1 MW SCALE SOLAR PV
POWER PLANT
By: Piyush Charan
Assistant Professor, Integral University, Lucknow
Background
 Solar energy is free source of energy
 Solar radiation on earth surface per hour is equal to total
power consumption of earth for whole year.
 Grid power in India is polluting, unreliable and inefficient
 Solar energy is a renewable, clean alternative to fossil
fuels.
 solar energy is converted into electricity by using either
photo-voltaic or solar thermal
A modest 2.5kw solar power system can have over its
lifetime equivalent to
300 barrels of oil not produced
270,000 miles not driven
1,100 lbs of acid rain emissions not discharged
550 lbs of smog emissions not produced
220,000 lbs of greenhouse gases not emitted
equivalent to planting 500 trees.
Solar Energy vs Conventional Energ
•Jawaharlal Nehru National Solar Mission (MNRE, Govt of
India) launched in, 2010 by the Prime Minister, a target of
deploying 20,000 MW of grid connected solar power by
2022. It is enhanced by new government to 100,000 MW.
Target by 2022 Old Revised
•Solar power 20,000 MW 100,000 MW
•Wind Energy 38500 MW 60,000 MW
• Others 13500 MW 15,000 MW
•Total 72,000 MW 175,000 MW
(Installed capacity of india as on April 2015 : 274,818 MW including renewable Energy
35,777 MW) Source: cea.nic.in powermin.nic.in
Incentives to Solar power plant
• Various incentives offered by central and state government, few
of them are
• Benefit in land registration for solar power plant
• 15-30 % subsidy for sanctioned project for equipments.
• Support in grid connectivity
• Depreciation benefits
1MW SPV Power Plant : Initial
costing
Sr NoItem Unit @ rate Cost
(lac)
1 Land 6 Acre 600000 36
2 Modules 1100000 Watt 33 363
3 Civil Structure 60,500 Kg 66 44
4 Inverter 1100000 VA 11 121
5 Transformer 1 27,00,000 27
6 Protective devices 1 10
7 Wires, Cables 10
8 SCADA/RMS 10
9 Installation 10
10 Legal & official work 24
11 Grid Evacuation 10
12 Execution & commisioning 30
Total 695
1MW SPV Power Plant:
Financial
Plant Capacity 1000 KW
Plant Cost (in lacs) 0.695 lac/KW 695
Equity 30% 208.5
Debt 70% 486.5
Interst rate 12% 1.01
Payment Period (yrs) 9 108
EMI 7.3871
Maintenance & Manpower 3%
P V of Inverter Cost 132
Price reduction rate of
Inverter 2%
• Area Shade free 3 Acre Only 80% of the input area is considered to adjust for potential
shaded areas
• Maintenance & Manpower 4% of project cost, with annual escalation of 5%
• Inverter lifespan is 10 years, with 2.00% annual cost reduction (110 % of capacity, @Rs
11/W)
• Accelerated depreciation is at 80.00%. It is assumed that the entire benefit of accelerated
depreciation can be claimed
• Corporate tax rate 35%
• Plant generation 4.7 kWh per KW per day, with 1% annual panel degradation and 10%
losses10%
• Debt service calculation assumes 70.00% debt; 2.00% interest rate; 9-year loan term with
no moratorium; repayable monthly through EMI
