SlideShare a Scribd company logo
INTRODUCTION TO ASME VIII DIV 1
FABRICATION & INSPECTION
(U, UG, UW & UCS)
Batam, 04 July 2023
1
(Ir. Decky Antony Kifta, ST, MM)
ASME SECTION VIII
RULES FOR CONSTRUCTION OF PRESSURE VESSELS
• ASME VIII Div. 1 is for Pressure Vessels with pressure above 15 psig to 3,000 psig (20 MPa)
• ASME VIII Div. 2 is for Pressure Vessels with pressure above 15 psig to 10,000 psig (70 MPa)
• ASME VIII Div. 3 is for Pressure Vessels with pressure above 10,000 psig (70 MPa)
• ASME VIII Div. 1 regulates stamps: U, UM, and PRT VIII-1.
• ASME VIII Div. 2 regulates stamps: U2 and PRT VIII-2
• ASME VIII Div. 3 regulates stamps: U3
• Requirements of Certification Markings of UV, UD, UV3 & UD3 were transferred to ASME XIII
• ASME VIII is issued every 2 years, the latest one was issued on 1st July 2023 and next issuance will be on
1st July 2025. The Edition will be effective 6 months after issuance.
• Contract signed prior to the effective date may use the older edition.
• Revision is indicated by (Year) or (23) at the page margin.
Common PV standards other than ASME VIII
• PD 5500
• EN 13445
• AS 1210
2
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
3
Ir. Decky Antony Kifta, ST, MM
Certification Marks/ Stamps covered in this
Division (based on Year 2023 Edition)
ASME VIII Div. 1 is divided into 3 subsections:
• Subsection A: General Requirements
• Part UG : General Requirements for all methods of constructions and materials
• Subsection B: Requirements Pertaining to Methods of Fabrication PV
• Part UW : Welding
• Part UF : Forging
• Part UB : Brazing
• Subsection C: Requirements Pertaining to Classes of Materials
• Part UCS : Carbon & Low Alloy Steels
• Part UNF : Non-Ferrous Materials
• Part UHA : High Alloy Steels
• Part UCI : Cast Iron
• Part UCL : Cladding, Overlay Cladding & Linings
• Part UCD : Cast Ductile Iron
• Part UHT : Heat Treated enhanced Tensile Ferritic Steels
• Part ULW : Layered Construction
• Part ULT : Low Temperature
• Part UHX : Shell & Tube Heat Exchanger
• Part UIG : Impregnated Graphite
ASME SECTION VIII DIV. 1
4
Ir. Decky Antony Kifta, ST, MM
[U-1] Vessels/pressure parts excluded from the scope are:
• Piping components (pipe, flange, fittings, valves, etc.)
• Vessels having an internal or external pressure not exceeding 15 psig.
• Vessels having inside diameter, width, height or cross-sectional diagram not exceeding 6-in.
• Pressure vessels for human occupancy.
• Vessels having design pressure exceeding 3,000 psig.
[U-1(j) The requirements of UM pressure vessels.
ASME SECTION VIII DIV. 1
[U-2] User’s Design form and involvement of RPE is required when below conditions are design requirements:
• Superimposed static reactions
• Cyclic or dynamic reactions
• Loadings due to wind, snow or seismic reactions
• Impact reactions
• Temperature effects
• Abnormal pressures
[U-4] Units of Measurements
• U.S. Customary, SI, or any local customary units may be used to demonstrate compliance with
requirements of this edition related to materials, fabrication, and overpressure protection, however, only
one or single system of units shall be used for all aspects of design except otherwise permitted by this
Division.
5
Ir. Decky Antony Kifta, ST, MM
SUBSECTION A
PART UG
GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION AND ALL
MATERIALS
6
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-4] General:
• Materials used shall conform with ASME Sect II Part D
• ASTM materials may be used provided conforming to
ASME Sect II Part A, Table II-200-1, i.e. within the
year specified in the table. This is also applicable for
SB materials.
[UG-10]
• Material identified with a specification not permitted by
this division and identified to a single production lot as
permitted by a permitted specification may be accepted
provided documentation is provided to the pressure
manufacturer that all applicable chemical and mechanical
properties meeting the permitted specification. When no
documentation is available the PV manufacturer can
perform chemical analysis and mechanical test and the
results are compared with a permitted specification.
