SlideShare a Scribd company logo
1 of 15
Download to read offline
Bar Graph Method
Student Name: Nzar Braim Omar
Class: 4th
stage
Course Title: Engineering Economy and Management
Department: Geomatics (Surveying)
College of Engineering
Salahaddin University-Erbil
Academic Year 2019-2020
2
Abstract
The main explanation of this report of Bar Graph Method in terms of
schedule and constriction planning.
The time allowed for Bar graph Schedule performance is usually an
important consideration for both the project owner and the project contractor.
I'm explained the good side of Bar Graph Method in terms of ( Clarity,
Communication ,Motivation, Coordination, Creativity, Time Management
Flexibility , Manageability ,Efficiency, Accountability ) and I've talked
about the downside .
I brought up an example that supports Bar Graph Method which is used in
Kurdistan Region, name of example is (Quantity Estimation and Bar
Graph Schedule for the Project of 150 m Road- Erbil City).
3
Table of Contents
Subject page
Abstract..........................................................................................................2
Table of Contents ..........................................................................................3
Introduction ...................................................................................................4
Methods.........................................................................................................6
Advantage of Bar Graph Method..................................................................9
Disadvantage of Bar Graph Method ...........................................................10
Prepared Bar Graph.....................................................................................11
Bar graph Schedule of 150 m road in Erbil.................................................12
Conclusion...................................................................................................14
References ...................................................................................................15
4
Introduction
Bar Graph or Bar Chart Schedule is a graphical schedule relating the
progress of items of work to a schedule, the bar schedule traces it is origin to
a chart developed by Henry L.Grant.
Generally before establishing the contract of any project, the bar graph
schedule must be made for the project and each project consists of more than
one activity means several activities, actually there is no open time for any
project that means any project in the world will be establish on fixed time
therefore the project must be finish in desired time because time is very
important and one of the most important factors that effect on the budget of
the project, so bar graph schedule play a vital role as a guide chart for (project
manager, contractor, and engineers, …), and the bar graph schedule is used
to determine the duration of performance of each activity of the project and
also used to show the starting time and end time of each activities that means
the sequence of the project, because each activity must be finish in proposed
duration and any delay of each activities will effect on the execution of the
project in proposed time, so by delay in any activity the contractor or project
manager must be increase the number of teams, equipment, and hours of
working(morning and evening), and efforts but in logical way…, because
generally any delay in duration of construction of the project will cause that
the contractor should pay money due to the delay in the proposed time of the
project, and in the procedure of making bar graph schedule, we have quantity
estimation of materials(i.e. earthwork, concrete, subbase, subgrade, and
asphalt), therefore we must calculate the quantity of materials in accurate
ways to make a precise bar graph schedule.
Cumulative Project Progress show in figure (2), a cumulative progress-
versus time curve for the bar graph.
5
The vertical scale represents cumulative project progress in percent and the
horizontal scale indicates time. Once the bar graph schedule has been
prepared and weighting factors calculated for each activity, scheduled
cumulative progress can be calculated and plotted.
6
Methods
A bar graph or bar chart schedule is a graphical schedule relating the
progress of items of work to a schedule. The bar schedule traces its origin
to a chart developed by Henry L.Grant. A simple bar graph schedule for a
construction project is shown in figure (1).
1 2 3 4 5 6 7 8
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
Total 5100
Excavation
Cut and fill
2000 39.37
Establish site 1000 19.61
Enbankment 1500 29.93
Concrete cut-
off
500 9.12
Grout cut-off 100 1.95
HoursActivity
Weight
%
Weeks
50 100
100
100
100
100
100
100
100
906030
654015
50
50
8040
6535
9085603520
755025
90
80
70
60
50
40
30
20
10
0
0
0
100
The major work items, or activities, making up the project are listed on the
left side of the schedule with a time scale across the top. The column headed
"Hours" indicates the estimated number of labor-hours required for each
activity. The column headed "Weight" indicates the portion of the total
project effort accounted for by each activity. For example "Clearing and
stripping" requires 1000 labor-hours of work, which represents 19.63 % of
Figure 1: Bar Graph Schedule for construction Project.
Construction Progress Chart
Project Rode 120 m
Date 7/4/2014
7
the 5100 labor-hours required for the entire project. While a weighting
column is not always present on a bar chart, its presence is very useful when
calculating cumulative project progress. Activities may be weighted on any
desired basis.
Notice that two horizontal blocks are provided opposite each activity. The
upper block (SCH) represents scheduled progress and the lower block
(ACT) is used to record actual progress as worked proceeds. For each block,
a bar extends from starting to ending times division. Again such a system
considerably simplifies the calculation of scheduled cumulative progress
and its comparison with actual progress. To aid in the evaluation of progress,
