Our clients, a music industry couple, approached us after seeing our successful development
of 2 houses adjoining their property
Having previously engaged the services of an architect who developed plans for the
refurbishment of the existing un modernised house on the property our clients felt increasingly
anxious about the scheme they were being recommended to pursue.
A quick desk top analysis from our team concluded that the best and correct scheme for the site would
be a brand new house. Our clients were persuaded by our vision and we set to work designing the new
house – 4,500 square feet split level contemporary detached house with indoor swimming pool
We lead the planning process and achieved permission in 9 months from a cold start.
The new house was delivered from start to finish on site in 9 months – on time and on budget.
Our clients now own a fantastic new home which benefits from considerable uplift in investment value .
P r o j e c t val u e : £ 1 . 4 5 m d e v el o p m e n t ( + l a n d c o s t o f £ 1 . 7 m )
P r o j e c t te r m : 21 M o n th s ( F r o m a p p o i n t m e n t , t h r o u g h p l a n n i n g t o h a n d o v e r )
C u r r e n t val u e : £ 4 . 5 m
01
02
03
04
05
06
07
WaughThistleton
ArchitectsLtd
74PaulStreet
LondonEC2A4NA
Telephone
+44(0)2076135727
Fax
+44(0)2076135749
email/web
waughthistleton.com
NOTES
Drawing not to be scaled. All dimensions to be verified o
site before commencing work. Any discrepencies to be
reported to designers. Read drawings in conjunction wit
relevant information. All building work is to comply with
current Building Regulations and British Standards.
STATUS
Waugharchitects
Job
Title
Date
Scale
Drawn
REV COMMENTS DATE CHK
27 HURST AVENUE
31 May 2012
RC
1-447-105E
SITE PLAN
1:200 @ A3
E Minor party wall amendments 12/4/12 RC
SITE PLAN001
Playroom
Kitchen Larder
Dining
No. 29
No. 25A
Existing pool
Shower
Changing
WC
Plant Room
Living Room
FFL +20.971
FFL +20.970
+21.440
FFL +21.440
+21.440
+19.969
+20.970
+18.995
+19.330
bin store
Sauna
D/W
L/C
+23.371
Footprint of existing house
Pool Plant
FFL +20.971
FFL +20.970
+21.440
FFL +21.440
+21.440
+19.969
+20.970
+18.995
+19.330
Studio 2
FFL +20.250
Existing end wall of house
retained - insulation and
render maintained on
no.25 side
6
B
4
3
2
1
C D EA B
5Gravel to driveway
Existing concrete steps to
be repaired /recast
Grass
Paving
Paving
Grass
Kebony decking
Decking
Pavers to stairs
Kebony decking
6
B
4
3
2
1
C D EA B
5
08
WaughThistleton
ArchitectsLtd
74PaulStreet
LondonEC2A4NA
Telephone
+44(0)2076135727
Fax
+44(0)2076135749
email/web
waughthistleton.com
NOTES
Drawing not to be scaled. All dimensions to be verified on
site before commencing work. Any discrepencies to be
reported to designers. Read drawings in conjunction with
relevant information. All building work is to comply with
current Building Regulations and British Standards.
STATUS
Waugh
Thistleton
architects
Job
Title
Date
Scale
Drawn
REV COMMENTS DATE CHK
27 HURST AVENUE
31 May 2012
MB
1-447-100D
GROUND FLOOR PLAN
1:100 @ A3
A General Design Layout and Grid Lines Revised 2/7/12
Minor amendments to layoutB 7/23/12
RWP and SVP positions addedC 8/15/12 RC
Add Gridlines, details references and labelsD 24/8/12
GROUND FLOOR PLAN001
W/M
T/D
D/W
FFL +18.995
FFL +20.250
+18.995
+18.995
