In this paper an attempt has been made to solve the profit based unit commitment problem (PBUC) using pre-prepared power demand (PPD) table with an artificial bee colony (ABC) algorithm. The PPD-ABC algorithm appears to be a robust and reliable optimization algorithm for the solution of PBUC problem. The profit based unit commitment problem is considered as a stochastic optimization problem in which the objective is to maximize their own profit and the decisions are needed to satisfy the standard operating constraints. The PBUC problem is solved by the proposed methodology in two stages. In the first step, the unit commitment scheduling is performed by considering the pre-prepared power demand (PPD) table and then the problem of fuel cost and revenue function is solved using ABC Algorithm. The PPD table suggests the operator to decide the units to be put into generation there by reducing the complexity of the problem. The proposed approach is demonstrated on 10 units 24 hour and 50 units 24 hour test systems and numerical results are tabulated. Simulation result shows that this approach effectively maximizes the GENCO’s profit than those obtained by other optimizing methods.
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
Optimal unit commitment of a power plant using particle swarm optimization ap...IJECEIAES
Economic load dispatch among generating units is very important for any power plant. In this work, the economic load dispatch was made at Egbin Thermal Power plant supplying a total load of 600MW using six generating units. In carrying out this study, transmission losses were assumed to be included into the load supplied. Also, three different combinations in the form of 6, 5- and 4-units commitment were considered. In each case, the total load was optimally dispatched between committed generating units using Particle Swarm Optimization (PSO). Similarly, the generation cost for each generating unit was determined. For case 1, the six generators were committed and the generation cost is 2,100,685.069$/h. For case 2, five generators were committed and the generation cost is 2,520,861.947$/h. For case 3, four generators were committed and the generation cost is 3,150,621.685$/h. From all considered cases, it was found that, the minimum generation cost was achieved when all six generating units were committed and a total of 420,178.878$/h was saved.
An Improved Particle Swarm Optimization for Proficient Solving of Unit Commit...IDES Editor
This paper presents a new approach to solving the
short-term unit commitment problem using an improved
Particle Swarm Optimization (IPSO). The objective of this
paper is to find the generation scheduling such that the total
operating cost can be minimized, when subjected to a variety
of constraints. This also means that it is desirable to find the
optimal generating unit commitment in the power system for
the next H hours. PSO, which happens to be a Global
Optimization technique for solving Unit Commitment
Problem, operates on a system, which is designed to encode
each unit’s operating schedule with regard to its minimum
up/down time. In this, the unit commitment schedule is coded
as a string of symbols. An initial population of parent
solutions is generated at random. Here, each schedule is
formed by committing all the units according to their initial
status (“flat start”). Here the parents are obtained from a predefined
set of solution’s i.e. each and every solution is adjusted
to meet the requirements. Then, a random decommitment is
carried out with respect to the unit’s minimum down times. A
thermal Power System in India demonstrates the effectiveness
of the proposed approach; extensive studies have also been
performed for different power systems consist of 10, 26, 34
generating units. Numerical results are shown comparing the
cost solutions and computation time obtained by using the
IPSO and other conventional methods like Dynamic
Programming (DP), Legrangian Relaxation (LR) in reaching
proper unit commitment.
Comparative study of the price penalty factors approaches for Bi-objective di...IJECEIAES
One of the main objectives of electricity dispatch centers is to schedule the operation of available generating units to meet the required load demand at minimum operating cost with minimum emission level caused by fossil-based power plants. Finding the right balance between the fuel cost the green gasemissionsis reffered as Combined Economic and Emission Dispatch (CEED) problem which is one of the important optimization problems related the operationmodern power systems. The Particle Swarm Optimization algorithm (PSO) is a stochastic optimization technique which is inspired from the social learning of birds or fishes. It is exploited to solve CEED problem. This paper examines the impact of six penalty factors like "Min-Max", "Max-Max", "Min-Min", "Max-Min", "Average" and "Common" price penalty factors for solving CEED problem. The Price Penalty Factor for the CEED is the ratio of fuel cost to emission value. This bi-objective dispatch problem is investigated in the Real West Algeria power network consisting of 22 buses with 7 generators. Results prove capability of PSO in solving CEED problem with various penalty factors and it proves that Min-Max price penalty factor provides the best compromise solution in comparison to the other penalty factors.
Multi Area Economic Dispatch Using Secant Method and Tie Line MatrixIJAPEJOURNAL
In this paper, Secant method and tie line matrix are proposed to solve multi area economic dispatch (MAED) problem with tie line loss. Generator limits of all generators in each area are calculated at given area power demands plus export (or import) using secant method and the generator limits of all generators are modified as modified generator limits. Central economic dispatch (CED) problem is used to determine the output powers of all generators and finally power flows in all tie lines are determined from tie line matrix. Here, Secant method is applied to solve the CED problem. A modified tie line matrix is used to find power flow in each tie line and then tie line loss is calculated from the power flow in each tie line. The proposed approach has been tested on two-area (two generators in each area) system and four-area (four generators in each area) system. It is observed from various cases that the proposed approach provides optimally best solution in terms of cost with tie line loss with less computational burden.
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
Optimal unit commitment of a power plant using particle swarm optimization ap...IJECEIAES
Economic load dispatch among generating units is very important for any power plant. In this work, the economic load dispatch was made at Egbin Thermal Power plant supplying a total load of 600MW using six generating units. In carrying out this study, transmission losses were assumed to be included into the load supplied. Also, three different combinations in the form of 6, 5- and 4-units commitment were considered. In each case, the total load was optimally dispatched between committed generating units using Particle Swarm Optimization (PSO). Similarly, the generation cost for each generating unit was determined. For case 1, the six generators were committed and the generation cost is 2,100,685.069$/h. For case 2, five generators were committed and the generation cost is 2,520,861.947$/h. For case 3, four generators were committed and the generation cost is 3,150,621.685$/h. From all considered cases, it was found that, the minimum generation cost was achieved when all six generating units were committed and a total of 420,178.878$/h was saved.
An Improved Particle Swarm Optimization for Proficient Solving of Unit Commit...IDES Editor
This paper presents a new approach to solving the
short-term unit commitment problem using an improved
Particle Swarm Optimization (IPSO). The objective of this
paper is to find the generation scheduling such that the total
operating cost can be minimized, when subjected to a variety
of constraints. This also means that it is desirable to find the
optimal generating unit commitment in the power system for
the next H hours. PSO, which happens to be a Global
Optimization technique for solving Unit Commitment
Problem, operates on a system, which is designed to encode
each unit’s operating schedule with regard to its minimum
up/down time. In this, the unit commitment schedule is coded
as a string of symbols. An initial population of parent
solutions is generated at random. Here, each schedule is
formed by committing all the units according to their initial
status (“flat start”). Here the parents are obtained from a predefined
set of solution’s i.e. each and every solution is adjusted
to meet the requirements. Then, a random decommitment is
carried out with respect to the unit’s minimum down times. A
thermal Power System in India demonstrates the effectiveness
of the proposed approach; extensive studies have also been
performed for different power systems consist of 10, 26, 34
generating units. Numerical results are shown comparing the
cost solutions and computation time obtained by using the
IPSO and other conventional methods like Dynamic
Programming (DP), Legrangian Relaxation (LR) in reaching
proper unit commitment.
Comparative study of the price penalty factors approaches for Bi-objective di...IJECEIAES
One of the main objectives of electricity dispatch centers is to schedule the operation of available generating units to meet the required load demand at minimum operating cost with minimum emission level caused by fossil-based power plants. Finding the right balance between the fuel cost the green gasemissionsis reffered as Combined Economic and Emission Dispatch (CEED) problem which is one of the important optimization problems related the operationmodern power systems. The Particle Swarm Optimization algorithm (PSO) is a stochastic optimization technique which is inspired from the social learning of birds or fishes. It is exploited to solve CEED problem. This paper examines the impact of six penalty factors like "Min-Max", "Max-Max", "Min-Min", "Max-Min", "Average" and "Common" price penalty factors for solving CEED problem. The Price Penalty Factor for the CEED is the ratio of fuel cost to emission value. This bi-objective dispatch problem is investigated in the Real West Algeria power network consisting of 22 buses with 7 generators. Results prove capability of PSO in solving CEED problem with various penalty factors and it proves that Min-Max price penalty factor provides the best compromise solution in comparison to the other penalty factors.
Multi Area Economic Dispatch Using Secant Method and Tie Line MatrixIJAPEJOURNAL
In this paper, Secant method and tie line matrix are proposed to solve multi area economic dispatch (MAED) problem with tie line loss. Generator limits of all generators in each area are calculated at given area power demands plus export (or import) using secant method and the generator limits of all generators are modified as modified generator limits. Central economic dispatch (CED) problem is used to determine the output powers of all generators and finally power flows in all tie lines are determined from tie line matrix. Here, Secant method is applied to solve the CED problem. A modified tie line matrix is used to find power flow in each tie line and then tie line loss is calculated from the power flow in each tie line. The proposed approach has been tested on two-area (two generators in each area) system and four-area (four generators in each area) system. It is observed from various cases that the proposed approach provides optimally best solution in terms of cost with tie line loss with less computational burden.
Optimal Expenditure and Benefit Cost Based Location, Size and Type of DGs in ...TELKOMNIKA JOURNAL
The economic issue is an essential element to determine whether DG should be installed or not. This work presents the economical approach for multi-type DGs placement in microgrid systems with more comprehensive overview from DG’s owner perspective. Adaptive Real Coded GA (ARC-GA) with replacement process is developed to determine the location, type, and rating of DGs so as the maximum profit is achieved. The objectives of this paper are maximizing benefit cost and minimizing expenditure cost. All objectives are optimized while maintaining the bus voltage at the acceptable range and the DGs penetration levels are below of the DGs capacities.The proposed method is applied on the 33 bus microgrids systems using conventional and renewable DG technology, namely Photovoltaic (PV), Wind Turbine (WT), Micro Turbine (MT) and Gas Turbine (GT). The simulation results show the effectiveness of the proposed approach.
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
Solar PV parameter estimation using multi-objective optimisationjournalBEEI
The estimation of the electrical model parameters of solar PV, such as light-induced current, diode dark saturation current, thermal voltage, series resistance, and shunt resistance, is indispensable to predict the actual electrical performance of solar photovoltaic (PV) under changing environmental conditions. Therefore, this paper first considers the various methods of parameter estimation of solar PV to highlight their shortfalls. Thereafter, a new parameter estimation method, based on multi-objective optimisation, namely, Non-dominated Sorting Genetic Algorithm-II (NSGA-II), is proposed. Furthermore, to check the effectiveness and accuracy of the proposed method, conventional methods, such as, ‘Newton-Raphson’, ‘Particle Swarm Optimisation, Search Algorithm, was tested on four solar PV modules of polycrystalline and monocrystalline materials. Finally, a solar PV module photowatt PWP201 has been considered and compared with six different state of art methods. The estimated performance indices such as current absolute error matrics, absolute relative power error, mean absolute error, and P-V characteristics curve were compared. The results depict the close proximity of the characteristic curve obtained with the proposed NSGA-II method to the curve obtained by the manufacturer’s datasheet.
