SlideShare a Scribd company logo
Comacchio Drilling Equipment
The longest anchors in Europe: A Case Study
The longest anchors in Europe: A
Case Study
Installation of strand anchors on the Mühltobel bridge
Dalaas, Austria
(Project carried out in 2011)
Engineering: GEOTEK Dönz + Mähr GmbH (Austria)
Contractor: GK Construction GmbH (Austria)
Foundations contractor: Greuter AG (Switzerland)
135.7 km rail connection between Innsbruck and Bludenz (Austria)
Arlberg Railway (Arlbergbahn)
Dating back to 1883, the Arlberg Railway is Austria's only east-west mountain railway,
Operated by the Austrian Federal Railways (ÖBB) and frequented by international trains,
including the Orient Express.
One of Europe's most problematic mountain railways, threatened by avalanches,
mudslides, rock falls and floods
Mühltobel Bridge
Located in Dalaas, Klostertal, one of the most problematic areas of the Arlberg Railway,
due to gypsum formations. Interrupts the 2 sections of the Mühltobel gallery as passage
for debris.
High gypsum percentage in the layers below the bridge foundations caused
displacements that endangered the bridge structure:
- Left abutment drifted approx. 10 cm from the wing wall of the gallery toward valley
- Right abutment had shear cracks showing overloading of the foundations
- Both abutments were secured by single anchors that were no longer functioning
The project
Engineering company
Geotek suggested installing
3 permanent pre-stressed
anchors for each abutment.
Double corrosion protection
steel 1570/1770
8 strands Ø 0.62"
Load capacity Ptk = 2124 kN
Safety class II
Length = 145 m
Bond length = 25 m
Pre-stressing at 700 kN
Test load 1200 kN
Anchor specs:
Reinforced concrete
cross member between
the two abutments
to support the forces in
track axle
The project
According to geotechnical report, the stable layer (limestone) in the slope was located at a
depth of approx. 130 m. Requested anchor length: 145 m
Additional ground consolidation with jet grouting was carried out on both abutments (22 m
columns for right abutment, 12 m columns for left abutment).
Challenges
Drilling of the holes through the 6 m thick reinforced concrete of both abutments to a
depth of 145 m in very complex geological conditions.
Supply of special anchors in lengths of 151 m, to be placed on a special drum and
transported just in time to the job site.
Installation of the anchors at an incline of just 10° causing strong friction and the risk
of strand anchors getting stuck during insertion.
Mountain job site with temporary electricity and water supply to be specially provided.
Working in day and night shifts of 10/12 hours with permanent supervision of the
contractor.
Drilling
Complex geological conditions:
Load bearing rock/marl stratum located under approx. 10 m scree deposits and 110 m
heavily swelling gypsum formations (gipskeuper).
The main risk was related to swelling of the chalk layers due to water inflows, that could
cause the blocking of the anchors inside the borehole. To avoid this, each borehole had
to be drilled working no-stop in day and night shifts.
High borehole accuracy at a depth never performed before, allowed borehole deviation
was set at 2%.
Drilling
Drilling was performed using a Comacchio machine MC-F 04.1 (MC 20)
Main features:
188 kW engine power
Double head system:
3600 daNm torque on the lower head
900 daNm torque on the upper head
10000 daN retract / feed force
Drilling
Telescopic drilling method: 5" DTH hammer using
114 mm rods
219 mm casings up to 45 m depth
178 mm casings to reach the 145 m depth required
Advantages of the method:
Reducing friction on the first 45 m of borehole
Keeping the casings constantly in movement up to the 145 m depth
Anchor installation
Six strand anchors specifically designed and manufactured by Swiss-based DYWIDAG-
Systems International at production plant Koenigsbrunn near Augsburg (Germany).
Longest anchors ever manufactured in Europe (max. production capacity in Switzerland
equal to 75 m).
Double corrosion protected strand anchors in length of 151 m. Each consisting of 6
strands (St1670/1860) with 0.62" nominal diameter, designed to support 1968 kN load at
yield strength and 2232 kN breaking load.
Anchor installation
Installation at in incline of only 10° using a special drum
Bond lengths grouted at a length of 25 m, using four 16 mm hoses. Each anchor required
10 tons grout. The sulfate-resisting cement Protego 4R HS from Swiss-based supplier
Holcim was used.
After a curing time of 1 week the first permanent strand anchor was tensioned in the
presence of the experts of Cottbus Technical University. Initially tensioning to more than
1,200 kN, afterwards anchoring was carried out at a working load of 700 kN. Testing was
performed according to DIN 4125.
The MOSE project
Protecting Venice from flooding
Some major projects
Versaille Palace - Paris
Some major projects
Consolidation of the foundations
Some major projects
New metro lines in Santiago, Naples, Rome …
Some major projects
Frejus: the deepest geothermal boreholes in
Italy (300 m)
20 models from 0,1 to 40 tons
GROUND ENGINEERING (MC line)
15 models from 1,5 to 22 tons
GEOTECHNICS (GEO line)
6 models from 4 to 20 tons
EXPLORATION (EX line)
Over 15 years experience in geothermal technology
GEOTHERMAL
TRUCK MOUNTED (MC-T LINE)
5 models from 6 to 21 tons
7 models from 0,5 to 9,5 tons
EXCAVATOR MOUNTED (MC-E LINE)
MC-S 1200 Special skid-mounted
unit for off-shore drilling
SPECIAL UNITS: MC-S LINE
SPECIAL UNITS: MC-S LINE
MC-S 400 Special unit for shaft
drilling
MC-S 450 Special unit for horizontal
drilling
MC-S 235 Special unit on platform
SPECIAL UNITS: MC-S LINE
Thank you