+19.330
Storage
(low ceiling)
Utility
Room Cloak
Room
Studio 1
Studio 2
L/C
W/C
consumer units
Footprint of existing house
New retaining wall with
render finish to extent of
existing house
Existing fence on retaining
wall to be replaced
Condenser unit
Existing fence
Existing conifers to be protected and
maintained during construction
+23.371
6
B
4
3
2
1
C D EA B
5
DG.1
DG.2
DG.3
DG.4
DG.5
DG.6 DG.7
2000
2990
1
402
1
403
1
401
1
400
1
405
1
404
1
411
1
410
A-A
300
A-A
300
C-C
302
C-C
302
B-B
301
B-B
301
D-D
303
D-D
303
RWP
RWP
RWP
SVP
SVP
SVP
E-E
304
E-E
304
09
WaughThistleton
ArchitectsLtd
74PaulStreet
LondonEC2A4NA
Telephone
+44(0)2076135727
Fax
+44(0)2076135749
email/web
waughthistleton.com
NOTES
Drawing not to be scaled. All dimensions to be verified on
site before commencing work. Any discrepencies to be
reported to designers. Read drawings in conjunction with
relevant information. All building work is to comply with
current Building Regulations and British Standards.
STATUS
Waugharchitects
Job
Title
Date
Scale
Drawn
REV COMMENTS DATE CHK
27 HURST AVENUE
31 May 2012
MB
1-447-101D
FIRST FLOOR PLAN
1:100 @ A3
A General Design Layout and Grid Lines Revised 2/7/12
Minor amendmentsB 7/23/12
RWP and SVP positions addedC 8/15/12 RC
Add Gridlines, details references and labels.
Add external gates
D 24/8/12
FIRST FLOOR PLAN001
Playroom
Kitchen Larder
Dining
bin store
No. 29
No. 25A
Existing pool
Shower
Changing
WC
Plant Room
Living Room
FFL +20.971
FFL +20.970
+21.440
FFL +21.440
+21.440
+19.969
+20.970
+18.995
+19.330
Sauna
D/W
L/C
Studio 2
+23.371
New retaining wall
with render finish
to extent of
existing house
Footprint of existing house
6
B
4
3
2
1
C D EA B
5
Pool Plant
FFL +20.971
FFL +20.970
+21.440
FFL +21.440
+21.440
+19.969
+20.970
+18.995
+19.330
D01.1
D01.2
D01.3D01.4
D01.5
D01.6
D01.7
1
431
2
430
1
432
1
420
1
412
1
413
Water butt and air
source heat pump
enclosure
SVP
SVP
RWP
SVP
flue
RWP
RWP
RWP
SVP
RWP
RWP
A-A
300
A-A
300
C-C
302
C-C
302
B-B
301
B-B
301
D-D
303
D-D
303
E-E
304
E-E
304
10
WaughThistleton
ArchitectsLtd
74PaulStreet
LondonEC2A4NA
Telephone
+44(0)2076135727
Fax
+44(0)2076135749
email/web
waughthistleton.com
NOTES
Drawing not to be scaled. All dimensions to be verified on
site before commencing work. Any discrepencies to be
reported to designers. Read drawings in conjunction with
relevant information. All building work is to comply with
current Building Regulations and British Standards.
STATUS
Waugharchitects
Job
Title
Date
Scale
Drawn
REV COMMENTS DATE CHK
27 HURST AVENUE
31 May 2012
MB
1-447-102C
SECOND FLOOR PLAN
1:100 @ A3
A General Design Layout and Grid Lines Revised 2/7/12
Minor amendmentsB 7/23/12
Add Gridlines, details references and labelsC 24/8/12
FIRST FLOOR PLAN001
Master
Bedroom
Master Bathroom
No. 29
No. 25A
Laundry chute
low level with
MVHR unit over
Bedroom 2
Bedroom 3
En-suite En-suite
Dressing
Room
FFL +24.076
FFL +24.942
L/C
Footprint of existing house
6
B
4
3
2
1
C D EA B
5
D02.1
D02.2
D02.3
D02.4
D02.5D02.6
D02.7
1
433
1
440
1
434
Single ply membrane to
roof laid to falls under
decking to front balcony
Single ply membrane
to roof laid to falls
Green roof over single ply
membrane laid to falls
A-A
300
A-A
300
C-C
302
C-C
302
B-B
301
B-B
301
D-D
303
D-D
303
E-E
304
E-E
304
11
blissspace.co.uk

