PROJECT PAPER
PROJEK INTERGRASI GASIFIKASI
SISA PEPEJAL & SOLAR POWER
BANDAR-BANDAR DI
TERENGGANU
Prepared by:
Dato’ Ir. Hj. Mat Isa Kadir
PRESENTATION CONTENTS
2
FASA 1- 650TPD Waste To Energy Gasification Power Plant
FASA 2- 30 MW Solar Photovoltaic Power Plant
2.1 Introduction& Purpose
2.2 Company Profile
2.3 What Photovoltaic Power Plant
2.4 Our Experience
2.5 The Proposed Solar Project
2.5.1 Site Location
2.5.2 Financial Forecast
2.5.3 Project Schedule
2.6 Our Request to Terengganu State
3
PROPOSED 50MW SOLAR POWER
PLANT AT KUALA TERENGGANU
( PHASE 2)
2.1 Introduction & Purpose
OBJECTIVE OF PROPOSAL
5
1. To brief YAB Menteri Besar on technical and financial aspects of the
proposal to build and operate a large scale 50MW Solar Power Plant
at Kampong Sungai Ikan in Kuala Terengganu.
2. To seek UPEN/State approval to develop the 50MW Solar
Photovoltaic Power plant at Kpg Sungai Ikan, Kuala Terengganu.
3. To seek Terengganu State Approval to acquire the Land of 120 acres
at Kg. Sungai Ikan Government Land for the building the Solar Power
Plant.
4. To seek YAB Menteri Besar’s support letter for us to apply for Power
Purchase Agreement (PPA) with TNB via Kementerian Tenaga, Tenaga
Hijau, dan Air ( KETTHA) and/or SEDA.
BENEFITS TO TERENGGANU
& MSIA
6
1. Environmental: Reduction of more than 90,000 tons of CO2
emission per year
2. Environmental: Reduce annual fossil fuel usage equivalent to
360,000Gj of Gas or 16,750 tons of Coal.
3. Social: Supply of clean, GREEN electric power to
20,500 rural houses.
4. Economic: Spur the state economic stance by
creating of employment to the local
population.
5. Education: Educating public on RE, become a
study/research center for TATIUC, UMT, etc
6. Manpower: To be the center of trining for undergraduate under
TVET scheme, Ministry of Higher Education
7. Tourism: Establishing land-mark as one of the
biggest single solar power plant in Malaysia
2.2 Company Profile
9
Tati Pro Energy Sdn Bhd
Tati Pro Energy Sdn. Bhd. (TPE) is collaborating
with Pengasus Capital. USA under TPE-PCA
Consortium to build a 50MWp Solar Power
Plant in Kuala Terengganu.
TATI Pro Energy Sdn. Bhd. was established as a
competent management & EPCC & investment
arm company serving the power generation, oil
& gas, and petrochemical industries.
We have our expertise in the renewable energy,
power cogeneration system. & oil /gas system
Over the years, TPE had evolved into a multi-discipline engineering company,
executing reputable projects together with reputable EPCC contractor . TATI has
gained an enviable reputation through provision of high engineering solutions, on
scheduled completion, competitive process and an invaluable customers services
to our customer.
10
Pegasus Capital LLC
TPE - PCA Consortium is owned by
Pegasus Capital.
Pegasus Capital Advisors, L.P. is a
private equity fund manager that
has been providing creative capital
and strategic solutions to
companies across a variety of
industries since 1996. Pegasus
partners with management teams
of growth companies, with a focus
on those that benefit from the
business implications of global
resource scarcity. Sectors where
this trend is most pronounced are
food, water, energy, health &
wellness and security.
PEGASUS is currently manage approximately
USD1.8 billion in assets. Our investment team
comprises over 50 talented investment
professionals and operating/strategic advisors.
11
KNM Renewable Energy Sdn Bhd
• Subsidiary of KNM Group Berhad
• Established in 1990
• Malaysian Home Grown Multi-
National Head office in MALAYSIA
• Listed on the Bursa Malaysia
Securities Berhad since 2003
• Revenue : About RM 2.5 Billion per
annum
• Over 5,500 employees worldwide
• One Stop Centre for World Class
Process Equipment & Industrial
Plants
• Strong portfolio of international
brands KNM, BORSIG, FBM-Hudson
& W.E. Smith
