The Marie Reed Modernization Project provides an update on the construction progress at the Marie Reed Community Learning Center in Washington D.C. The $61.5 million project involves renovating the school, community partner spaces, and Department of Parks and Recreation areas. Current construction activities include installing fire alarms and electrical systems, framing and drywall, ceiling grid installation, and concrete work for the pool and west addition foundations. The project is scheduled for completion in Summer 2017.