Aggregate planning is an intermediate production plan that spans 2-18 months to determine resource procurement quantities and timing to minimize total costs. It considers inputs like workforce, facilities, demand forecasts, and costs. Strategies include proactively altering demand, reactively altering capacity, or using both. The master production schedule converts the aggregate plan into a schedule of individual products over a shorter time period like weeks. It lists products, completion dates, and quantities including firm orders, forecasts, and spare parts. Aggregate planning and the MPS differ in their timeframes, with aggregate planning using months and MPS using weeks.
Demand Forecasting: Forecasting as planning tool, Forecasting Time Horizon, Sources of Data for Forecasting, Accuracy of Forecast, Capacity Planning. Production Planning: Aggregate production Planning, Alternatives for Managing Demand & Supply, Mater Production Schedule, capacity Planning, Overview of MRP, CRP, DRP & MRP-II Production Control: Scheduling & Loading, Scheduling of Job Shops & Floor
Shops, Gantt Chart.
Demand Forecasting: Forecasting as planning tool, Forecasting Time Horizon, Sources of Data for Forecasting, Accuracy of Forecast, Capacity Planning. Production Planning: Aggregate production Planning, Alternatives for Managing Demand & Supply, Mater Production Schedule, capacity Planning, Overview of MRP, CRP, DRP & MRP-II Production Control: Scheduling & Loading, Scheduling of Job Shops & Floor
Shops, Gantt Chart.
This topic is related to Material requirement planning, MRP.
Types of material requirement planning
Benefits of MRP. Limitation of MRP, Objective of MRP, MRP Input, MRP Output, Steps of MRP
Production Planning and Control
Objective of PPC
There are three stages in PPC
Classification/Functions of PPC
Benefits of PPC
Limitations of PPC
Production Planning / Operations Planning
Factors determining Production Planning Procedures
Production Planning System
Production Control
Factors Determining PC procedures
Main Functions of Production Planning
& Control Department
Plant Planning & Facility Planning
EOQ-complete, Just in Time (JIT), Lead time analysis, Inventory models (detai...Srishti Bhardwaj
SIM Unit-3
Economic order quantity (EOQ)
Derivation of EOQ formula,
reasons to modify EOQ to suit to real life situations,
Just in time,
Lead-time analysis,
Effect of long lead-time on costs and profitability,
elements of lead-time,
inventory models:
safety stocks,
fixation of re-order level and
desired inventory level,
designing of Q and P models of inventory control.
This topic is related to Material requirement planning, MRP.
Types of material requirement planning
Benefits of MRP. Limitation of MRP, Objective of MRP, MRP Input, MRP Output, Steps of MRP
Production Planning and Control
Objective of PPC
There are three stages in PPC
Classification/Functions of PPC
Benefits of PPC
Limitations of PPC
Production Planning / Operations Planning
Factors determining Production Planning Procedures
Production Planning System
Production Control
Factors Determining PC procedures
Main Functions of Production Planning
& Control Department
Plant Planning & Facility Planning
EOQ-complete, Just in Time (JIT), Lead time analysis, Inventory models (detai...Srishti Bhardwaj
SIM Unit-3
Economic order quantity (EOQ)
Derivation of EOQ formula,
reasons to modify EOQ to suit to real life situations,
Just in time,
Lead-time analysis,
Effect of long lead-time on costs and profitability,
elements of lead-time,
inventory models:
safety stocks,
fixation of re-order level and
desired inventory level,
designing of Q and P models of inventory control.
Aggregate planning is an operational activity that does an aggregate plan for the production process, in advance of 6 to 18 months, to give an idea to management as to what quantity of materials and other resources are to be procured and when, so that the total cost of operations of the organization is kept to the minimum over that period.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
4. It may be defined as an intermediate production plan
which has a range of 2 to 18 months to give an idea
to management as to what quantity of materials and
other resources are to be procured and when, so that
the total cost of operations of the organization is kept
to the minimum over that period..
It has different approaches strategies and objectives
which will be discussed next. . . . . . . .
Definition
5. There are certain inputs of aggregate planning that is
to say the factors which should be kept in mind while
planning for aggregate production;
These are
Inputs of aggregate planning
7. Total cost of a plan
Projected levels of inventory
Inventory
Output
Employment
Subcontracting
Backordering
Outputs of aggregate planning
8. Proactive
Alter demand to match capacity
Reactive
Alter capacity to match demand
Mixed
Some of each
Aggregate Planning Strategies
9. In a proactive strategy a firm plans to change the
demand by means of advertisements or by means of
offering benefits for a specific product.
Proactive strategy
10. A reactive planning strategy has two parts which are;
Level strategy
Chase strategy
Reactive strategy
11. A level strategy seeks to produce an aggregate plan that
maintains a steady production rate and/or a steady
employment level. In order to satisfy changes in customer
demand, the firm must raise or lower inventory levels in
anticipation of increased or decreased levels of forecast
demand. The firm maintains a level workforce and a steady
rate of output when demand is somewhat low. This allows
the firm to establish higher inventory levels than are
currently needed. As demand increases, the firm is able to
continue a steady production rate/steady employment
level, while allowing the inventory surplus to absorb the
increased demand
Level strategy
12.
13. A chase strategy implies matching demand and capacity
period by period. This could result in a considerable
amount of hiring, firing or laying off of employees;
insecure and unhappy employees; increased inventory
carrying costs; problems with labor unions; and erratic
utilization of plant and equipment. It also implies a great
deal of flexibility on the firm's part. The major advantage
of a chase strategy is that it allows inventory to be held to
the lowest level possible, and for some firms this is a
considerable savings. Most firms embracing the just-in-
time production concept utilize a chase strategy approach
to aggregate planning.
Chase strategy
14.
15. Level strategy
ADVANTAGES
- Stable output rates and workforce
DISADVANTAGES
-greater inventory costs
-increased over time and idle time
-resource utilizations vary over time
16. ADVANTAGES
-Investment in inventory is low
-Labor utilization in high
DISADVANTAGES
-The cost of fluctuating work force
-potential damage to employee morale
Chase strategy
18. Master Production Schedule
Lists the products to be manufactured, when they should be
completed, and in what quantities
It is the conversion of the aggregate schedule into a very
specific schedule of individual
products
Products listed in the master schedule generally divide into
three categories:
1. Firm customer orders
2. Forecasted demand
3. Spare parts
Master production schedule
19. Aggregate planning is a relatively longer term
planning that spans over a period of around 18months
on the other hand MPS is the putting of AP action i.e.
planning individual products for a shorter time span.
Time unit for aggregate planning is one month while
the time unit for MPS is a week.
Relationship between MPS and
aggregate planning
20. That’s all what we have today for
you
we could have explained it in more
detail but time constraint didn’t
allow us !!!!!!!!
21. Credits
This is a joint effort of
UMAR YAZDANI (D 11 IN 05)
AFSAAR ALI ( D 11 IN 27)
HANIF HAZARA (D 11 IN 39)
TAUQIR HAIDER ( D 11 IN 33)