More Related Content

What's hot

underwater construction
underwater constructionunderwater construction
underwater construction
Yasir Hashmi
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
Raghavendra Raghu
 
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...
Francois Lepers
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
HetviPatel58
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwater
AJITA PANDEY
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
Bhalchandra Tankkar
 
UNDER WATER CONCRETING
UNDER WATER CONCRETINGUNDER WATER CONCRETING
UNDER WATER CONCRETING
seminarppts
 
A Seminar on Under Water Concreting
A Seminar on Under Water ConcretingA Seminar on Under Water Concreting
A Seminar on Under Water Concreting
Sanjan Banerjee
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ABHISHEK THAKKAE
 
Underwater concreting and soil reinforcement techniques,
Underwater concreting and soil reinforcement techniques,Underwater concreting and soil reinforcement techniques,
Underwater concreting and soil reinforcement techniques,
Anmol Sahu
 
Concrete equipments and special concrete
Concrete equipments and special concreteConcrete equipments and special concrete
Concrete equipments and special concrete
Tushar Sonawane
 
Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...
Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...
Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...
A Makwana
 
Evolution Shotcrete brochure
Evolution Shotcrete brochureEvolution Shotcrete brochure
Evolution Shotcrete brochureNige Austin
 
Methods of concreting
Methods of concretingMethods of concreting
Methods of concreting
SachinKotian10
 

What's hot (16)

underwater construction
underwater constructionunderwater construction
underwater construction
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Shotcrete
ShotcreteShotcrete
Shotcrete
 
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwater
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
UNDER WATER CONCRETING
UNDER WATER CONCRETINGUNDER WATER CONCRETING
UNDER WATER CONCRETING
 
A Seminar on Under Water Concreting
A Seminar on Under Water ConcretingA Seminar on Under Water Concreting
A Seminar on Under Water Concreting
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Underwater concreting and soil reinforcement techniques,
Underwater concreting and soil reinforcement techniques,Underwater concreting and soil reinforcement techniques,
Underwater concreting and soil reinforcement techniques,
 
Concrete equipments and special concrete
Concrete equipments and special concreteConcrete equipments and special concrete
Concrete equipments and special concrete
 
Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...
Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...
Diaphragm wall construction_Advanced Construction Technology (Semester-6), Ci...
 
