Guildford High School Recital Hall
Project Address: Guildford High School, Nightingale Road, Guildford, Surrey
Client Name: United Church School Foundation Limited
Contract Name: Construction of new Recital Hall
Contract Awarded: November 2014
Contract Duration: 68 Weeks
Contract Value: £4,000,000.00
Type of Contract: JCT Standard Building Contract, 2011 Edition, Without Quantities
Contract Administrator: Synergy
Architects: Franklin Ellis LLP
Client Contact: Mr Graham Harvey Browne
Project Description
Construction of a new Recital Hall including external finishes and connections to existing building.
The building will become a focal point for the school, which will be holding many events in this
state of the art facility.
Key items on this project:
• Substantial concrete mass pour foundations
• Steel frame
• Caltite waterproof concrete slabs and upstands
• Concrete stairs
• Composite metal decking
• Complete lift installation
• Large curtain walling package
• Full mechanical and electrical installations
• In depth acoustic designs
• Brickwork package with a vast amount of detailing
Challenges overcome
Occupied site
The school is fully operational and overlooks the site on three elevations. This has required a very
proactive approach from Ash, working very closely with the design team and the school, to
understand their operations in order to plan accordingly to mitigate disruption and ensure the
safety of the students, staff and general public. Programming key packages such as the steel
frame erection to happen during school holiday periods has been key to the success of the project.
We continue to work with the design team and the school with regular board and design meetings,
but most importantly at site level the site agent and contracts manager have been key to
maintaining programme while at the same time causing minimal disruption to the school.
Caltite concrete works
A great amount of time has been spent selecting the correct waterproofing system for the project
and the final decision was to go with a Caltite Concrete slab in conjunction with a cementitious
tanking. The Slab contained over 30 tonne of steelwork that all had to be installed and inspected
by the Cementaid representatives as did the concrete pours to ensure compliance with their
details in order to satisfy their conditions before issuing a warranty. To make sure this critical
element of the project was done correctly we worked with a specialist concrete contractor and the
slabs and upstands have all been installed without incident.
Lift and stair install
Just before the steel frame was installed the client changed the specification on the lift, which
resulted in a reprograming of the stairwell as well as alterations to steel members and the lift pit.
The knock-on effect was the composite decking and stairs could not been installed in conjunction
with the steel frame resulting in additional crane visits that had to be managed to maintain the
safety of the students, staff and general public. The stairs have now been successfully installed as
well as the lift pit slab.
We continue to work with the design team and the school in order to complete this project on time
and within budget. Internal finishings are now well progressed and we are on target for a
completion date of 6th
May 2016.
Recital Hall
Guildford High School
Guildford High School

More Related Content

What's hot

Articles & Features
Articles & FeaturesArticles & Features
Articles & FeaturesDaniel Allen
 
Fall Open House: Mount Dennis - Caledonia
Fall Open House: Mount Dennis - CaledoniaFall Open House: Mount Dennis - Caledonia
Fall Open House: Mount Dennis - CaledoniaCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Evermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement ProjectEvermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement ProjectFairfax County
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCrosstown TO
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Crosstown TO
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014Crosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2David Matthew
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Resume_Jonathan-Iley_GetHired
Resume_Jonathan-Iley_GetHiredResume_Jonathan-Iley_GetHired
Resume_Jonathan-Iley_GetHiredJonathan Iley
 
UWP Consulting studios on park modular contruction
UWP Consulting studios on park modular contructionUWP Consulting studios on park modular contruction
UWP Consulting studios on park modular contructionUWP Consulting
 
Agilia dist v1
Agilia dist v1Agilia dist v1
Agilia dist v1gunalan7
 
Rehabilitation of a Parking Garage in Downtown Milwaukee, WI
 Rehabilitation of a Parking Garage in Downtown Milwaukee, WI Rehabilitation of a Parking Garage in Downtown Milwaukee, WI
Rehabilitation of a Parking Garage in Downtown Milwaukee, WIPostTensioningInstitute
 

What's hot (20)

Articles & Features
Articles & FeaturesArticles & Features
Articles & Features
 
Fall Open House: Mount Dennis - Caledonia
Fall Open House: Mount Dennis - CaledoniaFall Open House: Mount Dennis - Caledonia
Fall Open House: Mount Dennis - Caledonia
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Evermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement ProjectEvermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement Project
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank Station
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Presentation 2016
Presentation 2016Presentation 2016
Presentation 2016
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2
 
Daniel-Brady
Daniel-BradyDaniel-Brady
Daniel-Brady
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Resume_Jonathan-Iley_GetHired
Resume_Jonathan-Iley_GetHiredResume_Jonathan-Iley_GetHired
Resume_Jonathan-Iley_GetHired
 
UWP Consulting studios on park modular contruction
UWP Consulting studios on park modular contructionUWP Consulting studios on park modular contruction
UWP Consulting studios on park modular contruction
 
