STUDY OF JAIPUR-DEOLI HIGHWAY NH-12
Mandavi Bansal
2012btechce012
Prof. Jaya Gupta
ABSTRACT: The Highway Project described in this report is in construction and operation period, and runs from
km 18+700 to 165+000 between Jaipur and Deoli in the State of Rajasthan as shown in Fig 1. The Highway Road is
a Section of National Highway – 12, starting at Jaipur in the State of Rajasthan and traversing through the States of
Rajasthan and Madhya Pradesh. Total length of NH-12 is about 915 km. . Project stretch runs in mostly plain terrain
and has mostly flat gradients which have 1 - Major Bridge and 26 - Minor Bridge, 4 - Flyovers, and 2-ROB's on the
main Carriageway.
1 INTRODUCTION
1.1 SCOPE OF WORK
The scope of the Access Controlled Highway Project
as detailed in the Concession Agreement. Exit &
Entry ramps on the project highway to be provided. A
length of Km 18.381 service road is to be provided on
either side of Project Highway.09 nos. of RCC Box
culverts are to be newly constructed, 34 nos. of Box
culverts are to be widened and 81 nos. of pipe
culverts are to be improved.
1.2 ORGANISATION
In terms of Concession Agreement, National
Highways Authority of India is working as Authority.
Project Implementation Unit at Tonk is headed by
Project Director followed by Managers (Technical)
and other Administrative staffs. Independent
Engineer took charge of duty in the Mid of Sep-2010.
The team at site is headed by Team Leader. All key
staff members and supporting staff have been
mobilized.
2 CONSTRUCTION AND MAINTENANCE
2.1 Highway Construction
Highway construction is generally preceded by
detailed surveys and subgrade preparation as shown
in Fig 2. Typically, construction begins at the lowest
elevation of the site, regardless of the project type,
and moves upward. By reviewing the geotechnical
specifications of the project, information is given
about:
 Existing ground conditions
 Required equipment for excavation, grading,
and material transportation to and from the
site
 Properties of materials to be excavated
 Dewatering requirements necessary for
below-grade work
 Shoring requirements for excavation
protection
2.2 Subbase Course Construction
A subbase course is a layer designed of carefully
selected materials that is located between the
subgrade and base course of the pavement. The
subbase thickness is generally in the range of 4 to 16
inches, and it is designed to withstand the required
structural capacity of the pavement section. Common
materials used for a highway subbase include gravel,
crushed stone, or subgrade soil that is stabilized with
cement, fly ash, or lime. Permeable subbase courses
are becoming more prevalent because of their ability
to drain infiltrating water from the surface. They also
prevent subsurface water fromreaching the pavement
surface.
2.3 Base Course Construction
The base course is the region of the pavement section
that is located directly under the surface course. If
there is a subbase course, the base course is
constructed directly about this layer. Otherwise, it is
built directly on top of the subgrade. Typical base
course thickness ranges from 4 to 6 inches and is
governed by underlying layer properties. The base
course materials are often treated with cement,
bitumen, calcium chloride, sodium chloride, fly ash,
or lime. These treatments provide improved support
for heavy loads, frost susceptibility, and serves as a
moisture barrier between the base and surface layers.
2.4 Surface Course Construction
There are two most commonly used types of
pavement surfaces used in highway construction:
hot-mix asphalt and Portland cement concrete. These
pavement surface courses provide a smooth and safe
riding surface, while simultaneously transferring the
heavy traffic loads through the various base courses
and into the underlying subgrade soils.
2.5 Highway Maintenance
The overall purpose of highway maintenance is to fix
defects and preserve the pavement's structure and
serviceability. Defects must be defined, understood,
and recorded in order to select an appropriate
maintenance plan. Defects differ between flexible and
rigid pavements.
There are four main objectives of highway
maintenance:
 repair of functional pavement defects
 extend the functional and structural service
life of the pavement
 maintain road safety and signage
 keep road reserve in acceptable condition.
Fig-1 Location
Fig-2 Pavement Layer
Table-3 SALIENT FEATURES
Date of Agreement : 16th Dec. 2009
Period of Construction: 910 days
Extension of Time Recommended: 202 days
Total Project Cost (TPC): Rs. 792 Crores
Capital Cost: Rs. 1733 Crores
Concession Period: 25 Years
Project Length: 148.77 Km
No. of Bypasses: 08
No. of Major Bridge: 01
No of Minor Bridge: 26
No of Flyover: 04
No of ROB: 02
No of VUP’s: 11
No of PUP’s/CUP: 08
No of Toll Plaza: 02
No of Widening of Box Culverts: 34
No of New RCC Box Culverts: 09
No of Improvement of Pipe Culverts: 81
3 PREFERENCES AND ABBREVIATION
− Fig-1,Table-1 Modules provided by Aarvee
Associates Architects, Engineers & Consultant Pvt.
Ltd
−Fig-2 The South African National Roads Agency
Limited
 ROB- Railway Over Bridge
 VUP- Vehicle Under Pass
 CUP- Cattle Under Pass
 PUP- Public Under Pass
 RCC- Reinforced Cement Concrete
4 CONCLUSIONS
Four laning of Km 119.748 have been completed and
Provisional Completion Certificate issued on
27.09.2013 and Project Highway has been put on
Commercial use from midnight at 23:47 PM on 27th
Sep 2013 for 119.748 Km.
5 REFERENCES
- Gun Alan, K.N. “Highway Construction.” The
Handbook of Highway Engineering. Ed. T.W. Fwa.
CRC Press, 2005.
-"Highway engineering." McGraw-Hill Concise
Encyclopaedia of Science and Technology.New
York: McGraw-Hill, 2006. Credo Reference. Web. 13
February 2013.
-Van Wijk, Ian. “Highway Maintenance.” The
Handbook of Highway Engineering. Ed. T.W. Fwa.
CRC Press, 2005
-Modules provide by Aarvee Associates Architects,
Engineers & Consultant Pvt. during internship
period.