• More than 170 years of project
experience across the world in over
80 countries
Innova Benelux
Innova Benelux-WCT Ltd, an international project development company
from Germany/Belgium, with an established networks in solar energy, and
renewable energy expertise, will provide project management and project
development support and assume the role of EPC.
13
2.3 What Photovoltaic Power Plant
Solar Power System
14
Solar PV System , also known as Photovotaic system, is a process
whereby the sun's radiation is converted into usable electricity
by using photovoltaics arranging in several components, including
solar panels to absorb and directly convert sunlight into electricity,
a solar inverter to change the electrical current from DC to AC,
as well as mounting, cabling and other electrical accessories
to set-up a working system.
Schematics of a typical Grid-connected Solar PV system
Efficiency of Solar Panel
15
The viability &profitability of the project depend upon the amount of sunshine
that can be captured and the technology and proven durability of the Solar
PV Technology installed. The Power of the sun is about 1 kW/m, on the Earth's
surface, to a plane that is perpendicular to the sun's rays and solar panels
have an efficiency ranging from 17% to 27%.
With an effectiveness of 150 W/sq. M with 7000 m per sq. hectare, the power
output per one hectare will be around 1 MWp. (7000 sq. M x 150 Wp).
Hence 50 Hectares land size for modules will generate a peak power of 50
MW. The “p” or peak period will be less before and after noon at 12 O’ clock
on cloudless day
A system with a size of 1 kWp installed delivers about 1310 kWh per year
(Crystalline silica or Polysilicon modules) and varies with locations.
2.4 Our Experience
Our Experience 1
Our Experience 2
Our Experience 3
Our Experience 4
Our Experience 5
Oct/4/2013 22
Process of installation of Solar Power Plant in Germany
1. PLANNING
2
3
7.
6
4.
5
Our Experience 6
2.5 The Proposed 30MW
PV Solar Power Plant
2.5.1 Site Location
24
25
Location : Kg Sg Ikan Kuala Terengganu, Terengganu,
30km West Kuala Terengganu,20km from
KT Airport
Land Area : 120 acres, situated by side of main federal
road and having ease access to
neighbouring roadways
50MW require: Solar farm Land requirement 120
acres if using Benelux Technology
Distance PMU: Within the site area with capacity of
33KV/11KV
Others infor: This site is a vacant government area owned
by the State Government ( as on September
2015)
Brief Site Information
Proposed Location
26At Kg Sg Ikan Kuala Terengganu
Proposed Location
27At Kg Sg Ikan Kuala Terengganu
Proposed Location
28At Kg Sg Ikan Kuala Terengganu
2.5.2 Financial Forecast
29
30
Total project cost: USD83 million (RM332 million)
Cost per MW: USD1.7 million (competitive
market price)
Potential yield per year: 1,230 KWh/ Ha
Minimum (DSCR): 1.30 Debt Service Coverage
Ratio
Finance cost of interest: 0% per annum
IRR Project: 17.4%
NPV: Positive
Payback: 5.66 years
Financial Summary
Expected Profitability
31
Expected Profitability
32
Expected Profitability
33
2.5.3 Project Schedule
TIME-LINE
2.6 Our Request to
Terengganu State
36
1. Strong support letter to Tati Pro Energy from the State
Government in order for us to apply for PPA
(Power Purchase Agreement) to KETTHA
(Kementerian Tenaga & Tenaga Hijau dan Air)
2. State to provide land under Terengganu GLC as the GLC will
be the Co-developer/owner of the project partnering TPE-PCA
Consortium.
3. Others relevant approval/permits such as Majlis
Perbandaran, etc, etc
Our Request to State Government
Conditions for PPA eligibility set by
KETTHA
1) Strong State support letter to Tati Pro
Energy Sdn Bhd
2) Land availability, suitability & near to
PMU
3) Technically sounds company having
proven solar technology
4) Project funding capability
5) Experience in Solar power plants
installation
Conditions for PPA

