SlideShare a Scribd company logo
1 of 16
Project Scheduling 1
Prepared by Sebghatullah Karimi
(Junior Lecturer of Kabul Polytechnic University)
1392
Kardan University
Civil Engineering Faculty
Explain how scheduling is used in the pre-
construction, construction, and post-
construction phases of a project.
Explain the configuration and uses of a bar
chart.
Explain the configuration and uses of a network
diagram.
• Scheduling is the process of listing a number of
duties or events in the sequence that they will
occur.
• It is a timetable, and it formulates the activities
that must be accomplished to reach a certain
goal or objective.
• Schedules establish the start, duration, and
completion date of a project or a task.
Partial occupancy – The practice of allowing the
owner to begin occupying the facility while
construction is still underway.
Bar chart (Gantt chart) – A simple diagram showing
project activities depicted as horizontal bars
arranged along a time line.
Network-based schedule – A more complex and
sophisticated project schedule depicting project
activities arranged in a network, representing the
logical relationships between activities.
Scheduling is critically important during the pre-
construction, construction, and post-
construction phases of a project.
While a project is still being designed, the owner needs
to know if the project can be completed on time. To
obtain project financing, the owner must generally
establish firm commitments with the end user of the
project. For example, in the case of a highway, the
owner (the government) makes a firm commitment
with the user (the public) to complete the highway
by a certain date. If the project is a commercial
shopping center, the owner makes a commitment
with private retail tenants that the facility will be
ready for occupancy at a specified time.
• A carefully prepared project schedule is the only
practical way to accurately predict whether the
required completion date is actually attainable. This
schedule must accurately identify all tasks required
to be completed on a project. It must determine the
duration of each task and place all tasks into a
correct, logical sequence.
• The scheduling process during the pre-construction
stage should be viewed as an opportunity to think
through all aspects of project planning, prior to the
actual construction. This process provides an
opportunity for all parties to visualize the process
and to make all necessary project coordination.
Project schedules are not only useful during the pre-
construction stage; they are also essential to the
successful coordination of day-to-day construction
activities. Material deliveries and the utilization of
equipment and people are all managed through
the schedule. As a project progresses, delays
inevitably occur. The project manager's job is to
deal effectively with these delays and to anticipate
them as much as possible. It is the intelligent
response to bad weather, failures, strikes, design
errors, or omissions that separates a well-
managed project from a poorly managed one.
As a project nears completion the end user of
the facility becomes more involved in the
construction process. Most projects require
testing and acceptance of equipment,
training of the people who will ultimately
use and maintain the equipment on the
project, and the correction of deficiencies
included in the project punchlist.
The bar chart, or Gantt chart, is graphically the
simplest of the scheduling methods.
The bar chart is frequently used in the planning
stage of a project by owners, designers, and
construction professionals to quickly
examine the overall timing on a project.
In its simplest form, the bar chart can depict a project
in terms of just three major activities (each
represented by a bar)—design, bid and award, and
construction. A somewhat more detailed bar chart,
representing seven activities (procure formwork,
mobilize, lay out footings, excavate footings, concrete
formwork, set base plates, and erect steel).
The Gantt chart effectively communicates the
following important facts about the project:
The planned overall length of the project
The planned duration of each project component
The calendar start and finish dates for each project phase
The most powerful tool for construction project
scheduling is the network schedule. A network
schedule depicts all of the work to be performed
on the project as a series of activities, each of
which is a well-defined item of work. Each
activity is assigned a duration (how long the
activity will take in hours, days, or weeks), and all
activities are connected together in a network
diagram that fully depicts the logical relationships
between activities.
Mobilize
Layout
Footing
Excavation
Footing
Forms and
Concrete Erect Steel
Procure Formwork
Procure Steel
Mobilize
Layout
footing
Excavate
footing
Forms
and
concrete
Erect
steel
Procure
Formwork
Procure
steel
16

More Related Content

What's hot

Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Project management
Project managementProject management
Project managementSimran Kaur
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Project Management Process Groups
Project Management Process GroupsProject Management Process Groups
Project Management Process GroupsTechNoleGirl
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 

What's hot (20)

Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Project management
Project managementProject management
Project management
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Project Management Process Groups
Project Management Process GroupsProject Management Process Groups
Project Management Process Groups
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Project Charter Guide
Project Charter GuideProject Charter Guide
Project Charter Guide
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 

Viewers also liked

Odf sprawozdanie finansowe_2009
Odf sprawozdanie finansowe_2009Odf sprawozdanie finansowe_2009
Odf sprawozdanie finansowe_2009odfoundation
 
Network patterns of Japanese multinationals in Europe
Network patterns of Japanese multinationals in EuropeNetwork patterns of Japanese multinationals in Europe
Network patterns of Japanese multinationals in EuropeMartin
 