[UG-5] Plate, [UG-6] Forgings, [UG-7] Castings, [UG-
8] Pipe and Tubes, and [UG-9] welding materials
7
Ir. Decky Antony Kifta, ST, MM
[UG-10] Cont’d.
• Pressure vessels manufacturer may re-certify and
mark the materials to the permitted specification.
• Material without identification shall not be used.
ASME SECTION VIII DIV. 1
[UG-11] Prefabricated and preformed items may be
produced by other than PV manufacturer without a
certification mark as long as no permanent welding involved.
Permanent welding including weld overlay, except for
welded shell, heads or QOC, may be subcontracted to non-
ASME stamped shop provided the requirements specified in
this section are satisfied (UG-11(e).
[UG-12] Bolts & Studs, [UG-13] Nuts & Washers, [UG-14]
Rods & Bars, [UG-15] Product Specification
[UG-16 to UG-34] Design Issues (not discussed) except UG-
20(f) below
8
Ir. Decky Antony Kifta, ST, MM
[UG-20(f)] Impact test exemption for P-1
materials
• Impact test per UG-84 is not mandatory
for PV materials satisfying the bellow:
• The material shall be limited to P-1 gr. 1
& 2 and thickness shall not exceed:
• 13 mm materials for curve A
• 25 mm materials for curve B
• The PV shall be hydro-tested & designed
temp. Shall be from -29 to 345 °C.
[UG-35] Other Type of Closures
• Dished Covers (Dished head with bolting flanges)
• Quick Actuating Closures
• Quick Opening Closures (QOC) [UG-36 to UG-53] Design Issues (not discussed)
ASME SECTION VIII DIV. 1
[UG-54] Supports:
All vessels shall be supported, and the supporting members shall be attached to withhold maximum imposed
loadings.
[UG-55] Lugs for platforms, ladders, and other attachments to vessel walls
Lugs or clips may be welded, brazed, or bolted to the outside or inside of the vessel support ladders,
platforms, etc.
[UG-76] Cutting plates and other stock
Plates, edges of heads, and other parts may be cut to shape and size by mechanical means such as
machining, shearing, grinding or by oxygen or arc cutting. After oxygen or arc cutting all slags and
detrimental discoloration shall be removed by mechanical means.
[UG-77] Material identification
The manufacturer shall maintain traceability of the materials to the original identification markings by either
or combination of: [1] accurate transfer of identification (heat no.), [2] use of coded marking (unique no.)
traceable to the original marking, [3] recording the material identification on the tabulation (traceability
sheet) or as built drawings which ensure that identification of each material during fabrication to vessel
completion.
9
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-78] Repair of Defects in Materials
Defects in material may be repaired provided accepted by AI (Authorized Inspector)
[UG-79] Forming Pressure Parts
Shells or heads may be rolled or formed provided extreme fiber elongation (forming strains) are observed
and when required subsequent heat treatment shall be performed.
[UG-80] Permissible Out-of-Roundness of Cylindrical, Conical and Spherical Shells
The difference between the maximum and minimum inside diameters at any cross section shall not exceed
1% of the nominal diameter at the cross section under consideration.
10
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-81] Tolerance for Formed Heads
The inner surface of head shall not deviate outside of the specified shape by more than 1-1/4% of D nor
inside of the specified the specified shape by more than 5/8% of D, where D is the nominal inside diameter
of the vessel shell at point of attachment.
[UG-82] Lugs & Fitting Attachments
[UG-84] Charpy Impact Test
• Test procedure to follow: ASME SA-370 or ISO 148
• Test specimen shall be as per Fig. UG-84 & Fig. UG-84.5
• Acceptance criteria shall be as per Fig. UG-84.1
• When impact test on production required one test plate shall be made for each welding procedure used
for Category A and B, however, when manufacturer uses same welding procedure for both categories,
only Category A can represent the test plate. [UG-84(i)(1) – (3)].
• For production weld impact test, the test to be performed on weld metal and heat affected zone.
