SlideShare a Scribd company logo
1 of 12
JONA S, IZAAKS C, KEENDAWALA JGROUP 10
Content
 What is the Location-Time Diagram?
 Advantages of Location-time Diagram
 Disadvantages of Location-time Diagram
 Example
 Similarities
 Conclusion
 References
1.What is the Location-Time
Diagram?
 Is also known as Time-Chainage diagrams, is a c
ombination of the bar chart and line-of-balance s
cheduling formats .
 method of graphically presenting a time schedul
e for all types of longitudinal projects such as :
 Pipelines
 Railways
 Bridges
 Tunnels
 Road
What is the Location-Time
Diagram?...
 Activities in location-time diagrams are displayed
both along a time axis and along a distance axis
according to their relative linear position.
 It shows not only the location of the activity but al
so the direction of progress and the progress rat
e.
 Activities can be presented as geometrical shape
s showing the occupation of the work site over ti
me such that conflicting access can be detected
visually.
2. Advantages of Location-Time
Diagram
When Constructing
 Roads
 Railways
 Pipelines
 Tunnels
 Transmission Lines
 Bridges
Advantages of Location-Time
Diagram...
 Clearly communicate the scope by showing the p
roject details and the schedule in one view.
Easy to know :
 The order of activities or operations
 Where activities are happening locationally
 How activities must progress in relation to
direction and distance
 Time, key dates and holidays, etc.
3.Disadvantages of Location-Time
Diagram
 It does not retain the logical relationship among a
ctivities, so both planning and updating are very
difficult in cases of large project.
 Time consuming to produce and a good deal of p
ractice is required to get them right.
 Can be costly to rearrange the existing layout an
d not very robust to disruption.
 Critical path and float is only apparent through vi
sual interpretation.
Activities
 Program activities and Duration
Activities Duration (week)
Set up site 4
Activity 1 4
Activity 2 6
Activity 3 4
Activity 4 3
Activity 5 5
Activity 6 5
Holiday
Offices for contractor and engineer
Excavation
Construction of SSG
Construction of Culvert
Drainage
Construction of Sub-Base
Construction of Base
LOCATION-TIME DIAGRAM
5.SIMILARITIES
 all clearly depict time and sequence
 Applied to repetitive project ,except the bar char
t
 Good pictorial presentation of construction sequ
ences
 Indicate the progress
6.CONCLUSION
 Location time diagram is more superior to the
other two scheduling methods or tools
7.REFERENCES
 Cook,B & Williams,P.(2009). Construction plan
ning programming and control (3rd ed.). Singap
ore: john Wiley & Sons ltd.
 Peter, M, P. (2014). Time chainage: what is tim
e chainage. Retrieved from: http://www.timech
ainage.co.uk/principles.html

More Related Content

What's hot

Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract Venuri Lakshani
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction Thanigaivel Asokan
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project managementMC Tubera
 
Construction difficulties
Construction difficultiesConstruction difficulties
Construction difficultiesNahid0521
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge Kundan Sanap
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development ProcessDuncan Smith
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
Project management
Project managementProject management
Project managementAidiel Azhar
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryAkshika Mahanama
 
Trabajo nº 11 minaya chinga carlos - anaisis cronologico de los estilos arq...
Trabajo nº 11   minaya chinga carlos - anaisis cronologico de los estilos arq...Trabajo nº 11   minaya chinga carlos - anaisis cronologico de los estilos arq...
Trabajo nº 11 minaya chinga carlos - anaisis cronologico de los estilos arq...Julio Enrique Figueroa vilchez
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”Ary Jamil
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 

What's hot (20)

Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
 
Construction process
Construction processConstruction process
Construction process
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Construction difficulties
Construction difficultiesConstruction difficulties
Construction difficulties
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development Process
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project management
Project managementProject management
Project management
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
Trabajo nº 11 minaya chinga carlos - anaisis cronologico de los estilos arq...
Trabajo nº 11   minaya chinga carlos - anaisis cronologico de los estilos arq...Trabajo nº 11   minaya chinga carlos - anaisis cronologico de los estilos arq...
Trabajo nº 11 minaya chinga carlos - anaisis cronologico de los estilos arq...
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 

Viewers also liked

ADF DVT Speed Dating - Meeting the Gantt Charts
ADF DVT Speed Dating - Meeting the Gantt ChartsADF DVT Speed Dating - Meeting the Gantt Charts
ADF DVT Speed Dating - Meeting the Gantt ChartsLucas Jellema
 
VILLAGE 1 STORM SEWER 0401 - 0411
VILLAGE 1 STORM SEWER 0401 - 0411VILLAGE 1 STORM SEWER 0401 - 0411
VILLAGE 1 STORM SEWER 0401 - 0411Noel Carroll
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction ExplainedDavid H Moloney
 
2.horizontal curves
2.horizontal curves2.horizontal curves
2.horizontal curvesfenta dejene
 
Systemes constructifs
Systemes constructifsSystemes constructifs
Systemes constructifsArchi Guelma
 
Topic 4 curve lesson 2
Topic 4   curve lesson 2Topic 4   curve lesson 2
Topic 4 curve lesson 2kmasz kamal
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Horizontal curves pdf
Horizontal curves pdfHorizontal curves pdf
Horizontal curves pdfKaila Turla
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chartdanishrafiq
 

Viewers also liked (10)

ADF DVT Speed Dating - Meeting the Gantt Charts
ADF DVT Speed Dating - Meeting the Gantt ChartsADF DVT Speed Dating - Meeting the Gantt Charts
ADF DVT Speed Dating - Meeting the Gantt Charts
 