In this paper a load flow based method using MATLAB Software is used to determine the optimum location and optimum size of DG in a 43-bus distribution system for voltage profile improvement and loss reduction. This paper proposes analytical expressions for finding optimal size of three types of distributed generation (DG) units. DG units are sized to achieve the highest loss reduction in distribution networks. Single DG installation case was studied and compared to a case without DG, and 43-bus distribution system is used to demonstrate the effectiveness of the proposed method. The proposed analytical expressions are based on an improvement to the method that was limited to DG type, which is capable of injecting real power only, DG capable of injecting reactive power only and DG capable of injecting both real and reactive power can also be identified with their optimal size and location using the proposed method. This paper has been analysed with varying DG size and complexity and validated using analytical method for Summer case and Winter case in 43-bus distribution system in Myanmar.
Keywords- analytical method,distributed generation,power loss reduction,voltage profile improvement.
Optimal Power Generation in Energy-Deficient Scenarios Using Bagging EnsemblesKashif Mehmood
This paper presents an improved technique for optimal power generation using ensemble
artificial neural networks (EANN). The motive for using EANN is to benefit from multiple parallel processor
computing rather than traditional serial computation to reduce bias and variance in machine learning. The
load data is obtained from the load regulation authority of Pakistan for 24 hours. The data is analyzed on an
IEEE 30-bus test system by implementing two approaches; the conventional artificial neural network (ANN)
with feed-forward back-propagation model and a Bagging algorithm. To improve the training of ANN and
authenticate its result, first the Load Flow Analysis (LFA) on IEEE 30 bus is performed using Newton
Raphson Method and then the program is developed in MATLAB using Lagrange relaxation (LR) framework
to solve a power-generator scheduling problem. The bootstraps for the EANN are obtained through a disjoint
partition Bagging algorithm to handle the fluctuating power demand and is used to forecast the power
generation. The results of MATLAB simulations are analyzed and compared along with computational
complexity, therein showing the dominance of the EANN over the traditional ANN strategy that closed
to LR
Grid Connected Electricity Storage Systems (2/2)Leonardo ENERGY
Development and use of Renewable Energy Sources is one of the key elements in European Electricity Research. However, connecting energy sources such as photovoltaics and wind turbines to the electricity grid causes significant effects on these networks. Bottlenecks are stability, security, peaks in supply & demand and overall management of the grid. Energy storage systems provide means to overcome technical and economic hurdles for large-scale introduction of distributed sustainable energy sources. The GROW-DERS project (Grid Reliability and Operability with Distributed Generation using Flexible Storage) investigates the implementation of (transportable) distributed storage systems in the networks. The project is funded by the European Commission (FP6) and the consortium partners are KEMA, Liander, Iberdrola, MVV, EAC, SAFT, EXENDIS, CEA-INES and IPE.
In this project 3 storage systems (2 Li-ion battery systems and a flywheel) have been demonstrated at different test locations in Europe. Additionally, a dedicated software tool, PLATOS (PLAnning Tool for Optimizing Storage), has been developed by KEMA to optimize the energy management of electricity networks using storage. For each network, the location, size and type of storage systems is evaluated for all possible configurations and the most attractive option is selected.
Impact of Dispersed Generation on Optimization of Power ExportsIJERA Editor
Dispersed generation (DG) is defined as any source of electrical energy of limited size that is connected directly to the distribution system of a power network. It is also called decentralized generation, embedded generation or distributed generation. Dispersed generation is any modular generation located at or near the load center. It can be applied in the form of rechargeable, such as, mini-hydro, solar, wind and photovoltaic system or in the form of fuel-based systems, such as, fuel cells and micro-turbines. This paper presents the impact of dispersed generation on the optimization of power exports. Computer simulation was carried out using the hourly loads of the selected distribution feeders on Kaduna distribution system as input parameters for the computation of the line loss reduction ratio index (LLRI). The result showed that the line loss reduced from 163.56MW to 144.61 MW when DG was introduced which is an indication of a reduction in line losses with the installation of DG at the various feeders of the distribution system. In all the feeders where DG is integrated, the average magnitude of the line loss reduction index is 0.8754 MW which is less than 1 indicating a reduction in the electrical line losses with the introduction of DG. The line loss reduction index confirmed that by integrating DG into the distribution system, the distribution losses are reduced and optimization of power exports is achieved The results of this research paper will form a basis to establish that proper location of distributed generation units have significant impact on their effective capacity.
The optimal solution for unit commitment problem using binary hybrid grey wol...IJECEIAES
The aim of this work is to solve the unit commitment (UC) problem in power systems by calculating minimum production cost for the power generation and finding the best distribution of the generation among the units (units scheduling) using binary grey wolf optimizer based on particle swarm optimization (BGWOPSO) algorithm. The minimum production cost calculating is based on using the quadratic programming method and represents the global solution that must be arriving by the BGWOPSO algorithm then appearing units status (on or off). The suggested method was applied on “39 bus IEEE test systems”, the simulation results show the effectiveness of the suggested method over other algorithms in terms of minimizing of production cost and suggesting excellent scheduling of units.
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMaeijjournal
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its
exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is
equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the
optimization of the generative units to minimize the full action cost regarding problem constraints. In this
article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in
a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power
system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
Economic Dispatch using Quantum Evolutionary Algorithm in Electrical Power S...IJECEIAES
Unpredictable increase in power demands will overload the supply subsystems and insufficiently powered systems will suffer from instabilities, in which voltages drop below acceptable levels. Additional power sources are needed to satisfy the demand. Small capacity distributed generators (DGs) serve for this purpose well. One advantage of DGs is that they can be installed close to loads, so as to minimise loses. Optimum placements and sizing of DGs are critical to increase system voltages and to reduce loses. This will finally increase the overall system efficiency. This work exploits Quantum Evolutionary Algorithm (QEA) for the placements and sizing. This optimisation targets the cheapest generation cost. Quantum Evolutionary Algorithm is an Evolutionary Algorithm running on quantum computing, which works based on qubits and states superposition of quantum mechanics. Evolutionary algorithm with qubit representation has a better characteristic of diversity than classical approaches, since it can represent superposition of states.
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineIJAPEJOURNAL
Economic load dispatch (ELD) and Unit Commitment (UC) are significant research applications in power systems that optimize the total production cost of the predicted load demand. The UC problem determines a turn-on and turn-off schedule for a given combination of generating units, thus satisfying a set of dynamic operational constraints. ELD optimizes the operation cost for all scheduled generating units with respect to the load demands of customers. The first phase in this project is to economically schedule the distribution of generating units using Gauss seidal and the second phase is to determine optimal load distribution for the scheduled units using dynamic programming method is applied to select and choose the combination of generating units that commit and de-commit during each hour. These precommitted schedules are optimized by dynamic programming method thus producing a global optimum solution with feasible and effective solution quality, minimal cost and time and higher precision. The effectiveness of the proposed techniques is investigated on two test systems consisting of five generating units and the experiments are carried out using MATLAB R2010b software. Experimental results prove that the proposed method is capable of yielding higher quality solution including mathematical simplicity, fast convergence, diversity maintenance, robustness and scalability for the complex ELD-UC problem.
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...paperpublications3
Abstract: In this paper, an algorithm to solve the optimal unit commitment problem under deregulated environment has been proposed using Particle Swarm Optimization (PSO) intelligent technique accounting economic dispatch constraints. In the present electric power market, where renewable energy power plants have been included in the system, there is a lot of unpredictability in the demand and generation. This paper presents an improved particle swarm optimization algorithm (IPSO) for power system unit commitment with the consideration of various constraints. IPSO is an extension of the standard particle swarm optimization algorithm (PSO) which uses more particles information to control the mutation operation, and is similar to the social society in that a group of leaders could make better decisions. The program was developed in MATLAB and the proposed method implemented on IEEE 14 bus test system.
ECONOMIC LOAD DISPATCH USING GENETIC ALGORITHMIJARIIT
This paper present the application of Genetic Algorithm (GA) to Economic Load Dispatch problem of the power system. Economic Load Dispatch is one of the major optimization problems dealing with the modern power systems.ELD determines the electrical power to be generated by the committed generating units in a power system so that the total generation cost of the system is minimized, while satisfactory the load demand. The objective is to minimize the total generation fuel cost and maintain the power flow within safety limits. The introduced algorithm has been demonstrated for the given test systems considering the transmission line losses.
Economic dispatch by optimization techniquesIJECEIAES
The current paper offers the solution strategy for the economic dispatch problem in electric power system implementing ant lion optimization algorithm (ALOA) and bat algorithm (BA) techniques. In the power network, the economic dispatch (ED) is a short-term calculation of the optimum performance of several electricity generations or a plan of outputs of all usable power generation units from the energy produced to fulfill the necessary demand, although equivalent and unequal specifications need to be achieved at minimal fuel and carbon pollution costs. In this paper, two recent meta-heuristic approaches are introduced, the BA and ALOA. A rigorous stochastically developmental computing strategy focused on the action and intellect of ant lions is an ALOA. The ALOA imitates ant lions' hunting process. The introduction of a numerical description of its biological actions for the solution of ED in the power framework. These algorithms are applied to two systems: a small scale three generator system and a large scale six generator. Results show were compared on the metrics of convergence rate, cost, and average run time that the ALOA and BA are suitable for economic dispatch studies which is clear in the comparison set with other algorithms. Both of these algorithms are tested on IEEE-30 bus reliability test system.
Optimal Expenditure and Benefit Cost Based Location, Size and Type of DGs in ...TELKOMNIKA JOURNAL
The economic issue is an essential element to determine whether DG should be installed or not. This work presents the economical approach for multi-type DGs placement in microgrid systems with more comprehensive overview from DG’s owner perspective. Adaptive Real Coded GA (ARC-GA) with replacement process is developed to determine the location, type, and rating of DGs so as the maximum profit is achieved. The objectives of this paper are maximizing benefit cost and minimizing expenditure cost. All objectives are optimized while maintaining the bus voltage at the acceptable range and the DGs penetration levels are below of the DGs capacities.The proposed method is applied on the 33 bus microgrids systems using conventional and renewable DG technology, namely Photovoltaic (PV), Wind Turbine (WT), Micro Turbine (MT) and Gas Turbine (GT). The simulation results show the effectiveness of the proposed approach.
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
Solar PV parameter estimation using multi-objective optimisationjournalBEEI
The estimation of the electrical model parameters of solar PV, such as light-induced current, diode dark saturation current, thermal voltage, series resistance, and shunt resistance, is indispensable to predict the actual electrical performance of solar photovoltaic (PV) under changing environmental conditions. Therefore, this paper first considers the various methods of parameter estimation of solar PV to highlight their shortfalls. Thereafter, a new parameter estimation method, based on multi-objective optimisation, namely, Non-dominated Sorting Genetic Algorithm-II (NSGA-II), is proposed. Furthermore, to check the effectiveness and accuracy of the proposed method, conventional methods, such as, ‘Newton-Raphson’, ‘Particle Swarm Optimisation, Search Algorithm, was tested on four solar PV modules of polycrystalline and monocrystalline materials. Finally, a solar PV module photowatt PWP201 has been considered and compared with six different state of art methods. The estimated performance indices such as current absolute error matrics, absolute relative power error, mean absolute error, and P-V characteristics curve were compared. The results depict the close proximity of the characteristic curve obtained with the proposed NSGA-II method to the curve obtained by the manufacturer’s datasheet.
