NAME –TARUN GUPTA
ME –INFRASTRUCTURE(CIVIL)
PMGSY PROFILE
 Pradhan Mantri Gram Sadak Yojana (PMGSY) was launched on
25th December 2000 as a fully funded Centrally Sponsored
Scheme to provide all weather road connectivity in rural areas
of the country.
 The programme envisages connecting all habitations with a
population of 500 persons and above in the plain areas and 250
persons and above in hill States, the tribal and the desert areas.
 According to latest figures made available by the State
Governments under a survey to identify Core Network as
part of the PMGSY programme, about 1.67 lakh
Unconnected Habitations are eligible for coverage under the
programme. This involves construction of about 3.71 lakh
km. of roads for New Connectivity and 3.68 lakh km. under
upgradation.
NAME
OF
BLOCK
CODE TOTAL
NO. OF
HABITAT
ION
>1000 500-999 250-499 <250 TOTAL
ELIGIBL
E
HABITAT
ION
DHARM
PUR
HP-11 8 - 458 - 8
•SUMMARY SHEET O F HABITATION BENEFITTED:
DISTRICT BLOCK PACKAGE
NO.
NAME
OF
ROAD
LENGTH
KM.
ORIGNAL
VLAUE
MAINT.
SOLAN DHARMP
UR
HP-11-82 PRATHA
TO
NABON
8.000 185.18 LACS 24.10
LACS
AVG. CONSTRUCTION COST PER KM(Lacs)=23.15
TRANSECT WALK:
A walk along the suggested alignment by PIU with the communities, PRI and key
informants to observe, to listen, and to ask questions which would enable identification
of problems and collectively evolve solutions. The transect shall enable the PIU, to
quickly learn about the social structure, issues pertaining to land, social impacts, soils,
land use, and community assets and to triangulate data already available.
TOTAL NO. OF PEOPLE PRESENT IN TRANSECT WALK:
MALE =55 FEMALE 33 TOTAL =88
DEMOGRAPHIC INFO WHERE WALK WAS CONDUCTED KIAROO, GUTHAN,KALIND,DHAR
(BOTH SIDES APPLE OCHARDS) IN DIFF. RD’S
NO OF GOVT. EMPLOYE PRESENT=6
NO. OF CONTRACTOR EMPLOYE PRESENT=NIL
NO. OF PARTICIPANT FROM MINORITY COMMUNITY
SC=12 ST= - WOMEN=9
TRAFFIC SURVEY
s.no Type of vehicle Day 1 Day 2 Day 3 Avg.
1 Car, jeep, van 45 50 40 45
2 Tanker
3 LCV 28 32 30 30
4 Minibus
5 Minitruck 52 49 46 49
6 Tractor with
trailer
72 64 68 68
7 Tractor without
trailer
8 Cycle
9 Hand cart
10 Horse cart
11 Pedestrians
CVPD 169 163 152 162
TOTAL
MOTORIZE
D VEHICLE
PER DAY
197 195 184 192
TABLE-1.1: AVG 3-DAY TRAFFIC DATA
s.no Type of vehicle ADT AADT GROWTH
RATE
1 Car,jeep,van 45 48 53
2 Tanker 0
3 LCV 30 32 36
4 Minibus 0
5 minitruck 49 52 58
6 Tractor with
trailer
68 72 81
7 Tractor without
trailer
8 Cycle
9 Hand cart
10 Horse cart
11 pedestrians
CVPD 162 172 192
TOTAL
MOTORIZED
VEHICLE PER
DAY
192 204 228
TABLE-1.2: AVERAGE ANNUAL TRAFFIC DATA (BOTH WAYS)
DESIGN FOR COMMULATIVE
ESAL
 Since it is a new road so that field authorities have collected and supplied
the data from the adjoining road in the year of traffic count 192 having two
harvesting season.
 Assuming 50% of harvesting season so ADT during non harvesting season
=192/2=96
 AADT=VOLUME OF TRAFFIC IN YEAR/365
 96 + (TRAFFIC VOL. COUNT*DAILY FACTOR*SEASONAL FACTOR)
 365
 AADT=96+ (1.2*96*75) = 120
 365
 ASSUMING 6% GROWTH RATE BEFORE TWO YEAR WHILE ROAD IS
OPENED TO TRAFFIC
 AADT = 120(1+0.06)^2=135
 COMMULATIVE ESAL OVER 10 YEARS @6 % GROWTH RATE:
 N=55,037
 SO 55,037 fall in category T2 i.e. it fall in commutative ESAL application of
30000 to 60000 and against CBR value 0f 7-9% , a total crust thickness
may be provided as per the pavement catalogues of IRC SP-72 -2007
 The following specification has been recommended for this road section
