SlideShare a Scribd company logo
F _____
JOB TITLE / AIM: JSA for Hydrotesting (Utility water, fire water, potable water)
JSA DATE: 19/06/06 JSA NO./ REVISION: 101
SUPERVISOR/ JSA LEADER: M. Ramzan SCRIBE: Hernand Suyom/Abdullah Khan
PARTICIPANTS : Sharif Ullah Khan, Shoaib Farman
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
Approved:
Bruce Boxshall 21-June-06
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps:
1.Mobilization of Equipment & workers
2. Water Refilling
3. Hydro testing
4. Water Releasing
5.Demobilization
Alternatives Considered: N/A
Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the Hse personnel is the first response in case of
emergency
Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.
File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
-
1 Mobilization of the following
equipment:
- Hand pump
- Pressure gauge
- Flexible wire hose
Unauthorised equipment/tools brought out to
site
Before mobilizing any equipment/tools make sure
that the E &P Personnel & BHP got inspected the
equipment. Checklist are in equipment
Ensure that gas testing was conducted whenever
bringing the equipment in transition and
Operations areas
Unskilled and uninducted personnel starting
the job
Ensure that all personnel prior to start have been
inducted and oriented about the hazard in the job
site. All persons working in Operations areaa to
be Operaitons inducted. Only trained personnel
shall do the Hydrotesting
Workers starting the job unfit to work All personnel must be undergone fitness for work
assessment thru DEL doctor
Workers starting the job without necessary
controls in place (eg JSA, Permits as required)
JSA must be in place prior to work. Ensure all the
persons take part in the toolbox meeting
discussion. Persons signed at the back of JSA at
each toolbox meeting.
All works undertaken in Operations areas to be
performed under CWP.
Hand Injury Ensure proper hauling of materials/get help if
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
Back injury
Miscommunication
required/Wear hand gloves.
Ensure proper posture and positioning
Ensure standby radio fully charge are in place at
all times
Ensure that area to be secured and barricaded with
hydrotesting sign board in place
2 Water Refilling & Pressurizing to
15 bar manually using hand pump
Unauthorised person
Miscommunication
Trips/fallls
Poor visibility/lighting
Heat Stress/Exhaustion
Snake bite
Tripping hazards
SIMOPS
Ensure that all workers have been informed when
the Hydrotesting will be conducted properly lit
and barricaded by a barrier. Ensure only 15bars
max. pressure to be conducted for testing.
It is advised that the testing to be conducted at
night or break time hours to minimized the
SIMOPS or personnel interface
Ensure that workers shall not step of the pipe
walking across the pipe
Ensure workers are following the correct
procedure of positioning and lifting. Get help if
required.
Ensure sufficient light are in place.
Ensure that workers are oriented about the job and
no one will be allowed to work alone. Make
buddy system
Ensure potable water/sufficient shelter is available
each area where workers are doing the job. First
aid kit available at site.
Workers will inform and be aware about the
presence at the area. No killing of snakes
Ensure that workers accessing the right walkway
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
and watch your steps.
Other worker not involve in the job must not
come closer to the area
Ensure workers are accessing the right pathway
and equipment must maintain the speed limit
Ensure banks person are available at the area
Ensure no works shall perform when strong wind
comes
Ensure that whenever heavy equipment on the
area no works shall commence at excavated area
3. Hydro testing High Presssure Burst
Miscommunication
Tripping hazards
Ensure that the equipment was inspected by BHP
and calibrated prior to use. Calibration
certificates to be reviewed prior to use
Ensure that QC conducting the testing are wearing
Full PPE and a standby barrier to secure
themselves from high pressure leak
Ensure that no any person will be on the
Hydrotesting area.
Ensure max. 15bars pressure to be kept during
testing
Ensure sufficient man power will be designated as
watchman to ensure nobody will enter the
Hydrotesting zone
Ensure that workers performing the testing are
trained.
Unauthorized operator should not operate the
tester
Always refer to manufacturers methodology of
testing
Ensure that during Hydrotesting no other workers
touching the pipe
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
Ensure that the Relief valve was install
Ensure that gas testing was conducted whenever
working in transition zone area
Ensure that workers will not step on the pipe
Whenever strong wind comes the work must be
stop
4. Water Releasing Unauthorised person
Miscommunication
Trips/fallls
Poor visibility/lighting
Heat Stress/Exhaustion
Snake bite
Tripping hazards
SIMOPS
Ensure that all workers have been informed when
the water releasing will be conducted properly
lit and barricaded by a barrier.
It is advised that the testing to be conducted at
night or break time hours to minimized the
SIMOPS or personnel interface
Ensure that workers shall not step of the pipe
walking across the pipe
Ensure workers are following the correct
procedure of positioning and lifting. Get help if
required.
Ensure sufficient light are in place.
Ensure that workers are oriented about the job and
no one will be allowed to work alone. Make
buddy system
Ensure potable water/sufficient shelter is available
each area where workers are doing the job. First
aid kit available at site.
Workers will inform and be aware about the
presence at the area. No killing of snakes
Ensure that workers accessing the right walkway
and watch your steps.
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
Other worker not involve in the job must not
come closer to the area
Ensure workers are accessing the right pathway
and equipment must maintain the speed limit
Ensure banks person are available at the area
Ensure no works shall perform when strong wind
comes
Ensure that whenever heavy equipment on the
area no works shall commence at excavated area
5. Demobilization Same as item one Same as item one