More Related Content

What's hot

Utm slide cfo & ccc [compatibility mode]
Utm slide cfo & ccc [compatibility mode]Utm slide cfo & ccc [compatibility mode]
Utm slide cfo & ccc [compatibility mode]
Aeisyah Suhaili
 
A. portofolio ardi jiwandori
A. portofolio ardi jiwandoriA. portofolio ardi jiwandori
A. portofolio ardi jiwandori
Ardi Jiwandori
 
LAND LAW - Kuasa PBN
LAND LAW - Kuasa PBNLAND LAW - Kuasa PBN
LAND LAW - Kuasa PBN
AmirulAfiq30
 
Pengalaman di hari raya aidilfitri
Pengalaman di hari raya aidilfitriPengalaman di hari raya aidilfitri
Pengalaman di hari raya aidilfitri
asiyah97
 
Bio amali 2 tropisme
Bio amali 2   tropismeBio amali 2   tropisme
Bio amali 2 tropisme
Kevin Ming
 
Kajian Dapur Solar
Kajian Dapur SolarKajian Dapur Solar
Kajian Dapur Solaranuar032
 
Peranan dan tanggungjawab jawantankuasa pengurusan makmal sains
Peranan dan tanggungjawab jawantankuasa pengurusan makmal sainsPeranan dan tanggungjawab jawantankuasa pengurusan makmal sains
Peranan dan tanggungjawab jawantankuasa pengurusan makmal sains
mamadanial
 
Meor atiqulrahman ishak & yang lain
Meor atiqulrahman ishak & yang lainMeor atiqulrahman ishak & yang lain
Meor atiqulrahman ishak & yang lainazah narowi
 
Teknologi hijau
Teknologi hijauTeknologi hijau
Teknologi hijau
huzaifahsubky
 
NILAI HORMAT-MENGHORMATI
NILAI HORMAT-MENGHORMATINILAI HORMAT-MENGHORMATI
NILAI HORMAT-MENGHORMATI
Atiqah Noor
 
surat mohon maaf menolak tawaran latihan industri
surat mohon maaf menolak tawaran latihan industrisurat mohon maaf menolak tawaran latihan industri
surat mohon maaf menolak tawaran latihan industri
Xiao Doubles
 
Menjawab kps
Menjawab kpsMenjawab kps
Menjawab kps
AinIbrahim8
 
B2 morfologi (membina ayat)
B2 morfologi (membina ayat)B2 morfologi (membina ayat)
B2 morfologi (membina ayat)
Kementerian Pelajaran Malaysia
 
Laporan Akhir Latihan Industri
Laporan Akhir Latihan IndustriLaporan Akhir Latihan Industri
Laporan Akhir Latihan Industri
Kizizikachi Izzat
 
Art 13 rights to property
Art 13   rights to propertyArt 13   rights to property
Art 13 rights to property
Hafizul Mukhlis
 
Surat sumbangan
Surat sumbanganSurat sumbangan
Surat sumbanganfaraara
 
DI SEBALIK DINARA PENGAJARAN
DI SEBALIK DINARA PENGAJARANDI SEBALIK DINARA PENGAJARAN
DI SEBALIK DINARA PENGAJARAN
Shamsul Ponijan
 
Akta perkongsian 1961 pdf
Akta perkongsian 1961 pdfAkta perkongsian 1961 pdf
Akta perkongsian 1961 pdf
Atiqah Nuratiqah
 

What's hot (20)

Utm slide cfo & ccc [compatibility mode]
Utm slide cfo & ccc [compatibility mode]Utm slide cfo & ccc [compatibility mode]
Utm slide cfo & ccc [compatibility mode]
 
A. portofolio ardi jiwandori
A. portofolio ardi jiwandoriA. portofolio ardi jiwandori
A. portofolio ardi jiwandori
 
LAND LAW - Kuasa PBN
LAND LAW - Kuasa PBNLAND LAW - Kuasa PBN
LAND LAW - Kuasa PBN
 
Pengalaman di hari raya aidilfitri
Pengalaman di hari raya aidilfitriPengalaman di hari raya aidilfitri
Pengalaman di hari raya aidilfitri
 
Rancangan buku hijau
Rancangan buku hijau Rancangan buku hijau
Rancangan buku hijau
 
Bio amali 2 tropisme
Bio amali 2   tropismeBio amali 2   tropisme
Bio amali 2 tropisme
 
Kajian Dapur Solar
Kajian Dapur SolarKajian Dapur Solar
Kajian Dapur Solar
 
Peranan dan tanggungjawab jawantankuasa pengurusan makmal sains
Peranan dan tanggungjawab jawantankuasa pengurusan makmal sainsPeranan dan tanggungjawab jawantankuasa pengurusan makmal sains
Peranan dan tanggungjawab jawantankuasa pengurusan makmal sains
 
Meor atiqulrahman ishak & yang lain
Meor atiqulrahman ishak & yang lainMeor atiqulrahman ishak & yang lain
Meor atiqulrahman ishak & yang lain
 