it is suggested that the actual progress of each activity be inserted at the end
of each major period.
To find weight using the question as follow:
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑜𝑛𝑒 𝑡𝑎𝑠𝑘 (%) =
ℎ𝑜𝑢𝑟 𝑜𝑓 𝑜𝑛𝑒 𝑡𝑎𝑠𝑘
∑ ℎ𝑜𝑢𝑟
× 100 (1)
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑜𝑛𝑒 𝑡𝑎𝑠𝑘 (%) =
1000
5100
× 100 = 19.61%
𝐶𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝑝𝑟𝑜𝑔𝑟𝑒𝑠𝑠 = ∑(𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑝𝑟𝑜𝑔𝑟𝑒𝑠𝑠) 𝑖 x
𝑛
𝑖=1
(𝑊𝑒𝑖𝑔ℎ𝑡)𝑖 (2)
For example: for activating the Second week of Schedule as follow:
Activity 2 week = (1x19.61) + (0.25x 39.37) = 29.45%
This mean activity second of week 29.45% complete.
8
We have calculate all activity for the end of weeks for schedule (Planned)
and Actual in Table (1) as follow:
All Activity
End of Weeks
1 2 3 4 5 6 7 8
Schedule /
Planned
9.805 29.453 39.295 52.33 70.373 82.022 85.505 99.98
Actual 0 19.61 27.484 33.39 46.88 70.33 88.18 96.483
In the Figure (2), illumination of the bar graph schedule and vertical scale for
actual and planning, as follow:
1 2 3 4 5 6 7 8
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
Total 5100
Schedule / Planned
HoursActivity
Weight
%
Weeks
Establish site 1000 19.61
Enbankment 1500 29.93
Concrete cut-
off
500 9.12
Grout cut-off 100 1.95
Actual
Excavation
Cut and fill
2000 39.37
50 100
100
100
100
100
100
100
100
906030
654015
50
50
8040
6535
9085603520
755025
90
80
70
60
50
40
30
20
10
0
0
0
100
CumulativeProgress
Figure 2: Bar Graph with Cumulative progress curve
curve.Project. XXC
Table 1: Calculate all activity per weeks.
Construction Progress Chart
Project Rode 120 m
Date 7/4/2014
9
Advantage of Bar Graph Method
1- Gantt chart has the ability to show and clarify multiple tasks and
timelines [1].
2- It is a visual method to help project team members understand task
progress.
3- Project managers use these charts to break down projects into
manageable sets of tasks.
4- The use of Gantt charts often encourages new partnerships that might
not have evolved under traditional task assignment systems.
5- Time scheduling is considered as one of the major benefits of Gantt
charts.
6- It offers a view of project which can help team members adjust
changes.
7- Project managers can make more focused, effective decisions about
resources and timetables.
8- Visualizing resource usage during projects allows managers to make
better use of people, places, and things.
9- Using Gantt charts during critical projects allows both project
managers and participants to track team progress.
10
Disadvantage of Bar Graph Method
1- They can become very complex.
2- The length of the bar does not indicate the amount of work.
3- They all the time need to be updated.
4- Difficult to see on one sheet of paper.
5- The Critical path (C.P) cannot be clearly indicated.
11
Prepared Bar Graph
The anticipated start and completion date of each major activity is depicted
as a horizontal bar. The length of bar represents the duration of the activity
[2]. Figure (4) shows a simple bar graph. The amount of information shown
on each bar is very limited. The level of labor intensity during each activity,
which may vary considerably. An interrupted bar is used to show intermittent
activity.
The first step in preparing a bar chart is to develop a list of activities that
will be shown on the schedule. This list can be as extensive and detailed as
required, but usually is less than 25 items, representing a major group of
activities such as foundation, pier, cup, Girder, and so on. Next, the
durations of activities are estimated. On the horizontal axis select an
appropriate time scale which can be in days, Weeks, Months, or calendar
dates. Also shows vertical arrows which are intended to show logic
sequence ties. Some computer software packages are capable of showing
these logic ties. Float can also be shown by a narrow horizontal bar. A
dotted line, or a different color. Many other refinements can be made, but
the inclusion of too many features will nullify the simplicity of the bar chart.
12
Bar graph Schedule of 150 m road in Erbil
We have some student in Salahaddin University College of Engineering
Department Geomatics (Surveying) create research about (Quantity
Estimation and Bar Graph Schedule for the Project of 150 m Road-
Erbil City) [3], the aims of research is created bar graph schedule of the
project because the project was very big to take a specific part of zone work
will start from the station (6+000) to (13+000), so the length of the zone is
seven Kilometer, and the estimated for completed project work was 443 days
of work, and using software MS project to create a bar graph, The bar graph
schedule had been divided into 4 part in 7 km But it took just one part from
it which was the intersection between Erbil-Shaqlawa road that is 1 km long
Because it was concrete construction and the bar graph schedule would take
365 days, and we have 23 actives using this bar graph schedule, So now this
example support and available in Kurdistan region, shown in figure (4).
13
Figure4:BarGraphScheduleofInterchangeErbil-Shaqlawaof150mRoad
14
Conclusion
The results show us that bar graph methods have many benefits for
explaining well in terms of time and work to organize our activities.
By Setting a good schedule according to the activities we want to do in terms
of building construction, by comparison in difference between planning
schedule and actual schedule hat is main basis of bar graph method.
15
References
[1]. Book: Construction Project Management & Engineering
Economics, Dr. Adnan Fadhil, Assist. Lect. Mustafa Ayad,
https://webcache.googleusercontent.com/search?q=cache:Vy25qYPT6LYJ:https://uomu
stansiriyah.edu.iq/media/lectures/5/5_2017_11_27!07_30_29_PM.pdf+&cd=1&hl=ckb
&ct=clnk&gl=iq
[2].Book: Project Management, Authors: Zwikael, Ofer, Smyrk, John R,
chapter 10, page 239-241.
https://www.springer.com/gp/book/9783030031732#aboutBook
[3]. Research "Quantity Estimation and Bar Graph Schedule for the
Project of 150 m Road- Erbil City" (2019-2020), Create for (Nzar Braim,
Marwan Rashed, Muhammad Sarbaz, and Esra Mustafa) and supervisor by
(Dr. Kamaran Kakil Gardy), Email: nzarbraym@gmail.com .