More Related Content

What's hot

2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
Gaurav Singh Rajput
 
Mrcb forklift training
Mrcb forklift trainingMrcb forklift training
Mrcb forklift training
HASNIZAM BIN MD SAAD
 
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
fahadansari131
 
Near miss report
Near miss reportNear miss report
Near miss report
Tarique Hussain
 
Working at heights training powerpoint
Working at heights training powerpointWorking at heights training powerpoint
Working at heights training powerpoint
Jomish John
 
Pressure testing
Pressure testingPressure testing
Pressure testing
Joshua Danquah
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
Project hse plan
Project hse planProject hse plan
Project hse plan
YAWAR HASSAN KHAN
 
Lockout Tagout
Lockout TagoutLockout Tagout
Lockout Tagout
vtsiri
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
Dwarika Bhushan Sharma
 
DOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work ProcedureDOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work Procedure
HENRY EROMOSELE OIGIANGBE
 
Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging Safety
NickHawkins19
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptx
ssuser926916
 
HIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdfHIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdf
MuhammadAdliHamdan
 
General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1
debandleigh
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
Azmeel Contracting Company
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
HaGun Gunawan
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
Dwarika Bhushan Sharma
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
Dwarika Bhushan Sharma
 

What's hot (20)

2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
 
Mrcb forklift training
Mrcb forklift trainingMrcb forklift training
Mrcb forklift training
 
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
 
Near miss report
Near miss reportNear miss report
Near miss report
 
Working at heights training powerpoint
Working at heights training powerpointWorking at heights training powerpoint
Working at heights training powerpoint
 
Pressure testing
Pressure testingPressure testing
Pressure testing
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
 
Project hse plan
Project hse planProject hse plan
Project hse plan
 
Lockout Tagout
Lockout TagoutLockout Tagout
Lockout Tagout
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
DOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work ProcedureDOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work Procedure
 
Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging Safety
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptx
 
HIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdfHIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdf
 
General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 

Similar to JSA for Hydrotesting.pdf

Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk system
Yousif Fikry
 
Generic Hydrotest.doc
Generic Hydrotest.docGeneric Hydrotest.doc
Generic Hydrotest.doc
amrilalriza
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
FESTUS RICHARD SIAME
 
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
Task Risk Worksheet Rev1.pdf
Task Risk Worksheet Rev1.pdfTask Risk Worksheet Rev1.pdf
Task Risk Worksheet Rev1.pdf
IsmailMydeen3
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JESUSBASILIOANTONIO
 
Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenance
Yousif Fikry
 
Confined Space Presentation University of Technology,Mauritius
Confined Space Presentation University of Technology,MauritiusConfined Space Presentation University of Technology,Mauritius
Confined Space Presentation University of Technology,Mauritius
Tarun Kumar Cheddy
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdf
JESUSBASILIOANTONIO
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
Atif767782
 
confined-space-training.ppt
confined-space-training.pptconfined-space-training.ppt
confined-space-training.ppt
BuddyEko
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building
Alvin160771
 
SECONDARY PIPE RACK AND PIG LAUNCHER.docx
SECONDARY PIPE RACK AND PIG LAUNCHER.docxSECONDARY PIPE RACK AND PIG LAUNCHER.docx
SECONDARY PIPE RACK AND PIG LAUNCHER.docx
ferielvpk
 
Jha rock drill use and maintenance romo
Jha rock drill use and maintenance romoJha rock drill use and maintenance romo
Jha rock drill use and maintenance romo
nafable
 
