The West Point Club;
J Sisk Construction, Client Mr Ben Dunne;
First of nine swimming pool and health clubs for this client a 25 m X 18m pool with various
exercise rooms linked t the central poo and changing rooms.
RC pad foundations with structural steel main frame carrying gluelan beam trusses with
metal deck roof covered with tyrocal membrane. The pool is covered with a Teflin tent to
retain the heat. The HIVAC ,M&E systems and BMS are installed in a major plant room to
the rear and beneath the building.
Role site agent, reporting to contracts Manger and Client.
2 site engineers, 1 finishing foreman, direct labour sub-contractors.
Project Cost 4.5 M, Duration 8 months.
Industrial Complex ;
Oak Road off Nangor Road Dublin.
MDY Construction, Client Terry McGoff developer.
One large food processing and storage unit with designed office accommodation for a long
established renowned company . Four individual factory units with front offices and mezzanine
floor areas in the one block.
R C Pad/ strip foundation with structural steel portal frame construction , aluminium cladding and
windows colour coded with matching perimeter fence. All these buildings have a communal
enclosed loading yard.
Role Site Manager , reporting to the Contracts Director.
1 Company setting out engineer. 1 foreman. Direct labour sub-contractors.
Project Cost 2.5 M Duration 6 months.
Navan Race and Golf Course;
MDY Construction , Client, Navan Race course.
The demolition and renovation of existing buildings and the construction of a new Golf Club Building.
Traditional construction, masonry inner leaf and facing brickwork external finish. First floor construction
insitu RC. The works involved the renovation of numerous out -buildings ,the viewing stand, entrance
drive and front entrance.
Role Site Manager, reporting to Construction Director.
Project Cost 4.5 M Duration 6 months.
Mc Donald’s Mary St Dublin;
PJ Walls, Client John Keating, Keating pubs.
RC Basement construction with insitu RC construction three floors and roof shell and
core project with windows and façade stone installed . Fit out by others for Mc
Donald's.
Role Site Manager , reporting to Contracts Manager.
1 site engineer, sub-contractors.
Project Cost 1M Duration 6 months.
Saint Mary's Church Dublin;
P J Walls , Client, John Keating.
R C Basement construction under the church in the existing crypt areas, which
involved supporting the existing church as a 4 metre excavation was carried out
under and inside the existing church foundations. The existing timber columns were
temporarily supported, removed and reinstated when the basement was completed.
This was a shell and core project for this first stage and was later completed and
converted into a city centre restaurant.
Role Site Manager , reporting to contracts manager.
1 site engineer, sub-contractors.
Project Cost 1 M Duration 6 months.
Pier C Dublin Airport;
P J Walls, Client , Aer Rianta;
A six passenger bridge pier for the UK flights, waiting areas, mechanical access ways, lifts, fire exits
and plant rooms. BMS, HIVAC systems, M& E services.
RC Construction with structural steel roof, the envelop of the structure is fair faced RC to the land
side and the air side is an expanse of architectural structural glazing. Systems of operations on this
project had to conform with the Aer Rianta SH & E strategy.
Role Site Manager, reporting to Contracts Manager.
2 site engineers, 2-3 foremen, 1 safety officer, direct labour and sub- contractors.
Project Cost 15M Duration 24 months.
The offices of P J W alls;
Walls Tarmac ;
The Walls Group;
R C strip foundations, RC columns to instu RC floor 1st - 2ND floor. Masonry infill. Second floor to roof was
structural steel construction with membrane covered metal deck roof.
HIVAC and M& E systems installed on the roof level in plant rooms.
External finishes are architecturally designed imported cut stone to most facades with architectural metal
modular panels to building rear and resembles the stone facades. Window systems again relate to the stone