Agilia dist v1
Agilia dist v1Agilia dist v1
Agilia dist v1
 
Rehabilitation of a Parking Garage in Downtown Milwaukee, WI
 Rehabilitation of a Parking Garage in Downtown Milwaukee, WI Rehabilitation of a Parking Garage in Downtown Milwaukee, WI
Rehabilitation of a Parking Garage in Downtown Milwaukee, WI
 

Similar to Guildford High School

ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016Steve Edgson
 
Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial worksgrahamelanders
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
SIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGSIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGWilliam Wieners
 
number 1. pro cv
number 1. pro cvnumber 1. pro cv
number 1. pro cvDave Chase
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalChris Humphries
 
8. Stakeholder Presentation.pptx
8. Stakeholder Presentation.pptx8. Stakeholder Presentation.pptx
8. Stakeholder Presentation.pptxssuser6e7da0
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentationKunal Gudwani
 
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesNo 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesCSR Consultant and Associates
 
Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015Hal Forsyth
 
SCS -SOQ January 2015 II
SCS -SOQ January 2015 IISCS -SOQ January 2015 II
SCS -SOQ January 2015 IIHal Forsyth
 
Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)DC Department of General Services
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...DougDos
 

Similar to Guildford High School (20)

Steve Bailey CV
Steve Bailey CVSteve Bailey CV
Steve Bailey CV
 
Resume -Amarnath
Resume -AmarnathResume -Amarnath
Resume -Amarnath
 
Resume -Amarnath
Resume -AmarnathResume -Amarnath
Resume -Amarnath
 
ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2
 
ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016
 
Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial works
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
SIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGSIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERING
 
number 1. pro cv
number 1. pro cvnumber 1. pro cv
number 1. pro cv
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - Final
 
8. Stakeholder Presentation.pptx
8. Stakeholder Presentation.pptx8. Stakeholder Presentation.pptx
8. Stakeholder Presentation.pptx
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesNo 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
 
Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015
 
SCS -SOQ January 2015 II
SCS -SOQ January 2015 IISCS -SOQ January 2015 II
SCS -SOQ January 2015 II
 
AH15019
AH15019AH15019
AH15019
 
Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)Marie Reed Elementary School Construction Project Update (March 24, 2017)
Marie Reed Elementary School Construction Project Update (March 24, 2017)
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
Barwin profile
Barwin profileBarwin profile
Barwin profile
 

Guildford High School

  • 1. Guildford High School Recital Hall Project Address: Guildford High School, Nightingale Road, Guildford, Surrey Client Name: United Church School Foundation Limited Contract Name: Construction of new Recital Hall Contract Awarded: November 2014 Contract Duration: 68 Weeks Contract Value: £4,000,000.00 Type of Contract: JCT Standard Building Contract, 2011 Edition, Without Quantities Contract Administrator: Synergy Architects: Franklin Ellis LLP Client Contact: Mr Graham Harvey Browne Project Description Construction of a new Recital Hall including external finishes and connections to existing building. The building will become a focal point for the school, which will be holding many events in this state of the art facility. Key items on this project: • Substantial concrete mass pour foundations • Steel frame
  • 2. • Caltite waterproof concrete slabs and upstands • Concrete stairs • Composite metal decking • Complete lift installation • Large curtain walling package • Full mechanical and electrical installations • In depth acoustic designs • Brickwork package with a vast amount of detailing Challenges overcome Occupied site The school is fully operational and overlooks the site on three elevations. This has required a very proactive approach from Ash, working very closely with the design team and the school, to understand their operations in order to plan accordingly to mitigate disruption and ensure the safety of the students, staff and general public. Programming key packages such as the steel frame erection to happen during school holiday periods has been key to the success of the project. We continue to work with the design team and the school with regular board and design meetings, but most importantly at site level the site agent and contracts manager have been key to maintaining programme while at the same time causing minimal disruption to the school.
  • 3. Caltite concrete works A great amount of time has been spent selecting the correct waterproofing system for the project and the final decision was to go with a Caltite Concrete slab in conjunction with a cementitious tanking. The Slab contained over 30 tonne of steelwork that all had to be installed and inspected by the Cementaid representatives as did the concrete pours to ensure compliance with their details in order to satisfy their conditions before issuing a warranty. To make sure this critical element of the project was done correctly we worked with a specialist concrete contractor and the slabs and upstands have all been installed without incident.
  • 4. Lift and stair install Just before the steel frame was installed the client changed the specification on the lift, which resulted in a reprograming of the stairwell as well as alterations to steel members and the lift pit. The knock-on effect was the composite decking and stairs could not been installed in conjunction with the steel frame resulting in additional crane visits that had to be managed to maintain the safety of the students, staff and general public. The stairs have now been successfully installed as well as the lift pit slab.
  • 5. We continue to work with the design team and the school in order to complete this project on time and within budget. Internal finishings are now well progressed and we are on target for a completion date of 6th May 2016.