Safety in construction site
Safety in construction siteSafety in construction site
Safety in construction site
akshaykathalkar
 
07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdf07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdf
ajengps11
 
HSE Risk Register.docx
HSE Risk Register.docxHSE Risk Register.docx
HSE Risk Register.docx
almamunmolla96
 
HSE Weather working plan
HSE Weather working planHSE Weather working plan
HSE Weather working plan
Dwarika Bhushan Sharma
 
Confined space
Confined spaceConfined space
Confined space
turb022
 
23.plumbing method statement_gn23
23.plumbing method statement_gn2323.plumbing method statement_gn23
23.plumbing method statement_gn23
bhattbhai
 

Similar to JSA for Hydrotesting.pdf (20)

Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk system
 
Generic Hydrotest.doc
Generic Hydrotest.docGeneric Hydrotest.doc
Generic Hydrotest.doc
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
 
Task Risk Worksheet Rev1.pdf
Task Risk Worksheet Rev1.pdfTask Risk Worksheet Rev1.pdf
Task Risk Worksheet Rev1.pdf
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
 
Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenance
 
Confined Space Presentation University of Technology,Mauritius
Confined Space Presentation University of Technology,MauritiusConfined Space Presentation University of Technology,Mauritius
Confined Space Presentation University of Technology,Mauritius
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdf
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
confined-space-training.ppt
confined-space-training.pptconfined-space-training.ppt
confined-space-training.ppt
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building
 
SECONDARY PIPE RACK AND PIG LAUNCHER.docx
SECONDARY PIPE RACK AND PIG LAUNCHER.docxSECONDARY PIPE RACK AND PIG LAUNCHER.docx
SECONDARY PIPE RACK AND PIG LAUNCHER.docx
 
Jha rock drill use and maintenance romo
Jha rock drill use and maintenance romoJha rock drill use and maintenance romo
Jha rock drill use and maintenance romo
 
Safety in construction site
Safety in construction siteSafety in construction site
Safety in construction site
 
07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdf07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdf
 
HSE Risk Register.docx
HSE Risk Register.docxHSE Risk Register.docx
HSE Risk Register.docx
 
HSE Weather working plan
HSE Weather working planHSE Weather working plan
HSE Weather working plan
 
Confined space
Confined spaceConfined space
Confined space
 
23.plumbing method statement_gn23
23.plumbing method statement_gn2323.plumbing method statement_gn23
23.plumbing method statement_gn23
 

Recently uploaded

Constructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective CommunicationConstructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective Communication
Chevonnese Chevers Whyte, MBA, B.Sc.
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
imrankhan141184
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
Katrina Pritchard
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
HajraNaeem15
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
MJDuyan
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 

Recently uploaded (20)

Constructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective CommunicationConstructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective Communication
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 