• Tariff 7.5 /KWH through PPA for 12 years
• Annual inflation 7%
1MW SPV Power Plant : Financial in lacs
Year
Plant Expenditure
Net
Yearly
Expend
Generation
return
by
power
selling
REC
Return
@
3000/
MWH
Net
Return
Present
value
of Net
return
Equity/
Inverter
replacem
ent
Mainten
ance
Debt
Int
Debt
Prin
Power
Unit
(MWH)
Tariff
Rs per
KWH
earning
0 208.50 -208.50
-
208.50
-208.50 -208.50
1 20.85 56.66 31.99 -109.50 1478 7.50 110.85 1.35 1.35 1.27
2 21.89 52.60 36.04 -110.54 1463 7.50 109.73 -0.81 44.00 43.19 37.72
3 22.99 48.03 40.61 -111.63 1449 7.50 108.68 -2.96 43.00 40.04 32.69
4 24.14 42.88 45.77 -112.78 1434 7.50 107.55 -5.23 43.00 37.77 28.81
5 25.34 37.08 51.57 -113.99 1420 7.50 106.50 -7.49 43.00 35.51 25.32
6 26.61 30.54 58.11 -115.26 1406 7.50 105.45 -9.81 42.00 32.19 21.45
7 27.94 23.17 65.48 -116.59 1392 7.50 104.40 -12.19 42.00 29.81 18.57
8 29.34 14.86 73.78 -117.98 1378 7.50 103.35 -14.63 41.00 26.37 15.35
9 30.80 5.50 83.14 -119.45 1364 7.50 102.30 -17.15 41.00 23.85 12.97
10 108.29 32.35 0.00 0.00 -140.63 1350 7.50 101.25 -39.38 41.00 1.62 0.82
11 33.96 -33.96 1337 7.50 100.28 66.31 40.00 106.31 50.51
12 35.66 -35.66 1324 7.50 99.30 63.64 40.00 103.64 46.02
1MW SPV Power Plant : Financial in lacs
Year
Plant Expenditure
Net
Yearly
Expen
Generation
return
by
power
selling
REC
Return
@
3000/
MWH
Net
Return
Presen
t value
of Net
return
Equity/
Inverter
replace
ment
Mainten
ece
Debt
Int
Debt
Prin
Power
Unit
(MWH)
Tariff
Rs per
KWH
earning
13 37.44 -37.44 1310 10.00 131.00 93.56 39.00 132.56 55.01
14 39.32 -39.32 1297 10.00 129.70 90.38 39.00 129.38 50.18
15 41.28 -41.28 1284 10.00 128.40 87.12 39.00 126.12 45.71
16 43.35 -43.35 1271 10.00 127.10 83.75 38.00 121.75 41.24
17 45.51 -45.51 1259 10.00 125.90 80.39 38.00 118.39 37.48
18 47.79 -47.79 1246 10.00 124.60 76.81 37.00 113.81 33.67
19 50.18 -50.18 1234 10.00 123.40 73.22 37.00 110.22 30.48
20 88.83 52.69 -141.52 1221 10.00 122.10 -19.42 37.00 17.58 4.54
21 55.32 -55.32 1209 10.00 120.90 65.58 36.00 101.58 24.53
22 58.09 -58.09 1197 10.00 119.70 61.61 36.00 97.61 22.03
23 60.99 -60.99 1185 10.00 118.50 57.51 36.00 93.51 19.73
24 64.04 -64.04 1173 10.00 117.30 53.26 35.00 88.26 17.40
25 67.24 -67.24 1161 10.00 116.10 48.86 35.00 83.86 15.45
405.62 995.11 311.31 486.50-2198.54 32842.00 220.002864.33 665.79 942.001607.79 480.44
1MW SPV Power Plant :
Financial
• Initial Investment : 6.950 crore
Equity : 2.085 crore
Debt : 4.865 crore
• Present Value of Investment : 12.56 crore
• Present Value of earning (PPA & REC) : 17.36 crore
• Present Value of Profit before tax :4.80 crore
• Payback period : 6 years
• Levelized cost of power : Rs 3.28/unit
• After payback period capacity enhancement of another 1 MW in same land can be
done with maintenance covered by first project
(conservative estimate of earning is made. No incentive by government is considered
in investment)