facades.
The highest quality internal finishes were specified and installed by the internals architect Ethena Walls.
Role Site Manager , reporting to the Walls MD.
1 site engineer, 1 foreman , 1 site clerk. Direct labour ,Sub-contractors.
Project Cost 4.5 m Duration 8 months.
DCU Multi Storey Car Park;
P J Walls, Client DCU.
RC multi storey car park consisting of 8 parking levels and an elaborate front reception area with 4
lifts and an under ground connecting tunnel to the Helix theatre.
R C construction with various wall finishes, terracotta hanging tile, stone cladding cement plaster .
Installation of a sectional pre-cast RC tunnel and reinstatement of campus roads and services.
Role Site Manager, Reporting to Contracts manager.
2 site engineers , 1 foreman, 2 site clerks, Direct labour, sub-contractors.
Project Cost 12M Duration 9 months.
Horizon Logistics Park;
P J Walls,
Three high bay industrial units including road access and parking for future units; These units were
the designed proposal for future industrial development land around Dublin Airport by Air Rianta,
now Dublin Airport Authority DAA. Two units of approximately 2000 square metres and one unit of
3500 square metres. With high ceiling levels for storage to facilitate the near-by airport.
RC pad foundation with strip foundation between stanchions, Structural steel portal frame with
insulated wall panels and roof panels . All units had docking bays the large unit with 5 No. Unit
floors were super flat fibre reinforced concrete, each unit had varying sizes of office
accommodation.
Role Site Manager, reporting Wall’s MD;
2 engineers , 1 ganger , 1 foreman. Direct Labour sub-contractors.
Project Cost 8M , Duration 8 months.
Recreation Building
Blanchardstown Institute of Technology;
Cleary and Doyle, Dublin I T .
The recreation building one of four on this new campus, housing the campus reception offices ,
campus canteen , kitchens, recreation /study rooms, a basket ball court and changing rooms.
RC foundation and support columns for the structural steel designed roof. Traditional infill masonry
for external walls and internal partitions. Architectural glazing and metal clad soffits .
Role Site Manager, reporting to Contracts Director .
2 site engineers , 1 foreman, 1 safety officer, Direct Labour and sub- contractors.
Project Cost 8M of 30M, Duration 8months.
Roe buck Hill Apartments;
Midland Construction, Client, Jennings Family.
Major basement excavation and RC construction to G/L, insitu RC construction to all floors levels
with membrane roof covering at roof. 1 No apartment block with 30 apartments and a Duplex block
20 units. Commercial shop premises a G/L.
Role Site / Project Manager, reporting to Managing Director;
1 site engineer,2 Site Foremen, 1 site clerk, sub-contractors and direct labour.
Project Cost 8M Duration 12months.
The Steelworks;
Rogersonreddan, Client Macushla Property Developments;
176 apartments in three high rise blocks, with 8 office accommodation units at G/L . One
high rise office block 6 storeys with penthouse. Lifts, fire escapes , and security systems.
Major basement excavation and construction in R C to the 1ft floor, the remaining 6-7 floors
constructed in pre-cast RC wall/ floor units . The external wall finishes were in hanging wall
tiles, pyroc /stenidoard systems or insulated plastered finishes and the roofs with a
membrane covering. Windows by specialist contractor
Role Senior Construction Manager, reporting to a Contractors Director.
2 Construction managers, 1 finishing foreman, 1 safety officer. Package Contractors;
Project Cost 50M Duration 36 months.
PRONI @ TITANIC QUARTER
Williaam Cox Ireland Ltd; Client, Harcourt Construction.
The Co ordination of design and installation for the specialist daylight façade and window systems. Including
the planning of the Williaam Cox ventilation systems to environmental controlled areas.
Role, Northern Ireland Coordinator/ Manager
Reporting to the WCIL Operations Director .
Project cost 1.2 M Euro. Duration 12 Months.

