IRC : 9-1972
TRAFFIC CENSUS
ON
NON-URBAN ROADS
(First Revision)
THE INDIAN ROADS CONGRESS
IRC : 9-1972
TRAFFIC CENSUS
ON
NON-URBAN ROADS
(First Revision)
Published by
THE INDIAN ROADS CONGRESS
Jamnagar House, Sbabjahan Road,
New DelhMI
1989
Price Rs. 80/-
(plus packing and postage)
ICR: 9-1972
First Published
First Revision
Reprinted
Reprinted
Reprinted
Reprinted
1960
September, 1972
May, 1989
July, 2001
August, 2005
June, 2009
{Rights of Publication and of Translation are reserved)
Printed at Abhinav Prints, Delhi
(500 copies)
IRC : 9-1972
TRAFFIC CENSUS ON NON-URBAN ROADS
]. INTRODUCTION
l.I. Periodic traffic census are a valuable source of basic data
for highway planning. As such, these should be a regular feature in
all highway departments.
This Standard was originally published in 1960. The revised
Standard was considered and approved by the Specifications and
Standards Committee in their meeting held on the 18th and 19th
November, 1971 and by the Executive Committee in their meeting
held on the 26th and 27th April, 1972. Later, it was approved for
publication as the finalised Standard by the Council at their 78th
meeting held at Nainital on the 10th July, 1972.
2. SCOPE
2.1. It is desirable that traffic census operations be carried out
in a uniform manner throughout the country.
2.2 The repetition of census operations, on the scale recom-
mended here, should normally be limited to important trunk routes
like the National Highways, State Highways and Major District
Roads.
3. SELECTION OF CENSUS POINTS
3.1. Judicious location of traffic count stations is crucial to the
success of a census programme. For trunk routes serving inter-city
traffic, it is relevant that the census sites should be fixed well away
from all urbanised developments and villages. In particular, sites
within zone of influence of towns where there may be a regular flow
of commuter traffic must be avoided. If need be, additional stations
could be set up for these zones.
3.2. Every road should be divided into convenient sections,
each carrying approximately similar traffic between points of substan-
tial traffic change. Count stations should be set up for each section.
The limits of the sections could generally be the important towns
along the road or major roads intersecting or taking off from the
highway in question.
1
IRC : 9-1972
3.3. Since division of the highway into sections and fixation of
census points for them are decisions of lasting significance, these
should be taken at a senior level in each highway department after
considering the traffic pauern along the entire route.
3.4 Every subsequent census should be taken at the same
locations. New stations could, of course, be added as and when
needed.
4. FREQUENCY AND DURATION OF CENSUS
4.1. Traffic should be counted at each point at least twice every
year. One count should be taken during the peak season of harvest-
ing and marketing and the other during the lean season. Each time
the count should be made for a full week spread over 7 consecutive
days and 24 hours of each day.
4.2. Traffic census should not generally encompass abnormal
conditions of traffic like a fair or exhibition. In such cases, the count
in the area should be postponed by a few days till normalcy returns.
5. RECORDING OF DATA
5.1. For the purpose of counts, a day could be divided into
three shifts of 8 hours each and separate enumerators with a super-
visor assigned for each shift. Enumerators should be literate persons
with preferably middle or matriculation level qualification. It may
be worth-while to specially train supervisors to go round from one
census point to the next and initiate the other staff new to this kind
of work.
5.2. Recording should be done for each direction of travel sepa-
rately. For this it will be necessary to divide staff for every shift
into two parties.
5.3. A field data sheet form for the manual recording of hourly
flows is given in Plate I. Before start of enumeration, it should be
ensured by the supervisors that the information in the form at the top
is duly filled in by the enumerators.
5.4. In each hourly column, the traffic should be recorded by
making tally marks in the five dash system (vertical strokes for the
first four vehicles, followed by an oblique stroke for the fifth vehicle
so as to depict a total of five). Hourly totals should be made at the
end of the shift.
2
IRC : 9-1972
6. COMPILATION OF DATA
6.1. A form for daily traffic summary is shown at Plate II.
Information in this sheet should be compiled from the field data
sheets. The highest peak hour traffic in the day for fast as well as
slow vehicles may be highlighted in the summary sheets by drawing
a firm line in red around the figures in the appropriate column.
6.2. The information collected in the daily summary sheets
should be transferred to the weekly traffic summary form shown at
Plate III. The average daily traffic for the week should then be
determined and indicated in the space provided for that in the form.
6.3. The daily and weekly traffic summaries should be prepared
in quadruplicate so that one copy could be kept by the Executive
Engineer incharge of maintenance of the road and the other copies
sent to the planning division at the headquarters office which in turn
would remit this information to the other agencies concerned, e.g., the
Roads Wing of the Ministry of Shipping and Transport in the case of
National Highways. The field data sheets should be preserved as
permanent record for at least five years.
6.4. An index map indicating the location of the census site
should be attached to the traffic summary sheets.
3
Digitized by the Internet Archive
in 2014
https://archive.org/details/govlawircy1972sp09_0
7
TRAFFIC CENSUS
WEEKLY TRAFFIC SUMMARY «o« ,cm,o»
HOUR -
--^
f
—
IRC 9
IRC 9
IRC 9