investigated under the study for the design of flexible pavement.
TOP LAYER PREMIX CARPET
WITH TYPE B SEAL
COAT
20 MM
BASE LAYER WBM GRADING 3 75 MM
SUB BASE LAYER WBM 1 AND 2 (100+75 )MM
TOTAL THICKNESS 270 MM
LAYOUT OF FLEXIBLE PAVEMENT:
o GSB having a compacted thickness of 100mm of CBR less than 20%
o WBM GRADE 2 (63-45mm) having a single compacted layer thickness
of 75 MM
o For surfacing and sealing wearing course , a suitable layer of open
graded mix carpet (PMC) having a compacted thickness of 20mm with seal
coat provide at the top of surface for smoothness of road.
GEOMETRIC DESIGN
TERRAIN CLASSIFICATION CROSS SLOPE OF THE COUNTRY
PLAIN 0-10 % More than 1 in 10
ROLLING 10-25 % 1 in 10 to 1 in 4
MOUNTAINOUS 25-60 % 1 in 4 to 1 in 1.67
STEEP >60 % < 1.67
S.N
O
NAME OF
ROAD
ROAD
LENGTH
(KM)
ROAD
CONNECTING TO
LAND
WIDT
H
ROAD
WIDT
H
C/O 8/00 VR 7.50 5.00
JHANDURI
TO
NABOOWN
ROAD
CLASSIFICATION
PLAIN
TERRAIN
ROLLING
TERRAIN
MOUNTAINOUS
TERRAIN
STEEP
TERRAIN
RULI
NG
MIN. RULI
NG
MIN. RULIN
G
MIN. RULI
NG
MIN
RURAL ROAD 50 40 40 35 25 20 25 20
DESIGN SPEED:
DESIGN SPEED (km/hr) SAFE STOPPING SIGHT DISTANCE
(m)
20 20
30 30
40 45
50 60
LONGITUDNAL AND TRNSVERSE
SECTION
INTERSECTION
PAVEMENT MATERIAL
MATERIAL SOURCE LEAD (KM)
STONE BAROTIWALA CRUSHER SITE 37.00
STONE AGGREGATE 10MM BAROTIWALA CRUSHER SITE 37.00
STONE AGGREGATE 20MM BAROTIWALA CRUSHER SITE 37.00
STONE AGGREGATE 40MM BAROTIWALA CRUSHER SITE 37.00
BITUMEN PANIPAT 190.00
CEMENT PARWANOO 34.00
SAND BHARWALA NADI 66.00
HUME PIPE
ANY OTHER
TABLE:SOURCE OF PAVEMENT MATERIALS
STATE-HIMACHAL PRADESH DISTRICT-SOLAN BLOCK-
DHARMPUR
ROAD FROM JHANDURI TO NABOWN ROAD
DESIGN OF PAVEMENT
SECTION
EARTH-
WORK
SUBGRADE
GSB WBM BASE
COURSE
BITUMINOUS
SURFACE
CROSS
DRAINAGE
WORK
SUBGRADE
CBR VALUE TEST RESULT
UNSOAKED CBR TEST
 AT 2.5mm penetration 12.5%
 AT 5.0 mm penetration 14.0%
SOAKED CBR TEST
(AFTER 4 DAYS)
 AT 2.5mm penetration 6.8%
 AT 5.0 mm penetration 7.2%
Sub grade soil is an integral part of the road pavement structure as it provides the
support to the pavement from beneath. The sub grade soil and its properties are
important in the design of pavement structure. The main function of the sub grade is to
give adequate support to the pavement and for this the sub grade should possess
sufficient stability under adverse climatic and loading conditions. Therefore, it is very
essential to evaluate the sub grade by conducting tests.
SUBRADE THICKNESS FOR RURAL ROAD=300 MM
Descrip
tion
&
location
Identificatio
n
and
classification
Gradation analysis % age Atterberg
Limit
Gravel sand Fine(silt /clay) L.L
%
P.L
%
PI
%
Km
0/600
Generally,coar
se
Grained soil of
group
symbol
GM/GC
42.8 32.8 24.4 23 20 3
Km
1/350
46.2 31.2 22.6 22 19 3
Km
2/750
43.7 31.5 24.8 24 20 4
Km
3/600
45.2 32.6 21.5 23 20 3
OMC
%
MDD
gm
10.5 2.03
10.0 2.05
9.5 2.02
10.0 2.05
SUPERELEVATION:
( Max. Super elevation for this project is 5.0% )
CAMBER
THIN BIYUMINOUS ROAD 3.0 % ( RAINFALL<
1000MM)
3.5 % ( RAINFALL>
1000MM)
GSB (GRANULAR SUB BASE)
 Granular sub-base (GSB) is constructed with well graded Granular
Soil, maintaining suitable moisture content and compacted in layers
not exceeding 100mm. Compaction is done till required density is
achieved as per the design. A well finished GSB will be free from
movement (under compaction equipment), ridges, cracks or loose
material.
 GRADATION OF GSB MATERIAL:
IS SIEVE DESIGNATION % BY WEIGHT PASSING THE IS SIEVE