More Related Content

What's hot

IRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick DustIRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick DustIRJET Journal
 
Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...
Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...
Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...Hari Krishna Shrestha
 
Building construction 1 (MASONRY)
Building construction 1 (MASONRY)Building construction 1 (MASONRY)
Building construction 1 (MASONRY)Safiullah Khan
 
FIBER REINFORCED POLYMER CONCRETE
FIBER REINFORCED POLYMER CONCRETEFIBER REINFORCED POLYMER CONCRETE
FIBER REINFORCED POLYMER CONCRETEARCHITECTURE SCHOOL
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Fibre reinforced concrete
Fibre reinforced concreteFibre reinforced concrete
Fibre reinforced concreteRajat Nainwal
 
Design aids for tension members as per revised is 800 2007
Design aids for tension members as per revised is  800 2007Design aids for tension members as per revised is  800 2007
Design aids for tension members as per revised is 800 2007eSAT Journals
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Designmaylene san luis
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
Unit 1.civil engineering materials
Unit 1.civil engineering materialsUnit 1.civil engineering materials
Unit 1.civil engineering materialsChirag Bhanagale
 

What's hot (20)

Retaining wall
Retaining wallRetaining wall
Retaining wall
 
IRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick DustIRJET- Soil Stabilization by using Waste Material - Brick Dust
IRJET- Soil Stabilization by using Waste Material - Brick Dust
 
Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...
Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...
Engineering Professional Practice Chapter 2 Ethics and Professionalism Pokhar...
 