More Related Content

What's hot

World's Largest Solar Project
World's Largest Solar ProjectWorld's Largest Solar Project
World's Largest Solar Project
MitchellDong
 
Rajasthan Solar Policy Frist Green
Rajasthan Solar Policy Frist GreenRajasthan Solar Policy Frist Green
Rajasthan Solar Policy Frist Greenfirstgreen
 
10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design
Vignesh Sekar
 
Solar PV Panels And Invertors By Euro Solar System, Gandhinagar
Solar PV Panels And Invertors By Euro Solar System, Gandhinagar Solar PV Panels And Invertors By Euro Solar System, Gandhinagar
Solar PV Panels And Invertors By Euro Solar System, Gandhinagar
IndiaMART InterMESH Limited
 
installation of grid solar panel of electrical department
installation of grid solar panel of electrical departmentinstallation of grid solar panel of electrical department
installation of grid solar panel of electrical department
surendra gurjar
 
Financial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil NaduFinancial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil NaduIshan Rohit
 
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Sayanti Sanyal
 
Renewable energy course#00
Renewable energy course#00Renewable energy course#00
Renewable energy course#00Syed_Sajjad_Raza
 
Economics of Solar PV Power
Economics of Solar PV PowerEconomics of Solar PV Power
Economics of Solar PV PowerSudhanwa Sahoo
 
India solar power_plant_vpc
India solar power_plant_vpcIndia solar power_plant_vpc
India solar power_plant_vpcPasu Kumar
 
Ugsolar太阳能
Ugsolar太阳能Ugsolar太阳能
Ugsolar太阳能
Dr. Tan Boon Siong
 
Tri-Brid mobile
Tri-Brid mobileTri-Brid mobile
Tri-Brid mobilenatec1
 
Presentazione di Gruppo Veronagest
Presentazione di Gruppo VeronagestPresentazione di Gruppo Veronagest
Presentazione di Gruppo Veronagest
Veronagest
 
Integrated wte gasification & solar power plant for Terengganu
Integrated wte gasification & solar power plant for TerengganuIntegrated wte gasification & solar power plant for Terengganu
Integrated wte gasification & solar power plant for Terengganu
Dato Mat Isa
 
Dgset replacement. This is important due to high rise in price of diesel.
Dgset replacement.  This is important due to high rise in price of diesel. Dgset replacement.  This is important due to high rise in price of diesel.
Dgset replacement. This is important due to high rise in price of diesel.
J.P. GUPTA
 
Mnre report
Mnre reportMnre report
Mnre report
Pasu Kumar
 
The role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEThe role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAE
ReedExhibitionsMiddl
 
Cost of solar electricity
Cost of solar electricityCost of solar electricity
Cost of solar electricity
PVschool
 
Rooftop solar pv system
Rooftop solar pv systemRooftop solar pv system
Rooftop solar pv system
Rajendra Mahajan
 
1KV Solar Plant Establishment
1KV Solar Plant Establishment 1KV Solar Plant Establishment
1KV Solar Plant Establishment
Vinay Vishwakarma
 

What's hot (20)

World's Largest Solar Project
World's Largest Solar ProjectWorld's Largest Solar Project
World's Largest Solar Project
 
Rajasthan Solar Policy Frist Green
Rajasthan Solar Policy Frist GreenRajasthan Solar Policy Frist Green
Rajasthan Solar Policy Frist Green
 
10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design
 
Solar PV Panels And Invertors By Euro Solar System, Gandhinagar
Solar PV Panels And Invertors By Euro Solar System, Gandhinagar Solar PV Panels And Invertors By Euro Solar System, Gandhinagar
Solar PV Panels And Invertors By Euro Solar System, Gandhinagar
 
installation of grid solar panel of electrical department
installation of grid solar panel of electrical departmentinstallation of grid solar panel of electrical department
installation of grid solar panel of electrical department
 
Financial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil NaduFinancial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil Nadu
 
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
 
Renewable energy course#00
Renewable energy course#00Renewable energy course#00
Renewable energy course#00
 
Economics of Solar PV Power
Economics of Solar PV PowerEconomics of Solar PV Power
Economics of Solar PV Power
 
India solar power_plant_vpc
India solar power_plant_vpcIndia solar power_plant_vpc
India solar power_plant_vpc
 
Ugsolar太阳能
Ugsolar太阳能Ugsolar太阳能
Ugsolar太阳能
 
Tri-Brid mobile
Tri-Brid mobileTri-Brid mobile
Tri-Brid mobile
 
Presentazione di Gruppo Veronagest
Presentazione di Gruppo VeronagestPresentazione di Gruppo Veronagest
Presentazione di Gruppo Veronagest
 
Integrated wte gasification & solar power plant for Terengganu
Integrated wte gasification & solar power plant for TerengganuIntegrated wte gasification & solar power plant for Terengganu
Integrated wte gasification & solar power plant for Terengganu
 
Dgset replacement. This is important due to high rise in price of diesel.
Dgset replacement.  This is important due to high rise in price of diesel. Dgset replacement.  This is important due to high rise in price of diesel.
Dgset replacement. This is important due to high rise in price of diesel.
 