[UG-85] Heat Treatment
Heat treatment of plate may be performed by PV manufacturer
11
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-90] Inspection and Tests: Manufacturer’s responsibility
(1) Maintain Certificate of Authorization
(2) Prepare drawings & design calculations
(3) Materials identifications used for
Construction
(4) Obtain Partial Data Reports (if any)
(5) Prepare access for the Inspector
(6) Examination of materials, materials
identification, and traceability.
(7) Document impact tests and other tests
(8) Concurrence of the Inspector prior to any
base metal repairs.
(9) Examination of heads & shells are properly
formed.
(10) Qualification of welding procedures
(11) Qualification of welders & welding
operators
(12) Examination of all parts prior to joining for welding
(13) Examination of parts for material marking, defects,
and dimensional geometry.
(14) Provisions of controls to ensure that all required
heat treatments are performed.
(15) Provisions of records of NDT including RT images.
(16) Making the required hydrotest or pneumatic test &
arranging witness by the Inspector.
(17) Applying the required stamping/ nameplate to the
vessel
(18) Preparing the required Manufacturer’s Data
Reports & certifying by Inspector
(19) Providing the retention of RT & UT reports
Manufacturer’s Data Reports and other records.
12
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-93] Inspection of Materials
• Plates shall require materials test reports
• All other product forms can be accepted when the product has the correct marking of specification
including grade, type and class of the materials.
[UG-92] Inspection of Materials
• Manufacturer shall arrange free access to AI for performing inspection on PV.
[UG-91] The Inspector
• Individual employed by ASME Accredited Authorized Inspection Agency (AIA) as per ASME QAI-1.
[UG-94] Marking on Materials
• If the material identifying marks are obliterated or material is divided into two or more parts, the marks
shall be properly transferred by the Manufacturer.
[UG-95] Examination of surfaces during fabrication, [UG-96] Dimensional check of component parts & [UG-
97] Inspection During Fabrication.
13
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-98] Maximum Allowable working pressure
• MAWP is the maximum pressure permissible at the top of the vessel in its normal operating position at
the designated coincident temperature specified for that pressure.
[UG-99] Standard Hydrostatic Test
• Vessels designed for internal pressure shall be subjected to a hydrostatic test pressure that at every point
in the vessel is at least equal to 1.3 x MAWP multiplied by LSR (Lowest Stress Ratio) for the pressure
boundary materials of which the vessel is constructed.
• The vessel shall not be hydrotested with paint or internal lining unless approved by user or his designated
agent.
• The minimum temperature during hydrotest shall be 17 °C warmer than MDMT and maximum test
temperature is 48 °C.
• Vessel with Lethal service shall not be painted or internally lined prior to hydrotest.
14
Ir. Decky Antony Kifta, ST, MM
Ir. Decky Antony Kifta, ST, MM 15
[UG-100] Pneumatic Test
• Vessels shall be pneumatic tested that at every point in the vessel is at least equal to 1.1 x MAWP
multiplied by LSR (Lowest Stress Ratio) for the pressure boundary materials of which the vessel is
constructed.
• The vessel shall not be pneumatic tested with paint or internal lining unless approved by user or his
designated agent.
• The minimum temperature during hydrotest shall be 17 °C warmer than MDMT and maximum test
temperature is 48 °C.
• Vessel with Lethal service shall not be painted or internally lined prior to pneumatic testing.
ASME SECTION VIII DIV. 1
16
Ir. Decky Antony Kifta, ST, MM
Hydrotest Operation
ASME SECTION VIII DIV. 1
[UG-101] Proof Tests to establish MAWP
• Where design rule do not exist in this Division therefore this proof test method to be performed [U-2
(g)(1)]
[UG-102] Test Gages
• Dial indicating pressure gage used in testing shall be graduated over a range of about doble the
intended maximum test pressure, but in no case shall the range be less than 1-1/2 nor 4 times that
pressure. Digital reading pressure gages having wider range of pressure may be used, provided the
readings give the same or greater degree of accuracy as obtained with dial pressure gage.
[UG-103] NDT
• MPI shall be performed as per Mandatory Appendix 6 and PT shall be as per Mandatory Appendix 8.