More Related Content

What's hot

Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Crosstown TO
 
Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022
Crosstown TO
 
Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...
Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...
Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...
Derek Satnik
 
Samaritans property report2
Samaritans property report2Samaritans property report2
Samaritans property report2andrew_2706
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Crosstown TO
 
Stadium Project
Stadium ProjectStadium Project
Stadium Project
lakvij
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Crosstown TO
 
Sandrine Limbourg Interior design Portfolio
Sandrine Limbourg Interior design PortfolioSandrine Limbourg Interior design Portfolio
Sandrine Limbourg Interior design Portfolio
Sandrine Limbourg
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
Building permit 2
Building permit 2Building permit 2
Building permit 2
Lumbad 1989
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Crosstown TO
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Crosstown TO
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Crosstown TO
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020
Crosstown TO
 

What's hot (20)

Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022
 
Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...
Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...
Sustainable Communities and Net-Zero Energy: Municipal Incentives That Actual...
 
Samaritans property report2
Samaritans property report2Samaritans property report2
Samaritans property report2
 
Linkeden files
Linkeden filesLinkeden files
Linkeden files
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Stadium Project
Stadium ProjectStadium Project
Stadium Project
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Sandrine Limbourg Interior design Portfolio
Sandrine Limbourg Interior design PortfolioSandrine Limbourg Interior design Portfolio
Sandrine Limbourg Interior design Portfolio
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
 
LD-EL-01 @ issue B
LD-EL-01 @ issue BLD-EL-01 @ issue B
LD-EL-01 @ issue B
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Building permit 2
Building permit 2Building permit 2
Building permit 2
 
ReHab101
ReHab101ReHab101
ReHab101
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020
 

Viewers also liked

045 киш лорен
045 киш лорен045 киш лорен
045 киш лоренCulinarium
 
PRIMITIVAS ESTÁNDAR...
PRIMITIVAS ESTÁNDAR...PRIMITIVAS ESTÁNDAR...
PRIMITIVAS ESTÁNDAR...990429
 
กิจกรรมตรวจสอบความเข้าใจ 3
กิจกรรมตรวจสอบความเข้าใจ 3กิจกรรมตรวจสอบความเข้าใจ 3
กิจกรรมตรวจสอบความเข้าใจ 3
Toongneung SP
 
Анализ инвестиционной привлекательности Handelsvertretung wehner
Анализ инвестиционной привлекательности Handelsvertretung wehnerАнализ инвестиционной привлекательности Handelsvertretung wehner
Анализ инвестиционной привлекательности Handelsvertretung wehner
mystandanna
 
Атлас муниципальных практик
Атлас муниципальных практикАтлас муниципальных практик
Атлас муниципальных практик
mystandanna
 
Атлас муниципальных практик
Атлас муниципальных практикАтлас муниципальных практик
Атлас муниципальных практик
mystandanna
 
Proyectos de aula desde un enfoque tricerebral
Proyectos de aula desde un enfoque tricerebralProyectos de aula desde un enfoque tricerebral
Proyectos de aula desde un enfoque tricerebral
Ricardo_Nieto
 
2011 deep research report on china car gps industry
2011 deep research report on china car gps industry2011 deep research report on china car gps industry
2011 deep research report on china car gps industrysmarter2011
 
กิจกรรมตรวจสอบความเข้าใจ 1
กิจกรรมตรวจสอบความเข้าใจ 1กิจกรรมตรวจสอบความเข้าใจ 1
กิจกรรมตรวจสอบความเข้าใจ 1
Toongneung SP
 
กิจกรรมตรวจสอบความเข้าใจ 4 (1)
กิจกรรมตรวจสอบความเข้าใจ 4 (1)กิจกรรมตรวจสอบความเข้าใจ 4 (1)
กิจกรรมตรวจสอบความเข้าใจ 4 (1)
Toongneung SP
 
Presentation Skills - Session One
Presentation Skills - Session OnePresentation Skills - Session One
Presentation Skills - Session One
Kevin Smith
 

Viewers also liked (12)

045 киш лорен
045 киш лорен045 киш лорен
045 киш лорен
 
PRIMITIVAS ESTÁNDAR...
PRIMITIVAS ESTÁNDAR...PRIMITIVAS ESTÁNDAR...
PRIMITIVAS ESTÁNDAR...
 