In this paper a load flow based method using MATLAB Software is used to determine the optimum location and optimum size of DG in a 43-bus distribution system for voltage profile improvement and loss reduction. This paper proposes analytical expressions for finding optimal size of three types of distributed generation (DG) units. DG units are sized to achieve the highest loss reduction in distribution networks. Single DG installation case was studied and compared to a case without DG, and 43-bus distribution system is used to demonstrate the effectiveness of the proposed method. The proposed analytical expressions are based on an improvement to the method that was limited to DG type, which is capable of injecting real power only, DG capable of injecting reactive power only and DG capable of injecting both real and reactive power can also be identified with their optimal size and location using the proposed method. This paper has been analysed with varying DG size and complexity and validated using analytical method for Summer case and Winter case in 43-bus distribution system in Myanmar.
Keywords- analytical method,distributed generation,power loss reduction,voltage profile improvement.
Optimal Power Generation in Energy-Deficient Scenarios Using Bagging EnsemblesKashif Mehmood
This paper presents an improved technique for optimal power generation using ensemble
artificial neural networks (EANN). The motive for using EANN is to benefit from multiple parallel processor
computing rather than traditional serial computation to reduce bias and variance in machine learning. The
load data is obtained from the load regulation authority of Pakistan for 24 hours. The data is analyzed on an
IEEE 30-bus test system by implementing two approaches; the conventional artificial neural network (ANN)
with feed-forward back-propagation model and a Bagging algorithm. To improve the training of ANN and
authenticate its result, first the Load Flow Analysis (LFA) on IEEE 30 bus is performed using Newton
Raphson Method and then the program is developed in MATLAB using Lagrange relaxation (LR) framework
to solve a power-generator scheduling problem. The bootstraps for the EANN are obtained through a disjoint
partition Bagging algorithm to handle the fluctuating power demand and is used to forecast the power
generation. The results of MATLAB simulations are analyzed and compared along with computational
complexity, therein showing the dominance of the EANN over the traditional ANN strategy that closed
to LR
Grid Connected Electricity Storage Systems (2/2)Leonardo ENERGY
Development and use of Renewable Energy Sources is one of the key elements in European Electricity Research. However, connecting energy sources such as photovoltaics and wind turbines to the electricity grid causes significant effects on these networks. Bottlenecks are stability, security, peaks in supply & demand and overall management of the grid. Energy storage systems provide means to overcome technical and economic hurdles for large-scale introduction of distributed sustainable energy sources. The GROW-DERS project (Grid Reliability and Operability with Distributed Generation using Flexible Storage) investigates the implementation of (transportable) distributed storage systems in the networks. The project is funded by the European Commission (FP6) and the consortium partners are KEMA, Liander, Iberdrola, MVV, EAC, SAFT, EXENDIS, CEA-INES and IPE.
In this project 3 storage systems (2 Li-ion battery systems and a flywheel) have been demonstrated at different test locations in Europe. Additionally, a dedicated software tool, PLATOS (PLAnning Tool for Optimizing Storage), has been developed by KEMA to optimize the energy management of electricity networks using storage. For each network, the location, size and type of storage systems is evaluated for all possible configurations and the most attractive option is selected.
Impact of Dispersed Generation on Optimization of Power ExportsIJERA Editor
Dispersed generation (DG) is defined as any source of electrical energy of limited size that is connected directly to the distribution system of a power network. It is also called decentralized generation, embedded generation or distributed generation. Dispersed generation is any modular generation located at or near the load center. It can be applied in the form of rechargeable, such as, mini-hydro, solar, wind and photovoltaic system or in the form of fuel-based systems, such as, fuel cells and micro-turbines. This paper presents the impact of dispersed generation on the optimization of power exports. Computer simulation was carried out using the hourly loads of the selected distribution feeders on Kaduna distribution system as input parameters for the computation of the line loss reduction ratio index (LLRI). The result showed that the line loss reduced from 163.56MW to 144.61 MW when DG was introduced which is an indication of a reduction in line losses with the installation of DG at the various feeders of the distribution system. In all the feeders where DG is integrated, the average magnitude of the line loss reduction index is 0.8754 MW which is less than 1 indicating a reduction in the electrical line losses with the introduction of DG. The line loss reduction index confirmed that by integrating DG into the distribution system, the distribution losses are reduced and optimization of power exports is achieved The results of this research paper will form a basis to establish that proper location of distributed generation units have significant impact on their effective capacity.
The optimal solution for unit commitment problem using binary hybrid grey wol...IJECEIAES
The aim of this work is to solve the unit commitment (UC) problem in power systems by calculating minimum production cost for the power generation and finding the best distribution of the generation among the units (units scheduling) using binary grey wolf optimizer based on particle swarm optimization (BGWOPSO) algorithm. The minimum production cost calculating is based on using the quadratic programming method and represents the global solution that must be arriving by the BGWOPSO algorithm then appearing units status (on or off). The suggested method was applied on “39 bus IEEE test systems”, the simulation results show the effectiveness of the suggested method over other algorithms in terms of minimizing of production cost and suggesting excellent scheduling of units.
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMaeijjournal
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its
exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is
equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the
optimization of the generative units to minimize the full action cost regarding problem constraints. In this
article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in
a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power
system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
Economic Dispatch using Quantum Evolutionary Algorithm in Electrical Power S...IJECEIAES
Unpredictable increase in power demands will overload the supply subsystems and insufficiently powered systems will suffer from instabilities, in which voltages drop below acceptable levels. Additional power sources are needed to satisfy the demand. Small capacity distributed generators (DGs) serve for this purpose well. One advantage of DGs is that they can be installed close to loads, so as to minimise loses. Optimum placements and sizing of DGs are critical to increase system voltages and to reduce loses. This will finally increase the overall system efficiency. This work exploits Quantum Evolutionary Algorithm (QEA) for the placements and sizing. This optimisation targets the cheapest generation cost. Quantum Evolutionary Algorithm is an Evolutionary Algorithm running on quantum computing, which works based on qubits and states superposition of quantum mechanics. Evolutionary algorithm with qubit representation has a better characteristic of diversity than classical approaches, since it can represent superposition of states.
Economic Dispatch using Quantum Evolutionary Algorithm in Electrical Power S...
Similar to A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD Table and ABC Algorithm Under Deregulated Environment
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineIJAPEJOURNAL
Economic load dispatch (ELD) and Unit Commitment (UC) are significant research applications in power systems that optimize the total production cost of the predicted load demand. The UC problem determines a turn-on and turn-off schedule for a given combination of generating units, thus satisfying a set of dynamic operational constraints. ELD optimizes the operation cost for all scheduled generating units with respect to the load demands of customers. The first phase in this project is to economically schedule the distribution of generating units using Gauss seidal and the second phase is to determine optimal load distribution for the scheduled units using dynamic programming method is applied to select and choose the combination of generating units that commit and de-commit during each hour. These precommitted schedules are optimized by dynamic programming method thus producing a global optimum solution with feasible and effective solution quality, minimal cost and time and higher precision. The effectiveness of the proposed techniques is investigated on two test systems consisting of five generating units and the experiments are carried out using MATLAB R2010b software. Experimental results prove that the proposed method is capable of yielding higher quality solution including mathematical simplicity, fast convergence, diversity maintenance, robustness and scalability for the complex ELD-UC problem.
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...paperpublications3
Abstract: In this paper, an algorithm to solve the optimal unit commitment problem under deregulated environment has been proposed using Particle Swarm Optimization (PSO) intelligent technique accounting economic dispatch constraints. In the present electric power market, where renewable energy power plants have been included in the system, there is a lot of unpredictability in the demand and generation. This paper presents an improved particle swarm optimization algorithm (IPSO) for power system unit commitment with the consideration of various constraints. IPSO is an extension of the standard particle swarm optimization algorithm (PSO) which uses more particles information to control the mutation operation, and is similar to the social society in that a group of leaders could make better decisions. The program was developed in MATLAB and the proposed method implemented on IEEE 14 bus test system.
ECONOMIC LOAD DISPATCH USING GENETIC ALGORITHMIJARIIT
This paper present the application of Genetic Algorithm (GA) to Economic Load Dispatch problem of the power system. Economic Load Dispatch is one of the major optimization problems dealing with the modern power systems.ELD determines the electrical power to be generated by the committed generating units in a power system so that the total generation cost of the system is minimized, while satisfactory the load demand. The objective is to minimize the total generation fuel cost and maintain the power flow within safety limits. The introduced algorithm has been demonstrated for the given test systems considering the transmission line losses.
Economic dispatch by optimization techniquesIJECEIAES
The current paper offers the solution strategy for the economic dispatch problem in electric power system implementing ant lion optimization algorithm (ALOA) and bat algorithm (BA) techniques. In the power network, the economic dispatch (ED) is a short-term calculation of the optimum performance of several electricity generations or a plan of outputs of all usable power generation units from the energy produced to fulfill the necessary demand, although equivalent and unequal specifications need to be achieved at minimal fuel and carbon pollution costs. In this paper, two recent meta-heuristic approaches are introduced, the BA and ALOA. A rigorous stochastically developmental computing strategy focused on the action and intellect of ant lions is an ALOA. The ALOA imitates ant lions' hunting process. The introduction of a numerical description of its biological actions for the solution of ED in the power framework. These algorithms are applied to two systems: a small scale three generator system and a large scale six generator. Results show were compared on the metrics of convergence rate, cost, and average run time that the ALOA and BA are suitable for economic dispatch studies which is clear in the comparison set with other algorithms. Both of these algorithms are tested on IEEE-30 bus reliability test system.
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMAEIJjournal2
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its
exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is
equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the
optimization of the generative units to minimize the full action cost regarding problem constraints. In this
article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in
a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power
system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMAEIJjournal2
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the optimization of the generative units to minimize the full action cost regarding problem constraints. In this article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
Advanced Energy: An International Journal (AEIJ)AEIJjournal2
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its
exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is
equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the
optimization of the generative units to minimize the full action cost regarding problem constraints. In this
article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in
a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power
system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...IDES Editor
In the deregulated electricity market, each
generating company has to maximize its own profit by
committing suitable generation schedule termed as profit
based unit commitment (PBUC). This article proposes a
Parallel Particle Swarm Optimization (PPSO) solution to the
PBUC problem. This method has better convergence
characteristics in obtaining optimum solution. The proposed
approach uses a cluster of computers performing parallel
operations in a distributed environment for obtaining the
PBUC solution. The time complexity and the solution quality
with respect to the number of processors in the cluster are
thoroughly tested. The method has been applied to 10 unit
system and the results show that the proposed PPSO in a
distributed cluster constantly outperforms the other methods
which are available in the literature.