JSA for Hydrotesting.pdf

  • 1. F _____ JOB TITLE / AIM: JSA for Hydrotesting (Utility water, fire water, potable water) JSA DATE: 19/06/06 JSA NO./ REVISION: 101 SUPERVISOR/ JSA LEADER: M. Ramzan SCRIBE: Hernand Suyom/Abdullah Khan PARTICIPANTS : Sharif Ullah Khan, Shoaib Farman LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs: Approved: Bruce Boxshall 21-June-06 Attach copies of any relevant documentation/ drawings. Part 2: Job Safety Analysis Job Steps: 1.Mobilization of Equipment & workers 2. Water Refilling 3. Hydro testing 4. Water Releasing 5.Demobilization Alternatives Considered: N/A Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03. Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the Hse personnel is the first response in case of emergency
  • 2. Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system. File: 10.30 JSA No: JOB TITLE: Step Describe Job Step Potential Hazards Hazard Controls No (Copy from part 2 of form) (Use Hazard Checklist) - 1 Mobilization of the following equipment: - Hand pump - Pressure gauge - Flexible wire hose Unauthorised equipment/tools brought out to site Before mobilizing any equipment/tools make sure that the E &P Personnel & BHP got inspected the equipment. Checklist are in equipment Ensure that gas testing was conducted whenever bringing the equipment in transition and Operations areas Unskilled and uninducted personnel starting the job Ensure that all personnel prior to start have been inducted and oriented about the hazard in the job site. All persons working in Operations areaa to be Operaitons inducted. Only trained personnel shall do the Hydrotesting Workers starting the job unfit to work All personnel must be undergone fitness for work assessment thru DEL doctor Workers starting the job without necessary controls in place (eg JSA, Permits as required) JSA must be in place prior to work. Ensure all the persons take part in the toolbox meeting discussion. Persons signed at the back of JSA at each toolbox meeting. All works undertaken in Operations areas to be performed under CWP. Hand Injury Ensure proper hauling of materials/get help if
  • 3. JSA No: JOB TITLE: Step Describe Job Step Potential Hazards Hazard Controls No (Copy from part 2 of form) (Use Hazard Checklist) Back injury Miscommunication required/Wear hand gloves. Ensure proper posture and positioning Ensure standby radio fully charge are in place at all times Ensure that area to be secured and barricaded with hydrotesting sign board in place 2 Water Refilling & Pressurizing to 15 bar manually using hand pump Unauthorised person Miscommunication Trips/fallls Poor visibility/lighting Heat Stress/Exhaustion Snake bite Tripping hazards SIMOPS Ensure that all workers have been informed when the Hydrotesting will be conducted properly lit and barricaded by a barrier. Ensure only 15bars max. pressure to be conducted for testing. It is advised that the testing to be conducted at night or break time hours to minimized the SIMOPS or personnel interface Ensure that workers shall not step of the pipe walking across the pipe Ensure workers are following the correct procedure of positioning and lifting. Get help if required. Ensure sufficient light are in place. Ensure that workers are oriented about the job and no one will be allowed to work alone. Make buddy system Ensure potable water/sufficient shelter is available each area where workers are doing the job. First aid kit available at site. Workers will inform and be aware about the presence at the area. No killing of snakes Ensure that workers accessing the right walkway
  • 4. JSA No: JOB TITLE: Step Describe Job Step Potential Hazards Hazard Controls No (Copy from part 2 of form) (Use Hazard Checklist) and watch your steps. Other worker not involve in the job must not come closer to the area Ensure workers are accessing the right pathway and equipment must maintain the speed limit Ensure banks person are available at the area Ensure no works shall perform when strong wind comes Ensure that whenever heavy equipment on the area no works shall commence at excavated area 3. Hydro testing High Presssure Burst Miscommunication Tripping hazards Ensure that the equipment was inspected by BHP and calibrated prior to use. Calibration certificates to be reviewed prior to use Ensure that QC conducting the testing are wearing Full PPE and a standby barrier to secure themselves from high pressure leak Ensure that no any person will be on the Hydrotesting area. Ensure max. 15bars pressure to be kept during testing Ensure sufficient man power will be designated as watchman to ensure nobody will enter the Hydrotesting zone Ensure that workers performing the testing are trained. Unauthorized operator should not operate the tester Always refer to manufacturers methodology of testing Ensure that during Hydrotesting no other workers touching the pipe
  • 5. JSA No: JOB TITLE: Step Describe Job Step Potential Hazards Hazard Controls No (Copy from part 2 of form) (Use Hazard Checklist) Ensure that the Relief valve was install Ensure that gas testing was conducted whenever working in transition zone area Ensure that workers will not step on the pipe Whenever strong wind comes the work must be stop 4. Water Releasing Unauthorised person Miscommunication Trips/fallls Poor visibility/lighting Heat Stress/Exhaustion Snake bite Tripping hazards SIMOPS Ensure that all workers have been informed when the water releasing will be conducted properly lit and barricaded by a barrier. It is advised that the testing to be conducted at night or break time hours to minimized the SIMOPS or personnel interface Ensure that workers shall not step of the pipe walking across the pipe Ensure workers are following the correct procedure of positioning and lifting. Get help if required. Ensure sufficient light are in place. Ensure that workers are oriented about the job and no one will be allowed to work alone. Make buddy system Ensure potable water/sufficient shelter is available each area where workers are doing the job. First aid kit available at site. Workers will inform and be aware about the presence at the area. No killing of snakes Ensure that workers accessing the right walkway and watch your steps.
  • 6. JSA No: JOB TITLE: Step Describe Job Step Potential Hazards Hazard Controls No (Copy from part 2 of form) (Use Hazard Checklist) Other worker not involve in the job must not come closer to the area Ensure workers are accessing the right pathway and equipment must maintain the speed limit Ensure banks person are available at the area Ensure no works shall perform when strong wind comes Ensure that whenever heavy equipment on the area no works shall commence at excavated area 5. Demobilization Same as item one Same as item one