More Related Content

What's hot

Arl Project List
Arl Project ListArl Project List
Arl Project Listanthee13
 
Angelo_Hellawell_CV_January 15
Angelo_Hellawell_CV_January 15Angelo_Hellawell_CV_January 15
Angelo_Hellawell_CV_January 15Angelo Hellawell
 
Leed & Historic Tax Credit Certification
Leed & Historic Tax Credit CertificationLeed & Historic Tax Credit Certification
Leed & Historic Tax Credit Certification
Heritage Ohio
 
High-end refurbishment contractor in London.
High-end refurbishment contractor in London.High-end refurbishment contractor in London.
High-end refurbishment contractor in London.
Mariusz Gawecki
 
TJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTj Dickey
 
Joyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee
 
Multi Unit Housing.3.26.12
Multi Unit Housing.3.26.12Multi Unit Housing.3.26.12
Multi Unit Housing.3.26.12
charkins
 
Al's_Resume - Job Captain - Commercial
Al's_Resume - Job Captain - CommercialAl's_Resume - Job Captain - Commercial
Al's_Resume - Job Captain - CommercialAlfred Socias
 
Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams
 
Kbe parking structures
Kbe parking structuresKbe parking structures
Kbe parking structures
charkins
 
Gagnon Patrice new CV3 light
Gagnon Patrice new CV3 lightGagnon Patrice new CV3 light
Gagnon Patrice new CV3 lightPatrice Gagnon
 
09 flagship education projects 2012
09 flagship education projects 201209 flagship education projects 2012
09 flagship education projects 2012JerramFalkus
 
Resume - Celieto Rey Suarez
Resume - Celieto Rey SuarezResume - Celieto Rey Suarez
Resume - Celieto Rey Suarez
Celieto Rey Suarez
 
RBR Profile Aug 2013
RBR Profile Aug 2013 RBR Profile Aug 2013
RBR Profile Aug 2013 Ronan Hogan
 

What's hot (19)

Arl Project List
Arl Project ListArl Project List
Arl Project List
 
Angelo_Hellawell_CV_January 15
Angelo_Hellawell_CV_January 15Angelo_Hellawell_CV_January 15
Angelo_Hellawell_CV_January 15
 
Leed & Historic Tax Credit Certification
Leed & Historic Tax Credit CertificationLeed & Historic Tax Credit Certification
Leed & Historic Tax Credit Certification
 
High-end refurbishment contractor in London.
High-end refurbishment contractor in London.High-end refurbishment contractor in London.
High-end refurbishment contractor in London.
 
TJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTJ Dickey Resume.docx complete
TJ Dickey Resume.docx complete
 
Joyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CV
 
Multi Unit Housing.3.26.12
Multi Unit Housing.3.26.12Multi Unit Housing.3.26.12
Multi Unit Housing.3.26.12
 
CV_Rizeq 2016
CV_Rizeq 2016CV_Rizeq 2016
CV_Rizeq 2016
 
Steve Bailey CV
Steve Bailey CVSteve Bailey CV
Steve Bailey CV
 
PROJECT EXPERIENCE 2016
PROJECT EXPERIENCE 2016PROJECT EXPERIENCE 2016
PROJECT EXPERIENCE 2016
 
resume 2014
resume 2014resume 2014
resume 2014
 
Al's_Resume - Job Captain - Commercial
Al's_Resume - Job Captain - CommercialAl's_Resume - Job Captain - Commercial
Al's_Resume - Job Captain - Commercial
 
Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams Resume 2016
Ben Williams Resume 2016
 
Kbe parking structures
Kbe parking structuresKbe parking structures
Kbe parking structures
 
Gagnon Patrice new CV3 light
Gagnon Patrice new CV3 lightGagnon Patrice new CV3 light
Gagnon Patrice new CV3 light
 
09 flagship education projects 2012
09 flagship education projects 201209 flagship education projects 2012
09 flagship education projects 2012
 
Resume - Celieto Rey Suarez
Resume - Celieto Rey SuarezResume - Celieto Rey Suarez
Resume - Celieto Rey Suarez
 
Major projects
Major projectsMajor projects
Major projects
 
RBR Profile Aug 2013
RBR Profile Aug 2013 RBR Profile Aug 2013
RBR Profile Aug 2013
 

Similar to Projects presentation1

resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2john rhynold
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016Tim Read
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016Tim Read
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalChris Humphries
 
New Jersey Projects
New Jersey ProjectsNew Jersey Projects
New Jersey Projects
Gilsanz Murray Steficek
 
The Deep - Hull
The Deep -  HullThe Deep -  Hull
The Deep - Hull
Alan Wood & Partners
 
Dave Arkell Latest CV
Dave Arkell Latest CVDave Arkell Latest CV
Dave Arkell Latest CVDave Arkell
 
ProTec Recent Projects Brochure
ProTec Recent Projects BrochureProTec Recent Projects Brochure
ProTec Recent Projects BrochureSteven MacDonald
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project ReportPaul Warrington
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15Roman Rozek
 
Mark Brock Project list
Mark Brock Project listMark Brock Project list
Mark Brock Project listMark Brock
 
KBE Laboratories 2011
KBE Laboratories 2011 KBE Laboratories 2011
KBE Laboratories 2011
charkins
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
John Pattison CV 2016 for web
John Pattison CV 2016 for webJohn Pattison CV 2016 for web
John Pattison CV 2016 for webJohn Pattison
 
DRT Portfolio Works
DRT Portfolio WorksDRT Portfolio Works
DRT Portfolio Works
Dan Rymer Trenholme
 

Similar to Projects presentation1 (20)

resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2
 
Appendices
AppendicesAppendices
Appendices
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - Final
 
