2. Content
What is the Location-Time Diagram?
Advantages of Location-time Diagram
Disadvantages of Location-time Diagram
Example
Similarities
Conclusion
References
3. 1.What is the Location-Time
Diagram?
Is also known as Time-Chainage diagrams, is a c
ombination of the bar chart and line-of-balance s
cheduling formats .
method of graphically presenting a time schedul
e for all types of longitudinal projects such as :
Pipelines
Railways
Bridges
Tunnels
Road
4. What is the Location-Time
Diagram?...
Activities in location-time diagrams are displayed
both along a time axis and along a distance axis
according to their relative linear position.
It shows not only the location of the activity but al
so the direction of progress and the progress rat
e.
Activities can be presented as geometrical shape
s showing the occupation of the work site over ti
me such that conflicting access can be detected
visually.
6. Advantages of Location-Time
Diagram...
Clearly communicate the scope by showing the p
roject details and the schedule in one view.
Easy to know :
The order of activities or operations
Where activities are happening locationally
How activities must progress in relation to
direction and distance
Time, key dates and holidays, etc.
7. 3.Disadvantages of Location-Time
Diagram
It does not retain the logical relationship among a
ctivities, so both planning and updating are very
difficult in cases of large project.
Time consuming to produce and a good deal of p
ractice is required to get them right.
Can be costly to rearrange the existing layout an
d not very robust to disruption.
Critical path and float is only apparent through vi
sual interpretation.
8. Activities
Program activities and Duration
Activities Duration (week)
Set up site 4
Activity 1 4
Activity 2 6
Activity 3 4
Activity 4 3
Activity 5 5
Activity 6 5
Holiday
Offices for contractor and engineer
Excavation
Construction of SSG
Construction of Culvert
Drainage
Construction of Sub-Base
Construction of Base
10. 5.SIMILARITIES
all clearly depict time and sequence
Applied to repetitive project ,except the bar char
t
Good pictorial presentation of construction sequ
ences
Indicate the progress
12. 7.REFERENCES
Cook,B & Williams,P.(2009). Construction plan
ning programming and control (3rd ed.). Singap
ore: john Wiley & Sons ltd.
Peter, M, P. (2014). Time chainage: what is tim
e chainage. Retrieved from: http://www.timech
ainage.co.uk/principles.html