Teknologi hijau
Teknologi hijauTeknologi hijau
Teknologi hijau
 
cyberpreneurship
cyberpreneurshipcyberpreneurship
cyberpreneurship
 
NILAI HORMAT-MENGHORMATI
NILAI HORMAT-MENGHORMATINILAI HORMAT-MENGHORMATI
NILAI HORMAT-MENGHORMATI
 
surat mohon maaf menolak tawaran latihan industri
surat mohon maaf menolak tawaran latihan industrisurat mohon maaf menolak tawaran latihan industri
surat mohon maaf menolak tawaran latihan industri
 
Menjawab kps
Menjawab kpsMenjawab kps
Menjawab kps
 
B2 morfologi (membina ayat)
B2 morfologi (membina ayat)B2 morfologi (membina ayat)
B2 morfologi (membina ayat)
 
Laporan Akhir Latihan Industri
Laporan Akhir Latihan IndustriLaporan Akhir Latihan Industri
Laporan Akhir Latihan Industri
 
Art 13 rights to property
Art 13   rights to propertyArt 13   rights to property
Art 13 rights to property
 
Surat sumbangan
Surat sumbanganSurat sumbangan
Surat sumbangan
 
DI SEBALIK DINARA PENGAJARAN
DI SEBALIK DINARA PENGAJARANDI SEBALIK DINARA PENGAJARAN
DI SEBALIK DINARA PENGAJARAN
 
Akta perkongsian 1961 pdf
Akta perkongsian 1961 pdfAkta perkongsian 1961 pdf
Akta perkongsian 1961 pdf
 

Viewers also liked

Kemaman msw waste to energy gasification power plant
Kemaman msw waste to energy gasification power plantKemaman msw waste to energy gasification power plant
Kemaman msw waste to energy gasification power plant
Dato Mat Isa
 
Tenaga Boleh Baharu & Kecekapan Tenaga
Tenaga Boleh Baharu & Kecekapan TenagaTenaga Boleh Baharu & Kecekapan Tenaga
Tenaga Boleh Baharu & Kecekapan Tenaga
mohdsukri2000
 
Solar Power Plant Solution
Solar Power Plant SolutionSolar Power Plant Solution
Solar Power Plant Solution
vinodpandeyaxcend
 
Indonesia
IndonesiaIndonesia
science project 1
science project 1science project 1
science project 1
Wan Nurhidayati Wan Johari
 
mini gasification for handling MSW at upstream
mini gasification for handling MSW at upstreammini gasification for handling MSW at upstream
mini gasification for handling MSW at upstream
Dato Mat Isa
 
Smart city, a city which applies technologies making the city more usable for...
Smart city, a city which applies technologies making the city more usable for...Smart city, a city which applies technologies making the city more usable for...
Smart city, a city which applies technologies making the city more usable for...
Bristol Is Open
 
Melaka Greencity Cogeneration system
Melaka Greencity Cogeneration systemMelaka Greencity Cogeneration system
Melaka Greencity Cogeneration system
Dato Mat Isa
 
Modul kecekapan tenaga
Modul kecekapan tenagaModul kecekapan tenaga
Modul kecekapan tenagaMohd Ridzuan
 
Cicatih mini hydro site visit report
Cicatih mini hydro site visit report Cicatih mini hydro site visit report
Cicatih mini hydro site visit report
Dato Mat Isa
 
Panduan ringkas amalan kecekapan tenaga di rumah
Panduan ringkas amalan kecekapan tenaga di rumahPanduan ringkas amalan kecekapan tenaga di rumah
Panduan ringkas amalan kecekapan tenaga di rumah
ZAINI ABDUL WAHAB
 
Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...
Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...
Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...
Smart Villages
 
Cara ternak Udang kara lobster air tawar LAT di 017-2839861.
Cara ternak Udang kara lobster air tawar LAT di 017-2839861. Cara ternak Udang kara lobster air tawar LAT di 017-2839861.
Cara ternak Udang kara lobster air tawar LAT di 017-2839861.
Rena zainal2
 
Impact Investment in Mini Hydropower, Indonesia 2013
Impact Investment in Mini Hydropower, Indonesia 2013Impact Investment in Mini Hydropower, Indonesia 2013
Impact Investment in Mini Hydropower, Indonesia 2013
Eric Stryson
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
Nikhil Jaipurkar
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
Rajeev Kumar
 
Pengenalan kepada aplikasi penjimatan tenaga
Pengenalan kepada aplikasi penjimatan tenagaPengenalan kepada aplikasi penjimatan tenaga
Pengenalan kepada aplikasi penjimatan tenaga
ZAINI ABDUL WAHAB
 