[UG-115] Marking and Reports
• The unit of measurement used in Manufacturer’s Data Reports (U Stamp), Manufacturer’s Certificates of
Compliance (UM Stamp) and capacity certification of pressure relief devices and in marking or stamping
pressure vessels, vessel parts and pressure relief devices, required by this Division, shall be either US
Customary Units or any local customary units and a single system of units shall be used for all aspects of
design [U-4(b)]
17
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-116] Required Marking
• Each PV shall be marked with the following
[UG-116] Required Marking
• When RT or UT examination has been performed
• RT-1 when all pertaining butt welds other than Category B and C butt welds associated with nozzles and
communicating chambers that neither exceeds NPS 10 nor 1-1/8 in. wall thickness satisfy the full RT
requirements for their full length [UW-11(a)]
18
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-116] Required Marking (Cont’d)
• RT-2 when the complete vessel satisfies the
requirement UW-11(a)(5) (full RT on LS) and
when the spot radiography requirements of
UW-11(a)(5)(-b) (spot RT on circ seam which
intersect with LS) have been applied.
• RT-3 when the complete PV satisfies the spot RT
as per UW-11b.
• RT-4 when only part of the complete PV has
satisfied the RT [UW-11(a)] or where none of
the markings RT-1, RT-2 or RT-3 are applicable.
[UG-116] Required Marking (Cont’d)
• Parts of vessels for Which partial Data Reports
are required in UG-120 (c) shall be marked by
the manufacturer of the part, with a nameplate
or stamping, with the following:
• The U Designator shall stamp the word
‘PART’ below the Certification Mark.
• The PRT Designator shall stamp the name
of the manufacturer after/below the
words ‘certified by’ and the manufacturer’s
serial number. The word PART may not be
stamped.
19
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
[UG-117] Certificates of Authorization and
Certification Marks
• UM Certification Mark is granted by the
Society and is used by the manufacturer
• UM Designator shall employ a Certified
Individual qualified to ASME CA-1 and meeting
the requirements of ASME QAI-1
• Certified Individual shall certify Form U-3, U-
3A or U-3P (Manufacturer’s Certificate of
Compliances)
• UM Designator shall already have S or U
certificate.
• UM certification is valid for 1 year but the 1st
and 2nd reviews can be done by AI and AI
Supervisor. The third review or joint review will
be performed after 3 years
• Any Manufacturer holding U, UM & PRT VIII-1
Certification marks shall have QC System
(Manual) as per Appendix 10 & ASME CA-1.
[UG-118 & 119] Methods of Stamping & Nameplate
• The required marking shall be applied by one of the
following methods:
• Nameplate
• Stamped directly on the vessel
• Electrochemically etched
20
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
21
Ir. Decky Antony Kifta, ST, MM
U stamp Nameplates (Samples)
ASME SECTION VIII DIV. 1
22
Ir. Decky Antony Kifta, ST, MM
[UG-120] Date Reports
• Manufacturer’s Data reports to be filled by U
Designator are:
• Form U-1, U-1A or U-1P (Plate Heat
Exchanger) and U-4 (attachment) when
required.
• Form U-5 for Fixed Tube Sheet Heat
Exchanger
• Manufacturer’s Certificate of Compliance to be
issued by UM Designator are:
• Form U-3, U-3A or U-3P
• Parts manufacturer shall fill in Form U-2 or U-
2A.
[UG-120] Date Reports (Cont’d)
• U Designator shall maintain the Manufacturer’s
Data Reports for at least 3 years
• UM Designator shall maintain the
Manufacturer’s Certificate of Compliance for at
least 5 years.
• Vessel (U or UM) to be registered to National
Board, the Manufacturer’s Data Reports or
Manufacturer’s Certificate of Compliance shall
be sent to National Board of Boiler and
Pressure Vessel Inspector in Ohio, USA.
[UG-150 to 156] regarding the pressure relieve valves or devices (not discussed)
SUBSECTION B
PART UW
REQUIREMENTS PERTAINING METHODS OF FABRICATION OF PRESSURE VESSELS
23
Ir. Decky Antony Kifta, ST, MM
ASME SECTION VIII DIV. 1
24
Ir. Decky Antony Kifta, ST, MM
[UW-2] Service Restrictions
• PV contains lethal substances, all butt welds
shall be fully radiography
• When fabricated using carbon or low alloy
materials, PV shall be PWHT at any wall
thickness
• The meaning of lethal is liquid or gas that a
very small amount mixed or not mixed with air
is dangerous to life when inhaled.