Mnre report
Mnre reportMnre report
Mnre report
 
The role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEThe role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAE
 
Cost of solar electricity
Cost of solar electricityCost of solar electricity
Cost of solar electricity
 
Rooftop solar pv system
Rooftop solar pv systemRooftop solar pv system
Rooftop solar pv system
 
1KV Solar Plant Establishment
1KV Solar Plant Establishment 1KV Solar Plant Establishment
1KV Solar Plant Establishment
 

Similar to Lecture 1 piyush 21

Solar rooftop market analysis
Solar rooftop market analysisSolar rooftop market analysis
Solar rooftop market analysis
Arun kumar
 
Solar PPt.pptx
Solar PPt.pptxSolar PPt.pptx
Solar PPt.pptx
MissSeptember1
 
Inverted Energy: Diesel Generator Set Replacement
Inverted Energy: Diesel Generator Set Replacement Inverted Energy: Diesel Generator Set Replacement
Inverted Energy: Diesel Generator Set Replacement
Inverted2019
 
A Presentation made at the Sri Lanka Institution of Engineers in 2009
A Presentation made at the Sri Lanka Institution of Engineers in 2009A Presentation made at the Sri Lanka Institution of Engineers in 2009
A Presentation made at the Sri Lanka Institution of Engineers in 2009
Private Consultants
 
Project of a solar system on the roof of the house of Santa Claus
Project of a solar system on the roof of the house of Santa ClausProject of a solar system on the roof of the house of Santa Claus
Project of a solar system on the roof of the house of Santa Claus
EasySolar
 
Renewable Energy::Pakistan Perspective 2013
Renewable Energy::Pakistan Perspective 2013Renewable Energy::Pakistan Perspective 2013
Renewable Energy::Pakistan Perspective 2013akhtar ali
 
Project of a photovoltaic installation on the roof of the famous Paris Pantheon
Project of a photovoltaic installation on the roof of the famous Paris PantheonProject of a photovoltaic installation on the roof of the famous Paris Pantheon
Project of a photovoltaic installation on the roof of the famous Paris Pantheon
EasySolar
 
The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...
IrSOLaV Pomares
 
Sun trackin solar panel with auto dust cleaning system
Sun trackin solar panel with auto dust cleaning systemSun trackin solar panel with auto dust cleaning system
Sun trackin solar panel with auto dust cleaning system
sachin kumar
 
Solar street lights using solar tracker and
Solar street lights using solar tracker and Solar street lights using solar tracker and
Solar street lights using solar tracker and GITESHRMHATRE
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13
Seokho Shin
 
Sopitsuda thailandssolarfit
Sopitsuda thailandssolarfitSopitsuda thailandssolarfit
Sopitsuda thailandssolarfit
Next Gen Group of Company
 
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Muzaffar Ahmad
 
SOLAR TRAINING.pptx.pdf
SOLAR TRAINING.pptx.pdfSOLAR TRAINING.pptx.pdf
SOLAR TRAINING.pptx.pdf
AmitKumar497267
 
Off Grid PV System
Off Grid PV SystemOff Grid PV System
Off Grid PV System
Dilawez Alam
 
1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System
Manthan Thakkar
 
Energy Audit Results Presentation
Energy Audit Results PresentationEnergy Audit Results Presentation
Energy Audit Results Presentationeeaadil
 
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine FarmsMichael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
John Blue
 
Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...
Gururaj B Rawoor
 

Similar to Lecture 1 piyush 21 (20)

Solar rooftop market analysis
Solar rooftop market analysisSolar rooftop market analysis
Solar rooftop market analysis
 
Solar PPt.pptx
Solar PPt.pptxSolar PPt.pptx
Solar PPt.pptx
 
Inverted Energy: Diesel Generator Set Replacement
Inverted Energy: Diesel Generator Set Replacement Inverted Energy: Diesel Generator Set Replacement
Inverted Energy: Diesel Generator Set Replacement
 
A Presentation made at the Sri Lanka Institution of Engineers in 2009
A Presentation made at the Sri Lanka Institution of Engineers in 2009A Presentation made at the Sri Lanka Institution of Engineers in 2009
A Presentation made at the Sri Lanka Institution of Engineers in 2009
 
Project of a solar system on the roof of the house of Santa Claus
Project of a solar system on the roof of the house of Santa ClausProject of a solar system on the roof of the house of Santa Claus
Project of a solar system on the roof of the house of Santa Claus
 
Renewable Energy::Pakistan Perspective 2013
Renewable Energy::Pakistan Perspective 2013Renewable Energy::Pakistan Perspective 2013
Renewable Energy::Pakistan Perspective 2013
 
Project of a photovoltaic installation on the roof of the famous Paris Pantheon
Project of a photovoltaic installation on the roof of the famous Paris PantheonProject of a photovoltaic installation on the roof of the famous Paris Pantheon
Project of a photovoltaic installation on the roof of the famous Paris Pantheon
 
The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...
 
