Rig Name/#: BENNEVIS JSA Number : MA 023 Person Approving JSA: H.M
Work Activity (Job): Change out valve in bulk tanks Date Raised :
Work Team (Crew Members):
ABE / Welders / Roustabouts
Sequence of Basic Job Steps Potential Accidents or Hazards
Recommendation to Eliminate or Reduce Potential
Hazards
Who?
Initials
review the
procedure and any applicable
Alerts
None Ensure everyone involved understands their
duties, the hazards, what will be done to
communicate the hazards and what will be
done to control the job, Ensure that any
actions you take that would effect others on
the rig are properly communicated Using
proper planning to proceed with task at hand
Gather all equipment needed for
job and inspect same
Tools in poor condition, Improper type PPE Ensure all involved are aware of hazards of
using hand tools and any risks associated with
the grease be Inspect all equipment for wear
or defects
If personnel are not familiar with tools being
used, review manf. Specifications for same to
ensure proper precautions are taken ing used
Head up to work with isolation
certificate display on the work site
and lock out main air supply valve
to bulk tanks.
Trip hazards due to improperly maintained work
area,
Ensure all personnel are aware of hazards and
use proper communication throughout task
Proper hand a body placement to be used,
Work area inspected to ensure it is free of trip
hazards/slip hazards and safety barriers work
area.
Page 1 of 2
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-OCTOBER 07
Prepared By
QA/HSE
Approved By
HS
Level No.
2
Use spreader bolts to remove
valves, remove clean and reinstall
or repair/replace.
Exposure to high pressure, Slip and trip hazards
due to improperly maintained work area, pinch
points, fall hazards
Ensure all personnel are aware of hazards and
use proper communication throughout task
Work area inspected to ensure it is free of trip
hazards/slip hazards and safety devices to be
installed to main air supply valve, wear fall
body harness when working above main deck .
Repair worn out valves, install and
test.
Bad housekeeping, trip hazards and equipment
stored broken.
Ensure all personnel involved are aware of all
safety precautions.
Use proper vice area clean, when ever possible
and if available make all bolts to be same size
Deisolate the main air valve. And
pressure up the tank and check
valves replaced
Caught between , pinch points, exposure to high
pressure
Ensure all personnel are aware of any caught
between points, pinch points and pressure
Use proper hand and body placement to ensure
that no caught between hazards are
encountered and be away while tank pressure
up and watch from safe distance.
Safety Equipment To Do This Job
Hard Hats x Gloves x Face Shield ( Fire Extinguishers (
Safety Boots x Work Vest ( Goggles (x Lockout/Tagout (
Safety Glasses x Safety Harness ( Barriers ( Work Permit Required x
Page 2 of 2
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-OCTOBER 07
Prepared By
QA/HSE
Approved By
HS
Level No.
2

More Related Content

Viewers also liked

Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachestYousif Fikry
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatYousif Fikry
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick setYousif Fikry
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachestYousif Fikry
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmYousif Fikry
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deckYousif Fikry
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatYousif Fikry
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatYousif Fikry
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveYousif Fikry
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deckYousif Fikry
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladderYousif Fikry
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackYousif Fikry
 
Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringYousif Fikry
 

Viewers also liked (14)

Welding operation
Welding operationWelding operation
Welding operation
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachest
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boat
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick set
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachest
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obm
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deck
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boat
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boat
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valve
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deck
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladder
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rack
 
Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load lowering
 

Similar to Ma 023 change out butter fly valve for bulk system

JSA for Hydrotesting.pdf
JSA for Hydrotesting.pdfJSA for Hydrotesting.pdf
JSA for Hydrotesting.pdf
ROCENODodongVILLACER
 
Generic Hydrotest.doc
Generic Hydrotest.docGeneric Hydrotest.doc
Generic Hydrotest.doc
amrilalriza
 
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
FESTUS RICHARD SIAME
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
Dwarika Bhushan Sharma
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
Atif767782
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.ppt
ssuser0ebdc3
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
Paul Smith
 
Home Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula gaHome Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula ga
Chris Collins Dacula ga
 
Bouncy Castle Staff Training
Bouncy Castle Staff TrainingBouncy Castle Staff Training
Bouncy Castle Staff Training
MollyMarriott
 
Oil fieldsafetyneo1[1]
Oil fieldsafetyneo1[1]Oil fieldsafetyneo1[1]
Oil fieldsafetyneo1[1]snakehips1
 
New holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manualNew holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manual
fujsjezaqwfkskemm
 
New holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manualNew holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manual
fujsjefkskekmme
 
New holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manualNew holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manual
fjjskekmsemm
 
JSA Aerial Lift (english) KWW
JSA Aerial Lift (english) KWWJSA Aerial Lift (english) KWW
JSA Aerial Lift (english) KWWKelly Weaver
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment file
chopriroti
 
Safe Equipment Operation V17
Safe Equipment Operation V17Safe Equipment Operation V17
Safe Equipment Operation V17Eric Lestock Kay
 
Construction site safety rules and regulations:
Construction site safety rules and regulations:Construction site safety rules and regulations:
Construction site safety rules and regulations:
GHARBANWAO
 