Compromising between-eld-&-eed-using-gatool-matlabSubhankar Sau
Creating a compromising points between economic load dispatch & emission created from the plant to minimising those effects.
these are created by using MATLAB and GATOOL .
taking Weighted Sum Method,also Pareto optimal curve.
created by: SUBHANKAR SAU
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...IJAPEJOURNAL
This paper presents a new approach for considering all possible contingencies in short-term power system operation. Based on this new approach, both generator and transmission line outages would be modeled in network-based power system analysis. Multi generator and also parallel transmission lines is modeled in this methodology. We also investigate this claim that feasibility and applicability of this approach is much more than the previous analytical methodologies. Security Constrained Unit commitment (SCUC) program which is carried out by Independent System Operator (ISO), is one of the complex problems which would be handled by this approach. In this paper, a DC-Optimal Power Flow (DCOPF) methodology has been implemented by particle swarm optimization technique. The Lagrangian Relaxation technique is based on the derivatives and the PSO is a non- derivative technique. These approaches are effective tools which can be implemented for short-term and long-term power system analysis, especially for economic analysis of restructured power systems. The DCOPF methodology has been considered for LMP calculation in LR, which is not available in PSO techniques. In the other hand, PSO technique may be able to provide the optimal solution, where LR usually getting stuck at a local optimum in a large scale power system. The simulation results show that the presented methods are both satisfactory and consistent with expectation.
Techno-economical Unit Commitment Using Harmony Search Optimization ApproachIJAPEJOURNAL
In this paper, Security-Constrained Unit Commitment (SCUC) model is proposed in a restructured power system. This model consists of a closed-loop modified Unit Commitment (UC) and Security-constrained Optimal Power Flow (SCOPF). The objective of this SCUC model is to obtain the maximum social welfare-based system operating cost while maintaining the system security. In conventional power systems, the demand was forecasted before market operation and determined as a fixed constant. Supplying this demand was therefore considered as a constraint. However, in restructured power system which is based on Standard Market Design (SMD), DISCOs offer the demand and their proposed prices; therefore the demand is modeled as an elastic load. Independent System Operator (ISO) is responsible for operating the power market. The ISO performed the power market using the SCUC software to obtain feasible and economical operation as much as possible. In this paper, Harmony Search Algorithm (HSA) has been implemented to solve SCUC problem. Since the SCUC problem is a non-linear, mixed integer, large scale and non-convex problem, harmony search optimization is addressed as an efficient technique to overcome the aforementioned challenges. The simulation results show that the presented method is both satisfactory and consistent with expectation.
Operation cost reduction in unit commitment problem using improved quantum bi...IJECEIAES
Unit Commitment (UC) is a nonlinear mixed integer-programming problem. UC used to minimize the operational cost of the generation units in a power system by scheduling some of generators in ON state and the other generators in OFF state according to the total power outputs of generation units, load demand and the constraints of power system. This paper proposes an Improved Quantum Binary Particle Swarm Optimization (IQBPSO) algorithm. The tests have been made on a 10-units simulation system and the results show the improvement in an operation cost reduction after using the proposed algorithm compared with the ordinary Quantum Binary Particle Swarm Optimization (QBPSO) algorithm
International Journal of Engineering and Science Invention (IJESI) is an international journal intended for professionals and researchers in all fields of computer science and electronics. IJESI publishes research articles and reviews within the whole field Engineering Science and Technology, new teaching methods, assessment, validation and the impact of new technologies and it will continue to provide information on the latest trends and developments in this ever-expanding subject. The publications of papers are selected through double peer reviewed to ensure originality, relevance, and readability. The articles published in our journal can be accessed online.
Economic Load Dispatch for Multi-Generator Systems with Units Having Nonlinea...IJAPEJOURNAL
Economic Load Dispatch aims at distributing the load demand between various generation stations in a system such that the total cost of generation is minimum. This is of vital importance since it not only reduces the operation cost of the generation utility but also helps in conserving fast dwindling energy resources. Modern day power systems are large interconnected systems with a large number of generator units each having its own cost curve. Ideally the cost function of a unit is a quadratic function of the power generated by the unit and the cost curve obtained is a smooth parabola. But in practice cost curves deviate from the idealised one due the several reasons such as valve point effect, multi fuel operation, existence of forbidden zones etc. and as such may not be continuous or analytic. Also for a large interconnected system it becomes essential to consider the effect of transmission losses. Conventional numerical method based approaches work well with systems without losses but for large systems with losses obtaining convergence becomes difficult as the number of iterations required as well as the computational time are very high. These methods fail entirely if non ideal cost curves are considered. Hence soft computing based methods become essential. Here Gravity Search Algorithm(GSA) has been used to for finding economic load scheduling in a multi generator system, given a certain load demand, and taking into consideration the effects of practical constraints on the idealised load curve. The algorithms for finding the economic scheduling has been written in Matlab and has provided satisfactory results based on the given tolerance values. Also the traditional and soft computing based approaches have been compared to demonstrate the advantages of one over the other.
Similar to A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD Table and ABC Algorithm Under Deregulated Environment (20)
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...IJAPEJOURNAL
In power system, as any inequality between production and consumption results in an instantaneous change in frequency from nominal, frequency should be always monitored and controlled. Traditionally, frequency regulation is provided by varying the power output of generators which have restricted ramp rates. The Automatic Generation Control AGC process performs the task of adjusting system generation to meet the load demand and of regulating the large system frequency changes. A result of the mismatches between system load and system generation, system frequency and the desired value of 50 Hz is the accumulation of time error. How equilibrium system frequency is calculated if load parameters are frequency dependent, and how can frequency be controlled. Also, how do parameters of a speed governor affect generated power. The transient processes before system frequency settles down to steady state. Finally, AGC in what way is it different from governor action. This paper presents new approaches for AGC of power system including two areas having one steam turbines and one hydro turbine tied together through power lines.
Underwater Target Tracking Using Unscented Kalman FilterIJAPEJOURNAL
Unlike conventional active sonar, that transmits the sound signals and revealing their presence and position to enemy forces. The probable advantage of passive sonar is that it detects the signals emitted by the target, leads to improve localization, target tracking, and categorization. The challenging aspect is to estimate the true bearing and frequency measurements from the noisy measurements of the target. Here in this paper, it is recommended for the Unscented Kalman Filter (UKF) to track the target by using these noisy measurements. The Target Motion Analysis (TMA), which is the way to find the target’s trajectory by using frequency and bearing measurements, is explored. This method provides a tactical advantage over the classical bearing only tracking target motion analysis. It makes the observer maneuver unnecessary.
Investigation of Dependent Rikitake System to Initiation PointIJAPEJOURNAL
In this paper we investigate depending of the Rikitake system to initiation point, and monitor changing behavior of this system. We will have 4 initiation points in Cartesian system. We at 4 positions, will monitor behavior of this system, while holding constant other values, and after per position, will draw operation of system on axes of x, y, z and 3-D plot. We want to know, what is the effect of initiation point on Rikitake system? Numerical simulations to illustrate the effect of initiation point are presented, and at the end conclusions and comparing the states together are obtained.
Impact of Buried Conductor Length on Computation of Earth Grid ResistanceIJAPEJOURNAL
Effective design of substation earth grid implies achieving low earth grid resistance and fulfillment of the safety criteria at the lowest possible cost. This paper presents an evaluation of IEEE Standard 80-2000 Equations 50 to 52 to determine the impact of buried conductor length on computation of earth grid resistance. Calculated results indicated that a saturation point is reached beyond which further addition of more conductor length does not significantly reduce the earth grid resistance but incurs more economic implications. These were validated by earth grids designed using CDEGS where good agreement between the calculated and simulated results was found.
Enhancing Photoelectric Conversion Efficiency of Solar Panel by Water CoolingIJAPEJOURNAL
Photovoltaic solar cell generates electricity by receiving solar irradiance. The electrical efficiency of photovoltaic (PV) cell is adversely affected by the significant increase of cell operating temperature during absorption of solar radiation. This undesirable effect can be partially avoided by cooling the back side of the photovoltaic panel using water absorption sponge which was fixed on of PV panel and maintain wet condition by circulation of drop by drop water. The objective of the present work is to reduce the temperature of the solar cell in order to increase its electrical efficiency. Experiments were performed with and without water cooling. A linear trend between the efficiency and temperature was found. Without cooling, the temperature of the panel was high and solar cells were achieved an efficiency of 8–9%. However, when the panel was operated under water cooling condition, the temperature dropped maximally by 40C leading to an increase in efficiency of solar cells by 12%.
PMU-Based Transmission Line Parameter Identification at China Southern Power ...IJAPEJOURNAL
China Southern Power Grid Company (CSG) recently developed and implemented an online PMU-based transmission line (TL) parameter identification system (TPIS). Traditionally, TL parameters are calculated based on transmission tower geometries, conductor dimension, estimates of line length, conductor sags, etc. These parameters only approximate the effect of conductor sag and ignore the dependence of impedance parameters on temperature variation. Recent development in PMU technology has made it possible to calculate TL parameters accurately. The challenges are that such application requires highly accurate PMU data while the accuracy of PMU measurements under different working/system conditions can be uncertain. With a large number of PMUs widely installed in its system, CSG plans to improve and update the EMS database using the newly developed TPIS. TPIS provides an innovative yet practical problem formulation and solution for TL parameter identification. In addition, it proposes a new metric that can be used to determine the credibility of the calculated parameters, which is missing in the literature. This paper discusses the methodologies, challenges, as well as implementation issues noticed during the development of TPIS.
Investigation of Electric Field Distribution Inside 500/220 kV Transformation...IJAPEJOURNAL
This study depicts the electric field distributions inside a typical 500/220 kV open distribution substation under actual loading conditions and during different working conditions, Hot-Stick position and Bar-Hand position. The electric field is investigated for different workers heights of 1m, 1.5m and 1.8m above ground during normal working condition (Hot-Stick position) inside this substation. This in addition to assessment of the electric field at a height levels of 8m, 11m, 14m and 17m above ground as positions for live line maintenance under 220 kV Busbars, 500 kV Busbars, 220 kV Incoming and Outgoing feeders and 500 kV Incoming and Outgoing feeders respectively. In this study the simulation results of the electric field obtained using three dimensional (3D) computer model for existing typical high voltage transformation substation are compared with field values measured inside this typical substation and presented and discussed not only in the form of contour maps but also in the form 3D surface and wireframe maps. The simulation results are good matched and agreed with measured values. This in addition to the electric field will be tabulated and compared to international guidelines for personnel exposure to electric field. This study will serve for planning service works or for inspection of equipment inside high voltage (HV) power transformation substations.
Improving Light-Load Efficiency by Eliminating Interaction Effect in the Grid...IJAPEJOURNAL
A wind turbine equipped with doubly-fed induction generator (DFIG) is used in wind power plant industry. This paper studies the maximum power extraction of DFIG via evaluation of state-space equations in closed loop control condition for improving light-load efficiency. The DFIG state-space equations have been considered in the form of a multi-input- multi output (MIMO) system. Also, the tracing table has been used to determine the speed which the generated power will be proportional to the maximum load. The tracing table input is the generator speed, and its output is the optimum active power that has been considered as the reference power of the active power control system of the convertor. A controller is presented for the tracing table and the extracted power is able to follow the reference power with minimum ripple. Then, the results are compared with the single-input and single-output (SISO) case, for the values up to 0.2 times of the rated load. Therefore, in MIMO modeling, in the case that the DFIG connected to the grid, by eliminating the interaction effect, the efficiency in light-load can be increased
An Application of Ulam-Hyers Stability in DC MotorsIJAPEJOURNAL
In this paper, a generalization to nonlinear systems is proposed and applied to the motor dynamic, rotor model and stator model in DC motor equation. We argue that Ulam-Hyers stability concept is quite significant in design problems and in design analysis for the class of DC motor’s parameters. We prove the stability of nonlinear partial differential equation by using Banach’s contraction principle. As an application, the Ulam-Hyers stability of DC motor dynamics equations is investigated. To the best of our knowledge this is the first time Ulam-Hyers stability is considered from the applications point of view.