Evolution Shotcrete brochure
Evolution Shotcrete brochureEvolution Shotcrete brochure
Evolution Shotcrete brochure
 
Methods of concreting
Methods of concretingMethods of concreting
Methods of concreting
 

Similar to Comacchio Drilling Equipment

Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
arravindsai
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
Abi Abagun
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAbi Abagun
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
Abi Abagun
 
Immersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, IndiaImmersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, India
Abhay Ocean India ltd.
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
Mohammad Ali
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eJens Classen
 
The øresund bridge
The øresund bridge  The øresund bridge
The øresund bridge
Hariyali Pujara
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
Vicky Matwan
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
BPA-GmbH, Waterproofing is our Passion!
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
Amir Amdani
 
On the road
On the roadOn the road
On the road
Elias Chatzimpalis
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
Rajesh Prasad
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
ADARSH _
 
Fib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_aFib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_agefyra-rion
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
Jayanta Sen
 

Similar to Comacchio Drilling Equipment (20)

Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Pont oresund
Pont oresundPont oresund
Pont oresund
 
Immersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, IndiaImmersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, India
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_e
 
The øresund bridge
The øresund bridge  The øresund bridge
The øresund bridge
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
1115
11151115
1115
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
On the road
On the roadOn the road
On the road
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
 
Gunther koller
Gunther kollerGunther koller
Gunther koller
 
Fib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_aFib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_a
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 

More from MECandPMV

Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...
MECandPMV
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
MECandPMV
 
Chemical attack on the durability of underground structures
Chemical attack on the durability of underground structuresChemical attack on the durability of underground structures
Chemical attack on the durability of underground structures
MECandPMV
 
Building materials & pollutants
Building materials & pollutantsBuilding materials & pollutants
Building materials & pollutants
MECandPMV
 
Standards for mobile towers
Standards for mobile towersStandards for mobile towers
Standards for mobile towers
MECandPMV
 
Risk management
Risk managementRisk management
Risk management
MECandPMV
 
Guarantee mechanism for material supplied with guarantee certificates
Guarantee mechanism for material supplied with guarantee certificatesGuarantee mechanism for material supplied with guarantee certificates
Guarantee mechanism for material supplied with guarantee certificates
MECandPMV
 
Greening of concrete trends & priorities
Greening of concrete trends & prioritiesGreening of concrete trends & priorities
Greening of concrete trends & priorities
MECandPMV
 
Emergency procedure at height
Emergency procedure at heightEmergency procedure at height
Emergency procedure at height
MECandPMV
 
Concrete durability
Concrete durabilityConcrete durability
Concrete durability
MECandPMV
 
Al hail greens residential development
Al hail greens residential developmentAl hail greens residential development
Al hail greens residential development
MECandPMV
 
Advancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniquesAdvancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniques
MECandPMV
 
Tilt up concrete structures
Tilt up concrete structuresTilt up concrete structures
Tilt up concrete structures
MECandPMV
 
Vehicle tracking & fleet management
Vehicle tracking & fleet managementVehicle tracking & fleet management
Vehicle tracking & fleet management
MECandPMV
 
Tilt up concrete Construction advancec & Applications
Tilt up concrete Construction advancec & ApplicationsTilt up concrete Construction advancec & Applications
Tilt up concrete Construction advancec & Applications
MECandPMV
 
Working Safely while saving time & cost
Working Safely while saving time & costWorking Safely while saving time & cost
Working Safely while saving time & cost
MECandPMV
 
Structural health monitoring of intelligent infrastructure
Structural health monitoring of intelligent infrastructureStructural health monitoring of intelligent infrastructure
Structural health monitoring of intelligent infrastructure
MECandPMV
 
Concrete Durability and water resistance
Concrete Durability and water resistanceConcrete Durability and water resistance
Concrete Durability and water resistance
MECandPMV
 
Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...
Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...
Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...
MECandPMV
 
Cement based solutions for early return to service
Cement based solutions for early return to serviceCement based solutions for early return to service
Cement based solutions for early return to service
MECandPMV
 