Similar to Ma 023 change out butter fly valve for bulk system (20)

JSA for Hydrotesting.pdf
JSA for Hydrotesting.pdfJSA for Hydrotesting.pdf
JSA for Hydrotesting.pdf
 
Generic Hydrotest.doc
Generic Hydrotest.docGeneric Hydrotest.doc
Generic Hydrotest.doc
 
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
 
AHU.pdf
AHU.pdfAHU.pdf
AHU.pdf
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.ppt
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
Home Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula gaHome Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula ga
 
Bouncy Castle Staff Training
Bouncy Castle Staff TrainingBouncy Castle Staff Training
Bouncy Castle Staff Training
 
Oil fieldsafetyneo1[1]
Oil fieldsafetyneo1[1]Oil fieldsafetyneo1[1]
Oil fieldsafetyneo1[1]
 
New holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manualNew holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manual
 
New holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manualNew holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manual
 
New holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manualNew holland e150 bsr blade runner hydraulic excavator service repair manual
New holland e150 bsr blade runner hydraulic excavator service repair manual
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
JSA Aerial Lift (english) KWW
JSA Aerial Lift (english) KWWJSA Aerial Lift (english) KWW
JSA Aerial Lift (english) KWW
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment file
 
Safe Equipment Operation V17
Safe Equipment Operation V17Safe Equipment Operation V17
Safe Equipment Operation V17
 
Construction site safety rules and regulations:
Construction site safety rules and regulations:Construction site safety rules and regulations:
Construction site safety rules and regulations:
 

More from Yousif Fikry

Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatYousif Fikry
 
Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaYousif Fikry
 
Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wiresYousif Fikry
 
Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boatYousif Fikry
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deckYousif Fikry
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenanceYousif Fikry
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranesYousif Fikry
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsulesYousif Fikry
 
Ma 012 using working personnel basket
Ma 012 using working personnel basketMa 012 using working personnel basket
Ma 012 using working personnel basketYousif Fikry
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )Yousif Fikry
 

More from Yousif Fikry (11)

Ma 022 preloading
Ma 022 preloadingMa 022 preloading
Ma 022 preloading
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boat
 
Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to sea
 
Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wires
 
Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boat
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenance
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranes
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsules
 
Ma 012 using working personnel basket
Ma 012 using working personnel basketMa 012 using working personnel basket
Ma 012 using working personnel basket
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )
 

Ma 023 change out butter fly valve for bulk system

  • 1. Rig Name/#: BENNEVIS JSA Number : MA 023 Person Approving JSA: H.M Work Activity (Job): Change out valve in bulk tanks Date Raised : Work Team (Crew Members): ABE / Welders / Roustabouts Sequence of Basic Job Steps Potential Accidents or Hazards Recommendation to Eliminate or Reduce Potential Hazards Who? Initials review the procedure and any applicable Alerts None Ensure everyone involved understands their duties, the hazards, what will be done to communicate the hazards and what will be done to control the job, Ensure that any actions you take that would effect others on the rig are properly communicated Using proper planning to proceed with task at hand Gather all equipment needed for job and inspect same Tools in poor condition, Improper type PPE Ensure all involved are aware of hazards of using hand tools and any risks associated with the grease be Inspect all equipment for wear or defects If personnel are not familiar with tools being used, review manf. Specifications for same to ensure proper precautions are taken ing used Head up to work with isolation certificate display on the work site and lock out main air supply valve to bulk tanks. Trip hazards due to improperly maintained work area, Ensure all personnel are aware of hazards and use proper communication throughout task Proper hand a body placement to be used, Work area inspected to ensure it is free of trip hazards/slip hazards and safety barriers work area. Page 1 of 2 Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-OCTOBER 07 Prepared By QA/HSE Approved By HS Level No. 2
  • 2. Use spreader bolts to remove valves, remove clean and reinstall or repair/replace. Exposure to high pressure, Slip and trip hazards due to improperly maintained work area, pinch points, fall hazards Ensure all personnel are aware of hazards and use proper communication throughout task Work area inspected to ensure it is free of trip hazards/slip hazards and safety devices to be installed to main air supply valve, wear fall body harness when working above main deck . Repair worn out valves, install and test. Bad housekeeping, trip hazards and equipment stored broken. Ensure all personnel involved are aware of all safety precautions. Use proper vice area clean, when ever possible and if available make all bolts to be same size Deisolate the main air valve. And pressure up the tank and check valves replaced Caught between , pinch points, exposure to high pressure Ensure all personnel are aware of any caught between points, pinch points and pressure Use proper hand and body placement to ensure that no caught between hazards are encountered and be away while tank pressure up and watch from safe distance. Safety Equipment To Do This Job Hard Hats x Gloves x Face Shield ( Fire Extinguishers ( Safety Boots x Work Vest ( Goggles (x Lockout/Tagout ( Safety Glasses x Safety Harness ( Barriers ( Work Permit Required x Page 2 of 2 Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-OCTOBER 07 Prepared By QA/HSE Approved By HS Level No. 2