The Marie Reed Modernization Project is renovating the Marie Reed Community Learning Center in Washington D.C. with a budget of $61.5 million. Work began in Summer 2016 and is scheduled to be completed in Summer 2017. The project includes right-sizing classrooms, installing new lighting, ceilings, flooring, data connectivity and audiovisual equipment. Current work includes electrical and fire protection installations, pouring concrete, drywall and painting, pool changing room construction, and foundation wall waterproofing. Photos show progress on the grand stair, west addition steel columns, 4th floor tile work, and painted classroom doors.