Implementation of Hybrid Generation Power System in PakistanIJAPEJOURNAL
A solar-wind hybrid power generation system has been presented here. The application based system illustrated in this paper is designed on the basis of the solar and wind data for Pakistan. The power generated by the system is intended for domestic use. The most common source of unconventional power in homes is battery based UPS (Uninterrupted power supply) inverter. The UPS inverter charges the battery with conventional grid power. This system will charge the battery of UPS inverter by using only wind and solar power, which will make the system cost effective and more reliable. The reason for using both solar and wind is that recent studies have proven that combined system can be more productive and consistent and other thing is that neither of them can be used for continuous power generation. In the system illustrated in this paper the solar-wind system provides power periodically which is controlled by electronic methods and a microcontroller is used to monitor the power from both the inputs. The switching action is provided from the microcontroller to the battery charging based on the power received from solar photovoltaic panel and wind generators. In this paper, an efficient system has been presented comprising of solar panel, wind generator, charge controller and charge storage unit (battery). Solar panel is selected as the main input and the wind resource will be used only in the absence of the solar photovoltaic (PV) output.
Modeling and Simulation of SVPWM Based ApplicationIJAPEJOURNAL
Recent developments in power electronics and semiconductor technology have lead to widespread use of power electronic converters in the power electronic systems. A number of Pulse width modulation (PWM) schemes are used to obtain variable voltage and frequency supply from a three-phase voltage source inverter. Among the different PWM techniques proposed for voltage fed inverters, the sinusoidal PWM technique has been popularly accepted. But there is an increasing trend of using space vector PWM (SVPWM) because of their easier digital realization, reduced harmonics, reduced switching losses and better dc bus utilization. This project focuses on step by step development of SVPWM technique. Simulation results are obtained using MATLAB/Simulink software for effectiveness of the study.
Comparison of FACTS Devices for Two Area Power System Stability Enhancement u...IJAPEJOURNAL
Modern Power Transmission networks are becoming increasingly stressed due to growing demand and restrictions on building new lines. Losing stability is one of the major threat of such a stressed system following a disturbance. Flexible ac transmission system (FACTS) devices are found to be very effective in a transmission network for better utilization of its existing facilities without sacrificing the desired stability margin. The static synchronous compensator (STATCOM) and Static Var Compensator (SVC) are the shunt devices of the flexible AC transmission systems (FACTS) family. When system voltage is low, STATCOM generates reactive power and when system voltage is high it absorbs reactive power whereas the Static Var compensator provides the fast acting dynamic compensation in case of severe faults. In this Paper, the performance of SVC is compared with the performance of STATCOM. Proposed controllers are implemented using MATLAB/SIMULINK. Simulation results indicate that the STATCOM controller installed with two machine systems provides better damping characteristics in rotor angle as compared to two machine system installed with SVC. Thus, transient stability enhancement of the two machine system installed with STATCOM is better than that installed with SVC.
Influence of Static VAR Compensator for Undervoltage Load Shedding to Avoid V...IJAPEJOURNAL
In the recent years, operation of power systems at lower stability margins has increased the importance of system protection methods that protect the system stability against various disturbances. Among these methods, the load shedding serves as an effective and last-resort tool to prevent system frequency/voltage instability. The analysis of recent blackouts suggests that voltage collapse and voltage-related problems are also important concerns in maintaining system stability. For this reason, voltage also needs to be taken into account in load shedding schemes. This paper considers both parameters in designing a load shedding scheme to determine the amount of load to be shed and its appropriate location .The amount of load to be shed from each bus is decided using the fixed step size method and it’s location has been identified by using voltage collapse proximity index method. SVC is shunt connected FACTS device used to improve the voltage profile of the system. In this paper impact of SVC on load shedding for IEEE 14 bus system has been presented and analyzed.
Assessment of Electric Field Distribution Inside 500/220 kV Open Distribution...IJAPEJOURNAL
The high level electric field intensity produced by high voltage (HV) equipments inside 500/220 kV substations is harmful for the human (staff) health. Therefore the minimum health and safety requirements regarding the exposure of workers to the risk arising from electric fields produced inside these substations is still considered as a competitive topic for utility designers, world health organization (WHO) and biomedical field researchers. It is very important to have knowledge about levels distribution of electric field intensity within these high voltage substations as early stage in the process of substation design. This paper presents results of investigation 50Hz electric field intensity distribution inside 500/220 kV power transmission substations in Cairo, Egypt. This paper presents a method for assessment the distribution of 50HZ electric field intensity distribution inside this substation, this method of analysis is based on the charge simulation technique (CSM). This study will serve for planning service works or for inspection of equipment on HV power transmission substations.
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...IJAPEJOURNAL
Frequency dependence complete model is set up for describing the lightning transient behavior of the wind turbines (WTs).To get an appropriate wind turbine model, a high frequency models of surge arrester protecting the boost transformer, transformer and ground electrode soil ionization are implemented. The transient responses and Ground Potential Rise (GPR) can be obtained at different locations in the WTs and connected grid in the time domain as well as in the frequency domain using Fast Fourier Transform (FFT). To check the validity of the model, Surge arresters protection level at different locations, at i.e. LV, MV and HV, is compared with ABB manufacture data sheet, Also a comparison has been made between simple and frequency dependence model of overall wind farm components using ATP/EMTP. This paper provides an accurate simulation of wind farm components under transient condition.
Hybrid Generation Power System for Domestic ApplicationsIJAPEJOURNAL
This work presents the plan and model of the control strategy for the interconnection of the hybrid energy system able to regulating this load’s voltage and controlling the energy generation with the energy options. The control strategy contains controlling the energy generated through each energy source, in a hierarchical mode using sliding/dropping mode control, while consuming consideration elements that have an impact on each electrical power source and transform the energy generated in order to suitable circumstances for lower power and domestic programs. The cross alternative energy system consists of photovoltaic cellular material, fuel cellular material and battery packs. A numerical equation in order to estimate the perfect voltage involving photovoltaic systems for virtually every solar irradiance and temperature circumstances is suggested. Simulations of a single or a lot more systems interconnected towards the load with the entire proposed control scheme, under different ecological and weight conditions, usually are introduced to indicate this efficiency with the procedure.
Ash Cooler Heat Recovery Under Energy Conservation SchemeIJAPEJOURNAL
A healthy fluidization state in circulating fluidized-bed combustion (CFBC) combustor is attributed to proper quantity of hot bed material (ash), which acts as a thermal fly-wheel. It receives & stores thermal energy from the burning of fuel (lignite) & distributes uniformly throughout the combustor & helps in maintaining a sustained combustion. The quantity of bed ash inside the combustor or size of the bed, depends upon boiler load & subsequently upon combustor temperature, lignite feed rate and ash % in lignite. As these parameters varies during process continuously, sometimes it becomes necessary to drain out the ash from the combustor. As & when differential pressure across the bed is increased from a justified level, draining of hot bed ash starts into Ash Coolers. Bed ash is drained at very high temperature of 850 oC & it also contains burning particles of lignite. This paper describes the heat recovery from bed ash, unloaded from the combustor into ash cooler, by pre-heating the condensate water of turbine cycle in a 125 MW CFB boiler of Surat Lignite Power Plant in India. The thermal performance of ash cooler was derived by doing a heat balance calculation based on the measured temperature of ash and cooling water with different load. From the heat balance calculation influence of ash temperature and ash amount on heat transfer coefficient is determined. Simulation is carried out around main turbine cycle indicates improved thermal economy of the unit, higher plant thermal efficiency, lower plant heat rate and reduce fuel consumption rate. Also simulation result shows that the heat transfer coefficient increase with ash amount and decreases with increase in ash temperature.
Harmonic Voltage Distortions in Power Systems Due to Non Linear LoadsIJAPEJOURNAL
Harmonics are found to have deleterious effects on power system equipments including transformers, capacitor banks, rotating machines, switchgears and protective relays. Transformers, motors and switchgears may experience increased losses and excessive heating. Shunt filters are effective in minimizing voltage distortions. This paper describes the voltage distortions generated by non linear loads. The harmonic specifications such as harmonic factor, characteristic harmonic and non-characteristic harmonic are considered while explaining the paper. ‘MiPower’ software is used to compute the harmonic distortions in a sample power system. Accurate harmonic models are established for a non linear load. To reduce the harmonic voltages impressed upon specific parts of the sample power system, passive filters are installed at two buses. With the implementation of a passive filter at the bus with non linear load, the harmonics are greatly reduced. For the specified power system, at all the buses the total harmonic distortion has been evaluated.
A Survey on Quality Changes in Positive, Negative and Combined Switching Stra...IJAPEJOURNAL
In this paper uses positive, negative and combined switching strategies for three phase ac/ac matrix converter .the author compares these strategies. The performance comparison of these three strategies is made under balanced operation. The simulation of three phase matrix converter feeding a three phase load was accomplished by means of the matlab/simulink software. After the simulation the comparison of the waveforms THD in three switching sequence is done. It must be mentioned that the duty cycle of the whole switches in the converter is according to Venturini switching algorithm
Modeling Simulation and Design of Photovoltaic Array with MPPT Control Techni...IJAPEJOURNAL
The Renewable energy is important part of power generation system due to diminution of fossils fuel. Energy production from photovoltaic (PV) is widely accepted as it is clean, available in abundance, & free of cost. This paper deals with modeling of PV array including the effects of temperature and irradiation. The DC-DC converter is used for boosting low voltage of the PV array to high DC voltage. Since the efficiency of a PV array is around 13% which is low, it is desirable to operate the module at the peak power point to improve the utilization of the PV array. A maximum power point tracker (MPPT) is used for extracting the maximum power from the solar PV array and transferring that power to the load. To track maximum power point (MPP) Perturb & Observe (P & O) algorithm is used which periodically perturbs the array voltage or current and compare PV output power with that of previous perturbation cycle which controls duty cycle of DC-DC converter. The entire system is simulated in MATLAB /SIMULINK and simulation results are presented.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
2. ISSN: 2252-8792
IJAPE Vol. 2, No. 3, December 2013: 125 – 140
126
N number of generating units
ai, bi, ci cost co-efficient of ith
generator
GENCO generation Company
TRANSCO transmission Company
DISCO distribution Company
Ri (t) Reserve of ith
generating unit during hour of t
SR (t) spinning reserve during hour of t
Xit unit status
1. INTRODUCTION
In a vertically integrated utility environment, the objective of Unit Commitment (UC) involves
scheduling the generators apart from satisfying the system constraints. The Unit commitment performs the
scheduling process in a utility for minimizing the total generation cost over the time period [1]-[2]. The
introduction of deregulation and restructuring in Electric power system creates a competitive open market
scenario. The generation company adopts Unit Commitment for maximizing their own profit instead of
minimizing the total generation cost of the centralized power system. This problem is referred as Profit Based
Unit Commitment (PBUC) problem. Profit Based Unit Commitment is defined as a method which schedules
their generators economically based on forecasted information such as spot price, reserve price, demand and
unit data with an objective to maximize the GENCOs profit. So, the solution methodology of PBUC problem
seems to be complex than traditional UC problem. The PBUC problem is divided into two sub problems [3]-
[4]. The first sub-problem is the determination of status of the generating units and second sub-problem is the
determination of output powers of committed units.