Micro hydro power plant final 1
Micro hydro power plant final 1Micro hydro power plant final 1
Micro hydro power plant final 1
richa khatri
 
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Ryan Triadhitama
 
Final Year Project Presentation
Final Year Project Presentation Final Year Project Presentation
Final Year Project Presentation
As-Sufi Safwan Hashim
 

Viewers also liked (20)

Kemaman msw waste to energy gasification power plant
Kemaman msw waste to energy gasification power plantKemaman msw waste to energy gasification power plant
Kemaman msw waste to energy gasification power plant
 
Tenaga Boleh Baharu & Kecekapan Tenaga
Tenaga Boleh Baharu & Kecekapan TenagaTenaga Boleh Baharu & Kecekapan Tenaga
Tenaga Boleh Baharu & Kecekapan Tenaga
 
Solar Power Plant Solution
Solar Power Plant SolutionSolar Power Plant Solution
Solar Power Plant Solution
 
Indonesia
IndonesiaIndonesia
Indonesia
 
science project 1
science project 1science project 1
science project 1
 
mini gasification for handling MSW at upstream
mini gasification for handling MSW at upstreammini gasification for handling MSW at upstream
mini gasification for handling MSW at upstream
 
Smart city, a city which applies technologies making the city more usable for...
Smart city, a city which applies technologies making the city more usable for...Smart city, a city which applies technologies making the city more usable for...
Smart city, a city which applies technologies making the city more usable for...
 
Melaka Greencity Cogeneration system
Melaka Greencity Cogeneration systemMelaka Greencity Cogeneration system
Melaka Greencity Cogeneration system
 
Modul kecekapan tenaga
Modul kecekapan tenagaModul kecekapan tenaga
Modul kecekapan tenaga
 
Cicatih mini hydro site visit report
Cicatih mini hydro site visit report Cicatih mini hydro site visit report
Cicatih mini hydro site visit report
 
Panduan ringkas amalan kecekapan tenaga di rumah
Panduan ringkas amalan kecekapan tenaga di rumahPanduan ringkas amalan kecekapan tenaga di rumah
Panduan ringkas amalan kecekapan tenaga di rumah
 
Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...
Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...
Kuching | Jan-15 | Hydro Power Technology Development in Indonesia Lessons le...
 
Cara ternak Udang kara lobster air tawar LAT di 017-2839861.
Cara ternak Udang kara lobster air tawar LAT di 017-2839861. Cara ternak Udang kara lobster air tawar LAT di 017-2839861.
Cara ternak Udang kara lobster air tawar LAT di 017-2839861.
 
Impact Investment in Mini Hydropower, Indonesia 2013
Impact Investment in Mini Hydropower, Indonesia 2013Impact Investment in Mini Hydropower, Indonesia 2013
Impact Investment in Mini Hydropower, Indonesia 2013
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
 
Pengenalan kepada aplikasi penjimatan tenaga
Pengenalan kepada aplikasi penjimatan tenagaPengenalan kepada aplikasi penjimatan tenaga
Pengenalan kepada aplikasi penjimatan tenaga
 
Micro hydro power plant final 1
Micro hydro power plant final 1Micro hydro power plant final 1
Micro hydro power plant final 1
 
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)
 
Final Year Project Presentation
Final Year Project Presentation Final Year Project Presentation
Final Year Project Presentation
 

Similar to Integrated wte gasification & solar power plant for Terengganu

Ipp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fullerIpp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fuller
Peter Cockcroft
 
Staten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicantsStaten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicants
Rakesh Singh
 
Smart Grid to Drive the Energy Storage Market
Smart Grid to Drive the Energy Storage MarketSmart Grid to Drive the Energy Storage Market
Smart Grid to Drive the Energy Storage Market
Amit Singh
 
Proposal solar
Proposal solarProposal solar
Proposal solar
Sashikant Tiwari
 
BTE-Digital-Brochure.pdf
BTE-Digital-Brochure.pdfBTE-Digital-Brochure.pdf
BTE-Digital-Brochure.pdf
XolaniRadebeRadebe
 
영문=10mw. fiji
영문=10mw. fiji영문=10mw. fiji
영문=10mw. fiji
YongGi Kim 김용기
 
Zorays Inc.
Zorays Inc.Zorays Inc.
Peripheral interface controller-based maximum power point tracking algorithm ...
Peripheral interface controller-based maximum power point tracking algorithm ...Peripheral interface controller-based maximum power point tracking algorithm ...
Peripheral interface controller-based maximum power point tracking algorithm ...
TELKOMNIKA JOURNAL
 