Building construction 1 (MASONRY)
Building construction 1 (MASONRY)Building construction 1 (MASONRY)
Building construction 1 (MASONRY)
 
Construction material
Construction materialConstruction material
Construction material
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
 
FIBER REINFORCED POLYMER CONCRETE
FIBER REINFORCED POLYMER CONCRETEFIBER REINFORCED POLYMER CONCRETE
FIBER REINFORCED POLYMER CONCRETE
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Fibre reinforced concrete
Fibre reinforced concreteFibre reinforced concrete
Fibre reinforced concrete
 
Design aids for tension members as per revised is 800 2007
Design aids for tension members as per revised is  800 2007Design aids for tension members as per revised is  800 2007
Design aids for tension members as per revised is 800 2007
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
BUILDING MATERIALS 1
BUILDING MATERIALS 1BUILDING MATERIALS 1
BUILDING MATERIALS 1
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Quality management
Quality managementQuality management
Quality management
 
Walls
WallsWalls
Walls
 
Unit 1.civil engineering materials
Unit 1.civil engineering materialsUnit 1.civil engineering materials
Unit 1.civil engineering materials
 
Building materials
Building materialsBuilding materials
Building materials
 
Fresh and harden properties of concrete
Fresh and harden properties of concreteFresh and harden properties of concrete
Fresh and harden properties of concrete
 
Formwork
FormworkFormwork
Formwork
 

Similar to Bar Graph Method in Engineering management

Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Basics Planning PERT.ppt
Basics Planning PERT.pptBasics Planning PERT.ppt
Basics Planning PERT.pptKAhmedRehman
 
Chapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptChapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptJastienAndreanaYaran
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysisDr.R. SELVAM
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...IJERA Editor
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfkripeshdubey1
 
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635Claudia Acosta
 
Mba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aMba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aRai University
 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Sonali Srivastava
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARMitesh Kumar
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 

Similar to Bar Graph Method in Engineering management (20)

Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Basics Planning PERT.ppt
Basics Planning PERT.pptBasics Planning PERT.ppt
Basics Planning PERT.ppt
 
Chapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptChapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.ppt
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
civil engineer
civil engineercivil engineer
civil engineer
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Nce603 mod unit2
Nce603 mod unit2Nce603 mod unit2
Nce603 mod unit2
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
 
Mba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aMba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart a
 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMAR
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 

More from Nzar Braim

Engineering Project Management
Engineering Project Management Engineering Project Management
Engineering Project Management Nzar Braim
 
The Effect of Declination on The Tide Pattern in Hydroghraphic Surveying
The Effect of Declination on The Tide Pattern in Hydroghraphic SurveyingThe Effect of Declination on The Tide Pattern in Hydroghraphic Surveying
The Effect of Declination on The Tide Pattern in Hydroghraphic SurveyingNzar Braim
 
Contribution Of Real Time Network (NRTK) for improvement of accuracy
Contribution Of Real Time Network (NRTK) for improvement of accuracyContribution Of Real Time Network (NRTK) for improvement of accuracy
Contribution Of Real Time Network (NRTK) for improvement of accuracyNzar Braim
 
Nominal & effective Interest Rates
Nominal & effective Interest RatesNominal & effective Interest Rates
Nominal & effective Interest RatesNzar Braim
 
Types of Walls (Brick,Concrete Block & Stone Walls)
Types of Walls (Brick,Concrete Block & Stone Walls)Types of Walls (Brick,Concrete Block & Stone Walls)
Types of Walls (Brick,Concrete Block & Stone Walls)Nzar Braim
 
Comparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and ManagementComparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and ManagementNzar Braim
 
Differentiation between primary and secondary LIDAR system of Remote Sensing
Differentiation between primary and secondary LIDAR system of Remote SensingDifferentiation between primary and secondary LIDAR system of Remote Sensing
Differentiation between primary and secondary LIDAR system of Remote SensingNzar Braim
 