Sun trackin solar panel with auto dust cleaning system
Sun trackin solar panel with auto dust cleaning systemSun trackin solar panel with auto dust cleaning system
Sun trackin solar panel with auto dust cleaning system
 
Solar street lights using solar tracker and
Solar street lights using solar tracker and Solar street lights using solar tracker and
Solar street lights using solar tracker and
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13
 
A n srivastava
A n srivastavaA n srivastava
A n srivastava
 
Sopitsuda thailandssolarfit
Sopitsuda thailandssolarfitSopitsuda thailandssolarfit
Sopitsuda thailandssolarfit
 
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
 
SOLAR TRAINING.pptx.pdf
SOLAR TRAINING.pptx.pdfSOLAR TRAINING.pptx.pdf
SOLAR TRAINING.pptx.pdf
 
Off Grid PV System
Off Grid PV SystemOff Grid PV System
Off Grid PV System
 
1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System
 
Energy Audit Results Presentation
Energy Audit Results PresentationEnergy Audit Results Presentation
Energy Audit Results Presentation
 
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine FarmsMichael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
 
Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...
 

More from Dr Piyush Charan

Unit 1- Intro to Wireless Standards.pdf
Unit 1- Intro to Wireless Standards.pdfUnit 1- Intro to Wireless Standards.pdf
Unit 1- Intro to Wireless Standards.pdf
Dr Piyush Charan
 
Unit 1 Solar Collectors
Unit 1 Solar CollectorsUnit 1 Solar Collectors
Unit 1 Solar Collectors
Dr Piyush Charan
 
Unit 5 Quantization
Unit 5 QuantizationUnit 5 Quantization
Unit 5 Quantization
Dr Piyush Charan
 
Unit 4 Lossy Coding Preliminaries
Unit 4 Lossy Coding PreliminariesUnit 4 Lossy Coding Preliminaries
Unit 4 Lossy Coding Preliminaries
Dr Piyush Charan
 
Unit 3 Geothermal Energy
Unit 3 Geothermal EnergyUnit 3 Geothermal Energy
Unit 3 Geothermal Energy
Dr Piyush Charan
 
Unit 2: Programming Language Tools
Unit 2:  Programming Language ToolsUnit 2:  Programming Language Tools
Unit 2: Programming Language Tools
Dr Piyush Charan
 
Unit 4 Arrays
Unit 4 ArraysUnit 4 Arrays
Unit 4 Arrays
Dr Piyush Charan
 
Unit 3 Lecture Notes on Programming
Unit 3 Lecture Notes on ProgrammingUnit 3 Lecture Notes on Programming
Unit 3 Lecture Notes on Programming
Dr Piyush Charan
 
Unit 3 introduction to programming
Unit 3 introduction to programmingUnit 3 introduction to programming
Unit 3 introduction to programming
Dr Piyush Charan
 
Forensics and wireless body area networks
Forensics and wireless body area networksForensics and wireless body area networks
Forensics and wireless body area networks
Dr Piyush Charan
 
Final PhD Defense Presentation
Final PhD Defense PresentationFinal PhD Defense Presentation
Final PhD Defense Presentation
Dr Piyush Charan
 
Unit 3 Arithmetic Coding
Unit 3 Arithmetic CodingUnit 3 Arithmetic Coding
Unit 3 Arithmetic Coding
Dr Piyush Charan
 
Unit 2 Lecture notes on Huffman coding
Unit 2 Lecture notes on Huffman codingUnit 2 Lecture notes on Huffman coding
Unit 2 Lecture notes on Huffman coding
Dr Piyush Charan
 