Earlier, classical methods such as [5]-[11] Priority List (PL), Dynamic Programming (DP), Branch-
Bound, Mixed Integer Programming (MIP) and Lagrangian relaxation (LR) were used to solve the UC
problem. Among these methods, the Priority List method [6] is a simple method but the quality of solution is
rough. The Dynamic Programming [7] is a flexible method to solve the UC problem. This approach features
the classification of generating units into related groups so as to minimize the number of unit combinations
which must be tested without precluding the optimal path. The dynamic programming technique involves
huge computational time to obtain the solution because of its complex dimensionality with large number of
generating units. Another approach has been presented for solving the unit commitment problem based on
branch and bound techniques [8]. The method incorporates time-dependent start-up costs, demand and
reserve constraints and minimum up and down time constraints. The priority ordering of the units is not
necessary in this technique.
Lagrange Relaxation method [11] provides fast solution but sometimes it suffers from numerical
convergence problem especially when the problem is nonconvex. Besides, this method strongly depends on
the technique used to update Lagrange multipliers. Many researchers dealing with LR are using sub gradient
technique for solving this problem. Even though, the solution obtained from gradient-based method suffers
from convergence problem and always gets stuck into a local optimum. In order to overcome these problems,
many stochastic optimizations such as [12]-[19] genetic algorithm [12]-[13], Memetic algorithm [14], Ant
colony optimization [15], Particle swarm optimization [16]-[17] and Muller method [18]-[19] were
introduced into power system optimization. These methods begin with a population of starting points, use
only the objective function information, and search a solution in parallel using operators borrowed from
natural biology. These methods are seems to be fast and reliable, but it has a problem of convergence on
large scale power system problem. Hybrid methods such as LR-MIP [20], LR-GA [21] and LR-EP [22]-[23]
have been used for solving the PBUC problems
In this article, a simple method for maximizing the profit of GENCOs is developed based on Pre-
prepared Power Demand (PPD) table with an Artificial Bee Colony (ABC) algorithm. The preparation of
PPD table simplifies the solution methodology of Profit Based Unit Commitment problem irrespective of
dimensionality of the system size. Also the execution time of the proposed approach is reduced when
compared with the existing methods. The proposed PPD-ABC approach has been tested on two test systems
and numerical results are presented to prove the effectiveness of the proposed method.
2. PROBLEM FORMULATION
2.1 Traditional unit commitment problem
In the past, UC is defined as a method to schedule generators economically in a power system in
order to meet the requirements of load and spinning reserve. Traditional UC can be defined mathematically
as an optimization problem as follows:
3. IJAPE ISSN: 2252-8792
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD (K. Asokan)
127
The objective function
(1)
Constraints
The following constraints must be satisfied during the optimization process:
1. Power balance constraint
N
i
tDitit PXP
1
Tt ............2,1 (2)
2. Spinning reserve constraint
N
i
ttDiti SRPXP
1
max
Tt ........2,1 (3)
Generation limit constraint
maxmin
iii PPP Ni .......2,1 (4)
4. Minimum up and down-time constraints
Ni
Ni
..........1
...........1
(5)
2.2 Profit based unit commitment problem
The objective is to determine the generating unit schedules for maximizing the profit of Generation
Companies subject to all prevailing constraints such as load demand, spinning reserve and market prices. The
term profit is defined as the difference between revenue obtained from sale of energy with market price and
total operating cost of the generating company.
The objective function
The PBUC can be mathematically formulated by the following equations.
Maximize TCRVPF (6)
T
t
N
i
ittit XSPPRV
1 1 (7)
T
t
N
i
ititit XSTXPFTC
1 1
.)(
(8)
The total operating cost, over the entire scheduling period is the sum of production cost and start-
up/shutdown cost for all the units. Here, the shutdown cost is considered as equal to zero for all units. The
production cost of the scheduled units is given in a quadratic form
2
)(. itiitiiitit PCPbaPFMin (9)
Constraints
1. Load demand constraint
N
i
tDitit PXP
1
Ni 1 (10)
T
t
N
i
ititit XSTXPFTC
1 1
.)(
,
,
ii
ii
TdownToff
TupTon
4. ISSN: 2252-8792
IJAPE Vol. 2, No. 3, December 2013: 125 – 140
128
2. Generator limits constraint
maxmin
iii PPP Ni 1 (11)
3. Spinning reserve constraint
N
i
itit SRXR
1
Tt 1 (12)
4. Minimum up/down time constraints
,
,
ii
ii
TdownToff
TupTon
Ni
Ni
..........1
...........1
(13)
3. SOLUTION METHODOLOGY
It is experienced from the literatures, that most of the prevailing algorithms have limitations to
provide optimal solution. Therefore, this paper is focused to derive a simple approach to improve GENCOs
profit under deregulated environment. For this, a table namely pre-prepared power demand is prepared using
the unit data, forecasted price and system demand. The PPD table identifies the commitment of units and
then ABC algorithm is prescribed to solve the fuel cost and revenue function. Remaining part of the article is
described as follows.
3.1. Mathematiacal model of Pre-prepared Power Demand (PPD) table
A complete algorithmic steps to prepare the PPD table is given below.
1. The minimum and maximum values of lambda are calculated for all generating units at their
minimum and maximum output powers (Pimin , Pimax ). Two lambda values are possible for each
generating units.
The value of lambda () are estimated by using the following equations
i
i
i
i
j
c
c
b
p
2
1
2
min
min
(14)
(15)
2. The lambda values are arranged in ascending order and label them as j (where j =1, 2…2N).
3. The output powers for all generators at each j value are calculated using the formulation
(16)
4. The minimum and maximum output power of generators are fixed as follows.
(i) For minimum output power limit
If minij then set 0jip
(17)
i
i
ji
c
b
p
2
i
i
i
i
j
c
c
b
p
2
1
2
max
max
5. IJAPE ISSN: 2252-8792
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD (K. Asokan)
129
If minij then set miniji pp
(18)
(ii) For maximum output power limit
If maxij then set maxiji pp
(19)
5. Lambda () value, output powers (Pji) and sum of output powers (SOP) for each are listed in the
table in ascending order. This table is referred as Pre-prepared Power Demand (PPD) table.
To illustrate the preparation of PPD Table, a typical 10 unit system is considered and unit data are shown in
Table -1.
Table 1. Fuel cost and generator limits data for 10 unit system
Unit
a
($)
b
($/MW)
c
($/MW2
)
Pimin
(MW)
Pimax
(MW)
1 1000 16.19 0.00048 150 455
2 970 17.26 0.00031 150 455
3 700 16.60 0.00200 20 130
4 680 16.50 0.00211 20 130
5 450 19.70 0.00398 25 162
6 370 22.26 0.00712 20 80
7 480 27.74 0.00079 25 85
8 660 25.92 0.00413 10 55
9 665 27.27 0.00222 10 55
10 670 27.79 0.00173 10 55
Table 2. Ascending order values of lambda for ten generating units
The ascending order values of lambda are given in Table - 2. Finally the PPD Table is prepared by
applying the above algorithmic steps and shown in Table – 3.
3.2. Mathematical model of Reduced Pre-prepared Power Demand (RPPD) table:
The Forecasted price plays an important role in preparing the RPPD Table. Because GENCOs yield
profit only when the forecasted price at the given hour is more than the incremental fuel cost of the
generators.
There are two ways to form the RPPD table from the PPD table.
1. From the PPD table, two rows are selected for the predicted power demand, such that the power
demand lies within the Sum of Powers (SOP) limits. The corresponding rows are considered k and
1k .
2. Here, two rows corresponds to the forecasted price are selected from the PPD table .So that
forecasted
price falls within the incremental cost. The rows are considered as l and 1l .
S.No λ S.No λ S.No λ S.No λ
1 16.33 6 17.12 11 22.54 16 27.51
2 16.58 7 17.35 12 23.48 17 27.78
3 16.63 8 17.54 13 26.00 18 27.82
4 16.68 9 19.90 14 26.37 19 27.87
5 17.05 10 20.99 15 27.31 20 27.98
6. ISSN: 2252-8792
IJAPE Vol. 2, No. 3, December 2013: 125 – 140
130
Table 3. Pre-prepared power demand (PPD) table for 10 unit 24 hour systems
(Including generator limits, minimum up and down time constraints and initial status of generators)
Therefore, the Reduced Pre-prepared Power Demand (RPPD) table is formed by
a) If the row lk , then the RPPD table is formed by considering the option 1.
b) If the row kl , then the RPPD table is formed by choosing the option 2.
The RPPD Table for various power demands are developed and shown in the Table - 4 to Table - 8.
Table 4. RPPD Table for Forecasted Demand of 700 MW to 850 MW
λ
($/MW)
P1
(MW)
P2
(MW)
P3
(MW)
P4
(MW)
P5
(MW)
P6
(MW)
P7
(MW)
P8
(MW)
P9
(MW)
P10
(MW)
SOP
(MW)
16.33 150 455 0 0 0 0 0 0 0 0 605.00
16.58 455 455 0 0 0 0 0 0 0 0 910.00
Table 5. RPPD Table for Forecasted Demand of 950 MW to 1150 MW
Table 6. RPPD Table for Forecasted Demand of 1200 MW to 1300 MW
λ
($/MW)
P1
(MW)
P2
(MW)
P3
(MW)
P4
(MW)
P5
(MW)
P6
(MW)
P7
(MW)
P8
(MW)
P9
(MW)
P10
(MW)
SOP
(MW)
16.68 455 455 0 42.65 0 0 0 0 0 0 952.65
17.05 455 455 112.50 130 0 0 0 0 0 0 1152.50
λ
($/MW)
P1
(MW)
P2
(MW)
P3
(MW)
P4
(MW)
P5
(MW)
P6
(MW)
P7
(MW)
P8
(MW)
P9
(MW)
P10
(MW)
SOP
(MW)
19.90 455 455 130 130 25.12 0 0 0 0 0 1195.12
20.99 455 455 130 130 162 0 0 0 0 0 1332.00
7. IJAPE ISSN: 2252-8792
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD (K. Asokan)
131
Table 7. RPPD Table for Forecasted Demand of 1400 MW
Table 8. RPPD Table for Forecasted Demand of 1500 MW
Now, it is necessary to form the Reduced Scheduling Units (RSU) table which explains the status of
committed units. The RSU table is obtained from RPPD table by substituting the binary values such a way
that if any element in the table is non zero, then it is replaced by 1. Therefore, if binary value is zero, then the
corresponding unit is in OFF state. Similarly if binary value is 1, then the unit is in ON state.