CV Peter Heinzelmann
CV Peter HeinzelmannCV Peter Heinzelmann
CV Peter Heinzelmann
Peter Heinzelmann
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
ratnajiundavalli
 
Soventix Company Presentation
Soventix Company PresentationSoventix Company Presentation
Soventix Company Presentation
Kirchhoff Consult AG
 
Ewi profile eng new
Ewi profile eng newEwi profile eng new
Ewi profile eng new
Johnson Pit
 
Renewable energy program particularly the solar pv in buildings in Malaysia (...
Renewable energy program particularly the solar pv in buildings in Malaysia (...Renewable energy program particularly the solar pv in buildings in Malaysia (...
Renewable energy program particularly the solar pv in buildings in Malaysia (...
Steve Lojuntin
 
ENERGIAS-MARINAS_CAT_EN
ENERGIAS-MARINAS_CAT_ENENERGIAS-MARINAS_CAT_EN
ENERGIAS-MARINAS_CAT_EN
TECNALIA Marine Energy
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.
Hagi Sahib
 
solar consultants corporate credentials (1).pdf
solar consultants corporate credentials  (1).pdfsolar consultants corporate credentials  (1).pdf
solar consultants corporate credentials (1).pdf
sanjay vashishtha
 
PV Cottage Industry in Malaysia
PV Cottage Industry in MalaysiaPV Cottage Industry in Malaysia
PV Cottage Industry in Malaysia
Noor Shahiwan
 
HARTEK POWER - SOLAR PROFILE
HARTEK POWER - SOLAR PROFILE HARTEK POWER - SOLAR PROFILE
HARTEK POWER - SOLAR PROFILE
HARTEK POWER
 
Renewable Energy & Entrepreneurship Workshop_21Feb2024.pdf
Renewable Energy & Entrepreneurship Workshop_21Feb2024.pdfRenewable Energy & Entrepreneurship Workshop_21Feb2024.pdf
Renewable Energy & Entrepreneurship Workshop_21Feb2024.pdf
odunowoeminence2019
 
NTPC LTD.
NTPC LTD.NTPC LTD.

Similar to Integrated wte gasification & solar power plant for Terengganu (20)

Ipp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fullerIpp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fuller
 
Staten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicantsStaten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicants
 
Smart Grid to Drive the Energy Storage Market
Smart Grid to Drive the Energy Storage MarketSmart Grid to Drive the Energy Storage Market
Smart Grid to Drive the Energy Storage Market
 
Proposal solar
Proposal solarProposal solar
Proposal solar
 
BTE-Digital-Brochure.pdf
BTE-Digital-Brochure.pdfBTE-Digital-Brochure.pdf
BTE-Digital-Brochure.pdf
 
영문=10mw. fiji
영문=10mw. fiji영문=10mw. fiji
영문=10mw. fiji
 
Zorays Inc.
Zorays Inc.Zorays Inc.
Zorays Inc.
 
Peripheral interface controller-based maximum power point tracking algorithm ...
Peripheral interface controller-based maximum power point tracking algorithm ...Peripheral interface controller-based maximum power point tracking algorithm ...
Peripheral interface controller-based maximum power point tracking algorithm ...
 
CV Peter Heinzelmann
CV Peter HeinzelmannCV Peter Heinzelmann
CV Peter Heinzelmann
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Soventix Company Presentation
Soventix Company PresentationSoventix Company Presentation
Soventix Company Presentation
 
Ewi profile eng new
Ewi profile eng newEwi profile eng new
Ewi profile eng new
 
Renewable energy program particularly the solar pv in buildings in Malaysia (...
Renewable energy program particularly the solar pv in buildings in Malaysia (...Renewable energy program particularly the solar pv in buildings in Malaysia (...
Renewable energy program particularly the solar pv in buildings in Malaysia (...
 