GRADING 1 GRADING 2 GRADING 3
75MM 100
53MM
26.5 MM 55-75 50-80 100
4.75 MM 10-30 15-35 25-45
0.075 MM <10 <10 <10
WATER BOUND MACADAM
SUBBASE/BASE:
Providing,laying,spreading and compacting stone aggregates of specific size to
water bound macadam specification including spreading in uniform
thickness,hand packing, rolling with three wheel 80-100 KN static roller in stages
to proper grade and camber ,applying and brooming,stone screening /binding
material to fill up the interstics of coarse agg. ,watering and compacting to the
required density grading 1 as per technical specification clause 404
IS SIEVE DESPERATION % BY WEIGHT PASSING IS SIEVE
GRAD. A GRAD. B GRAD. C
53 MM 100
37.5MM 97-100 100
26.5MM 97-100 100
19MM 67-81 97-100
9.5MM 56-70 67-79
4.75M 33-47 39-53 47-59
.425MM 10-19 12-21 12-21
.075MM 4-8 4-8 4-8
BITUMINOUS SURFACE
Bituminous layer is laid over the base course to ensure that rainwater does not
damage the base, that moving traffic does not remove the metal and other material.
The Bituminous layer also provides for dust free and comfortable riding.
CROSS DRAINAGE
STRUCTURES
The pavement surface should be absolutely impermeable to prevent seepage of water into the
pavement layers. Further, both the geometry and texture of pavement surface should help in
draining out the water from the surface in less time.
S.NO CHAINAGE (KM) DESCRIPTION OF EXISTING STRUCTURES
TYPE SPAN/DIA(m) CONDITION
0/105 HUME PIPE 900 MM DIA GOOD
0/225 HUME PIPE 900 MM DIA GOOD
0/390 HUME PIPE 900 MM DIA GOOD
0/600 HUME PIPE 900 MM DIA GOOD
1/115 HUME PIPE 900 MM DIA GOOD
1/495 HUME PIPE 900 MM DIA GOOD
1/795 SLAB CULVERT 3 MTR. SPAN GOOD
1/915 HUME PIPE 900 MM DIA GOOD
1/960 HUME PIPE 900 MM DIA GOOD
2/195 HUME PIPE 900 MM DIA GOOD
2/390 HUME PIPE 900 MM DIA GOOD
2/815 HUME PIPE 900 MM DIA GOOD
3/00 SLAB CULVERT 3 MTR. SPAN GOOD
LIST AND CONDITION OF EXISTING CULVERT:
QUALITY MONITORING:
Efforts are made to ensure quality of rural roads under the Pradhan Mantri Gram
Sadak Yojana. Rigorous tearing for quality of material and workmanship is to be
carried out on all the road works. A three-tier quality control monitoring system has
been adopted for these roads. While the executive engineer or the PIU is the first tier,
the second tier is an independent state level agency. As the third tier, senior technical
persons are engaged as National Quality Monitor (NQMs) to inspect road works in
different states.
A 3-tier Quality Control System has been designed to ensure the quality of the
road works. While the concerned Executive Engineer is the first tier, all the
states have been requested to enlist the services of a State level independent
Agency to verify the quality of the roads. On its part, the National Rural Roads
Development Agency, an agency set up by the Ministry of Rural development,
engages senior technical personnel as National Quality Monitors to inspect the
road works.
Logo Sign Board And Other
Road Furniture
 Immediately on starting the work, all the roads
under the PMGSY are required to have
informatory Sign Board giving the particulars of the
road work as well as the name of the contractor .
Road furniture like Km Stones, 200m Stones,
Cautionary Signs etc. are to be provided on all
roads constructed under Pradhan Mantri Gram
Sadak Yojana.
SPECIAL THANKS TO A PERSON WWHO MADE PMGSY COME
TRUE AND TOOK INDIA TO NEXT LEVEL OF DEVELOPMENT
AND CONNECTIVITY.

