financing Expected Year of commissi -oning 10- 220 kV Mirpur Khas 2x160 220 kV D/C T/L from Hala Rd. to .M.Khan Rd. (10 km) In/Out of one circuit of above 220 kV proposed T/L at Mirpur Khas New (70 km). 2975 35 PC-I under preparation ADB Tr-IV 2013-14 11- 220 kV Taxila. 2x250 In/Out of 220 kV Burhan - ISPR S/C at Taxila. (6 km) 2295 27 PC-I under preparation ADB Tr-IV 2013-14 12- 220 kV Manshera 2x160 In/out of 220 kV Alai Khawar-Sangjani T/L at Manshera (0.5+.0.5 km) 1105 13 PC-I under preparation Iranian Loan 2013-14 13- 220 kV D.M Jamali 1x160 1x100 in/out of 220 kV Uch-Guddu S/C at D.M. Jamali (5 km) 850 10 PC-I submitted to GoP PM’s Fund 2013-14 14- Interconnection of 1200 MW AES Imported coal based Power Plant near Karachi (Part-I) - 500 kV Jamshoro-- R.Y.K (535 km) 500 kV Moro-Dadu (55 km) 25330 298 PC-I cleared by CDWP on 18.03.2010 ADB Tr-III 2015-16 NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
  • 35.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST* (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 1- 220 kV Chakwal 2x160 In/out of 220 kV Mangla- Rewat S/C at Chakwal (50 km) 2890 34 2012-13 2- 220 kV GIS Jhang Rd. Faisalabad 2x250 220 kV Samundri Rd. – Jhang Rd. D/C T/L (40 km) 2975 35 2012-13 3- 220 kV Chiniot. Industrial 2x250 220 kV Gatti - Ludewala D/C In/Out at Chiniot Industrial. (2+2 km) 2380 28 2012-13 4- 220 kV Shadman 2x250 220 kV D/C cable from Shadman to Bund Road (30 km) 4250 50 2012-13 5- 220 kV D.I Khan 2x250 220 kV D/C T/Line for In/out of 220 kV Chashma Nuclear – Ludewala S/C at D.I Khan (100 km) 3825 45 2012-13 7- 220 kV Gharo 2x250 220 kV Gharo – T.M Khan Road ((130) 4590 54 2012-13 NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
  • 36.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRD YEAR OF COMMISSIO- NING 8- 220 kV Jhimpir 2x250 In/Out of 220 kV Gharo – T.M Khan Road at Jhimpir (65 km) 3230 38 2012-13 9- 220 kV Mastung 2x250 220 KV Mastung Sibbi (120 km) 4080 48 2013-14 10- 220 kV Jamrud` 2x250 220 kV Jamrud – Sh. Muhammadi (10 km) 1445 17 2013-14 11- 500 kV Faisalabad New 2x750 In/out of 500 kV Muzaffargarh – Gatti 1st circuit at at Faisalabad new (1+1 km) 6630 78 2013-14 2x250 220 kV Faisalabad New – T.T Singh D/C T/Line (70 km) 12- 220 kV M-3 Industrial Estate Faisalabad 2x250 220 kV M3 Industrial Estate – Faisalabad New (70 km) In/Out of 220 kV Faisalabad New - M3 Industrial Estate at 220 kV Chinot Industrial New (30 km) 3570 42 2013-14 NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
  • 37.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 13- 500 kV Peshawar New 2x750 In/out of Tarbela – Sh. Muhammadi at Peshawar New (2+2 km) In/Out of 220 kV Sh. Muhammadi-Shahibagh at Peshawar New (5 km) 5440 64 2014-15 14- 220 kV Kohat 2x250 220 kV Kohat – Peshawar New (50 km) 220 kV Kohat – Bannu (150 km) 5950 70 2014-15 15- 220 kV Islamabad I-10 2x250 In/Out of 220 kV Rewat – Islamabad University D/C at Islamabad I-10 (30+30 km) 2635 31 2014-15 16- Ext. at 220 kV Gujrat 1x250 - 425 5 2014-15 17- 220 kV Kamalabad 2x250 In/out of Rewat – Islamabad Peshawar Rd. at Kamalabad (5+5 km) 1445 17 2015-16 NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
  • 38.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 18- Ext. at 500 kV Gujranwala 1x600 - 1700 20 2015-16 19- Ext. at 500 kV Lahore New 1x750 - 2040 24 2015-16 20- 220 kV Kamra 2x250 In/out of 220 kV Tarbela – Taxila at Kamra (5 km) 1275 15 2015-16 21- 220 kV Iqbal Town 2x250 In/Out of 220 kV Lahore – Wapda Town D/C at Iqbal Town (20+20 km) 2125 25 2015-16 22- 220 kV Gujranwala New 2x250 In/Out of 220 kV Mangala – K.S.K at Gujranwala New (20 km) 220 kV Nokhar - Gujranwala New (50 kM) 2890 34 2015-16 23- 220 kV Pindi Bhattian 2x250 220 kV Pindi Bhattian Ind. – Gujranwala (50 km) 2380 28 2015-16 24- 220 kV Head Faqirian 2x250 220 kV Head Faqirian – Ludewala (60 km) 2380 28 2015-16 NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