The concept of total Horizontal and Vertical Uncertainty
The concept of total Horizontal and Vertical UncertaintyThe concept of total Horizontal and Vertical Uncertainty
The concept of total Horizontal and Vertical UncertaintyNzar Braim
 
Thermostone in Constrication or Thermostone
Thermostone in Constrication or ThermostoneThermostone in Constrication or Thermostone
Thermostone in Constrication or ThermostoneNzar Braim
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Nzar Braim
 
Erbil Citadel - قةلَاي هةوليَر
Erbil Citadel - قةلَاي هةوليَرErbil Citadel - قةلَاي هةوليَر
Erbil Citadel - قةلَاي هةوليَرNzar Braim
 
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...Nzar Braim
 
Law of supply and demand
Law of supply and demandLaw of supply and demand
Law of supply and demandNzar Braim
 
Role of electromagnetic Radiation in Remote Sensing
Role of electromagnetic Radiation in  Remote SensingRole of electromagnetic Radiation in  Remote Sensing
Role of electromagnetic Radiation in Remote SensingNzar Braim
 
The Hyperbolic Radio System
The Hyperbolic Radio SystemThe Hyperbolic Radio System
The Hyperbolic Radio SystemNzar Braim
 
Car Parking Design in Urban Planning
Car Parking Design in Urban PlanningCar Parking Design in Urban Planning
Car Parking Design in Urban PlanningNzar Braim
 
Portland cement in concrete
Portland cement  in concrete Portland cement  in concrete
Portland cement in concrete Nzar Braim
 
Segregation in Concrete
Segregation in Concrete Segregation in Concrete
Segregation in Concrete Nzar Braim
 
Reconnaissance for Hydrographic Surveying Project
Reconnaissance for Hydrographic  Surveying ProjectReconnaissance for Hydrographic  Surveying Project
Reconnaissance for Hydrographic Surveying ProjectNzar Braim
 
Reconnaissance for Hydrographic Survey Project
Reconnaissance for Hydrographic  Survey ProjectReconnaissance for Hydrographic  Survey Project
Reconnaissance for Hydrographic Survey ProjectNzar Braim
 

More from Nzar Braim (20)

Engineering Project Management
Engineering Project Management Engineering Project Management
Engineering Project Management
 
The Effect of Declination on The Tide Pattern in Hydroghraphic Surveying
The Effect of Declination on The Tide Pattern in Hydroghraphic SurveyingThe Effect of Declination on The Tide Pattern in Hydroghraphic Surveying
The Effect of Declination on The Tide Pattern in Hydroghraphic Surveying
 
Contribution Of Real Time Network (NRTK) for improvement of accuracy
Contribution Of Real Time Network (NRTK) for improvement of accuracyContribution Of Real Time Network (NRTK) for improvement of accuracy
Contribution Of Real Time Network (NRTK) for improvement of accuracy
 
Nominal & effective Interest Rates
Nominal & effective Interest RatesNominal & effective Interest Rates
Nominal & effective Interest Rates
 
Types of Walls (Brick,Concrete Block & Stone Walls)
Types of Walls (Brick,Concrete Block & Stone Walls)Types of Walls (Brick,Concrete Block & Stone Walls)
Types of Walls (Brick,Concrete Block & Stone Walls)
 
Comparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and ManagementComparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and Management
 
Differentiation between primary and secondary LIDAR system of Remote Sensing
Differentiation between primary and secondary LIDAR system of Remote SensingDifferentiation between primary and secondary LIDAR system of Remote Sensing
Differentiation between primary and secondary LIDAR system of Remote Sensing
 
The concept of total Horizontal and Vertical Uncertainty
The concept of total Horizontal and Vertical UncertaintyThe concept of total Horizontal and Vertical Uncertainty
The concept of total Horizontal and Vertical Uncertainty
 
Thermostone in Constrication or Thermostone
Thermostone in Constrication or ThermostoneThermostone in Constrication or Thermostone
Thermostone in Constrication or Thermostone
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management
 