More Related Content

What's hot

Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...PrashannaKumar2
 
Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37 Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37 SupriyaPal10
 
Project report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash GargProject report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash Gargharshit315
 
Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement designM Firdaus
 
pavement analysis
pavement analysis pavement analysis
pavement analysis Saeed Badeli
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDevesh Chaurasia
 
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Pranamesh Chakraborty
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness designSohail Khan
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavementBhavik A Shah
 
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...IAEME Publication
 
Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designImran Nawaz
 
Rigid pavement-manual
Rigid pavement-manualRigid pavement-manual
Rigid pavement-manualWencivil
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignRiaz Zalil
 
RoadstaB - Road Stabilization
RoadstaB - Road StabilizationRoadstaB - Road Stabilization
RoadstaB - Road StabilizationNikhil Sharma
 
Rehabilitation of low volume flexible pavements by white topping a case study
Rehabilitation of low volume flexible pavements by white topping a case studyRehabilitation of low volume flexible pavements by white topping a case study
Rehabilitation of low volume flexible pavements by white topping a case studyeSAT Publishing House
 
RoadstaB : Road Stabilization
RoadstaB : Road Stabilization RoadstaB : Road Stabilization
RoadstaB : Road Stabilization Nikhil Sharma
 

What's hot (20)

Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...
 
Training PPT
Training PPTTraining PPT
Training PPT
 
Design of a rigid pavement (jpcp &amp; crcp)
Design of a rigid pavement (jpcp &amp; crcp)Design of a rigid pavement (jpcp &amp; crcp)
Design of a rigid pavement (jpcp &amp; crcp)
 
Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37 Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37
 
Project report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash GargProject report file on construction of flexible pavement by Harshit Prakash Garg
Project report file on construction of flexible pavement by Harshit Prakash Garg
 
Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement design
 
Aashto design
Aashto designAashto design
Aashto design
 
pavement analysis
pavement analysis pavement analysis
pavement analysis
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeT
 
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
 
Flexible pavement
Flexible pavement  Flexible pavement
Flexible pavement
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...
 
Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement design
 
Rigid pavement-manual
Rigid pavement-manualRigid pavement-manual
Rigid pavement-manual
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
RoadstaB - Road Stabilization
RoadstaB - Road StabilizationRoadstaB - Road Stabilization
RoadstaB - Road Stabilization
 
Rehabilitation of low volume flexible pavements by white topping a case study
Rehabilitation of low volume flexible pavements by white topping a case studyRehabilitation of low volume flexible pavements by white topping a case study
Rehabilitation of low volume flexible pavements by white topping a case study
 
RoadstaB : Road Stabilization
RoadstaB : Road Stabilization RoadstaB : Road Stabilization
RoadstaB : Road Stabilization
 

Viewers also liked

Caterware case-study-cutty-sark
Caterware case-study-cutty-sarkCaterware case-study-cutty-sark
Caterware case-study-cutty-sarkNigel Brown
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas Anshul Shakya
 
Road Construction
Road ConstructionRoad Construction
Road ConstructionDanish Mohd
 
road construction project
road construction projectroad construction project
road construction projectnishant singh
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 

Viewers also liked (6)

Caterware case-study-cutty-sark
Caterware case-study-cutty-sarkCaterware case-study-cutty-sark
Caterware case-study-cutty-sark
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
road construction project
road construction projectroad construction project
road construction project
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 