DSHS
DSHSDSHS
DSHS
 
กิจกรรมตรวจสอบความเข้าใจ 3
กิจกรรมตรวจสอบความเข้าใจ 3กิจกรรมตรวจสอบความเข้าใจ 3
กิจกรรมตรวจสอบความเข้าใจ 3
 
Анализ инвестиционной привлекательности Handelsvertretung wehner
Анализ инвестиционной привлекательности Handelsvertretung wehnerАнализ инвестиционной привлекательности Handelsvertretung wehner
Анализ инвестиционной привлекательности Handelsvertretung wehner
 
Атлас муниципальных практик
Атлас муниципальных практикАтлас муниципальных практик
Атлас муниципальных практик
 
Атлас муниципальных практик
Атлас муниципальных практикАтлас муниципальных практик
Атлас муниципальных практик
 
Proyectos de aula desde un enfoque tricerebral
Proyectos de aula desde un enfoque tricerebralProyectos de aula desde un enfoque tricerebral
Proyectos de aula desde un enfoque tricerebral
 
2011 deep research report on china car gps industry
2011 deep research report on china car gps industry2011 deep research report on china car gps industry
2011 deep research report on china car gps industry
 
กิจกรรมตรวจสอบความเข้าใจ 1
กิจกรรมตรวจสอบความเข้าใจ 1กิจกรรมตรวจสอบความเข้าใจ 1
กิจกรรมตรวจสอบความเข้าใจ 1
 
กิจกรรมตรวจสอบความเข้าใจ 4 (1)
กิจกรรมตรวจสอบความเข้าใจ 4 (1)กิจกรรมตรวจสอบความเข้าใจ 4 (1)
กิจกรรมตรวจสอบความเข้าใจ 4 (1)
 
Presentation Skills - Session One
Presentation Skills - Session OnePresentation Skills - Session One
Presentation Skills - Session One
 

Similar to 27 Hurst Ave

New Street In Colour
New Street In ColourNew Street In Colour
New Street In ColourKen Crook
 
Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Obi-Ugbo Alex
 
67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA s67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA sMike Darwich
 
Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project
MatthewSelleck1
 
QEN Portfolio CV Residential
QEN Portfolio CV ResidentialQEN Portfolio CV Residential
Andrew_Wellbelove's_CV_July_2016_ doc_a1
Andrew_Wellbelove's_CV_July_2016_ doc_a1Andrew_Wellbelove's_CV_July_2016_ doc_a1
Andrew_Wellbelove's_CV_July_2016_ doc_a1andrew wellbelove
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)kevin breiter
 
Raymond Guo 2016
Raymond Guo 2016Raymond Guo 2016
Raymond Guo 2016Raymond Guo
 
Stage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista releaseStage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista release
Providence Ripley Valley
 
DRT Portfolio Works
DRT Portfolio WorksDRT Portfolio Works
DRT Portfolio Works
Dan Rymer Trenholme
 
Dave Arkell Latest CV
Dave Arkell Latest CVDave Arkell Latest CV
Dave Arkell Latest CVDave Arkell
 
Richard bartlett 2017 july
Richard bartlett 2017 julyRichard bartlett 2017 july
Richard bartlett 2017 july
Richard Bartlett
 
Alexander_Pace_Resume2016
Alexander_Pace_Resume2016Alexander_Pace_Resume2016
Alexander_Pace_Resume2016Alexander Pace
 
Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)
DC Department of General Services
 
Stephen Burke-Design Portfolio 2015
Stephen Burke-Design Portfolio 2015Stephen Burke-Design Portfolio 2015
Stephen Burke-Design Portfolio 2015stephen burke
 
Project Charter Completed
Project Charter CompletedProject Charter Completed
Project Charter CompletedDonny Olson
 

Similar to 27 Hurst Ave (20)

New Street In Colour
New Street In ColourNew Street In Colour
New Street In Colour
 
william-second-revision (3)
william-second-revision (3)william-second-revision (3)
william-second-revision (3)
 
Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)
 
67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA s67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA s
 
william-first-revision
william-first-revisionwilliam-first-revision
william-first-revision
 
Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project
 
QEN Portfolio CV Residential
QEN Portfolio CV ResidentialQEN Portfolio CV Residential
QEN Portfolio CV Residential
 
33 Sheldon Avenue
33 Sheldon Avenue33 Sheldon Avenue
33 Sheldon Avenue
 
Andrew_Wellbelove's_CV_July_2016_ doc_a1
Andrew_Wellbelove's_CV_July_2016_ doc_a1Andrew_Wellbelove's_CV_July_2016_ doc_a1
Andrew_Wellbelove's_CV_July_2016_ doc_a1
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)
 
Raymond Guo 2016
Raymond Guo 2016Raymond Guo 2016
Raymond Guo 2016
 
Degotardi_Portfolio
Degotardi_PortfolioDegotardi_Portfolio
Degotardi_Portfolio
 
Stage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista releaseStage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista release
 