[UW-3] Welded Joint Category
• Cat A = longitudinal welded joint (shell &
head) and circ seam shell to heads other than
the dished head.
• Cat B = circumferential welded joint
• Cat C = weld connecting flanges, flat head to
main shell.
• Cat D = weld connecting nozzles to main shells,
to heads
ASME SECTION VIII DIV. 1
25
Ir. Decky Antony Kifta, ST, MM
[UW-5 & UW-6] Materials and Weld Consumables (not discussed)
[UW-8 & UW-9] Design (not discussed)
[UW-10] PWHT, refer to UW-40 and UCS-56 (for carbon and low
alloy steels)
[UW-11] Radiography and Ultrasonic Examination
• Full radiography to be performed on:
• All butt welds in the shell and heads of vessels to contain
lethal substances
• All butt welds in the shell and heads of vessels with
thickness exceed 1-1/2 in (38 mm) or for carbon and low
alloy steels as per Table UCS-57.
[UW-12] Joint Efficiencies
• Refer to Table UW-12 below
PAUT (Phased Array UT)
ASME SECTION VIII DIV. 1
26
Ir. Decky Antony Kifta, ST, MM
Ir. Decky Antony Kifta, ST, MM 27
[UW-13] Attachment Details not designed
[UW-14] Openings in or adjacent to welds
• Single opening may be located in head-to-shell or Category B or C butt-welded joints, provided the weld
meets the radiographic requirements in UW-51 for a length equal to three times the diameter of the
opening with the center of the hole at midlength. Defects that are completely removed in cutting the hole
shall not be considered in judging the acceptability of the weld.
[UW-15 to UW-20] regarding design (not discussed)
ASME SECTION VIII DIV. 1
28
Ir. Decky Antony Kifta, ST, MM
[UW-26] Fabrication
• Each manufacturer shall be responsible for the quality of the welding done by the organization
• All welding shall be performed in accordance with Manufacturer’s WPS in accordance with ASME IX.
• All welders shall be qualified by the manufacturer in accordance with ASME IX
• The manufacturer shall be responsible for Code compliance of the vessel or part, including Certification
Mark Stamping and providing Manufacturer’s Data Report Forms properly and countersigned by the
Inspector.
[UW-27] Welding Processes
• The welding processes that may be used in the construction of vessel are limited to those listed in ASME IX.
[UW-28] Qualification of welding procedure
• Each welding procedure used in joining pressure parts to pressure parts or joining pressure parts to load
carrying non-pressure parts, shall be recorded in detail by the manufacturer and qualified in accordance
with ASME IX.
ASME SECTION VIII DIV. 1
29
Ir. Decky Antony Kifta, ST, MM
[UW-29] Tests of welders and welding operators
• The welders and welding operators used in
welding pressure parts and in joining load-
carrying non-pressure parts to pressure parts
shall be qualified in accordance with ASME
IX.
• Each welder and welding operator shall be
assigned an identifying number, letter, or
symbol by the manufacturer which shall be
used to identify the work of that welder or
welding operator.
• The manufacturer shall maintain a record of
the welders and welding operators showing
the date and results of tests and identification
mark assigned to each.
[UW-30] Lowest permissible temperature for
welding
• It is recommended that no welding of any
kind be done when the temperature of the
base metal is lower than -20 °C. At temp.
between 0 °C and -20 °C, the surface of all
areas within 75 mm of the point where a
weld is to be started should be heated to a
temp. at least warm to the hand (about 15
°C) before welding is started.
[UW-31] Cutting, Fitting, and Alignment
• When plates are shaped by oxygen or arc
cutting, the edges to be welded shall uniform
and smooth and shall be free of all loose
scale and slag accumulations before welding.
ASME SECTION VIII DIV. 1
30
Ir. Decky Antony Kifta, ST, MM
[UW-32] Cleaning of Surfaces to be welded
• The surfaces to be welded shall be clean and
free of scale, rust, oil, grease, slag,
detrimental oxides, and other deleterious
foreign material.