Similar to Six week industrial training presentation BY GUPTA TARUN

Village networking ppt
Village networking pptVillage networking ppt
Village networking pptPatel Tapan
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD hitendra pendam
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Gargharshit315
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptbala506586
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)Utsav Tripathy
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometricsKHUSHBU SHAH
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdf
09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdf09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdf
09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdfSandipPaul46
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 
Influence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavementsInfluence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavementsIAEME Publication
 
IRJET- Flexible Pavement
IRJET-  	  Flexible PavementIRJET-  	  Flexible Pavement
IRJET- Flexible PavementIRJET Journal
 
IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...
IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...
IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...IRJET Journal
 
PPT, PIU Ratlam_8-lane Delhi-Mumbai Expressway
PPT, PIU Ratlam_8-lane Delhi-Mumbai ExpresswayPPT, PIU Ratlam_8-lane Delhi-Mumbai Expressway
PPT, PIU Ratlam_8-lane Delhi-Mumbai ExpresswayvenkateswararaoPothi1
 

Similar to Six week industrial training presentation BY GUPTA TARUN (20)

Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Presentation sayed
Presentation sayedPresentation sayed
Presentation sayed
 
Guniting ppt.pptx
Guniting ppt.pptxGuniting ppt.pptx
Guniting ppt.pptx
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Garg
 
Roadstab 2017
Roadstab 2017Roadstab 2017
Roadstab 2017
 
Road of construction
Road of construction Road of construction
Road of construction
 
SUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWDSUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWD
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
 
123 VIKASH.pptx
123 VIKASH.pptx123 VIKASH.pptx
123 VIKASH.pptx
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdf
09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdf09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdf
09_VV_Pavement Design IRC37-2018_29Jan2020 - Admin KHRI.pdf
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Influence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavementsInfluence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavements
 
IRJET- Flexible Pavement
IRJET-  	  Flexible PavementIRJET-  	  Flexible Pavement
IRJET- Flexible Pavement
 
IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...
IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...
IRJET- Effect of Various Parameters on Performance of Rural Roads Constructed...
 
PPT, PIU Ratlam_8-lane Delhi-Mumbai Expressway
PPT, PIU Ratlam_8-lane Delhi-Mumbai ExpresswayPPT, PIU Ratlam_8-lane Delhi-Mumbai Expressway
PPT, PIU Ratlam_8-lane Delhi-Mumbai Expressway
 
AVNEET TRAINING
AVNEET TRAININGAVNEET TRAINING
AVNEET TRAINING
 

Recently uploaded

SD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxSD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxjanettecruzeiro1
 
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...Suhani Kapoor
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CANestorGamez6
 
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...BarusRa
 
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...Pooja Nehwal
 
Fashion trends before and after covid.pptx
Fashion trends before and after covid.pptxFashion trends before and after covid.pptx
Fashion trends before and after covid.pptxVanshNarang19
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...babafaisel
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxmirandajeremy200221
 
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...Call Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...Call Girls in Nagpur High Profile
 
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Gariahat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Petrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptxPetrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptxIgnatiusAbrahamBalin
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsCharles Obaleagbon
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130Suhani Kapoor
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵anilsa9823
 
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779Delhi Call girls
 

Recently uploaded (20)

SD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxSD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptx
 
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
 
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
 
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
 
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
 
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...
 
Fashion trends before and after covid.pptx
Fashion trends before and after covid.pptxFashion trends before and after covid.pptx
Fashion trends before and after covid.pptx
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptx
 
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...Booking open Available Pune Call Girls Nanded City  6297143586 Call Hot India...
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
 
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
B. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdfB. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdf
 
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Gariahat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Room
 
Petrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptxPetrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptx
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past Questions
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
 