Erbil Citadel - قةلَاي هةوليَر
Erbil Citadel - قةلَاي هةوليَرErbil Citadel - قةلَاي هةوليَر
Erbil Citadel - قةلَاي هةوليَر
 
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
 
Law of supply and demand
Law of supply and demandLaw of supply and demand
Law of supply and demand
 
Role of electromagnetic Radiation in Remote Sensing
Role of electromagnetic Radiation in  Remote SensingRole of electromagnetic Radiation in  Remote Sensing
Role of electromagnetic Radiation in Remote Sensing
 
The Hyperbolic Radio System
The Hyperbolic Radio SystemThe Hyperbolic Radio System
The Hyperbolic Radio System
 
Car Parking Design in Urban Planning
Car Parking Design in Urban PlanningCar Parking Design in Urban Planning
Car Parking Design in Urban Planning
 
Portland cement in concrete
Portland cement  in concrete Portland cement  in concrete
Portland cement in concrete
 
Segregation in Concrete
Segregation in Concrete Segregation in Concrete
Segregation in Concrete
 
Reconnaissance for Hydrographic Surveying Project
Reconnaissance for Hydrographic  Surveying ProjectReconnaissance for Hydrographic  Surveying Project
Reconnaissance for Hydrographic Surveying Project
 
Reconnaissance for Hydrographic Survey Project
Reconnaissance for Hydrographic  Survey ProjectReconnaissance for Hydrographic  Survey Project
Reconnaissance for Hydrographic Survey Project
 

Recently uploaded

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 

Recently uploaded (20)