  • 39.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 25- 220 kV Joharabad 2x250 In/out of 220 kV D/C Ludewala –Chashma at Jauharabad (5+6 km) 1445 17 2015-16 26- 220 kV Alizai 2x250 220 kV Kohat – Ali zai D/C (110 km) 3825 45 2015-16 27- 2nd Source of supply to 220 kV Chakwal substation - In/out of 220 kV Mangla -Rewat 2nd circuit at Chakwal (60 km) 1530 18 2015-16 28- 2nd Source of supply to 220 kV Bhawalpur substation - 220 kV R.Y.K – Bahalawlpur D/C T/L (150 km) 3825 45 2015-16 29- 220 kV Arif Wala 2x250 In/Out of 220 kV Yousafwala – Kassowal D/C at Arifwala (5+5 km) 1445 17 2015-16 Total: 82620 972 NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
  • 40.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 1- Power Dispersal from 747 MW CCPP at Guddu - 500 kV Guddu New PP – M. Garh (256 km) In/Out of Guddu – Multan at New Guddu (10+10 km) 7735 91 2012-13 2- Dispersal of Power from Uch-2 - 220 kV Uch-II – Sibbi D/C (125 km) 2975 35 2012-13 3- UAE Combined Cycle power plant at GTPS Faisalabad 1x160 In/out of existing 220 kV T/lines at Proposed power plant 1700 20 2012-13 4- Interconnection of 1200 MW AES Imported coal based power near Karachi (Part-II) 500 kV switch ing statio n at Matiari 500 kV S/C T/Line from AES Power Plant to Matiari switching station (200 km) In/Out of 500 kV Hub- Jamshoro S/C T/Line at AES (45+45 km) In/out of 500 kV Jamshoro-R.Y.K at Matiari (5+5 km) 14450 (PC-I cleared by CDWP on 18.3.10) 170 2015-16 POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
  • 41.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 5- Interconnection of 1200 MW Engro & 1200 MW PEPCO’s Thar Coal Based Power Plants at Thar - 500 kV D/C T/L form Thar coal power plants to Matiari (275 km) 500 kV HVDC Matiari – Lahore/ Faisalabad T/L (1100 km) Terminal Stations at both ends 88400 1040 2015-16 6 Interconnection of 1200 MW Imported coal based PPIB and 1000 MW Imported Coal based PEPCO’s power Plants at Karachi - Two 500 kV circuits from Power Plants to Matiari (200 km each) 500 kV HVDC Matiari – Lahore/Faisalabad T/L (1100 km) Extension of Terminal Stations at both ends 85000 1000 2015-16 POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
  • 42.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 7- Import of 1000 MW Power from Iran - Two 500 kV HVAC S/C T/Lines from Zahidan to Quetta with series compensation (198 km) Switching station at Zahidan, Quetta and midpoint between Zahidan & Quetta 40120 472 2015-16 8- Import of 1000 MW Power from Tajikistan (CASA- 1000) - 500 kV HVDC T/L from Pak-Afghan Border to Peshawar (71 km) 500 kV Converter Station Peshawar 16065 189 2015-16 9- Dispersal of Power from 340 MW Chashma-III - 220 kV Chashma New – Bannu (125 km) In/out of 220 kV D.I. Kahan – Jahurabad S/C at Chashma New (1 km) 3000 35 2016-17 POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
  • 43.
    SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSIONLINES ESTIMATE D COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 10- Interconnection of 2x1000 MW Nuclear Power Plants at Karachi - Three 500 kV Circuits from Nuclear Plants to Matiari (200 km each) 25500 300 2018-19 Total 284945 3352 POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
  • 44.