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
 

Six week industrial training presentation BY GUPTA TARUN

  • 1. NAME –TARUN GUPTA ME –INFRASTRUCTURE(CIVIL)
  • 2. PMGSY PROFILE  Pradhan Mantri Gram Sadak Yojana (PMGSY) was launched on 25th December 2000 as a fully funded Centrally Sponsored Scheme to provide all weather road connectivity in rural areas of the country.  The programme envisages connecting all habitations with a population of 500 persons and above in the plain areas and 250 persons and above in hill States, the tribal and the desert areas.  According to latest figures made available by the State Governments under a survey to identify Core Network as part of the PMGSY programme, about 1.67 lakh Unconnected Habitations are eligible for coverage under the programme. This involves construction of about 3.71 lakh km. of roads for New Connectivity and 3.68 lakh km. under upgradation.
  • 3. NAME OF BLOCK CODE TOTAL NO. OF HABITAT ION >1000 500-999 250-499 <250 TOTAL ELIGIBL E HABITAT ION DHARM PUR HP-11 8 - 458 - 8 •SUMMARY SHEET O F HABITATION BENEFITTED: DISTRICT BLOCK PACKAGE NO. NAME OF ROAD LENGTH KM. ORIGNAL VLAUE MAINT. SOLAN DHARMP UR HP-11-82 PRATHA TO NABON 8.000 185.18 LACS 24.10 LACS AVG. CONSTRUCTION COST PER KM(Lacs)=23.15
  • 4. TRANSECT WALK: A walk along the suggested alignment by PIU with the communities, PRI and key informants to observe, to listen, and to ask questions which would enable identification of problems and collectively evolve solutions. The transect shall enable the PIU, to quickly learn about the social structure, issues pertaining to land, social impacts, soils, land use, and community assets and to triangulate data already available. TOTAL NO. OF PEOPLE PRESENT IN TRANSECT WALK: MALE =55 FEMALE 33 TOTAL =88 DEMOGRAPHIC INFO WHERE WALK WAS CONDUCTED KIAROO, GUTHAN,KALIND,DHAR (BOTH SIDES APPLE OCHARDS) IN DIFF. RD’S NO OF GOVT. EMPLOYE PRESENT=6 NO. OF CONTRACTOR EMPLOYE PRESENT=NIL NO. OF PARTICIPANT FROM MINORITY COMMUNITY SC=12 ST= - WOMEN=9
  • 5. TRAFFIC SURVEY s.no Type of vehicle Day 1 Day 2 Day 3 Avg. 1 Car, jeep, van 45 50 40 45 2 Tanker 3 LCV 28 32 30 30 4 Minibus 5 Minitruck 52 49 46 49 6 Tractor with trailer 72 64 68 68 7 Tractor without trailer 8 Cycle 9 Hand cart 10 Horse cart 11 Pedestrians CVPD 169 163 152 162 TOTAL MOTORIZE D VEHICLE PER DAY 197 195 184 192 TABLE-1.1: AVG 3-DAY TRAFFIC DATA
  • 6. s.no Type of vehicle ADT AADT GROWTH RATE 1 Car,jeep,van 45 48 53 2 Tanker 0 3 LCV 30 32 36 4 Minibus 0 5 minitruck 49 52 58 6 Tractor with trailer 68 72 81 7 Tractor without trailer 8 Cycle 9 Hand cart 10 Horse cart 11 pedestrians CVPD 162 172 192 TOTAL MOTORIZED VEHICLE PER DAY 192 204 228 TABLE-1.2: AVERAGE ANNUAL TRAFFIC DATA (BOTH WAYS)
  • 7. DESIGN FOR COMMULATIVE ESAL  Since it is a new road so that field authorities have collected and supplied the data from the adjoining road in the year of traffic count 192 having two harvesting season.  Assuming 50% of harvesting season so ADT during non harvesting season =192/2=96  AADT=VOLUME OF TRAFFIC IN YEAR/365  96 + (TRAFFIC VOL. COUNT*DAILY FACTOR*SEASONAL FACTOR)  365  AADT=96+ (1.2*96*75) = 120  365  ASSUMING 6% GROWTH RATE BEFORE TWO YEAR WHILE ROAD IS OPENED TO TRAFFIC  AADT = 120(1+0.06)^2=135  COMMULATIVE ESAL OVER 10 YEARS @6 % GROWTH RATE:  N=55,037  SO 55,037 fall in category T2 i.e. it fall in commutative ESAL application of 30000 to 60000 and against CBR value 0f 7-9% , a total crust thickness may be provided as per the pavement catalogues of IRC SP-72 -2007  The following specification has been recommended for this road section investigated under the study for the design of flexible pavement.