New Jersey Projects
New Jersey ProjectsNew Jersey Projects
New Jersey Projects
 
The Deep - Hull
The Deep -  HullThe Deep -  Hull
The Deep - Hull
 
Dave Arkell Latest CV
Dave Arkell Latest CVDave Arkell Latest CV
Dave Arkell Latest CV
 
ProTec Recent Projects Brochure
ProTec Recent Projects BrochureProTec Recent Projects Brochure
ProTec Recent Projects Brochure
 
Long Resume
Long ResumeLong Resume
Long Resume
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15
 
Mark Brock Project list
Mark Brock Project listMark Brock Project list
Mark Brock Project list
 
KBE Laboratories 2011
KBE Laboratories 2011 KBE Laboratories 2011
KBE Laboratories 2011
 
AnthonyCurrent HTR
AnthonyCurrent HTRAnthonyCurrent HTR
AnthonyCurrent HTR
 
0609_PenRen
0609_PenRen0609_PenRen
0609_PenRen
 
zk resume
zk resumezk resume
zk resume
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
John Pattison CV 2016 for web
John Pattison CV 2016 for webJohn Pattison CV 2016 for web
John Pattison CV 2016 for web
 
DRT Portfolio Works
DRT Portfolio WorksDRT Portfolio Works
DRT Portfolio Works
 

Recently uploaded

How to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and BusinessHow to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and Business
ideatoipo
 
My Story of Getting into Tech By Gertrude Chilufya Westrin
My Story of Getting into Tech By Gertrude Chilufya WestrinMy Story of Getting into Tech By Gertrude Chilufya Westrin
My Story of Getting into Tech By Gertrude Chilufya Westrin
AlinaseFaith
 
New Explore Careers and College Majors 2024.pdf
New Explore Careers and College Majors 2024.pdfNew Explore Careers and College Majors 2024.pdf
New Explore Careers and College Majors 2024.pdf
Dr. Mary Askew
 
欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】
欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】
欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】
foismail170
 
Andrea Kate Portfolio Presentation.pdf
Andrea Kate  Portfolio  Presentation.pdfAndrea Kate  Portfolio  Presentation.pdf
Andrea Kate Portfolio Presentation.pdf
andreakaterasco
 
欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】
欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】
欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】
foismail170
 
131. Reviewer Certificate in BP International
131. Reviewer Certificate in BP International131. Reviewer Certificate in BP International
131. Reviewer Certificate in BP International
Manu Mitra
 
Widal Agglutination Test: A rapid serological diagnosis of typhoid fever
Widal Agglutination Test: A rapid serological diagnosis of typhoid feverWidal Agglutination Test: A rapid serological diagnosis of typhoid fever
Widal Agglutination Test: A rapid serological diagnosis of typhoid fever
taexnic
 
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
Chapters 3  Contracts.pptx Chapters 3  Contracts.pptxChapters 3  Contracts.pptx Chapters 3  Contracts.pptx
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
Sheldon Byron
 
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
gobogo3542
 
135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering
Manu Mitra
 
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring ChapterHow Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
Hector Del Castillo, CPM, CPMM
 
The Impact of Artificial Intelligence on Modern Society.pdf
The Impact of Artificial Intelligence on Modern Society.pdfThe Impact of Artificial Intelligence on Modern Society.pdf
The Impact of Artificial Intelligence on Modern Society.pdf
ssuser3e63fc
 
Personal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignmentPersonal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignment
ragingokie
 
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdfDr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam
 
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
larisashrestha558
 
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
foismail170
 
133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research
Manu Mitra
 
DIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptxDIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptx
FarzanaRbcomcs
 
132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences
Manu Mitra
 

Recently uploaded (20)

How to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and BusinessHow to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and Business
 
My Story of Getting into Tech By Gertrude Chilufya Westrin
My Story of Getting into Tech By Gertrude Chilufya WestrinMy Story of Getting into Tech By Gertrude Chilufya Westrin
My Story of Getting into Tech By Gertrude Chilufya Westrin
 
New Explore Careers and College Majors 2024.pdf
New Explore Careers and College Majors 2024.pdfNew Explore Careers and College Majors 2024.pdf
New Explore Careers and College Majors 2024.pdf
 
欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】
欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】
欧洲杯投注app-欧洲杯投注app推荐-欧洲杯投注app| 立即访问【ac123.net】
 