More Related Content

What's hot

GEOTECHNICAL INVESTIGATIONS
GEOTECHNICAL INVESTIGATIONSGEOTECHNICAL INVESTIGATIONS
GEOTECHNICAL INVESTIGATIONS
KYI KHIN
 
Importance and Classification of Road
Importance and Classification of RoadImportance and Classification of Road
Importance and Classification of Road
Shrikant Ingale
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
Sachin PatiL
 
Highway Classifications
Highway ClassificationsHighway Classifications
Highway Classifications
Muhammad Saleem
 
Seismic Refraction Test
Seismic Refraction TestSeismic Refraction Test
Seismic Refraction Test
Maliha Mehr
 
SURVEY CAMPING THEORY REPORT
SURVEY CAMPING THEORY REPORT SURVEY CAMPING THEORY REPORT
SURVEY CAMPING THEORY REPORT
Sabin Acharya
 
Dock and harbour
Dock and harbourDock and harbour
Dock and harbour
Dipankar Sarkar
 
harbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionharbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introduction
Hasna Hassan
 
Iirs Remote sensing application in Urban Planning
Iirs Remote sensing application in Urban PlanningIirs Remote sensing application in Urban Planning
Iirs Remote sensing application in Urban Planning
Tushar Dholakia
 
Bombay road plan
Bombay road planBombay road plan
Bombay road plan
Abhishek Dixit
 
Survey camp final_report_(g9)_095556
Survey camp final_report_(g9)_095556Survey camp final_report_(g9)_095556
Survey camp final_report_(g9)_095556
SunnyMahato2
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failure
Nabaraj Poudel
 
Site selection for a harbour
Site selection for a harbourSite selection for a harbour
Site selection for a harbour
Latif Hyder Wadho
 
Bridge pier
Bridge pierBridge pier
Bridge pier
Pritesh Parmar
 
Application of GIS in Transportation Planning
Application of GIS in Transportation Planning Application of GIS in Transportation Planning
Application of GIS in Transportation Planning
shrikrishna kesharwani
 
Introduction to surveying
Introduction to surveyingIntroduction to surveying
Introduction to surveying
Mir Zafarullah
 
bridge design
 bridge design bridge design
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and rails
Deven Diran
 
3. lecture 2 cadastral surveying rpv
3. lecture 2   cadastral surveying rpv3. lecture 2   cadastral surveying rpv
3. lecture 2 cadastral surveying rpv
FenTaHun6
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
Hossam Shafiq I
 

What's hot (20)