More Related Content

What's hot

ROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERINGROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERINGRanBir ShaRma
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemeakram akhtar
 
Article for Africon FACET
Article for Africon FACETArticle for Africon FACET
Article for Africon FACETChristo Beukes
 
Complete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectComplete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectEngr_Emad Khan
 
ROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD finalROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD finalAvneet Grewall
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016VDOT Northern Virginia
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementNIWASHISH VISWAS
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Project report on CC road
Project report on CC roadProject report on CC road
Project report on CC roadvikash mishra
 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement Awinash Tiwari
 

What's hot (20)

ROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERINGROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERING
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage system
 
Flexible pavement
Flexible pavementFlexible pavement
Flexible pavement
 
Paper
PaperPaper
Paper
 
Think Outside The Box
Think Outside The BoxThink Outside The Box
Think Outside The Box
 
Article for Africon FACET
Article for Africon FACETArticle for Africon FACET
Article for Africon FACET
 
Flexible pavement
Flexible pavement  Flexible pavement
Flexible pavement
 
Complete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectComplete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric Project
 
Construction of cc_road
Construction of cc_roadConstruction of cc_road
Construction of cc_road
 
ROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD finalROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD final
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Chapter1
Chapter1Chapter1
Chapter1
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
I-64 Kanawha River Bridge
I-64 Kanawha River BridgeI-64 Kanawha River Bridge
I-64 Kanawha River Bridge
 
Project report on CC road
Project report on CC roadProject report on CC road
Project report on CC road
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement
 

Similar to PS-1 SUMMARY NHAI

PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUSubhendu Samui
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUISubhendu Samui
 
EASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTEASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTATUL SHUKLA
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfDanielWisman1
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadIRJET Journal
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge ConstructionSukhdeep Jat
 
CTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxCTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxAnandBaratePatil
 
New ppt on road construction
New ppt on road construction New ppt on road construction
New ppt on road construction Kuldeep317348
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTSatyam Anand
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Roadshashanksingh593
 
RDSO- GE G-1
 RDSO-   GE  G-1 RDSO-   GE  G-1
RDSO- GE G-1selva65
 
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...SaurabhPawar76
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxDolanGhosh4
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...AamerShakoor
 

Similar to PS-1 SUMMARY NHAI (20)

PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDU
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
 
EASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTEASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORT
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
VCS Resume_May 2015
VCS Resume_May 2015VCS Resume_May 2015
VCS Resume_May 2015
 
ProjectReport.pdf
ProjectReport.pdfProjectReport.pdf
ProjectReport.pdf
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing Road
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
CTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxCTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptx
 
Metro Work
Metro WorkMetro Work
Metro Work
 
AVNEET TRAINING
AVNEET TRAININGAVNEET TRAINING
AVNEET TRAINING
 
New ppt on road construction
New ppt on road construction New ppt on road construction
New ppt on road construction
 
Shib
ShibShib
Shib
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Road
 
RDSO- GE G-1
 RDSO-   GE  G-1 RDSO-   GE  G-1
RDSO- GE G-1
 
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptx
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
 