Andrea Kate Portfolio Presentation.pdf
Andrea Kate  Portfolio  Presentation.pdfAndrea Kate  Portfolio  Presentation.pdf
Andrea Kate Portfolio Presentation.pdf
 
欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】
欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】
欧洲杯投注网站-欧洲杯投注网站推荐-欧洲杯投注网站| 立即访问【ac123.net】
 
131. Reviewer Certificate in BP International
131. Reviewer Certificate in BP International131. Reviewer Certificate in BP International
131. Reviewer Certificate in BP International
 
Widal Agglutination Test: A rapid serological diagnosis of typhoid fever
Widal Agglutination Test: A rapid serological diagnosis of typhoid feverWidal Agglutination Test: A rapid serological diagnosis of typhoid fever
Widal Agglutination Test: A rapid serological diagnosis of typhoid fever
 
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
Chapters 3  Contracts.pptx Chapters 3  Contracts.pptxChapters 3  Contracts.pptx Chapters 3  Contracts.pptx
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
 
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
 
135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering
 
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring ChapterHow Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
 
The Impact of Artificial Intelligence on Modern Society.pdf
The Impact of Artificial Intelligence on Modern Society.pdfThe Impact of Artificial Intelligence on Modern Society.pdf
The Impact of Artificial Intelligence on Modern Society.pdf
 
Personal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignmentPersonal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignment
 
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdfDr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
 
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
 
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
 
133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research
 
DIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptxDIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptx
 