GEOTECHNICAL INVESTIGATIONS
GEOTECHNICAL INVESTIGATIONSGEOTECHNICAL INVESTIGATIONS
GEOTECHNICAL INVESTIGATIONS
 
Importance and Classification of Road
Importance and Classification of RoadImportance and Classification of Road
Importance and Classification of Road
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
 
Highway Classifications
Highway ClassificationsHighway Classifications
Highway Classifications
 
Seismic Refraction Test
Seismic Refraction TestSeismic Refraction Test
Seismic Refraction Test
 
SURVEY CAMPING THEORY REPORT
SURVEY CAMPING THEORY REPORT SURVEY CAMPING THEORY REPORT
SURVEY CAMPING THEORY REPORT
 
Dock and harbour
Dock and harbourDock and harbour
Dock and harbour
 
harbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionharbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introduction
 
Iirs Remote sensing application in Urban Planning
Iirs Remote sensing application in Urban PlanningIirs Remote sensing application in Urban Planning
Iirs Remote sensing application in Urban Planning
 
Bombay road plan
Bombay road planBombay road plan
Bombay road plan
 
Survey camp final_report_(g9)_095556
Survey camp final_report_(g9)_095556Survey camp final_report_(g9)_095556
Survey camp final_report_(g9)_095556
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failure
 
Site selection for a harbour
Site selection for a harbourSite selection for a harbour
Site selection for a harbour
 
Bridge pier
Bridge pierBridge pier
Bridge pier
 
Application of GIS in Transportation Planning
Application of GIS in Transportation Planning Application of GIS in Transportation Planning
Application of GIS in Transportation Planning
 
Introduction to surveying
Introduction to surveyingIntroduction to surveying
Introduction to surveying
 
bridge design
 bridge design bridge design
bridge design
 
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and rails
 
3. lecture 2 cadastral surveying rpv
3. lecture 2   cadastral surveying rpv3. lecture 2   cadastral surveying rpv
3. lecture 2 cadastral surveying rpv
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
 

Similar to IRC 9

1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf
ShivamKumar423966
 
Assessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer StationAssessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer Station
IRJET Journal
 
5 (1)
5 (1)5 (1)
IRJET- Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...
IRJET-  	  Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...IRJET-  	  Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...
IRJET- Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...
IRJET Journal
 
Feasibility Study of Mass Transport in Nasik City
Feasibility Study of Mass Transport in Nasik CityFeasibility Study of Mass Transport in Nasik City
Feasibility Study of Mass Transport in Nasik City
IRJET Journal
 
TRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIESTRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIES
tp jayamohan
 
IRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic SignalIRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic Signal
IRJET Journal
 
Traffic analysis and Road Widening
Traffic analysis and Road WideningTraffic analysis and Road Widening
Traffic analysis and Road Widening
Abhinav Pateriya
 
Traffic analysis and Widening of Roads
Traffic analysis and Widening of RoadsTraffic analysis and Widening of Roads
Traffic analysis and Widening of Roads
Abhinav Pateriya
 
Dromas 2 presentation v4
Dromas 2 presentation v4Dromas 2 presentation v4
Dromas 2 presentation v4
Arnold Kilaini
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
IRJET Journal
 
Transportation planning 1
Transportation planning 1Transportation planning 1
Transportation planning 1
EngrABRahimoon
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
Waliur Rahman
 
Public Transport Reform in Seoul
Public Transport Reformin SeoulPublic Transport Reformin Seoul
Public Transport Reform in Seoul
urbanbairam
 
Traffic volume studies
Traffic volume studiesTraffic volume studies
Traffic volume studies
Janak Parmar
 
Traffic volume count .pptx
Traffic volume count                             .pptxTraffic volume count                             .pptx
Traffic volume count .pptx
AshishGahlawat9
 
5. renewing of indonesia highway capacity manual urban road segment with traf...
5. renewing of indonesia highway capacity manual urban road segment with traf...5. renewing of indonesia highway capacity manual urban road segment with traf...
5. renewing of indonesia highway capacity manual urban road segment with traf...
wandi rusfiandi
 