Aprender3C - Presentation Library 2.015
Aprender3C - Presentation Library 2.015Aprender3C - Presentation Library 2.015
Aprender3C - Presentation Library 2.015Aprender 3C
 
Train ต.8(peerawat) 5307231
Train ต.8(peerawat) 5307231Train ต.8(peerawat) 5307231
Train ต.8(peerawat) 5307231IndyArch Osk
 
Hướng dẫn kết nối máy chấm công với máy tính
Hướng dẫn kết nối máy chấm công với máy tínhHướng dẫn kết nối máy chấm công với máy tính
Hướng dẫn kết nối máy chấm công với máy tínhgiaiphapchamcong
 
Data-Driven Marketing Roadshow ERN - March 26, 2014
Data-Driven Marketing Roadshow ERN - March 26, 2014Data-Driven Marketing Roadshow ERN - March 26, 2014
Data-Driven Marketing Roadshow ERN - March 26, 2014DDM Alliance
 
Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.
Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.
Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.nouxristina
 
Midagon - presentation
Midagon - presentationMidagon - presentation
Midagon - presentationMartin Ivanov
 
TechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временемTechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временемDA-14
 
Hướng dẫn cách mở port mát chấm công
Hướng dẫn cách mở port mát chấm côngHướng dẫn cách mở port mát chấm công
Hướng dẫn cách mở port mát chấm cônggiaiphapchamcong
 
Accomplish Your Wishes With Rapid Cash
Accomplish Your Wishes With Rapid CashAccomplish Your Wishes With Rapid Cash
Accomplish Your Wishes With Rapid CashJustin Mirage
 
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 125 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1odfoundation
 
小小說書人
小小說書人小小說書人
小小說書人yuruli
 

Viewers also liked (19)

Odf sprawozdanie finansowe_2009
Odf sprawozdanie finansowe_2009Odf sprawozdanie finansowe_2009
Odf sprawozdanie finansowe_2009
 
Dvd kurimas dvd_santa
Dvd kurimas dvd_santaDvd kurimas dvd_santa
Dvd kurimas dvd_santa
 
Paskaita nr8 voip
Paskaita nr8 voipPaskaita nr8 voip
Paskaita nr8 voip
 
Network patterns of Japanese multinationals in Europe
Network patterns of Japanese multinationals in EuropeNetwork patterns of Japanese multinationals in Europe
Network patterns of Japanese multinationals in Europe
 
Aprender3C - Presentation Library 2.015
Aprender3C - Presentation Library 2.015Aprender3C - Presentation Library 2.015
Aprender3C - Presentation Library 2.015
 
Top画面でできる事
Top画面でできる事Top画面でできる事
Top画面でできる事
 
Train ต.8(peerawat) 5307231
Train ต.8(peerawat) 5307231Train ต.8(peerawat) 5307231
Train ต.8(peerawat) 5307231
 
Hướng dẫn kết nối máy chấm công với máy tính
Hướng dẫn kết nối máy chấm công với máy tínhHướng dẫn kết nối máy chấm công với máy tính
Hướng dẫn kết nối máy chấm công với máy tính
 
Paskaita nr7 windows_os
Paskaita nr7 windows_osPaskaita nr7 windows_os
Paskaita nr7 windows_os
 
Data-Driven Marketing Roadshow ERN - March 26, 2014
Data-Driven Marketing Roadshow ERN - March 26, 2014Data-Driven Marketing Roadshow ERN - March 26, 2014
Data-Driven Marketing Roadshow ERN - March 26, 2014
 
Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.
Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.
Παρουσίαση αποτελεσμάτων Σ.Κ.Ζ.
 
Midagon - presentation
Midagon - presentationMidagon - presentation
Midagon - presentation
 
TechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временемTechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временем
 
Hướng dẫn cách mở port mát chấm công
Hướng dẫn cách mở port mát chấm côngHướng dẫn cách mở port mát chấm công
Hướng dẫn cách mở port mát chấm công
 
Sebastian Serna Satizabal
Sebastian Serna Satizabal Sebastian Serna Satizabal
Sebastian Serna Satizabal
 
Accomplish Your Wishes With Rapid Cash
Accomplish Your Wishes With Rapid CashAccomplish Your Wishes With Rapid Cash
Accomplish Your Wishes With Rapid Cash
 
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 125 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
 
nes recruitment capabilities
nes recruitment capabilitiesnes recruitment capabilities
nes recruitment capabilities
 
小小說書人
小小說書人小小說書人
小小說書人
 

Similar to 09 lecture project scheduling 1

10 lecture project scheduling 2
10 lecture project scheduling 210 lecture project scheduling 2
10 lecture project scheduling 2Ahmad Basim Hamza
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
Work scheduling(2)
Work scheduling(2)Work scheduling(2)
Work scheduling(2)ngiyari
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxRaoAnkitYadav1
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxRaoAnkitYadav1
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfGagandeepKaur617299
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptxBahredinAbdella1
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 