ENERGIAS-MARINAS_CAT_EN
ENERGIAS-MARINAS_CAT_ENENERGIAS-MARINAS_CAT_EN
ENERGIAS-MARINAS_CAT_EN
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.
 
solar consultants corporate credentials (1).pdf
solar consultants corporate credentials  (1).pdfsolar consultants corporate credentials  (1).pdf
solar consultants corporate credentials (1).pdf
 
PV Cottage Industry in Malaysia
PV Cottage Industry in MalaysiaPV Cottage Industry in Malaysia
PV Cottage Industry in Malaysia
 
HARTEK POWER - SOLAR PROFILE
HARTEK POWER - SOLAR PROFILE HARTEK POWER - SOLAR PROFILE
HARTEK POWER - SOLAR PROFILE
 
Renewable Energy & Entrepreneurship Workshop_21Feb2024.pdf
Renewable Energy & Entrepreneurship Workshop_21Feb2024.pdfRenewable Energy & Entrepreneurship Workshop_21Feb2024.pdf
Renewable Energy & Entrepreneurship Workshop_21Feb2024.pdf
 
NTPC LTD.
NTPC LTD.NTPC LTD.
NTPC LTD.
 

Recently uploaded

Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
akankshawande
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
Octavian Nadolu
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
Uni Systems S.M.S.A.
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
Zilliz
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
IndexBug
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
Mariano Tinti
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
Zilliz
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
Kari Kakkonen
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
Matthew Sinclair
 
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdfAI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
Techgropse Pvt.Ltd.
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
kumardaparthi1024
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
Zilliz
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
Edge AI and Vision Alliance
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 

Recently uploaded (20)

Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
 
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdfAI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 