Ce6006 iq
Ce6006 iqCe6006 iq
Ce6006 iq
sathishkumarp13
 
Traffic analysis with respect to pedestrian facilities
Traffic analysis with respect to pedestrian facilitiesTraffic analysis with respect to pedestrian facilities
Traffic analysis with respect to pedestrian facilities
Abhinav Pateriya
 
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
IRJET Journal
 

Similar to IRC 9 (20)

1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf
 
Assessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer StationAssessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer Station
 
5 (1)
5 (1)5 (1)
5 (1)
 
IRJET- Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...
IRJET-  	  Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...IRJET-  	  Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...
IRJET- Detailed Survey & Analysis of a Traffic System on Mid Block Sectio...
 
Feasibility Study of Mass Transport in Nasik City
Feasibility Study of Mass Transport in Nasik CityFeasibility Study of Mass Transport in Nasik City
Feasibility Study of Mass Transport in Nasik City
 
TRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIESTRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIES
 
IRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic SignalIRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic Signal
 
Traffic analysis and Road Widening
Traffic analysis and Road WideningTraffic analysis and Road Widening
Traffic analysis and Road Widening
 
Traffic analysis and Widening of Roads
Traffic analysis and Widening of RoadsTraffic analysis and Widening of Roads
Traffic analysis and Widening of Roads
 
Dromas 2 presentation v4
Dromas 2 presentation v4Dromas 2 presentation v4
Dromas 2 presentation v4
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
 
Transportation planning 1
Transportation planning 1Transportation planning 1
Transportation planning 1
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
Public Transport Reform in Seoul
Public Transport Reformin SeoulPublic Transport Reformin Seoul
Public Transport Reform in Seoul
 
Traffic volume studies
Traffic volume studiesTraffic volume studies
Traffic volume studies
 
Traffic volume count .pptx
Traffic volume count                             .pptxTraffic volume count                             .pptx
Traffic volume count .pptx
 
5. renewing of indonesia highway capacity manual urban road segment with traf...
5. renewing of indonesia highway capacity manual urban road segment with traf...5. renewing of indonesia highway capacity manual urban road segment with traf...
5. renewing of indonesia highway capacity manual urban road segment with traf...
 
Ce6006 iq
Ce6006 iqCe6006 iq
Ce6006 iq
 
Traffic analysis with respect to pedestrian facilities
Traffic analysis with respect to pedestrian facilitiesTraffic analysis with respect to pedestrian facilities
Traffic analysis with respect to pedestrian facilities
 
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
 

Recently uploaded

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 

Recently uploaded (20)