VILLAGE 1 STORM SEWER 0401 - 0411
VILLAGE 1 STORM SEWER 0401 - 0411VILLAGE 1 STORM SEWER 0401 - 0411
VILLAGE 1 STORM SEWER 0401 - 0411
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction Explained
 
2.horizontal curves
2.horizontal curves2.horizontal curves
2.horizontal curves
 
Systemes constructifs
Systemes constructifsSystemes constructifs
Systemes constructifs
 
Topic 4 curve lesson 2
Topic 4   curve lesson 2Topic 4   curve lesson 2
Topic 4 curve lesson 2
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Horizontal curves pdf
Horizontal curves pdfHorizontal curves pdf
Horizontal curves pdf
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 

Similar to Location time diagram

TILOS: World Pipelines Article
TILOS: World Pipelines ArticleTILOS: World Pipelines Article
TILOS: World Pipelines ArticleCisco
 
Bar Graph Method in Engineering management
Bar Graph Method in Engineering management Bar Graph Method in Engineering management
Bar Graph Method in Engineering management Nzar Braim
 
Using TILOS in Pipelines
Using TILOS  in PipelinesUsing TILOS  in Pipelines
Using TILOS in PipelinesLorne Duncan
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptxPigPug1
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.pptMdHelalHossain6
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Surajkumar Sonar
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Basics Planning PERT.ppt
Basics Planning PERT.pptBasics Planning PERT.ppt
Basics Planning PERT.pptKAhmedRehman
 
Chapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptChapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptJastienAndreanaYaran
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingIJERA Editor
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
Week 10 - 22W Students.pdf
Week 10 - 22W Students.pdfWeek 10 - 22W Students.pdf
Week 10 - 22W Students.pdfAnshulAggarwal94
 

Similar to Location time diagram (20)

TILOS: World Pipelines Article
TILOS: World Pipelines ArticleTILOS: World Pipelines Article
TILOS: World Pipelines Article
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 
S curve1
S curve1S curve1
S curve1
 
S curve1
S curve1S curve1
S curve1
 
Bar Graph Method in Engineering management
Bar Graph Method in Engineering management Bar Graph Method in Engineering management
Bar Graph Method in Engineering management
 
Using TILOS in Pipelines
Using TILOS  in PipelinesUsing TILOS  in Pipelines
Using TILOS in Pipelines
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptx
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Basics Planning PERT.ppt
Basics Planning PERT.pptBasics Planning PERT.ppt
Basics Planning PERT.ppt
 
Chapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptChapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.ppt
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise Building
 
Unit 1
Unit 1Unit 1
Unit 1
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Week 10 - 22W Students.pdf
Week 10 - 22W Students.pdfWeek 10 - 22W Students.pdf
Week 10 - 22W Students.pdf
 

Recently uploaded

Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 

Recently uploaded (20)

Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 

Location time diagram

  • 1. JONA S, IZAAKS C, KEENDAWALA JGROUP 10
  • 2. Content  What is the Location-Time Diagram?  Advantages of Location-time Diagram  Disadvantages of Location-time Diagram  Example  Similarities  Conclusion  References
  • 3. 1.What is the Location-Time Diagram?  Is also known as Time-Chainage diagrams, is a c ombination of the bar chart and line-of-balance s cheduling formats .  method of graphically presenting a time schedul e for all types of longitudinal projects such as :  Pipelines  Railways  Bridges  Tunnels  Road
  • 4. What is the Location-Time Diagram?...  Activities in location-time diagrams are displayed both along a time axis and along a distance axis according to their relative linear position.  It shows not only the location of the activity but al so the direction of progress and the progress rat e.  Activities can be presented as geometrical shape s showing the occupation of the work site over ti me such that conflicting access can be detected visually.
  • 5. 2. Advantages of Location-Time Diagram When Constructing  Roads  Railways  Pipelines  Tunnels  Transmission Lines  Bridges
  • 6. Advantages of Location-Time Diagram...  Clearly communicate the scope by showing the p roject details and the schedule in one view. Easy to know :  The order of activities or operations  Where activities are happening locationally  How activities must progress in relation to direction and distance  Time, key dates and holidays, etc.
  • 7. 3.Disadvantages of Location-Time Diagram  It does not retain the logical relationship among a ctivities, so both planning and updating are very difficult in cases of large project.  Time consuming to produce and a good deal of p ractice is required to get them right.  Can be costly to rearrange the existing layout an d not very robust to disruption.  Critical path and float is only apparent through vi sual interpretation.
  • 8. Activities  Program activities and Duration Activities Duration (week) Set up site 4 Activity 1 4 Activity 2 6 Activity 3 4 Activity 4 3 Activity 5 5 Activity 6 5 Holiday Offices for contractor and engineer Excavation Construction of SSG Construction of Culvert Drainage Construction of Sub-Base Construction of Base
  • 10. 5.SIMILARITIES  all clearly depict time and sequence  Applied to repetitive project ,except the bar char t  Good pictorial presentation of construction sequ ences  Indicate the progress
  • 11. 6.CONCLUSION  Location time diagram is more superior to the other two scheduling methods or tools
  • 12. 7.REFERENCES  Cook,B & Williams,P.(2009). Construction plan ning programming and control (3rd ed.). Singap ore: john Wiley & Sons ltd.  Peter, M, P. (2014). Time chainage: what is tim e chainage. Retrieved from: http://www.timech ainage.co.uk/principles.html