Unit 1 Introduction to Data Compression
Unit 1 Introduction to Data CompressionUnit 1 Introduction to Data Compression
Unit 1 Introduction to Data Compression
Dr Piyush Charan
 
Unit 3 Dictionary based Compression Techniques
Unit 3 Dictionary based Compression TechniquesUnit 3 Dictionary based Compression Techniques
Unit 3 Dictionary based Compression Techniques
Dr Piyush Charan
 
Unit 1 Introduction to Non-Conventional Energy Resources
Unit 1 Introduction to Non-Conventional Energy ResourcesUnit 1 Introduction to Non-Conventional Energy Resources
Unit 1 Introduction to Non-Conventional Energy Resources
Dr Piyush Charan
 
Unit 5-Operational Amplifiers and Electronic Measurement Devices
Unit 5-Operational Amplifiers and Electronic Measurement DevicesUnit 5-Operational Amplifiers and Electronic Measurement Devices
Unit 5-Operational Amplifiers and Electronic Measurement Devices
Dr Piyush Charan
 
Unit 1 Introduction to Data Compression
Unit 1 Introduction to Data CompressionUnit 1 Introduction to Data Compression
Unit 1 Introduction to Data Compression
Dr Piyush Charan
 
Unit 4 Switching Theory and Logic Gates
Unit 4 Switching Theory and Logic GatesUnit 4 Switching Theory and Logic Gates
Unit 4 Switching Theory and Logic Gates
Dr Piyush Charan
 
Unit 1 Numerical Problems on PN Junction Diode
Unit 1 Numerical Problems on PN Junction DiodeUnit 1 Numerical Problems on PN Junction Diode
Unit 1 Numerical Problems on PN Junction Diode
Dr Piyush Charan
 

More from Dr Piyush Charan (20)

Unit 1- Intro to Wireless Standards.pdf
Unit 1- Intro to Wireless Standards.pdfUnit 1- Intro to Wireless Standards.pdf
Unit 1- Intro to Wireless Standards.pdf
 
Unit 1 Solar Collectors
Unit 1 Solar CollectorsUnit 1 Solar Collectors
Unit 1 Solar Collectors
 
Unit 5 Quantization
Unit 5 QuantizationUnit 5 Quantization
Unit 5 Quantization
 
Unit 4 Lossy Coding Preliminaries
Unit 4 Lossy Coding PreliminariesUnit 4 Lossy Coding Preliminaries
Unit 4 Lossy Coding Preliminaries
 
Unit 3 Geothermal Energy
Unit 3 Geothermal EnergyUnit 3 Geothermal Energy
Unit 3 Geothermal Energy
 
Unit 2: Programming Language Tools
Unit 2:  Programming Language ToolsUnit 2:  Programming Language Tools
Unit 2: Programming Language Tools
 
Unit 4 Arrays
Unit 4 ArraysUnit 4 Arrays
Unit 4 Arrays
 
Unit 3 Lecture Notes on Programming
Unit 3 Lecture Notes on ProgrammingUnit 3 Lecture Notes on Programming
Unit 3 Lecture Notes on Programming
 
Unit 3 introduction to programming
Unit 3 introduction to programmingUnit 3 introduction to programming
Unit 3 introduction to programming
 
Forensics and wireless body area networks
Forensics and wireless body area networksForensics and wireless body area networks
Forensics and wireless body area networks
 
Final PhD Defense Presentation
Final PhD Defense PresentationFinal PhD Defense Presentation
Final PhD Defense Presentation
 
Unit 3 Arithmetic Coding
Unit 3 Arithmetic CodingUnit 3 Arithmetic Coding
Unit 3 Arithmetic Coding
 
Unit 2 Lecture notes on Huffman coding
Unit 2 Lecture notes on Huffman codingUnit 2 Lecture notes on Huffman coding
Unit 2 Lecture notes on Huffman coding
 
Unit 1 Introduction to Data Compression
Unit 1 Introduction to Data CompressionUnit 1 Introduction to Data Compression
Unit 1 Introduction to Data Compression
 
Unit 3 Dictionary based Compression Techniques
Unit 3 Dictionary based Compression TechniquesUnit 3 Dictionary based Compression Techniques
Unit 3 Dictionary based Compression Techniques
 