DRT Portfolio Works
DRT Portfolio WorksDRT Portfolio Works
DRT Portfolio Works
 
Dave Arkell Latest CV
Dave Arkell Latest CVDave Arkell Latest CV
Dave Arkell Latest CV
 
Richard bartlett 2017 july
Richard bartlett 2017 julyRichard bartlett 2017 july
Richard bartlett 2017 july
 
Alexander_Pace_Resume2016
Alexander_Pace_Resume2016Alexander_Pace_Resume2016
Alexander_Pace_Resume2016
 
Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)
 
Stephen Burke-Design Portfolio 2015
Stephen Burke-Design Portfolio 2015Stephen Burke-Design Portfolio 2015
Stephen Burke-Design Portfolio 2015
 
Project Charter Completed
Project Charter CompletedProject Charter Completed
Project Charter Completed
 

27 Hurst Ave

  • 1. 27 HURST AVENUE H I G H G A T E L o n d o n N 6 5 T X
  • 2. description Our clients, a music industry couple, approached us after seeing our successful development of 2 houses adjoining their property Having previously engaged the services of an architect who developed plans for the refurbishment of the existing un modernised house on the property our clients felt increasingly anxious about the scheme they were being recommended to pursue. A quick desk top analysis from our team concluded that the best and correct scheme for the site would be a brand new house. Our clients were persuaded by our vision and we set to work designing the new house – 4,500 square feet split level contemporary detached house with indoor swimming pool We lead the planning process and achieved permission in 9 months from a cold start. The new house was delivered from start to finish on site in 9 months – on time and on budget. Our clients now own a fantastic new home which benefits from considerable uplift in investment value . P r o j e c t val u e : £ 1 . 4 5 m d e v el o p m e n t ( + l a n d c o s t o f £ 1 . 7 m ) P r o j e c t te r m : 21 M o n th s ( F r o m a p p o i n t m e n t , t h r o u g h p l a n n i n g t o h a n d o v e r ) C u r r e n t val u e : £ 4 . 5 m
  • 3. 01
  • 4. 02
  • 5. 03
  • 6. 04
  • 7. 05
  • 8. 06
  • 9. 07
  • 10. WaughThistleton ArchitectsLtd 74PaulStreet LondonEC2A4NA Telephone +44(0)2076135727 Fax +44(0)2076135749 email/web waughthistleton.com NOTES Drawing not to be scaled. All dimensions to be verified o site before commencing work. Any discrepencies to be reported to designers. Read drawings in conjunction wit relevant information. All building work is to comply with current Building Regulations and British Standards. STATUS Waugharchitects Job Title Date Scale Drawn REV COMMENTS DATE CHK 27 HURST AVENUE 31 May 2012 RC 1-447-105E SITE PLAN 1:200 @ A3 E Minor party wall amendments 12/4/12 RC SITE PLAN001 Playroom Kitchen Larder Dining No. 29 No. 25A Existing pool Shower Changing WC Plant Room Living Room FFL +20.971 FFL +20.970 +21.440 FFL +21.440 +21.440 +19.969 +20.970 +18.995 +19.330 bin store Sauna D/W L/C +23.371 Footprint of existing house Pool Plant FFL +20.971 FFL +20.970 +21.440 FFL +21.440 +21.440 +19.969 +20.970 +18.995 +19.330 Studio 2 FFL +20.250 Existing end wall of house retained - insulation and render maintained on no.25 side 6 B 4 3 2 1 C D EA B 5Gravel to driveway Existing concrete steps to be repaired /recast Grass Paving Paving Grass Kebony decking Decking Pavers to stairs Kebony decking 6 B 4 3 2 1 C D EA B 5 08
