The Marie Reed Modernization Project is renovating the Marie Reed Community Learning Center in Washington, D.C. with a budget of $61.5 million. The project is currently in construction with a completion date of Summer 2017. Updates provided on March 24, 2017 include that roof work and mechanical, electrical, and plumbing rough-ins are ongoing on the top floors, drywall and painting continues on lower floors, and site work like foundation waterproofing and pile cap construction also progress. Photos show concrete formwork at the main entrance, new lights installed in corridors, and a classroom mock-up being used to gather feedback.