PS-1 SUMMARY NHAI

  • 1. STUDY OF JAIPUR-DEOLI HIGHWAY NH-12 Mandavi Bansal 2012btechce012 Prof. Jaya Gupta ABSTRACT: The Highway Project described in this report is in construction and operation period, and runs from km 18+700 to 165+000 between Jaipur and Deoli in the State of Rajasthan as shown in Fig 1. The Highway Road is a Section of National Highway – 12, starting at Jaipur in the State of Rajasthan and traversing through the States of Rajasthan and Madhya Pradesh. Total length of NH-12 is about 915 km. . Project stretch runs in mostly plain terrain and has mostly flat gradients which have 1 - Major Bridge and 26 - Minor Bridge, 4 - Flyovers, and 2-ROB's on the main Carriageway. 1 INTRODUCTION 1.1 SCOPE OF WORK The scope of the Access Controlled Highway Project as detailed in the Concession Agreement. Exit & Entry ramps on the project highway to be provided. A length of Km 18.381 service road is to be provided on either side of Project Highway.09 nos. of RCC Box culverts are to be newly constructed, 34 nos. of Box culverts are to be widened and 81 nos. of pipe culverts are to be improved. 1.2 ORGANISATION In terms of Concession Agreement, National Highways Authority of India is working as Authority. Project Implementation Unit at Tonk is headed by Project Director followed by Managers (Technical) and other Administrative staffs. Independent Engineer took charge of duty in the Mid of Sep-2010. The team at site is headed by Team Leader. All key staff members and supporting staff have been mobilized. 2 CONSTRUCTION AND MAINTENANCE 2.1 Highway Construction Highway construction is generally preceded by detailed surveys and subgrade preparation as shown in Fig 2. Typically, construction begins at the lowest elevation of the site, regardless of the project type, and moves upward. By reviewing the geotechnical specifications of the project, information is given about:  Existing ground conditions  Required equipment for excavation, grading, and material transportation to and from the site  Properties of materials to be excavated  Dewatering requirements necessary for below-grade work  Shoring requirements for excavation protection 2.2 Subbase Course Construction A subbase course is a layer designed of carefully selected materials that is located between the subgrade and base course of the pavement. The subbase thickness is generally in the range of 4 to 16 inches, and it is designed to withstand the required structural capacity of the pavement section. Common materials used for a highway subbase include gravel, crushed stone, or subgrade soil that is stabilized with cement, fly ash, or lime. Permeable subbase courses are becoming more prevalent because of their ability to drain infiltrating water from the surface. They also prevent subsurface water fromreaching the pavement surface. 2.3 Base Course Construction The base course is the region of the pavement section that is located directly under the surface course. If there is a subbase course, the base course is constructed directly about this layer. Otherwise, it is built directly on top of the subgrade. Typical base course thickness ranges from 4 to 6 inches and is governed by underlying layer properties. The base course materials are often treated with cement, bitumen, calcium chloride, sodium chloride, fly ash, or lime. These treatments provide improved support for heavy loads, frost susceptibility, and serves as a moisture barrier between the base and surface layers. 2.4 Surface Course Construction There are two most commonly used types of pavement surfaces used in highway construction: hot-mix asphalt and Portland cement concrete. These pavement surface courses provide a smooth and safe riding surface, while simultaneously transferring the heavy traffic loads through the various base courses and into the underlying subgrade soils.
  • 2. 2.5 Highway Maintenance The overall purpose of highway maintenance is to fix defects and preserve the pavement's structure and serviceability. Defects must be defined, understood, and recorded in order to select an appropriate maintenance plan. Defects differ between flexible and rigid pavements. There are four main objectives of highway maintenance:  repair of functional pavement defects  extend the functional and structural service life of the pavement  maintain road safety and signage  keep road reserve in acceptable condition. Fig-1 Location Fig-2 Pavement Layer Table-3 SALIENT FEATURES Date of Agreement : 16th Dec. 2009 Period of Construction: 910 days Extension of Time Recommended: 202 days Total Project Cost (TPC): Rs. 792 Crores Capital Cost: Rs. 1733 Crores Concession Period: 25 Years Project Length: 148.77 Km No. of Bypasses: 08 No. of Major Bridge: 01 No of Minor Bridge: 26 No of Flyover: 04 No of ROB: 02 No of VUP’s: 11 No of PUP’s/CUP: 08 No of Toll Plaza: 02 No of Widening of Box Culverts: 34 No of New RCC Box Culverts: 09 No of Improvement of Pipe Culverts: 81 3 PREFERENCES AND ABBREVIATION − Fig-1,Table-1 Modules provided by Aarvee Associates Architects, Engineers & Consultant Pvt. Ltd −Fig-2 The South African National Roads Agency Limited  ROB- Railway Over Bridge  VUP- Vehicle Under Pass  CUP- Cattle Under Pass  PUP- Public Under Pass  RCC- Reinforced Cement Concrete 4 CONCLUSIONS Four laning of Km 119.748 have been completed and Provisional Completion Certificate issued on 27.09.2013 and Project Highway has been put on Commercial use from midnight at 23:47 PM on 27th Sep 2013 for 119.748 Km. 5 REFERENCES - Gun Alan, K.N. “Highway Construction.” The Handbook of Highway Engineering. Ed. T.W. Fwa. CRC Press, 2005. -"Highway engineering." McGraw-Hill Concise Encyclopaedia of Science and Technology.New York: McGraw-Hill, 2006. Credo Reference. Web. 13 February 2013. -Van Wijk, Ian. “Highway Maintenance.” The Handbook of Highway Engineering. Ed. T.W. Fwa. CRC Press, 2005 -Modules provide by Aarvee Associates Architects, Engineers & Consultant Pvt. during internship period.