For example, the status of generating units for forecasted power demand of 700 MW is as follows
U1 U2 U3 U4 U5 U6 U7 U8 U9 U10
1 1 0 0 0 0 0 0 0 0
1 1 0 0 0 0 0 0 0 0
The decommitment of units, Inclusion of minimum up time and minimum down time constraints are
incorporated in the PBUC problem.
3.3. De-commitment of units
The profit of GENCOs depends on the proper scheduling of units. Sometimes, the spinning reserve
of the system is increased, due to the large gap between the selected lambda values in the RPPD table. So, it
is important to note that the decommitment of the unit is necessary to improve the financial benefits of
GENCOs.
If there is any excessive spinning reserve, then the RPPD table is examined. Then the excessive
units in the RPPD Table are decommitted after satisfying the spinning reserve constraints.
3.4. Minimum up time and minimum down time constraints
The OFF time of the unit is less than the minimum down- time, then status of that unit will be OFF.
Similarly if ON time of the unit is greater than the up time of the unit, then that unit will be ON. All these
useful information are applied in RPPD Table to perform the final unit commitment scheduling. Then
Artificial Bee Colony (ABC) algorithm has been proposed to solve the Economic Dispatch (ED) problem.
3.5. Artificial Bee Colony (ABC) Algorithm
Artificial Bee Colony (ABC) is the recently defined algorithms by Dervis Karaboga in 2005,
motivated by the intelligent behavior of honey bees [24]-[25]. ABC in an optimization tool provides a
population-based search procedure in which individuals called foods positions are modified by the artificial
bees with time and the bee’s aim is to discover the places of food sources with high nectar amount and finally
the one with the highest nectar.
In the ABC algorithm, the colony of artificial bees contains of three groups of bees: employed bees,
onlookers and scouts. The food source represents a possible solution of the optimization problem and the
nectar amount of a food source corresponds to the quality (fitness) of the associated solution. Every food
source has only one employed bee. Thus, the number of employed bees or the onlooker bees is equal to the
number of food sources (solutions).
The onlooker bees evaluate the nectar information and choose a food source depending on the
probability value associated with that food source ( , calculated by the following expression.
λ
($/MW)
P1
(MW)
P2
(MW)
P3
(MW)
P4
(MW)
P5
(MW)
P6
(MW)
P7
(MW)
P8
(MW)
P9
(MW)
P10
(MW)
SOP
(MW)
22.54 455 455 130 130 162 20 0 0 0 0 1352.00
23.48 455 455 130 130 162 80 0 0 0 0 1412.00
λ
($/MW)
P1
(MW)
P2
(MW)
P3
(MW)
P4
(MW)
P5
(MW)
P6
(MW)
P7
(MW)
P8
(MW)
P9
(MW)
P10
(MW)
SOP
(MW)
27.31 455 455 130 130 162 80 0 55 10 0 1477.00
27.51 455 455 130 130 162 80 0 55 54.05 0 1521.05
8. ISSN: 2252-8792
IJAPE Vol. 2, No. 3, December 2013: 125 – 140
132
Figure 1. Flow chart for proposed method
Initialize colony size, food number and food source
position of ABC parameters
Read unit data, Forecasted price
and system demand
Calculate lambda values, output powers
and sum of output powers (SOP)
to form PPD table
Time t = 1
Form RPPD table using PPD table for
the given time interval of system demand
Form reduced committed units (RCU)
table using RPPD table
Is maximum time
interval reached
Obtain the reduced committed units
(RCU) table for 24 hour interval
Incorporate decommitment of units,
minimum up and down and time
constraints
Form final unit commitment scheduling
for 24 hour interval including all
constraints
Call ABC algorithm to solve
economic dispatch (ED) subproblem
Evaluate fitness function of the ED
subproblem
Is optimal
solution reached
Print simulation results
Stop
Yes
Yes
No
t = t+1
No
Start
9. IJAPE ISSN: 2252-8792
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD (K. Asokan)
133
(20)
Where fiti is the fitness value of the solution i which is proportional to the nectar amount of the food
source in the position i and SN is the number of food sources is equal to the number of employed bees.
The employed bees exchange their information with the onlookers. In order to produce a candidate
food position from the old one, the ABC uses the following expression
(21)
Where, }.,..........2,1{ BNk and }.,..........2,1{ Dj are randomly chosen indexes. Although k is
determined randomly, it has to be different fromi . ij is a random number between [0, 1]. It controls the
production of a neighbour food source position around ijX and the modification represents the comparison
of the neighbour food positions visually by the bee.
If a predetermined number of trials does not improve a solution representing a food source, then that
food source is abandoned and the employed bee associated with that food source becomes a scout. The
number of trials for releasing a food source is equal to the value of ‘limit’, which is an important control
parameter of ABC algorithm.
The limit value usually varies from 0.001neD to neD. If the abandoned source is ijX , j (1,2,...D)
then the scout discovers a new food source ijX , calculated by using the equation.
)()1,0( minmaxmin jjjij XXrandXX
(22)
Where minjX and maxjX are the minimum and maximum limits of the parameter to be optimized.
There are four control parameters used in ABC algorithm. They are the number of employed bees, number of
unemployed or onlooker bees, the limit value and the colony size. Thus, ABC system combines local search
carried out by employed and onlooker bees, and global search managed by onlookers and scouts, attempting
to balance exploration and exploitation process.
4. SIMULATION AND RESULTS COMPARISON
The Pre-prepared power demand (PPD) table with an artificial bee colony algorithm (ABC) based
PBUC is first tested on 10 unit system available in the literature [18] and [23] as Case 1. It is also validated
on multiple test systems of 50 units in Case 2.
4.1 Test case: 1 (Ten unit Test System)
This test system adapted from [23] consisting of ten generating units with Twenty Four hour
scheduling periods and the fuel cost of each generators is estimated into quadratic form. The generator data,
forecasted market and demand price are also considered from the same reference.
Table 9. Unit Data for Ten Unit System
Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 Unit 8 Unit 9 Unit 10
Pmax 455 455 130 130 162 80 85 55 55 55
P min 150 150 20 20 25 20 25 10 10 10
a 1000 970 700 680 450 370 480 660 665 670
b 16.19 17.26 16.60 16.50 19.70 22.26 27.74 25.92 27.27 27.79
c 0.00048 0.00031 0.00200 0.00211 0.00398 0.00712 0.00079 0.00413 0.00222 0.00173
Min up 8 8 5 5 6 3 3 1 1 1
Min down 8 8 5 5 6 3 3 1 1 1
ST 4500 5000 550 560 900 170 260 30 30 30
Initial 8 8 -5 -5 -6 -3 -3 -1 -1 -1
SN
n
n
i
i
fit
fit
p
1
)( kjijijijij XXXV
10. ISSN: 2252-8792
IJAPE Vol. 2, No. 3, December 2013: 125 – 140
134
These data are described in Table-9 and Table-10. The feasible parameters obtained by various
processes for Artificial Bee Colony (ABC) algorithm are as follows. Colony size = 20; food number = 10;
Food source limit =100; and maximum number of iterations = 1000.
The proposed PPD-ABC methodology is tested to demonstrate its superior performance on ten units
twenty four hour system using MATLAB. Final unit commitment scheduling and output powers of
committed generators are displayed in Table - 11 and Table - 12 in detail. From this table, it is observed that
the GENCO decides to shut off Units 7 to 10 in all the commitment period and to sell power and reserve
below the forecasted level in some periods. This is because the objective of PBUC is not to minimize the
costs as before, but to maximize the profit with relaxation of the demand fulfillment and constraint.
Comparative studies have also been made to analyze the total cost, revenue and profit of Traditional and
PBUC system. The numerical results are presented in Table - 13. In order to verify the performance
advantages of PPD-ABC further, the simulation results were compared with that of other optimizing
techniques and comparison results are given in Table - 14 and 15. Fig-2 exhibits the graphical representation
of total cost, revenue and profit. Also Fig-3 compares the profit of four different optimization algorithm viz.,
traditional unit commitment, Muller method, parallel PSO and nodal ACO. From the results, it is clear that
the proposed methods provides maximum profits and are compared with those published in the recent
literatures.
Table 10. Forecasted Demand and Spot Price for Ten Unit 24 Hour System
Hour
(h)
Forecasted
Demand
(MW)
Forecasted
Reserve
(MW)
Forecasted
Market price
($/MWh)
1 700 70 22.15
2 750 75 22.00
3 850 85 23.10
4 950 95 23.65
5 1000 100 22.25
6 1100 110 22.95
7 1150 115 22.50
8 1200 120 22.15
9 1300 130 22.80
10 1400 140 29.35
11 1450 145 30.15
12 1500 150 31.65
13 1400 140 24.60
14 1300 130 24.50
15 1200 120 22.50
16 1050 105 22.30
17 1000 100 22.25
18 1100 110 22.05
19 1200 120 22.20
20 1400 140 22.65
21 1300 130 23.10
22 1100 110 22.95
23 900 90 22.75
24 800 80 22.55
13. IJAPE ISSN: 2252-8792
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD (K. Asokan)
137
Table 15. Comparison of hourly profits of existing methods with the proposed method
Figure 2. Revenue, Fuel cost and profit for the Ten unit 24 hour system
4.2 Test Case: 2 (Fifty Unit Test System)
In this example, the test system consists of multiple generating units such as 50 generating units.
More number of generating units is considered in order to validate the feasibility of the application of PPD-
ABC for large scale power system. The data for different groups of generating units are obtained by
duplicating the 10 unit system data. The demand is multiplied with respect to the system size; however the
generator limits, the minimum up/down time constraints remain same. Based on the forecasted market price
of energy information, the proposed approach is used to generate dispatch schedule for 24 hours time period.
The parameter setting of the 10 unit system is extended for the multiple test systems. The simulation results
0
10000
20000
30000
40000
50000
1 2 3 4 5 6 7 8 9 101112131415161718192021222324
Total cost ($)
Profit ($)
Revenue ($)
Cost ($)
Hour (h) Demand
(MW)
Traditional UC Muller method Parallel
PSO
Nodal
ACO
PPD-ABC
(Proposed)
1 700 1822 1822 1821.87 1822 1822
2 750 1946 1946 1945.50 1946 1946
3 850 3333 3333 3333.11 3333 3333
4 950 1647 3259 3258.20 3259 3259
5 1000 629 3805 3804.20 3805 3805
6 1100 697 1146 1145.67 2534 2544
7 1150 3120 3120 3119.96 3186 3186
8 1200 -34 2810 2809.74 2822 2822
9 1300 3456 1656 1655.98 2470 3570
10 1400 11982 11982 11981.79 10182 12320
11 1450 11813 13524 13523.82 13524 13524
12 1500 13658 15225 15641.82 15642 15642
13 1400 5672 5672 5671.79 5672 5672
14 1300 5666 5666 5261.04 5666 5654
15 1200 2175 3219 3219.24 3066 2809
16 1050 2410 2410 2409.83 2410 1892
17 1000 -3334 865 2117.44 2117 1573
18 1100 2376 2376 2375.67 2376 1851
19 1200 2868 2868 2868.24 2868 2446
20 1400 -5375 3395 3394.74 3395 3318
21 1300 -241 3921 3921.24 3921 3817
22 1100 2897 3366 3365.67 3623 3366
23 900 3297 3297 3297.09 3297 3297
24 800 2613 2613 2612.58 2613 2613
Total profit ($) 75093 103296 104556.23 105549 106081
14. ISSN: 2252-8792
IJAPE Vol. 2, No. 3, December 2013: 125 – 140
138
such as unit status, total cost, revenue and profit for 50 Unit 24 Hour System are given in Table – 16. From
the results, it is evident that the proposed method improves the profit of the GENCOs than existing methods.