[UW-33] Alignment Tolerance
• Alignment of sections at edges to be butt
welded shall be such that maximum offset is
not greater that the applicable amount for
the welded joint category under consideration
(Refer to Table UW-33).
• Any offset within the allowable tolerance
provided in the table above shall be faired
at a three to one taper over the width of the
finished weld, or if necessary, by adding
additional weld metal (buildup) beyond what
would otherwise be the edge of the weld.
Table UW-33
[UW-32] Finished Longitudinal and Circumferential
Joints
• Butt-welded joints shall have complete
penetration and full fusion. As-welded surfaces
are permitted, however, the surface of welds
shall be sufficiently free from coarse ripples,
grooves, overlaps, and abrupt ridges and
valleys to permit proper RT interpretation and
NDT inspections.
ASME SECTION VIII DIV. 1
31
Ir. Decky Antony Kifta, ST, MM
[UW-32] Finished Longitudinal and Circumferential
Joints (Cont’d)
• Butt-welded joints shall have complete
penetration and full fusion. As-welded surfaces
are permitted, however, the surface of welds
shall be sufficiently free from coarse ripples,
grooves, overlaps, and abrupt ridges and
valleys to permit proper RT interpretation and
NDT inspections.
• Reduction in thickness shall not reduce the
material of adjoining surfaces below the design
thickness at any point.
• Reduction in thickness shall not exceed 1mm or
10% of the nominal thickness of the adjoining
surface, whichever is less.
• The thickness of the weld reinforcement on each
face shall not exceed the below table.
[UW-36] Fillet welds
• Fillet weld shall be deposited in such a way
that adequate penetration into the base
metal at the root of the weld is secured.
ASME SECTION VIII DIV. 1
32
Ir. Decky Antony Kifta, ST, MM
[UW-37] Miscellaneous Welding Requirements
• Each welder and welding operator shall stamp
the identifying number, letter, or symbol
assigned by the manufacturer, on or adjacent to
and at intervals of the manufacturer, on or
adjacent to and intervals of not more than 1m
along the welds which he makes in steel plates
6mm and over in thickness and in nonferrous
plates 13mm and over in thickness; or a record
shall be kept by the Manufacturer of welders
and welding operators employed on each joint
which shall be available to the Inspector. For
identifying welds on vessels in wall thickness is
less than 6mm for steel material and less than
13mm for nonferrous material, suitable stencil
or other surface markings shall be used; or a
record shall be kept by the Manufacturer of
welders and welding operators employed on
each joint which shall be available to the
Inspector.
[UW-37] Miscellaneous Welding Requirements
• The Manufacturer’s Quality Control System (QC
Manual) includes a procedure that will identify
the welders or welding operators that made
such welds on each vessel so that the Inspector
can verify that the welders or welding
operators were all properly qualified.
• Permanent identification of welders or welding
operators making tack welds that become part
of the final pressure weld is not required
provided the manufacturer’s Quality Control
System includes a procedure to permit the
Inspector to verify that such tack welds were
made by qualified welders or welding
operators.
ASME SECTION VIII DIV. 1
33
Ir. Decky Antony Kifta, ST, MM
[UW-38] Repair of Weld Defects
• Defects, such as cracks, pinholes, and incomplete
fusion, detected visually or by the hydrostatic or
pneumatic test or by the examination
prescribed in UW-11 shall be removed by
mechanical means or by thermal gouging
processes, after which the joint shall be
rewelded. Re-welded may use groove
WPS/PQR [ASME IX – QW-202.3]
[UW-39] Peening
• Weld metal and heat affected zones may be
peened by manual, electric, or pneumatic means
when it is deemed necessary or helpful to
control distortion, to relieve residual stresses, or
to improve the quality of the weld.
• Peening is not performed in lieu of any PWHT
required by this Code.
[UW-40] Procedures for PWHT
• Heating the vessel in an enclosed furnace
• Heating the vessel in more than one heat in a
furnace, provided the overlap of the heated
sections of the vessel is at least 5 feet (1.5 M).
• Partial PWHT
• Internal firing
• Localized heating
• PWHT shall be done before hydrostatic test
and after any welded repairs.