  • 8. TOP LAYER PREMIX CARPET WITH TYPE B SEAL COAT 20 MM BASE LAYER WBM GRADING 3 75 MM SUB BASE LAYER WBM 1 AND 2 (100+75 )MM TOTAL THICKNESS 270 MM LAYOUT OF FLEXIBLE PAVEMENT: o GSB having a compacted thickness of 100mm of CBR less than 20% o WBM GRADE 2 (63-45mm) having a single compacted layer thickness of 75 MM o For surfacing and sealing wearing course , a suitable layer of open graded mix carpet (PMC) having a compacted thickness of 20mm with seal coat provide at the top of surface for smoothness of road.
  • 9. GEOMETRIC DESIGN TERRAIN CLASSIFICATION CROSS SLOPE OF THE COUNTRY PLAIN 0-10 % More than 1 in 10 ROLLING 10-25 % 1 in 10 to 1 in 4 MOUNTAINOUS 25-60 % 1 in 4 to 1 in 1.67 STEEP >60 % < 1.67 S.N O NAME OF ROAD ROAD LENGTH (KM) ROAD CONNECTING TO LAND WIDT H ROAD WIDT H C/O 8/00 VR 7.50 5.00 JHANDURI TO NABOOWN
  • 10. ROAD CLASSIFICATION PLAIN TERRAIN ROLLING TERRAIN MOUNTAINOUS TERRAIN STEEP TERRAIN RULI NG MIN. RULI NG MIN. RULIN G MIN. RULI NG MIN RURAL ROAD 50 40 40 35 25 20 25 20 DESIGN SPEED: DESIGN SPEED (km/hr) SAFE STOPPING SIGHT DISTANCE (m) 20 20 30 30 40 45 50 60
  • 13. PAVEMENT MATERIAL MATERIAL SOURCE LEAD (KM) STONE BAROTIWALA CRUSHER SITE 37.00 STONE AGGREGATE 10MM BAROTIWALA CRUSHER SITE 37.00 STONE AGGREGATE 20MM BAROTIWALA CRUSHER SITE 37.00 STONE AGGREGATE 40MM BAROTIWALA CRUSHER SITE 37.00 BITUMEN PANIPAT 190.00 CEMENT PARWANOO 34.00 SAND BHARWALA NADI 66.00 HUME PIPE ANY OTHER TABLE:SOURCE OF PAVEMENT MATERIALS STATE-HIMACHAL PRADESH DISTRICT-SOLAN BLOCK- DHARMPUR ROAD FROM JHANDURI TO NABOWN ROAD
  • 14. DESIGN OF PAVEMENT SECTION EARTH- WORK SUBGRADE GSB WBM BASE COURSE BITUMINOUS SURFACE CROSS DRAINAGE WORK
  • 15. SUBGRADE CBR VALUE TEST RESULT UNSOAKED CBR TEST  AT 2.5mm penetration 12.5%  AT 5.0 mm penetration 14.0% SOAKED CBR TEST (AFTER 4 DAYS)  AT 2.5mm penetration 6.8%  AT 5.0 mm penetration 7.2% Sub grade soil is an integral part of the road pavement structure as it provides the support to the pavement from beneath. The sub grade soil and its properties are important in the design of pavement structure. The main function of the sub grade is to give adequate support to the pavement and for this the sub grade should possess sufficient stability under adverse climatic and loading conditions. Therefore, it is very essential to evaluate the sub grade by conducting tests. SUBRADE THICKNESS FOR RURAL ROAD=300 MM
  • 16. Descrip tion & location Identificatio n and classification Gradation analysis % age Atterberg Limit Gravel sand Fine(silt /clay) L.L % P.L % PI % Km 0/600 Generally,coar se Grained soil of group symbol GM/GC 42.8 32.8 24.4 23 20 3 Km 1/350 46.2 31.2 22.6 22 19 3 Km 2/750 43.7 31.5 24.8 24 20 4 Km 3/600 45.2 32.6 21.5 23 20 3 OMC % MDD gm 10.5 2.03 10.0 2.05 9.5 2.02 10.0 2.05
  • 17. SUPERELEVATION: ( Max. Super elevation for this project is 5.0% )
  • 18. CAMBER THIN BIYUMINOUS ROAD 3.0 % ( RAINFALL< 1000MM) 3.5 % ( RAINFALL> 1000MM)
  • 19. GSB (GRANULAR SUB BASE)  Granular sub-base (GSB) is constructed with well graded Granular Soil, maintaining suitable moisture content and compacted in layers not exceeding 100mm. Compaction is done till required density is achieved as per the design. A well finished GSB will be free from movement (under compaction equipment), ridges, cracks or loose material.  GRADATION OF GSB MATERIAL: IS SIEVE DESIGNATION % BY WEIGHT PASSING THE IS SIEVE GRADING 1 GRADING 2 GRADING 3 75MM 100 53MM 26.5 MM 55-75 50-80 100 4.75 MM 10-30 15-35 25-45 0.075 MM <10 <10 <10