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 

Bar Graph Method in Engineering management

  • 1. Bar Graph Method Student Name: Nzar Braim Omar Class: 4th stage Course Title: Engineering Economy and Management Department: Geomatics (Surveying) College of Engineering Salahaddin University-Erbil Academic Year 2019-2020
  • 2. 2 Abstract The main explanation of this report of Bar Graph Method in terms of schedule and constriction planning. The time allowed for Bar graph Schedule performance is usually an important consideration for both the project owner and the project contractor. I'm explained the good side of Bar Graph Method in terms of ( Clarity, Communication ,Motivation, Coordination, Creativity, Time Management Flexibility , Manageability ,Efficiency, Accountability ) and I've talked about the downside . I brought up an example that supports Bar Graph Method which is used in Kurdistan Region, name of example is (Quantity Estimation and Bar Graph Schedule for the Project of 150 m Road- Erbil City).
  • 3. 3 Table of Contents Subject page Abstract..........................................................................................................2 Table of Contents ..........................................................................................3 Introduction ...................................................................................................4 Methods.........................................................................................................6 Advantage of Bar Graph Method..................................................................9 Disadvantage of Bar Graph Method ...........................................................10 Prepared Bar Graph.....................................................................................11 Bar graph Schedule of 150 m road in Erbil.................................................12 Conclusion...................................................................................................14 References ...................................................................................................15
  • 4. 4 Introduction Bar Graph or Bar Chart Schedule is a graphical schedule relating the progress of items of work to a schedule, the bar schedule traces it is origin to a chart developed by Henry L.Grant. Generally before establishing the contract of any project, the bar graph schedule must be made for the project and each project consists of more than one activity means several activities, actually there is no open time for any project that means any project in the world will be establish on fixed time therefore the project must be finish in desired time because time is very important and one of the most important factors that effect on the budget of the project, so bar graph schedule play a vital role as a guide chart for (project manager, contractor, and engineers, …), and the bar graph schedule is used to determine the duration of performance of each activity of the project and also used to show the starting time and end time of each activities that means the sequence of the project, because each activity must be finish in proposed duration and any delay of each activities will effect on the execution of the project in proposed time, so by delay in any activity the contractor or project manager must be increase the number of teams, equipment, and hours of working(morning and evening), and efforts but in logical way…, because generally any delay in duration of construction of the project will cause that the contractor should pay money due to the delay in the proposed time of the project, and in the procedure of making bar graph schedule, we have quantity estimation of materials(i.e. earthwork, concrete, subbase, subgrade, and asphalt), therefore we must calculate the quantity of materials in accurate ways to make a precise bar graph schedule. Cumulative Project Progress show in figure (2), a cumulative progress- versus time curve for the bar graph.
  • 5. 5 The vertical scale represents cumulative project progress in percent and the horizontal scale indicates time. Once the bar graph schedule has been prepared and weighting factors calculated for each activity, scheduled cumulative progress can be calculated and plotted.
  • 6. 6 Methods A bar graph or bar chart schedule is a graphical schedule relating the progress of items of work to a schedule. The bar schedule traces its origin to a chart developed by Henry L.Grant. A simple bar graph schedule for a construction project is shown in figure (1). 1 2 3 4 5 6 7 8 SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT Total 5100 Excavation Cut and fill 2000 39.37 Establish site 1000 19.61 Enbankment 1500 29.93 Concrete cut- off 500 9.12 Grout cut-off 100 1.95 HoursActivity Weight % Weeks 50 100 100 100 100 100 100 100 100 906030 654015 50 50 8040 6535 9085603520 755025 90 80 70 60 50 40 30 20 10 0 0 0 100 The major work items, or activities, making up the project are listed on the left side of the schedule with a time scale across the top. The column headed "Hours" indicates the estimated number of labor-hours required for each activity. The column headed "Weight" indicates the portion of the total project effort accounted for by each activity. For example "Clearing and stripping" requires 1000 labor-hours of work, which represents 19.63 % of Figure 1: Bar Graph Schedule for construction Project. Construction Progress Chart Project Rode 120 m Date 7/4/2014
  • 7. 7 the 5100 labor-hours required for the entire project. While a weighting column is not always present on a bar chart, its presence is very useful when calculating cumulative project progress. Activities may be weighted on any desired basis. Notice that two horizontal blocks are provided opposite each activity. The upper block (SCH) represents scheduled progress and the lower block (ACT) is used to record actual progress as worked proceeds. For each block, a bar extends from starting to ending times division. Again such a system considerably simplifies the calculation of scheduled cumulative progress and its comparison with actual progress. To aid in the evaluation of progress, it is suggested that the actual progress of each activity be inserted at the end of each major period. To find weight using the question as follow: 𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑜𝑛𝑒 𝑡𝑎𝑠𝑘 (%) = ℎ𝑜𝑢𝑟 𝑜𝑓 𝑜𝑛𝑒 𝑡𝑎𝑠𝑘 ∑ ℎ𝑜𝑢𝑟 × 100 (1) 𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑜𝑛𝑒 𝑡𝑎𝑠𝑘 (%) = 1000 5100 × 100 = 19.61% 𝐶𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝑝𝑟𝑜𝑔𝑟𝑒𝑠𝑠 = ∑(𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑝𝑟𝑜𝑔𝑟𝑒𝑠𝑠) 𝑖 x 𝑛 𝑖=1 (𝑊𝑒𝑖𝑔ℎ𝑡)𝑖 (2) For example: for activating the Second week of Schedule as follow: Activity 2 week = (1x19.61) + (0.25x 39.37) = 29.45% This mean activity second of week 29.45% complete.