More from MECandPMV (20)

Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Chemical attack on the durability of underground structures
Chemical attack on the durability of underground structuresChemical attack on the durability of underground structures
Chemical attack on the durability of underground structures
 
Building materials & pollutants
Building materials & pollutantsBuilding materials & pollutants
Building materials & pollutants
 
Standards for mobile towers
Standards for mobile towersStandards for mobile towers
Standards for mobile towers
 
Risk management
Risk managementRisk management
Risk management
 
Guarantee mechanism for material supplied with guarantee certificates
Guarantee mechanism for material supplied with guarantee certificatesGuarantee mechanism for material supplied with guarantee certificates
Guarantee mechanism for material supplied with guarantee certificates
 
Greening of concrete trends & priorities
Greening of concrete trends & prioritiesGreening of concrete trends & priorities
Greening of concrete trends & priorities
 
Emergency procedure at height
Emergency procedure at heightEmergency procedure at height
Emergency procedure at height
 
Concrete durability
Concrete durabilityConcrete durability
Concrete durability
 
Al hail greens residential development
Al hail greens residential developmentAl hail greens residential development
Al hail greens residential development
 
Advancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniquesAdvancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniques
 
Tilt up concrete structures
Tilt up concrete structuresTilt up concrete structures
Tilt up concrete structures
 
Vehicle tracking & fleet management
Vehicle tracking & fleet managementVehicle tracking & fleet management
Vehicle tracking & fleet management
 
Tilt up concrete Construction advancec & Applications
Tilt up concrete Construction advancec & ApplicationsTilt up concrete Construction advancec & Applications
Tilt up concrete Construction advancec & Applications
 
Working Safely while saving time & cost
Working Safely while saving time & costWorking Safely while saving time & cost
Working Safely while saving time & cost
 
Structural health monitoring of intelligent infrastructure
Structural health monitoring of intelligent infrastructureStructural health monitoring of intelligent infrastructure
Structural health monitoring of intelligent infrastructure
 
Concrete Durability and water resistance
Concrete Durability and water resistanceConcrete Durability and water resistance
Concrete Durability and water resistance
 
Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...
Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...
Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...
 
Cement based solutions for early return to service
Cement based solutions for early return to serviceCement based solutions for early return to service
Cement based solutions for early return to service
 