[UW-41] Sectioning of welded joints
• Welded joint may be examined by sectioning
when agreed by user and manufacturer.
ASME SECTION VIII DIV. 1
34
Ir. Decky Antony Kifta, ST, MM
[UW-42] Weld Metal Buildup
• Weld metal buildup is permitted to be
performed on the construction base metal and
weld to restore the thickness of base metal for
strength consideration or to modify the
configuration of weld such as taper transition,
etc. provided that a groove welding procedure
qualification is available and covering the
thickness of weld metal deposited.
• All weld metal surfaces shall be buildup shall
be examined by MT or PT. When the buildup
incorporated into the weld joint requires RT (full
or spot), the weld metal buildup can be
included. Weld metal buildup welding shall may
use groove WPS/PQR [ASME IX – QW-202.3]
Inspection and Tests
[UW-47] Check of Welding Procedure
• The Inspector shall ensure that the Welding
Procedure employed in the construction has
been qualified to ASME IX.
[UW-48] Check of Welder and Welding Operator
Qualification
• The Manufacturer shall certify that all the
welders and welding operators employed in
construction are qualified for ASME IX.
• The Inspector shall have access to check the
welder’s or welding operator’s records.
[UW-49] Check of PWHT Practice
• The Inspector shall check and verify the PWHT
practice
ASME SECTION VIII DIV. 1
35
Ir. Decky Antony Kifta, ST, MM
[UW-50] NDE on welds of Pneumatically tested
Vessels
• On welded vessels to be pneumatically tested
the MPI or PT to be tested on:
• All welds around the opening
• Fillet welds of pressure parts with throat
thickness of more than 6 mm
• Exemption may be given to vessels with
MAWP not greater than 500 psig.
[UW-51] RT of weld joints
• Examination to be performed as per ASME V,
Article 2.
• Defects revealed by RT exceeding the specified
criteria shall be repaired
• UT may be used as an alternative provided
complying with methods specified in UW-53(b)
[automated or semi-automated UT] and UW-
53(c) [PAUT]
[UW-52] Spot examination of weld joints
• One spot shall be examined on each vessel for
each 50 ft (15 m) increment of weld
• For identical vessels 50 ft (15 m) increment will
be taken across all vessels welds.
• The minimum length of the spot radiography
shall be 6 in. (150 mm)
• The acceptability of welds examined by spot
radiography shall be as per these paragraphs.
• When repair is found on the spot radiography,
two additional spots shall be radiography.
• If either of the two additional spots reveals
repair, the entire increment of weld represented
shall be rejected.
[UW-53] Ultrasonic examination of welded joints
• Ultrasonic examination of welds performed in
lieu of RT [as per UW-51(a)(4)] shall be as per
ASME VIII Div. 2 para 7.5.5 (automatic or semi-
auto UT) or by using of PAUT.
ASME SECTION VIII DIV. 1
36
Ir. Decky Antony Kifta, ST, MM
SUBSECTION C
PART UCS
REQUIREMENTS FOR PRESSURE VESSELS CONSTRUCTED OF CARBON AND LOW
ALLOY STEELS
ASME SECTION VIII DIV. 1
37
Ir. Decky Antony Kifta, ST, MM
Materials
[UCS-5] General
• All carbon and low alloy steel material used for
pressure vessels shall be as per ASME II and
limited to Table UCS-23 except as permitted in
UG-10 &UG-11
[UCS 6 to UCS-12] These paragraphs explain the
materials similar to UCS-5 requirements, therefore,
not discussed.
Design
[UCS-16 to UCS-33] Not discussed
ASME SECTION VIII DIV. 1
38
Ir. Decky Antony Kifta, ST, MM
[UCS-56] Requirements for PWHT
• The temperature of the furnace shall not exceed
425 °C when the vessel is placed in the furnace
• Above 425 °C, the heating rate shall be not more
than 222 °C/hr divided by PV max. thickness.
During the heating, the temp variation shall be
max. 140 °C within any 4.6 m.
• Holding temp. shall be as per Table UCS-56-1
and the temp. variation during the holding temp.
shall be within 83 °C.
• Above 425 °C, the cooling rate shall be not more
than 280 °C/hr divided by PV max. thickness.
During the cooling, the temp variation shall be
max. 140 °C within any 4.6 m.