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 

IRC 9

  • 1. IRC : 9-1972 TRAFFIC CENSUS ON NON-URBAN ROADS (First Revision) THE INDIAN ROADS CONGRESS
  • 2.
  • 3. IRC : 9-1972 TRAFFIC CENSUS ON NON-URBAN ROADS (First Revision) Published by THE INDIAN ROADS CONGRESS Jamnagar House, Sbabjahan Road, New DelhMI 1989 Price Rs. 80/- (plus packing and postage)
  • 4. ICR: 9-1972 First Published First Revision Reprinted Reprinted Reprinted Reprinted 1960 September, 1972 May, 1989 July, 2001 August, 2005 June, 2009 {Rights of Publication and of Translation are reserved) Printed at Abhinav Prints, Delhi (500 copies)
  • 5. IRC : 9-1972 TRAFFIC CENSUS ON NON-URBAN ROADS ]. INTRODUCTION l.I. Periodic traffic census are a valuable source of basic data for highway planning. As such, these should be a regular feature in all highway departments. This Standard was originally published in 1960. The revised Standard was considered and approved by the Specifications and Standards Committee in their meeting held on the 18th and 19th November, 1971 and by the Executive Committee in their meeting held on the 26th and 27th April, 1972. Later, it was approved for publication as the finalised Standard by the Council at their 78th meeting held at Nainital on the 10th July, 1972. 2. SCOPE 2.1. It is desirable that traffic census operations be carried out in a uniform manner throughout the country. 2.2 The repetition of census operations, on the scale recom- mended here, should normally be limited to important trunk routes like the National Highways, State Highways and Major District Roads. 3. SELECTION OF CENSUS POINTS 3.1. Judicious location of traffic count stations is crucial to the success of a census programme. For trunk routes serving inter-city traffic, it is relevant that the census sites should be fixed well away from all urbanised developments and villages. In particular, sites within zone of influence of towns where there may be a regular flow of commuter traffic must be avoided. If need be, additional stations could be set up for these zones. 3.2. Every road should be divided into convenient sections, each carrying approximately similar traffic between points of substan- tial traffic change. Count stations should be set up for each section. The limits of the sections could generally be the important towns along the road or major roads intersecting or taking off from the highway in question. 1
  • 6. IRC : 9-1972 3.3. Since division of the highway into sections and fixation of census points for them are decisions of lasting significance, these should be taken at a senior level in each highway department after considering the traffic pauern along the entire route. 3.4 Every subsequent census should be taken at the same locations. New stations could, of course, be added as and when needed. 4. FREQUENCY AND DURATION OF CENSUS 4.1. Traffic should be counted at each point at least twice every year. One count should be taken during the peak season of harvest- ing and marketing and the other during the lean season. Each time the count should be made for a full week spread over 7 consecutive days and 24 hours of each day. 4.2. Traffic census should not generally encompass abnormal conditions of traffic like a fair or exhibition. In such cases, the count in the area should be postponed by a few days till normalcy returns. 5. RECORDING OF DATA 5.1. For the purpose of counts, a day could be divided into three shifts of 8 hours each and separate enumerators with a super- visor assigned for each shift. Enumerators should be literate persons with preferably middle or matriculation level qualification. It may be worth-while to specially train supervisors to go round from one census point to the next and initiate the other staff new to this kind of work. 5.2. Recording should be done for each direction of travel sepa- rately. For this it will be necessary to divide staff for every shift into two parties. 5.3. A field data sheet form for the manual recording of hourly flows is given in Plate I. Before start of enumeration, it should be ensured by the supervisors that the information in the form at the top is duly filled in by the enumerators. 5.4. In each hourly column, the traffic should be recorded by making tally marks in the five dash system (vertical strokes for the first four vehicles, followed by an oblique stroke for the fifth vehicle so as to depict a total of five). Hourly totals should be made at the end of the shift. 2
  • 7. IRC : 9-1972 6. COMPILATION OF DATA 6.1. A form for daily traffic summary is shown at Plate II. Information in this sheet should be compiled from the field data sheets. The highest peak hour traffic in the day for fast as well as slow vehicles may be highlighted in the summary sheets by drawing a firm line in red around the figures in the appropriate column. 6.2. The information collected in the daily summary sheets should be transferred to the weekly traffic summary form shown at Plate III. The average daily traffic for the week should then be determined and indicated in the space provided for that in the form. 6.3. The daily and weekly traffic summaries should be prepared in quadruplicate so that one copy could be kept by the Executive Engineer incharge of maintenance of the road and the other copies sent to the planning division at the headquarters office which in turn would remit this information to the other agencies concerned, e.g., the Roads Wing of the Ministry of Shipping and Transport in the case of National Highways. The field data sheets should be preserved as permanent record for at least five years. 6.4. An index map indicating the location of the census site should be attached to the traffic summary sheets. 3
  • 8.
  • 9.
  • 10. Digitized by the Internet Archive in 2014 https://archive.org/details/govlawircy1972sp09_0
  • 11. 7
  • 12.
  • 13. TRAFFIC CENSUS WEEKLY TRAFFIC SUMMARY «o« ,cm,o» HOUR - --^ f —