Table 16. Simulation results for 50 unit 24 hour system
Hour
(hr)
Demand
(MW)
Unit status Fuel cost
($)
Revenue
($)
Profit
($)
1 3500 1111111111000000000000000
0000000000000000000000000
68420 77530 9110
2 3750 1111111111000000000000000
0000000000000000000000000
72780 82500 9720
3 4250 1111111111000000000000000
0000000000000000000000000
81510 98180 16670
4 4750 1111111111000000000000000
0000000000000000000000000
86770 103060 16290
5 5000 1111111111000000000000000
0000000000000000000000000
86770 105790 19020
6 5500 1111111111000001111100000
0000000000000000000000000
101070 119640 18570
7 5750 1111111111000001111100000
0000000000000000000000000
101070 117000 15930
8 6000 1111111111000001111100000
0000000000000000000000000
101070 115180 14110
9 6500 1111111111111111111100000
0000000000000000000000000
115530 133380 17850
10 7000 1111111111111111111111111
1111100000000000000000000
143940 205450 61510
11 7250 1111111111111111111111111
1111100000000000000000000
145240 212860 67620
12 7500 1111111111111111111111111
1111100000000000000000000
145240 223450 78210
13 7000 1111111111111111111111111
1111100000000000000000000
144010 172200 28190
14 6500 1111111111111111111111111
0000000000000000000000000
131160 159250 28090
15 6000 1111111111111111111111111
0000000000000000000000000
122060 135000 12940
16 5250 1111111111111111111111111
0000000000000000000000000
108500 117080 8580
17 5000 1111111111111111111111111
0000000000000000000000000
104040 111250 7210
18 5500 1111111111111111111111111
0000000000000000000000000
112710 121280 8570
19 6000 1111111111111111111111111
0000000000000000000000000
122020 133200 11180
20 7000 1111111111111111111111111
0000000000000000000000000
134260 150850 16590
21 6500 1111111111111111111111111
0000000000000000000000000
131220 150150 18930
22 5500 1111111111111111111100000
0000000000000000000000000
109440 126230 16790
23 4500 1111111111000000000000000
0000000000000000000000000
85890 102380 16490
24 4000 1111111111000000000000000
0000000000000000000000000
77140 90200 13060
Total profit 531330
15. IJAPE ISSN: 2252-8792
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit Using PPD (K. Asokan)
139
Fig-3. Comparison of profits with proposed and existing methods for ten unit 24 hour system
5. CONCLUSION
In this research work, the Profit Based Unit Commitment (PBUC) problem is described under
deregulated environment. A simple and reliable approach of pre-prepared power demand (PPD) table with an
Artificial Bee Colony (ABC) algorithm is proposed to solve the PBUC problem. The devised algorithm finds
the most economical scheduling plan for GENCO by considering both power and reserve generation. To
demonstrate the effectiveness and applicability of this method, it has been tested on ten units 24 hour and
fifty units 24 hour test systems and numerical results are tabulated. Results are obtained for the optimal unit
commitment schedule and MW values for real power, hourly profit and also the total profit of the GENCO.
The simulation result has been compared with Traditional method, PSO, parallel PSO, nodal ACO, Muller
method and hybrid methods such as TS-RP and TS-TRP. This results show that the proposed algorithm
provides maximum profit with less computational time compared to existing methods. Therefore it can be
concluded that the proposed PPD-ABC approach paves the best way for solving the power system
optimization problems under deregulated environment.
ACKNOWLEDGEMENTS
The authors gratefully acknowledge the authorities of Annamalai University for the facilities offered
to carry out this work.
REFERENCES
[1] Mohammad Shahidehpour, H.Yamin, and Zuyili. Market Operations in Electric Power Systems Forecasting,
Scheduling and Risk Management, Wiley, New York, 2002.
[2] Mohammad Shahidehpour, Muwaffaq and Alomoush. Restructured electrical power systems, Operation, Trading,
and volatility, Wiley, New York, 2000.
[3] Mohammad Shahidehpour and Hatim yamin, Saleem, AI–agtash. “Security Constrained Optimal Generation
Scheduling for GENCOs”, IEEE Transactions on power systems, Vol/Issue: 19(3). Pp. 1365-1371, 2004.
[4] Narayana Prasad Padhy. “Unit Commitment—A Bibliographical Survey”, IEEE Transactions on power systems,
Vol/Issue: 19(2). Pp. 1196-1205, 2004.
[5] Narayana Prasad Padhy. “Unit commitment problem under deregulated environment- a review”, Power Engineering
Society General Meeting, Vol. 2. Pp. 1088-1094, 2003.
[6] Wood A. J. and Woolenberg B. F. Power generation, operation and control, New York, NY: John Wiley Sons,
1996.
[7] Walter Snyder L., David Powell H. and John Rayburn C. “Dynamic programming approach tounit commitment”,
IEEE Transactions on Power System, Vol/Issue: 2(2). Pp. 339-348, 1987.
[8] Cohen A. I. and Yoshimura M. “A branch and bound algorithm for unit commitment”, IEEE Transaction on Power
Apparatus System, Vol/Issue: 102(2). Pp. 444-451, 1983.
[9] Dillon T. S, Edwin K. W, Taud R. and Kochs H. D. “Integer programming approach to the problem of optimal unit
commitment with probabilistic reserve Determination”, IEEE Transaction on Power Apparatus Systems, Vol/Issue:
97(6). Pp. 2156-2166, 1978.
‐10000
‐5000
0
5000
10000
15000
20000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Traditional UC
Muller method
Parallel PSO
Nodal ACO
PPD‐ABC (Proposed)
Profit($)
16. ISSN: 2252-8792
IJAPE Vol. 2, No. 3, December 2013: 125 – 140
140
[10] Arroyo M. C. and Jose M. “A computationally efficient mixed-integer linear formulation for the thermal unit
commitment problem”, IEEE Transactions on Power System, Vol/Issue: 21(3). Pp. 1371-348, 2006.
[11] Sudhir V., Adrian E. C., Imhof K. and Shishir M. “Implementation of a Lagrangian based unit commitment
problem”, IEEE Transactions on Power System, Vol/Issue: 4(4). Pp. 1373-1380, 1989.
[12] Arroyo J. M. and Conejo A. J. “A parallel repair genetic algorithm to solve the unit commitment problem”, IEEE
Transactions on Power System, Vol/Issue: 17(4). Pp. 1216-1224, 2002.
[13] C. W. Richter, Jr. and G. B. Sheble. “A profit-based unit commitment for the competitive environment,” IEEE
Transactions on Power System, Vol. 15. Pp. 715–721, 2000.
[14] Dionisios K. Dimitroulas, Pavlos S. Georgilakis. “A new memetic algorithm approach for the price based unit
commitment problem”, Applied Energy, Vol/Issue: 88(12). Pp. 4687–4699, 2011.
[15] C.Christopher Columbus, K. Chandrasekaran, Sishaj P.Simon. “Nodal ant colony optimization for solving profit
based unit commitment problem for GENCOs”, Applied soft computing, Vol. 12. Pp. 145-160, 2012.
[16] Jacob Raglend , C. Raghuveer, G. Rakesh Avinash, N.P. Padhy , D.P. Kothari. “Solution to profit based unit
commitment problem using particle swarm optimization”, Applied Soft Computing, Vol/Issue: 10(4). Pp. 1247–
1256, 2010.
[17] C.Christopher Columbus and Sishaj P Simon. “Profit based unit commitment for GENCOs using parallel in
distributed cluster”, ACEEE Int.J.onElectrical andPowerEngineering, Vol/Issue: 02(03), 2011.
[18] K. Chandram, N. Subrahmanyam, Member, IEEE, M.Sydulu. “New approach with Muller method for solving
Profit Based Unit Commitment”, DRPT2008 6-9 April 2008 Nanjing hina. Pp. 952-957, 2008.
[19] K. Chandram, N. Subrahmanyam and M. Sydulu. “Improved Pre-prepared Power Demand Table and Muller’s
Method to Solve the Profit Based Unit Commitment Problem”, Journal of Electrical Engineering & Technology,
Vol/Issue: 4(2). Pp. 159-167, 2009.
[20] Tao Li, Member, IEEE, and Mohammad Shahidehpour, Fellow. “Price-Based Unit Commitment: A Case of
Lagrangian Relaxation Versus Mixed Integer Programming”, IEEE Transactions On Power Systems, Vol/Issue:
20(4). Pp. 2015-2025, 2005.
[21] Cheng C. P., Liu C.W. and Liu C. C. “Unit commitment by Lagrangian relaxation and genetic algorithm”, IEEE
Transactions on Power System, Vol/Issue: 15(2). Pp. 707-714, 2000.
[22] H.Y.Yamin,Q.El-Dawirin,S.M.Shahidehpour. “A new approach for GenCos Profit based unit commitment in day-
ahead competitive electricity markets considering reserve uncertainty”, Electrical power and energy systems, Vol.
29. Pp. 609-616, 2007.
[23] Pathom Attaviriyanupap, Hiroyuki kita, Eiichi tanka and Jun Hasegawa. “A Hybrid LR-EP for Solving New Profit-
Based UC Problem Under Competitive Environment”, IEEE Transactions on power systems, Vol/Issue: 18(1).Pp.
229-237, 2003.
[24] Xiang liao, Jianzhong zhou, Rui zhang and Yongchuan zhang. “An adaptive artificial bee colony algorithm for long
term economic dispatch in cascaded hydropower systems”, Electrical power energy systems, Vol. 43. Pp. 1340-
1345, 2012.
[25] M. Basu. “Bee colony optimization for combined heat and power economic dispatch”, Expert system with
applications, Vol. 38. Pp. 13527-13531, 2011.
BIOGRAPHIES OF AUTHORS
K. Asokan received the B.E degree in Electrical and Electronics Engineering and the M.E
degree in Power Systems with distinction from Annamalai University, Annamalainagar, India
in the year 2001 and 2008 respectively. He is currently pursuing his research program in the
Department of Electrical Engineering and working as a Assistant Professor in the same
department. His research interests include power system operation and control, Deregulated
power systems and computational intelligence applications.
R. Ashok Kumar is presently the Professor of Electrical Engineering, Annamalai University,
India .His research interest includes Power system operation and control, Design analysis of
Electrical Machines, Radial distributed system and deregulated power system studies. He has
published many reports and journal articles in his research area. He received M.E degree
(Power System Engineering) in 1999 and Ph.D degree in 2009 both from Annamalai
University. In 1994 he joined Annamalai University as a Lecturer then elevated to the level of
Professor. He is a member of ISTE and other technical bodies.