  • 20. WATER BOUND MACADAM SUBBASE/BASE: Providing,laying,spreading and compacting stone aggregates of specific size to water bound macadam specification including spreading in uniform thickness,hand packing, rolling with three wheel 80-100 KN static roller in stages to proper grade and camber ,applying and brooming,stone screening /binding material to fill up the interstics of coarse agg. ,watering and compacting to the required density grading 1 as per technical specification clause 404 IS SIEVE DESPERATION % BY WEIGHT PASSING IS SIEVE GRAD. A GRAD. B GRAD. C 53 MM 100 37.5MM 97-100 100 26.5MM 97-100 100 19MM 67-81 97-100 9.5MM 56-70 67-79 4.75M 33-47 39-53 47-59 .425MM 10-19 12-21 12-21 .075MM 4-8 4-8 4-8
  • 21. BITUMINOUS SURFACE Bituminous layer is laid over the base course to ensure that rainwater does not damage the base, that moving traffic does not remove the metal and other material. The Bituminous layer also provides for dust free and comfortable riding.
  • 22. CROSS DRAINAGE STRUCTURES The pavement surface should be absolutely impermeable to prevent seepage of water into the pavement layers. Further, both the geometry and texture of pavement surface should help in draining out the water from the surface in less time. S.NO CHAINAGE (KM) DESCRIPTION OF EXISTING STRUCTURES TYPE SPAN/DIA(m) CONDITION 0/105 HUME PIPE 900 MM DIA GOOD 0/225 HUME PIPE 900 MM DIA GOOD 0/390 HUME PIPE 900 MM DIA GOOD 0/600 HUME PIPE 900 MM DIA GOOD 1/115 HUME PIPE 900 MM DIA GOOD 1/495 HUME PIPE 900 MM DIA GOOD 1/795 SLAB CULVERT 3 MTR. SPAN GOOD 1/915 HUME PIPE 900 MM DIA GOOD 1/960 HUME PIPE 900 MM DIA GOOD 2/195 HUME PIPE 900 MM DIA GOOD 2/390 HUME PIPE 900 MM DIA GOOD 2/815 HUME PIPE 900 MM DIA GOOD 3/00 SLAB CULVERT 3 MTR. SPAN GOOD LIST AND CONDITION OF EXISTING CULVERT:
  • 23. QUALITY MONITORING: Efforts are made to ensure quality of rural roads under the Pradhan Mantri Gram Sadak Yojana. Rigorous tearing for quality of material and workmanship is to be carried out on all the road works. A three-tier quality control monitoring system has been adopted for these roads. While the executive engineer or the PIU is the first tier, the second tier is an independent state level agency. As the third tier, senior technical persons are engaged as National Quality Monitor (NQMs) to inspect road works in different states. A 3-tier Quality Control System has been designed to ensure the quality of the road works. While the concerned Executive Engineer is the first tier, all the states have been requested to enlist the services of a State level independent Agency to verify the quality of the roads. On its part, the National Rural Roads Development Agency, an agency set up by the Ministry of Rural development, engages senior technical personnel as National Quality Monitors to inspect the road works.
  • 24.
  • 25.
  • 26. Logo Sign Board And Other Road Furniture  Immediately on starting the work, all the roads under the PMGSY are required to have informatory Sign Board giving the particulars of the road work as well as the name of the contractor . Road furniture like Km Stones, 200m Stones, Cautionary Signs etc. are to be provided on all roads constructed under Pradhan Mantri Gram Sadak Yojana.
  • 27.
  • 28. SPECIAL THANKS TO A PERSON WWHO MADE PMGSY COME TRUE AND TOOK INDIA TO NEXT LEVEL OF DEVELOPMENT AND CONNECTIVITY.