  • 8. 8 We have calculate all activity for the end of weeks for schedule (Planned) and Actual in Table (1) as follow: All Activity End of Weeks 1 2 3 4 5 6 7 8 Schedule / Planned 9.805 29.453 39.295 52.33 70.373 82.022 85.505 99.98 Actual 0 19.61 27.484 33.39 46.88 70.33 88.18 96.483 In the Figure (2), illumination of the bar graph schedule and vertical scale for actual and planning, as follow: 1 2 3 4 5 6 7 8 SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT Total 5100 Schedule / Planned HoursActivity Weight % Weeks Establish site 1000 19.61 Enbankment 1500 29.93 Concrete cut- off 500 9.12 Grout cut-off 100 1.95 Actual Excavation Cut and fill 2000 39.37 50 100 100 100 100 100 100 100 100 906030 654015 50 50 8040 6535 9085603520 755025 90 80 70 60 50 40 30 20 10 0 0 0 100 CumulativeProgress Figure 2: Bar Graph with Cumulative progress curve curve.Project. XXC Table 1: Calculate all activity per weeks. Construction Progress Chart Project Rode 120 m Date 7/4/2014
  • 9. 9 Advantage of Bar Graph Method 1- Gantt chart has the ability to show and clarify multiple tasks and timelines [1]. 2- It is a visual method to help project team members understand task progress. 3- Project managers use these charts to break down projects into manageable sets of tasks. 4- The use of Gantt charts often encourages new partnerships that might not have evolved under traditional task assignment systems. 5- Time scheduling is considered as one of the major benefits of Gantt charts. 6- It offers a view of project which can help team members adjust changes. 7- Project managers can make more focused, effective decisions about resources and timetables. 8- Visualizing resource usage during projects allows managers to make better use of people, places, and things. 9- Using Gantt charts during critical projects allows both project managers and participants to track team progress.
  • 10. 10 Disadvantage of Bar Graph Method 1- They can become very complex. 2- The length of the bar does not indicate the amount of work. 3- They all the time need to be updated. 4- Difficult to see on one sheet of paper. 5- The Critical path (C.P) cannot be clearly indicated.
  • 11. 11 Prepared Bar Graph The anticipated start and completion date of each major activity is depicted as a horizontal bar. The length of bar represents the duration of the activity [2]. Figure (4) shows a simple bar graph. The amount of information shown on each bar is very limited. The level of labor intensity during each activity, which may vary considerably. An interrupted bar is used to show intermittent activity. The first step in preparing a bar chart is to develop a list of activities that will be shown on the schedule. This list can be as extensive and detailed as required, but usually is less than 25 items, representing a major group of activities such as foundation, pier, cup, Girder, and so on. Next, the durations of activities are estimated. On the horizontal axis select an appropriate time scale which can be in days, Weeks, Months, or calendar dates. Also shows vertical arrows which are intended to show logic sequence ties. Some computer software packages are capable of showing these logic ties. Float can also be shown by a narrow horizontal bar. A dotted line, or a different color. Many other refinements can be made, but the inclusion of too many features will nullify the simplicity of the bar chart.
  • 12. 12 Bar graph Schedule of 150 m road in Erbil We have some student in Salahaddin University College of Engineering Department Geomatics (Surveying) create research about (Quantity Estimation and Bar Graph Schedule for the Project of 150 m Road- Erbil City) [3], the aims of research is created bar graph schedule of the project because the project was very big to take a specific part of zone work will start from the station (6+000) to (13+000), so the length of the zone is seven Kilometer, and the estimated for completed project work was 443 days of work, and using software MS project to create a bar graph, The bar graph schedule had been divided into 4 part in 7 km But it took just one part from it which was the intersection between Erbil-Shaqlawa road that is 1 km long Because it was concrete construction and the bar graph schedule would take 365 days, and we have 23 actives using this bar graph schedule, So now this example support and available in Kurdistan region, shown in figure (4).
  • 14. 14 Conclusion The results show us that bar graph methods have many benefits for explaining well in terms of time and work to organize our activities. By Setting a good schedule according to the activities we want to do in terms of building construction, by comparison in difference between planning schedule and actual schedule hat is main basis of bar graph method.
  • 15. 15 References [1]. Book: Construction Project Management & Engineering Economics, Dr. Adnan Fadhil, Assist. Lect. Mustafa Ayad, https://webcache.googleusercontent.com/search?q=cache:Vy25qYPT6LYJ:https://uomu stansiriyah.edu.iq/media/lectures/5/5_2017_11_27!07_30_29_PM.pdf+&cd=1&hl=ckb &ct=clnk&gl=iq [2].Book: Project Management, Authors: Zwikael, Ofer, Smyrk, John R, chapter 10, page 239-241. https://www.springer.com/gp/book/9783030031732#aboutBook [3]. Research "Quantity Estimation and Bar Graph Schedule for the Project of 150 m Road- Erbil City" (2019-2020), Create for (Nzar Braim, Marwan Rashed, Muhammad Sarbaz, and Esra Mustafa) and supervisor by (Dr. Kamaran Kakil Gardy), Email: nzarbraym@gmail.com .