132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences
 

Projects presentation1

  • 1. The West Point Club; J Sisk Construction, Client Mr Ben Dunne; First of nine swimming pool and health clubs for this client a 25 m X 18m pool with various exercise rooms linked t the central poo and changing rooms. RC pad foundations with structural steel main frame carrying gluelan beam trusses with metal deck roof covered with tyrocal membrane. The pool is covered with a Teflin tent to retain the heat. The HIVAC ,M&E systems and BMS are installed in a major plant room to the rear and beneath the building. Role site agent, reporting to contracts Manger and Client. 2 site engineers, 1 finishing foreman, direct labour sub-contractors. Project Cost 4.5 M, Duration 8 months.
  • 2. Industrial Complex ; Oak Road off Nangor Road Dublin. MDY Construction, Client Terry McGoff developer. One large food processing and storage unit with designed office accommodation for a long established renowned company . Four individual factory units with front offices and mezzanine floor areas in the one block. R C Pad/ strip foundation with structural steel portal frame construction , aluminium cladding and windows colour coded with matching perimeter fence. All these buildings have a communal enclosed loading yard. Role Site Manager , reporting to the Contracts Director. 1 Company setting out engineer. 1 foreman. Direct labour sub-contractors. Project Cost 2.5 M Duration 6 months.
  • 3. Navan Race and Golf Course; MDY Construction , Client, Navan Race course. The demolition and renovation of existing buildings and the construction of a new Golf Club Building. Traditional construction, masonry inner leaf and facing brickwork external finish. First floor construction insitu RC. The works involved the renovation of numerous out -buildings ,the viewing stand, entrance drive and front entrance. Role Site Manager, reporting to Construction Director. Project Cost 4.5 M Duration 6 months.
  • 4. Mc Donald’s Mary St Dublin; PJ Walls, Client John Keating, Keating pubs. RC Basement construction with insitu RC construction three floors and roof shell and core project with windows and façade stone installed . Fit out by others for Mc Donald's. Role Site Manager , reporting to Contracts Manager. 1 site engineer, sub-contractors. Project Cost 1M Duration 6 months.
  • 5. Saint Mary's Church Dublin; P J Walls , Client, John Keating. R C Basement construction under the church in the existing crypt areas, which involved supporting the existing church as a 4 metre excavation was carried out under and inside the existing church foundations. The existing timber columns were temporarily supported, removed and reinstated when the basement was completed. This was a shell and core project for this first stage and was later completed and converted into a city centre restaurant. Role Site Manager , reporting to contracts manager. 1 site engineer, sub-contractors. Project Cost 1 M Duration 6 months.
  • 6. Pier C Dublin Airport; P J Walls, Client , Aer Rianta; A six passenger bridge pier for the UK flights, waiting areas, mechanical access ways, lifts, fire exits and plant rooms. BMS, HIVAC systems, M& E services. RC Construction with structural steel roof, the envelop of the structure is fair faced RC to the land side and the air side is an expanse of architectural structural glazing. Systems of operations on this project had to conform with the Aer Rianta SH & E strategy. Role Site Manager, reporting to Contracts Manager. 2 site engineers, 2-3 foremen, 1 safety officer, direct labour and sub- contractors. Project Cost 15M Duration 24 months.
  • 7. The offices of P J W alls; Walls Tarmac ; The Walls Group; R C strip foundations, RC columns to instu RC floor 1st - 2ND floor. Masonry infill. Second floor to roof was structural steel construction with membrane covered metal deck roof. HIVAC and M& E systems installed on the roof level in plant rooms. External finishes are architecturally designed imported cut stone to most facades with architectural metal modular panels to building rear and resembles the stone facades. Window systems again relate to the stone facades. The highest quality internal finishes were specified and installed by the internals architect Ethena Walls. Role Site Manager , reporting to the Walls MD. 1 site engineer, 1 foreman , 1 site clerk. Direct labour ,Sub-contractors. Project Cost 4.5 m Duration 8 months.
  • 8. DCU Multi Storey Car Park; P J Walls, Client DCU. RC multi storey car park consisting of 8 parking levels and an elaborate front reception area with 4 lifts and an under ground connecting tunnel to the Helix theatre. R C construction with various wall finishes, terracotta hanging tile, stone cladding cement plaster . Installation of a sectional pre-cast RC tunnel and reinstatement of campus roads and services. Role Site Manager, Reporting to Contracts manager. 2 site engineers , 1 foreman, 2 site clerks, Direct labour, sub-contractors. Project Cost 12M Duration 9 months.
  • 9. Horizon Logistics Park; P J Walls, Three high bay industrial units including road access and parking for future units; These units were the designed proposal for future industrial development land around Dublin Airport by Air Rianta, now Dublin Airport Authority DAA. Two units of approximately 2000 square metres and one unit of 3500 square metres. With high ceiling levels for storage to facilitate the near-by airport. RC pad foundation with strip foundation between stanchions, Structural steel portal frame with insulated wall panels and roof panels . All units had docking bays the large unit with 5 No. Unit floors were super flat fibre reinforced concrete, each unit had varying sizes of office accommodation. Role Site Manager, reporting Wall’s MD; 2 engineers , 1 ganger , 1 foreman. Direct Labour sub-contractors. Project Cost 8M , Duration 8 months.
  • 10. Recreation Building Blanchardstown Institute of Technology; Cleary and Doyle, Dublin I T . The recreation building one of four on this new campus, housing the campus reception offices , campus canteen , kitchens, recreation /study rooms, a basket ball court and changing rooms. RC foundation and support columns for the structural steel designed roof. Traditional infill masonry for external walls and internal partitions. Architectural glazing and metal clad soffits . Role Site Manager, reporting to Contracts Director . 2 site engineers , 1 foreman, 1 safety officer, Direct Labour and sub- contractors. Project Cost 8M of 30M, Duration 8months.
  • 11. Roe buck Hill Apartments; Midland Construction, Client, Jennings Family. Major basement excavation and RC construction to G/L, insitu RC construction to all floors levels with membrane roof covering at roof. 1 No apartment block with 30 apartments and a Duplex block 20 units. Commercial shop premises a G/L. Role Site / Project Manager, reporting to Managing Director; 1 site engineer,2 Site Foremen, 1 site clerk, sub-contractors and direct labour. Project Cost 8M Duration 12months.
  • 12. The Steelworks; Rogersonreddan, Client Macushla Property Developments; 176 apartments in three high rise blocks, with 8 office accommodation units at G/L . One high rise office block 6 storeys with penthouse. Lifts, fire escapes , and security systems. Major basement excavation and construction in R C to the 1ft floor, the remaining 6-7 floors constructed in pre-cast RC wall/ floor units . The external wall finishes were in hanging wall tiles, pyroc /stenidoard systems or insulated plastered finishes and the roofs with a membrane covering. Windows by specialist contractor Role Senior Construction Manager, reporting to a Contractors Director. 2 Construction managers, 1 finishing foreman, 1 safety officer. Package Contractors; Project Cost 50M Duration 36 months.
  • 13. PRONI @ TITANIC QUARTER Williaam Cox Ireland Ltd; Client, Harcourt Construction. The Co ordination of design and installation for the specialist daylight façade and window systems. Including the planning of the Williaam Cox ventilation systems to environmental controlled areas. Role, Northern Ireland Coordinator/ Manager Reporting to the WCIL Operations Director . Project cost 1.2 M Euro. Duration 12 Months.