    SR #. NAME OF NEW SUBSTATIONS T/FCAP. (MVA) ASSOCIATED TRANSMISSION LINES ESTIMATED COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 1- Dispersal of Power from 969 MW Neelum Jhelum Hydro Power Project to Rawat & Gujranwala - 500 kV Neelum Jhelum – Rawat S/C T/Line (110 km). 500 kV Neelum Jhelum – Gujranwala S/C T/Line (235 km) 19125 225 2015-16 2- Dispersal of Power from 720 MW Karot HPP - 500 kV Karot – Lahore New (270 km) In/Out of 500 kV Neelum Jhelum – Gujranwala at Karot (10 km) 13250 156 2015-16 3- Power Dispersal of 740 MW Munda HPP - In/Out of 220 kV Peshawar – Shahi Bagh at Munda (35 km) 850 10 2016-17 LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS
  • 45.
    SR #. NAME OF NEW SUBSTATIONS T/FCAP. (MVA) ASSOCIATED TRANSMISSION LINES ESTIMATED COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 11000 LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS
  • 46.
    SR #. NAME OF NEW SUBSTATIONS T/FCAP. (MVA) ASSOCIATED TRANSMISSION LINES ESTIMATED COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO- NING 6- Dispersal of Power from 4500 MW Diamer Basha HPP to Lahore with interconnection at Dasu and Gujar Khan 765 kV HVAC substations at Gujar Khan & Lahore with 765/500 kV 3x500 MVA T/Fs 500 MVAR SVC at Gujar Khan Three 765 kV HVAC T/Ls from Basha to Gujar Khan (407 km long each) Two 765 kV HVAC T/Ls from Gujar Khan to Lahore (260 km long each) 113900 1340 2018-19 LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS
  • 47.
    SR #. NAME OF NEW SUBSTATIONS T/FCAP. (MVA) ASSOCIATED TRANSMISSION LINES ESTIMATED COST (Rs.in Million) Eqt. US$ in Million REQUIREDD YEAR OF COMMISSIO- NING 7- Dispersal of Power from 5400 -7000 MW Bunji Hydro Power Project to Lahore with interconnection at Gujar Khan 765 kV HVAC substatin extn at: Basha, Dasu, Thakot, Gujar khan Lahore 765 kV new substation at Bunji.  2 x 765 kV HVAC 110 km long Bunji - Basha S/C T/Lines 1x765 kV HVAC 759 km long Bunji – Dasu-Thakot-Gujar Khan-Lahore S/C T/Lines 126225 1485  2019-20 Total 296170 3484 LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS PC-I for dispersal of Power from Neelum Jhelum HPP has been approved by ECNEC Studies are being carried out to ascertain the interconnection schemes for the projects at Sr. No: 2 to 7
  • 48.
  • 49.
    Bottle Necks • Atpresent no major system constraints • Intermittent over-loading of transformers at some places being addressed by addition of following transformation capacities up to 2014-15 – 500/220 KV 11400 MVA – 220/132 KV 19330 MVA 49
  • 50.
    50 • For hugefuture development the bottle necks would be 1. Availability of finance 2. Responsibility of dispersal from power plants & uncertainty of generation project. • Capacity of 1. Planning department 2. Local Consultant 3. Local contractors • Inconducive Law & order situation for foreign consultants and contractors.
  • 51.
  • 52.
    Reference documents • NTDCGRID CODE (JUNE 2005) • NEPRA PERFORMANCE STANDARDS (TRANSMISSION) RULES (NOV. 2005) 52
  • 53.
    KEY PERFORMANCE INDICATORS 1.SystemReliability • Transmission System incl. Tie Lines a) System Duration of Interruption = A/N where A= sum of the total outage hours recorded at all the interconnection points (other than 132 kV line tripping) in a period N = Number of monitoring points (Interconnection Point) Tie lines means interconnection facility for the transfer of electric power between the licensee and other utilities not governed by the Act. 53
  • 54.
    KEY PERFORMANCE INDICATORS 1.System Reliability b)System Frequency Interruption = A/N Where A= sum of the total outage hours recorded at all the interconnection points (other than 132 kV line tripping) in a period N= Number of circuits 54
  • 55.
    KEY PERFORMANCE INDICATORS 2.System Security (Energy not served) = ∑ Pi x T Where Pi = Power interrupted in MW in a circuit T = Time Duration in Hours 55
  • 56.
    KEY PERFORMANCE INDICATORS 3.Quality of Supply A) System Voltage Variation Grid Performance Code Standard -500 kV Under Normal Conditions -5 +8% -+ 5% Under N-1 Conditions -+10% -+ 10% -220 kV Under Normal Conditions -5 +8% -+ 5% Under N-1 Conditions -+10% -+ 10% -132 kV Under Normal Conditions -5 +8% -+ 5% Under N-1 Conditions -+10% -+56
  • 57.