Unit 1 Introduction to Non-Conventional Energy Resources
Unit 1 Introduction to Non-Conventional Energy ResourcesUnit 1 Introduction to Non-Conventional Energy Resources
Unit 1 Introduction to Non-Conventional Energy Resources
 
Unit 5-Operational Amplifiers and Electronic Measurement Devices
Unit 5-Operational Amplifiers and Electronic Measurement DevicesUnit 5-Operational Amplifiers and Electronic Measurement Devices
Unit 5-Operational Amplifiers and Electronic Measurement Devices
 
Unit 1 Introduction to Data Compression
Unit 1 Introduction to Data CompressionUnit 1 Introduction to Data Compression
Unit 1 Introduction to Data Compression
 
Unit 4 Switching Theory and Logic Gates
Unit 4 Switching Theory and Logic GatesUnit 4 Switching Theory and Logic Gates
Unit 4 Switching Theory and Logic Gates
 
Unit 1 Numerical Problems on PN Junction Diode
Unit 1 Numerical Problems on PN Junction DiodeUnit 1 Numerical Problems on PN Junction Diode
Unit 1 Numerical Problems on PN Junction Diode
 

Recently uploaded

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

Lecture 1 piyush 21

  • 1. 1 MW SCALE SOLAR PV POWER PLANT By: Piyush Charan Assistant Professor, Integral University, Lucknow
  • 2. Background  Solar energy is free source of energy  Solar radiation on earth surface per hour is equal to total power consumption of earth for whole year.  Grid power in India is polluting, unreliable and inefficient  Solar energy is a renewable, clean alternative to fossil fuels.  solar energy is converted into electricity by using either photo-voltaic or solar thermal
  • 3. A modest 2.5kw solar power system can have over its lifetime equivalent to 300 barrels of oil not produced 270,000 miles not driven 1,100 lbs of acid rain emissions not discharged 550 lbs of smog emissions not produced 220,000 lbs of greenhouse gases not emitted equivalent to planting 500 trees. Solar Energy vs Conventional Energ
  • 4. •Jawaharlal Nehru National Solar Mission (MNRE, Govt of India) launched in, 2010 by the Prime Minister, a target of deploying 20,000 MW of grid connected solar power by 2022. It is enhanced by new government to 100,000 MW. Target by 2022 Old Revised •Solar power 20,000 MW 100,000 MW •Wind Energy 38500 MW 60,000 MW • Others 13500 MW 15,000 MW •Total 72,000 MW 175,000 MW (Installed capacity of india as on April 2015 : 274,818 MW including renewable Energy 35,777 MW) Source: cea.nic.in powermin.nic.in
  • 5. Incentives to Solar power plant • Various incentives offered by central and state government, few of them are • Benefit in land registration for solar power plant • 15-30 % subsidy for sanctioned project for equipments. • Support in grid connectivity • Depreciation benefits
  • 6. 1MW SPV Power Plant : Initial costing Sr NoItem Unit @ rate Cost (lac) 1 Land 6 Acre 600000 36 2 Modules 1100000 Watt 33 363 3 Civil Structure 60,500 Kg 66 44 4 Inverter 1100000 VA 11 121 5 Transformer 1 27,00,000 27 6 Protective devices 1 10 7 Wires, Cables 10 8 SCADA/RMS 10 9 Installation 10 10 Legal & official work 24 11 Grid Evacuation 10 12 Execution & commisioning 30 Total 695