  • 11. WaughThistleton ArchitectsLtd 74PaulStreet LondonEC2A4NA Telephone +44(0)2076135727 Fax +44(0)2076135749 email/web waughthistleton.com NOTES Drawing not to be scaled. All dimensions to be verified on site before commencing work. Any discrepencies to be reported to designers. Read drawings in conjunction with relevant information. All building work is to comply with current Building Regulations and British Standards. STATUS Waugh Thistleton architects Job Title Date Scale Drawn REV COMMENTS DATE CHK 27 HURST AVENUE 31 May 2012 MB 1-447-100D GROUND FLOOR PLAN 1:100 @ A3 A General Design Layout and Grid Lines Revised 2/7/12 Minor amendments to layoutB 7/23/12 RWP and SVP positions addedC 8/15/12 RC Add Gridlines, details references and labelsD 24/8/12 GROUND FLOOR PLAN001 W/M T/D D/W FFL +18.995 FFL +20.250 +18.995 +18.995 +19.330 Storage (low ceiling) Utility Room Cloak Room Studio 1 Studio 2 L/C W/C consumer units Footprint of existing house New retaining wall with render finish to extent of existing house Existing fence on retaining wall to be replaced Condenser unit Existing fence Existing conifers to be protected and maintained during construction +23.371 6 B 4 3 2 1 C D EA B 5 DG.1 DG.2 DG.3 DG.4 DG.5 DG.6 DG.7 2000 2990 1 402 1 403 1 401 1 400 1 405 1 404 1 411 1 410 A-A 300 A-A 300 C-C 302 C-C 302 B-B 301 B-B 301 D-D 303 D-D 303 RWP RWP RWP SVP SVP SVP E-E 304 E-E 304 09
  • 12. WaughThistleton ArchitectsLtd 74PaulStreet LondonEC2A4NA Telephone +44(0)2076135727 Fax +44(0)2076135749 email/web waughthistleton.com NOTES Drawing not to be scaled. All dimensions to be verified on site before commencing work. Any discrepencies to be reported to designers. Read drawings in conjunction with relevant information. All building work is to comply with current Building Regulations and British Standards. STATUS Waugharchitects Job Title Date Scale Drawn REV COMMENTS DATE CHK 27 HURST AVENUE 31 May 2012 MB 1-447-101D FIRST FLOOR PLAN 1:100 @ A3 A General Design Layout and Grid Lines Revised 2/7/12 Minor amendmentsB 7/23/12 RWP and SVP positions addedC 8/15/12 RC Add Gridlines, details references and labels. Add external gates D 24/8/12 FIRST FLOOR PLAN001 Playroom Kitchen Larder Dining bin store No. 29 No. 25A Existing pool Shower Changing WC Plant Room Living Room FFL +20.971 FFL +20.970 +21.440 FFL +21.440 +21.440 +19.969 +20.970 +18.995 +19.330 Sauna D/W L/C Studio 2 +23.371 New retaining wall with render finish to extent of existing house Footprint of existing house 6 B 4 3 2 1 C D EA B 5 Pool Plant FFL +20.971 FFL +20.970 +21.440 FFL +21.440 +21.440 +19.969 +20.970 +18.995 +19.330 D01.1 D01.2 D01.3D01.4 D01.5 D01.6 D01.7 1 431 2 430 1 432 1 420 1 412 1 413 Water butt and air source heat pump enclosure SVP SVP RWP SVP flue RWP RWP RWP SVP RWP RWP A-A 300 A-A 300 C-C 302 C-C 302 B-B 301 B-B 301 D-D 303 D-D 303 E-E 304 E-E 304 10
  • 13. WaughThistleton ArchitectsLtd 74PaulStreet LondonEC2A4NA Telephone +44(0)2076135727 Fax +44(0)2076135749 email/web waughthistleton.com NOTES Drawing not to be scaled. All dimensions to be verified on site before commencing work. Any discrepencies to be reported to designers. Read drawings in conjunction with relevant information. All building work is to comply with current Building Regulations and British Standards. STATUS Waugharchitects Job Title Date Scale Drawn REV COMMENTS DATE CHK 27 HURST AVENUE 31 May 2012 MB 1-447-102C SECOND FLOOR PLAN 1:100 @ A3 A General Design Layout and Grid Lines Revised 2/7/12 Minor amendmentsB 7/23/12 Add Gridlines, details references and labelsC 24/8/12 FIRST FLOOR PLAN001 Master Bedroom Master Bathroom No. 29 No. 25A Laundry chute low level with MVHR unit over Bedroom 2 Bedroom 3 En-suite En-suite Dressing Room FFL +24.076 FFL +24.942 L/C Footprint of existing house 6 B 4 3 2 1 C D EA B 5 D02.1 D02.2 D02.3 D02.4 D02.5D02.6 D02.7 1 433 1 440 1 434 Single ply membrane to roof laid to falls under decking to front balcony Single ply membrane to roof laid to falls Green roof over single ply membrane laid to falls A-A 300 A-A 300 C-C 302 C-C 302 B-B 301 B-B 301 D-D 303 D-D 303 E-E 304 E-E 304 11