Integrated wte gasification & solar power plant for Terengganu

  • 1. PROJECT PAPER PROJEK INTERGRASI GASIFIKASI SISA PEPEJAL & SOLAR POWER BANDAR-BANDAR DI TERENGGANU Prepared by: Dato’ Ir. Hj. Mat Isa Kadir
  • 2. PRESENTATION CONTENTS 2 FASA 1- 650TPD Waste To Energy Gasification Power Plant FASA 2- 30 MW Solar Photovoltaic Power Plant 2.1 Introduction& Purpose 2.2 Company Profile 2.3 What Photovoltaic Power Plant 2.4 Our Experience 2.5 The Proposed Solar Project 2.5.1 Site Location 2.5.2 Financial Forecast 2.5.3 Project Schedule 2.6 Our Request to Terengganu State
  • 3. 3 PROPOSED 50MW SOLAR POWER PLANT AT KUALA TERENGGANU ( PHASE 2)
  • 5. OBJECTIVE OF PROPOSAL 5 1. To brief YAB Menteri Besar on technical and financial aspects of the proposal to build and operate a large scale 50MW Solar Power Plant at Kampong Sungai Ikan in Kuala Terengganu. 2. To seek UPEN/State approval to develop the 50MW Solar Photovoltaic Power plant at Kpg Sungai Ikan, Kuala Terengganu. 3. To seek Terengganu State Approval to acquire the Land of 120 acres at Kg. Sungai Ikan Government Land for the building the Solar Power Plant. 4. To seek YAB Menteri Besar’s support letter for us to apply for Power Purchase Agreement (PPA) with TNB via Kementerian Tenaga, Tenaga Hijau, dan Air ( KETTHA) and/or SEDA.
  • 6. BENEFITS TO TERENGGANU & MSIA 6 1. Environmental: Reduction of more than 90,000 tons of CO2 emission per year 2. Environmental: Reduce annual fossil fuel usage equivalent to 360,000Gj of Gas or 16,750 tons of Coal. 3. Social: Supply of clean, GREEN electric power to 20,500 rural houses. 4. Economic: Spur the state economic stance by creating of employment to the local population. 5. Education: Educating public on RE, become a study/research center for TATIUC, UMT, etc 6. Manpower: To be the center of trining for undergraduate under TVET scheme, Ministry of Higher Education 7. Tourism: Establishing land-mark as one of the biggest single solar power plant in Malaysia
  • 8.
  • 9. 9 Tati Pro Energy Sdn Bhd Tati Pro Energy Sdn. Bhd. (TPE) is collaborating with Pengasus Capital. USA under TPE-PCA Consortium to build a 50MWp Solar Power Plant in Kuala Terengganu. TATI Pro Energy Sdn. Bhd. was established as a competent management & EPCC & investment arm company serving the power generation, oil & gas, and petrochemical industries. We have our expertise in the renewable energy, power cogeneration system. & oil /gas system Over the years, TPE had evolved into a multi-discipline engineering company, executing reputable projects together with reputable EPCC contractor . TATI has gained an enviable reputation through provision of high engineering solutions, on scheduled completion, competitive process and an invaluable customers services to our customer.
  • 10. 10 Pegasus Capital LLC TPE - PCA Consortium is owned by Pegasus Capital. Pegasus Capital Advisors, L.P. is a private equity fund manager that has been providing creative capital and strategic solutions to companies across a variety of industries since 1996. Pegasus partners with management teams of growth companies, with a focus on those that benefit from the business implications of global resource scarcity. Sectors where this trend is most pronounced are food, water, energy, health & wellness and security. PEGASUS is currently manage approximately USD1.8 billion in assets. Our investment team comprises over 50 talented investment professionals and operating/strategic advisors.
  • 11. 11 KNM Renewable Energy Sdn Bhd • Subsidiary of KNM Group Berhad • Established in 1990 • Malaysian Home Grown Multi- National Head office in MALAYSIA • Listed on the Bursa Malaysia Securities Berhad since 2003 • Revenue : About RM 2.5 Billion per annum • Over 5,500 employees worldwide • One Stop Centre for World Class Process Equipment & Industrial Plants • Strong portfolio of international brands KNM, BORSIG, FBM-Hudson & W.E. Smith • More than 170 years of project experience across the world in over 80 countries
  • 12. Innova Benelux Innova Benelux-WCT Ltd, an international project development company from Germany/Belgium, with an established networks in solar energy, and renewable energy expertise, will provide project management and project development support and assume the role of EPC.
  • 14. Solar Power System 14 Solar PV System , also known as Photovotaic system, is a process whereby the sun's radiation is converted into usable electricity by using photovoltaics arranging in several components, including solar panels to absorb and directly convert sunlight into electricity, a solar inverter to change the electrical current from DC to AC, as well as mounting, cabling and other electrical accessories to set-up a working system. Schematics of a typical Grid-connected Solar PV system
  • 15. Efficiency of Solar Panel 15 The viability &profitability of the project depend upon the amount of sunshine that can be captured and the technology and proven durability of the Solar PV Technology installed. The Power of the sun is about 1 kW/m, on the Earth's surface, to a plane that is perpendicular to the sun's rays and solar panels have an efficiency ranging from 17% to 27%. With an effectiveness of 150 W/sq. M with 7000 m per sq. hectare, the power output per one hectare will be around 1 MWp. (7000 sq. M x 150 Wp). Hence 50 Hectares land size for modules will generate a peak power of 50 MW. The “p” or peak period will be less before and after noon at 12 O’ clock on cloudless day A system with a size of 1 kWp installed delivers about 1310 kWh per year (Crystalline silica or Polysilicon modules) and varies with locations.
  • 22. Oct/4/2013 22 Process of installation of Solar Power Plant in Germany 1. PLANNING 2 3 7. 6 4. 5 Our Experience 6
  • 23. 2.5 The Proposed 30MW PV Solar Power Plant
  • 25. 25 Location : Kg Sg Ikan Kuala Terengganu, Terengganu, 30km West Kuala Terengganu,20km from KT Airport Land Area : 120 acres, situated by side of main federal road and having ease access to neighbouring roadways 50MW require: Solar farm Land requirement 120 acres if using Benelux Technology Distance PMU: Within the site area with capacity of 33KV/11KV Others infor: This site is a vacant government area owned by the State Government ( as on September 2015) Brief Site Information
  • 26. Proposed Location 26At Kg Sg Ikan Kuala Terengganu
  • 27. Proposed Location 27At Kg Sg Ikan Kuala Terengganu
  • 28. Proposed Location 28At Kg Sg Ikan Kuala Terengganu
  • 30. 30 Total project cost: USD83 million (RM332 million) Cost per MW: USD1.7 million (competitive market price) Potential yield per year: 1,230 KWh/ Ha Minimum (DSCR): 1.30 Debt Service Coverage Ratio Finance cost of interest: 0% per annum IRR Project: 17.4% NPV: Positive Payback: 5.66 years Financial Summary
  • 36. 2.6 Our Request to Terengganu State 36
  • 37. 1. Strong support letter to Tati Pro Energy from the State Government in order for us to apply for PPA (Power Purchase Agreement) to KETTHA (Kementerian Tenaga & Tenaga Hijau dan Air) 2. State to provide land under Terengganu GLC as the GLC will be the Co-developer/owner of the project partnering TPE-PCA Consortium. 3. Others relevant approval/permits such as Majlis Perbandaran, etc, etc Our Request to State Government
  • 38. Conditions for PPA eligibility set by KETTHA 1) Strong State support letter to Tati Pro Energy Sdn Bhd 2) Land availability, suitability & near to PMU 3) Technically sounds company having proven solar technology 4) Project funding capability 5) Experience in Solar power plants installation Conditions for PPA