Recently uploaded

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

Comacchio Drilling Equipment

  • 2. The longest anchors in Europe: A Case Study Installation of strand anchors on the Mühltobel bridge Dalaas, Austria (Project carried out in 2011) Engineering: GEOTEK Dönz + Mähr GmbH (Austria) Contractor: GK Construction GmbH (Austria) Foundations contractor: Greuter AG (Switzerland)
  • 3. 135.7 km rail connection between Innsbruck and Bludenz (Austria) Arlberg Railway (Arlbergbahn) Dating back to 1883, the Arlberg Railway is Austria's only east-west mountain railway, Operated by the Austrian Federal Railways (ÖBB) and frequented by international trains, including the Orient Express. One of Europe's most problematic mountain railways, threatened by avalanches, mudslides, rock falls and floods
  • 4. Mühltobel Bridge Located in Dalaas, Klostertal, one of the most problematic areas of the Arlberg Railway, due to gypsum formations. Interrupts the 2 sections of the Mühltobel gallery as passage for debris. High gypsum percentage in the layers below the bridge foundations caused displacements that endangered the bridge structure: - Left abutment drifted approx. 10 cm from the wing wall of the gallery toward valley - Right abutment had shear cracks showing overloading of the foundations - Both abutments were secured by single anchors that were no longer functioning
  • 5. The project Engineering company Geotek suggested installing 3 permanent pre-stressed anchors for each abutment. Double corrosion protection steel 1570/1770 8 strands Ø 0.62" Load capacity Ptk = 2124 kN Safety class II Length = 145 m Bond length = 25 m Pre-stressing at 700 kN Test load 1200 kN Anchor specs: Reinforced concrete cross member between the two abutments to support the forces in track axle
  • 6. The project According to geotechnical report, the stable layer (limestone) in the slope was located at a depth of approx. 130 m. Requested anchor length: 145 m Additional ground consolidation with jet grouting was carried out on both abutments (22 m columns for right abutment, 12 m columns for left abutment).
  • 7. Challenges Drilling of the holes through the 6 m thick reinforced concrete of both abutments to a depth of 145 m in very complex geological conditions. Supply of special anchors in lengths of 151 m, to be placed on a special drum and transported just in time to the job site. Installation of the anchors at an incline of just 10° causing strong friction and the risk of strand anchors getting stuck during insertion. Mountain job site with temporary electricity and water supply to be specially provided. Working in day and night shifts of 10/12 hours with permanent supervision of the contractor.
  • 8. Drilling Complex geological conditions: Load bearing rock/marl stratum located under approx. 10 m scree deposits and 110 m heavily swelling gypsum formations (gipskeuper). The main risk was related to swelling of the chalk layers due to water inflows, that could cause the blocking of the anchors inside the borehole. To avoid this, each borehole had to be drilled working no-stop in day and night shifts. High borehole accuracy at a depth never performed before, allowed borehole deviation was set at 2%.
  • 9. Drilling Drilling was performed using a Comacchio machine MC-F 04.1 (MC 20) Main features: 188 kW engine power Double head system: 3600 daNm torque on the lower head 900 daNm torque on the upper head 10000 daN retract / feed force
  • 10. Drilling Telescopic drilling method: 5" DTH hammer using 114 mm rods 219 mm casings up to 45 m depth 178 mm casings to reach the 145 m depth required Advantages of the method: Reducing friction on the first 45 m of borehole Keeping the casings constantly in movement up to the 145 m depth
  • 11. Anchor installation Six strand anchors specifically designed and manufactured by Swiss-based DYWIDAG- Systems International at production plant Koenigsbrunn near Augsburg (Germany). Longest anchors ever manufactured in Europe (max. production capacity in Switzerland equal to 75 m). Double corrosion protected strand anchors in length of 151 m. Each consisting of 6 strands (St1670/1860) with 0.62" nominal diameter, designed to support 1968 kN load at yield strength and 2232 kN breaking load.
  • 12. Anchor installation Installation at in incline of only 10° using a special drum Bond lengths grouted at a length of 25 m, using four 16 mm hoses. Each anchor required 10 tons grout. The sulfate-resisting cement Protego 4R HS from Swiss-based supplier Holcim was used. After a curing time of 1 week the first permanent strand anchor was tensioned in the presence of the experts of Cottbus Technical University. Initially tensioning to more than 1,200 kN, afterwards anchoring was carried out at a working load of 700 kN. Testing was performed according to DIN 4125.
  • 13. The MOSE project Protecting Venice from flooding Some major projects
  • 14. Versaille Palace - Paris Some major projects Consolidation of the foundations
  • 15. Some major projects New metro lines in Santiago, Naples, Rome …
  • 16. Some major projects Frejus: the deepest geothermal boreholes in Italy (300 m)
  • 17. 20 models from 0,1 to 40 tons GROUND ENGINEERING (MC line)
  • 18. 15 models from 1,5 to 22 tons GEOTECHNICS (GEO line)
  • 19. 6 models from 4 to 20 tons EXPLORATION (EX line)
  • 20. Over 15 years experience in geothermal technology GEOTHERMAL
  • 21. TRUCK MOUNTED (MC-T LINE) 5 models from 6 to 21 tons
  • 22. 7 models from 0,5 to 9,5 tons EXCAVATOR MOUNTED (MC-E LINE)
  • 23. MC-S 1200 Special skid-mounted unit for off-shore drilling SPECIAL UNITS: MC-S LINE
  • 24. SPECIAL UNITS: MC-S LINE MC-S 400 Special unit for shaft drilling
  • 25. MC-S 450 Special unit for horizontal drilling MC-S 235 Special unit on platform SPECIAL UNITS: MC-S LINE