  • 7. 1MW SPV Power Plant: Financial Plant Capacity 1000 KW Plant Cost (in lacs) 0.695 lac/KW 695 Equity 30% 208.5 Debt 70% 486.5 Interst rate 12% 1.01 Payment Period (yrs) 9 108 EMI 7.3871 Maintenance & Manpower 3% P V of Inverter Cost 132 Price reduction rate of Inverter 2% • Area Shade free 3 Acre Only 80% of the input area is considered to adjust for potential shaded areas • Maintenance & Manpower 4% of project cost, with annual escalation of 5% • Inverter lifespan is 10 years, with 2.00% annual cost reduction (110 % of capacity, @Rs 11/W) • Accelerated depreciation is at 80.00%. It is assumed that the entire benefit of accelerated depreciation can be claimed • Corporate tax rate 35% • Plant generation 4.7 kWh per KW per day, with 1% annual panel degradation and 10% losses10% • Debt service calculation assumes 70.00% debt; 2.00% interest rate; 9-year loan term with no moratorium; repayable monthly through EMI • Tariff 7.5 /KWH through PPA for 12 years • Annual inflation 7%
  • 8. 1MW SPV Power Plant : Financial in lacs Year Plant Expenditure Net Yearly Expend Generation return by power selling REC Return @ 3000/ MWH Net Return Present value of Net return Equity/ Inverter replacem ent Mainten ance Debt Int Debt Prin Power Unit (MWH) Tariff Rs per KWH earning 0 208.50 -208.50 - 208.50 -208.50 -208.50 1 20.85 56.66 31.99 -109.50 1478 7.50 110.85 1.35 1.35 1.27 2 21.89 52.60 36.04 -110.54 1463 7.50 109.73 -0.81 44.00 43.19 37.72 3 22.99 48.03 40.61 -111.63 1449 7.50 108.68 -2.96 43.00 40.04 32.69 4 24.14 42.88 45.77 -112.78 1434 7.50 107.55 -5.23 43.00 37.77 28.81 5 25.34 37.08 51.57 -113.99 1420 7.50 106.50 -7.49 43.00 35.51 25.32 6 26.61 30.54 58.11 -115.26 1406 7.50 105.45 -9.81 42.00 32.19 21.45 7 27.94 23.17 65.48 -116.59 1392 7.50 104.40 -12.19 42.00 29.81 18.57 8 29.34 14.86 73.78 -117.98 1378 7.50 103.35 -14.63 41.00 26.37 15.35 9 30.80 5.50 83.14 -119.45 1364 7.50 102.30 -17.15 41.00 23.85 12.97 10 108.29 32.35 0.00 0.00 -140.63 1350 7.50 101.25 -39.38 41.00 1.62 0.82 11 33.96 -33.96 1337 7.50 100.28 66.31 40.00 106.31 50.51 12 35.66 -35.66 1324 7.50 99.30 63.64 40.00 103.64 46.02
  • 9. 1MW SPV Power Plant : Financial in lacs Year Plant Expenditure Net Yearly Expen Generation return by power selling REC Return @ 3000/ MWH Net Return Presen t value of Net return Equity/ Inverter replace ment Mainten ece Debt Int Debt Prin Power Unit (MWH) Tariff Rs per KWH earning 13 37.44 -37.44 1310 10.00 131.00 93.56 39.00 132.56 55.01 14 39.32 -39.32 1297 10.00 129.70 90.38 39.00 129.38 50.18 15 41.28 -41.28 1284 10.00 128.40 87.12 39.00 126.12 45.71 16 43.35 -43.35 1271 10.00 127.10 83.75 38.00 121.75 41.24 17 45.51 -45.51 1259 10.00 125.90 80.39 38.00 118.39 37.48 18 47.79 -47.79 1246 10.00 124.60 76.81 37.00 113.81 33.67 19 50.18 -50.18 1234 10.00 123.40 73.22 37.00 110.22 30.48 20 88.83 52.69 -141.52 1221 10.00 122.10 -19.42 37.00 17.58 4.54 21 55.32 -55.32 1209 10.00 120.90 65.58 36.00 101.58 24.53 22 58.09 -58.09 1197 10.00 119.70 61.61 36.00 97.61 22.03 23 60.99 -60.99 1185 10.00 118.50 57.51 36.00 93.51 19.73 24 64.04 -64.04 1173 10.00 117.30 53.26 35.00 88.26 17.40 25 67.24 -67.24 1161 10.00 116.10 48.86 35.00 83.86 15.45 405.62 995.11 311.31 486.50-2198.54 32842.00 220.002864.33 665.79 942.001607.79 480.44
  • 10. 1MW SPV Power Plant : Financial • Initial Investment : 6.950 crore Equity : 2.085 crore Debt : 4.865 crore • Present Value of Investment : 12.56 crore • Present Value of earning (PPA & REC) : 17.36 crore • Present Value of Profit before tax :4.80 crore • Payback period : 6 years • Levelized cost of power : Rs 3.28/unit • After payback period capacity enhancement of another 1 MW in same land can be done with maintenance covered by first project (conservative estimate of earning is made. No incentive by government is considered in investment)