Similar to 09 lecture project scheduling 1 (20)

10 lecture project scheduling 2
10 lecture project scheduling 210 lecture project scheduling 2
10 lecture project scheduling 2
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Work scheduling(2)
Work scheduling(2)Work scheduling(2)
Work scheduling(2)
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 

More from Ahmad Basim Hamza

History of Afghanistan Railway Network
History of Afghanistan Railway NetworkHistory of Afghanistan Railway Network
History of Afghanistan Railway NetworkAhmad Basim Hamza
 
History of afghanistan railway network
History of afghanistan railway networkHistory of afghanistan railway network
History of afghanistan railway networkAhmad Basim Hamza
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 
11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3Ahmad Basim Hamza
 

More from Ahmad Basim Hamza (7)

History of Afghanistan Railway Network
History of Afghanistan Railway NetworkHistory of Afghanistan Railway Network
History of Afghanistan Railway Network
 
History of afghanistan railway network
History of afghanistan railway networkHistory of afghanistan railway network
History of afghanistan railway network
 
Project Management (Soft)
Project Management (Soft)Project Management (Soft)
Project Management (Soft)
 
Project Management
Project ManagementProject Management
Project Management
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3
 

Recently uploaded

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 

Recently uploaded (20)

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

09 lecture project scheduling 1

  • 1. Project Scheduling 1 Prepared by Sebghatullah Karimi (Junior Lecturer of Kabul Polytechnic University) 1392 Kardan University Civil Engineering Faculty
  • 2. Explain how scheduling is used in the pre- construction, construction, and post- construction phases of a project. Explain the configuration and uses of a bar chart. Explain the configuration and uses of a network diagram.
  • 3. • Scheduling is the process of listing a number of duties or events in the sequence that they will occur. • It is a timetable, and it formulates the activities that must be accomplished to reach a certain goal or objective. • Schedules establish the start, duration, and completion date of a project or a task.
  • 4. Partial occupancy – The practice of allowing the owner to begin occupying the facility while construction is still underway. Bar chart (Gantt chart) – A simple diagram showing project activities depicted as horizontal bars arranged along a time line. Network-based schedule – A more complex and sophisticated project schedule depicting project activities arranged in a network, representing the logical relationships between activities.
  • 5.
  • 6. Scheduling is critically important during the pre- construction, construction, and post- construction phases of a project.
  • 7. While a project is still being designed, the owner needs to know if the project can be completed on time. To obtain project financing, the owner must generally establish firm commitments with the end user of the project. For example, in the case of a highway, the owner (the government) makes a firm commitment with the user (the public) to complete the highway by a certain date. If the project is a commercial shopping center, the owner makes a commitment with private retail tenants that the facility will be ready for occupancy at a specified time.
  • 8. • A carefully prepared project schedule is the only practical way to accurately predict whether the required completion date is actually attainable. This schedule must accurately identify all tasks required to be completed on a project. It must determine the duration of each task and place all tasks into a correct, logical sequence. • The scheduling process during the pre-construction stage should be viewed as an opportunity to think through all aspects of project planning, prior to the actual construction. This process provides an opportunity for all parties to visualize the process and to make all necessary project coordination.
  • 9. Project schedules are not only useful during the pre- construction stage; they are also essential to the successful coordination of day-to-day construction activities. Material deliveries and the utilization of equipment and people are all managed through the schedule. As a project progresses, delays inevitably occur. The project manager's job is to deal effectively with these delays and to anticipate them as much as possible. It is the intelligent response to bad weather, failures, strikes, design errors, or omissions that separates a well- managed project from a poorly managed one.
  • 10. As a project nears completion the end user of the facility becomes more involved in the construction process. Most projects require testing and acceptance of equipment, training of the people who will ultimately use and maintain the equipment on the project, and the correction of deficiencies included in the project punchlist.
  • 11. The bar chart, or Gantt chart, is graphically the simplest of the scheduling methods. The bar chart is frequently used in the planning stage of a project by owners, designers, and construction professionals to quickly examine the overall timing on a project.
  • 12. In its simplest form, the bar chart can depict a project in terms of just three major activities (each represented by a bar)—design, bid and award, and construction. A somewhat more detailed bar chart, representing seven activities (procure formwork, mobilize, lay out footings, excavate footings, concrete formwork, set base plates, and erect steel). The Gantt chart effectively communicates the following important facts about the project: The planned overall length of the project The planned duration of each project component The calendar start and finish dates for each project phase
  • 13. The most powerful tool for construction project scheduling is the network schedule. A network schedule depicts all of the work to be performed on the project as a series of activities, each of which is a well-defined item of work. Each activity is assigned a duration (how long the activity will take in hours, days, or weeks), and all activities are connected together in a network diagram that fully depicts the logical relationships between activities.
  • 16. 16