• Repair, after PWHT can be performed without
subsequent re-PWHT, provided the vessel is
made from P No. 1 Group 1, 2, and 3 materials
and total repair depth shall not exceed 1-1/2 in
thickness.
ASME SECTION VIII DIV. 1
39
Ir. Decky Antony Kifta, ST, MM
Furnace PWHT
PWHT Internal Firing
Localized Heating Band
PWHT
ASME SECTION VIII DIV. 1
40
Ir. Decky Antony Kifta, ST, MM
Table UCS-56.1 Alternative Heat Treatment
Requirements for Carbon and Low Alloy Steels.
The holding temperature may be decreased,
however, the holding time will become longer.
[UCS-57] Radiography examination
• In addition to the requirement of UW-11, a
complete radiography examination is required
for PV with thickness: see below Table UCS-57
ASME SECTION VIII DIV. 1
41
Ir. Decky Antony Kifta, ST, MM
Low-Temperature Operation
[UCS-66 to UCS-68] Impact test Exemption
• Impact exemption based on UG-20(f)
• Impact exemption based on Fig. UCS-66 and
Table UCS-66.
• Reduction temp based on the coincident ratio
when the ratio < 1, a reduction to exemption may
be given as per Fig. UCS-66.1. Deduct the MDMT
from Table UCS to find the new MDMT exempted
from the impact test.
• [UCS-68(c)] allows reduction temp. by 17 °C
when the material is to be stress relieved (without
Code requirements)
Low-Temperature Operation – for example
[UCS-66 to UCS-68] Impact test Exemption
• Material of SA 516-70 Normalized with thickness 32
mm, coincident ratio 0.64, and the vessel will be
PWHT as per Client request, what will be the MDMT?
• As per Fig.UCS-66 material SA 516-70 belongs
to Curve D
• Based on Table UCS-66 Curve D with a thickness
of 32 mm showing MDMT of -30 °C
• As per Fig. UCS-66.1 with the coincident ratio of
0.64 will give a reduction of 20 °C, this will give
new MDMT of -30 – 20 °C becomes -50 °
• The vessel will be heat treated and when
performed the final MDMT will be -50 -17 °C =
-67 °C [Refer to UCS 68(c)].
Ir. Decky Antony Kifta, ST, MM 42
Figure UCS-66M
Ir. Decky Antony Kifta, ST, MM 43
Table UCS-66 Figure UCS-66.1M
-30 °C
Reduction 20 °C
ASME SECTION VIII DIV. 1
44
Ir. Decky Antony Kifta, ST, MM
Fabrication
[UCS-75 to UCS-79]
• Carbon & low alloy steel plates shall not be
formed cold by blows, however, may be formed
by blows at a forging temperature.
• P No. 1 Gr No. 1 & 2 materials heat treatment is
required when extreme fiber elongation of
forming exceeds 40% or if the extreme fiber
elongation exceeds 5% and any of the following
conditions exist:
• The vessel will contain lethal substances
• Material requires impact test
• Nominal thickness before cold forming
exceeds 16 mm.
• The thickness reduction by cold forming is
more than 10% at any location where the
extreme fiber elongation exceeds 5%.
[UCS-85]
• The material used in the vessel shall be
represented by test specimens that have been
subjected to the same heat treatments exceeding
900 °F (480 °C), except as exempted below:
• The materials belong to P No. 1 Gr. 1 & 2 and
all carbon and low alloy steels used in the
annealed condition as permitted by the material
specification are exempt from the above testing
requirement provided that heat treatments are
limited to PWHT at below lower transformation
temp. of the steel, except for SA-841.
ASME SECTION VIII DIV. 1
45
Ir. Decky Antony Kifta, ST, MM
MANDATORY APPENDIX 47
ASME SECTION VIII DIV. 1
46
Ir. Decky Antony Kifta, ST, MM
Mandatory Appendix 47
• Certifying Engineer
• As RPE registered in USA or Canada, or
• Authorized member of the International
Professional Engineers Agreement (IPEA), or
• Authorized member of Asia Pacific Economic
Operation (APEC), or
• Authorized member of the European
Federation of National Engineering
Association (FEANI)
• Shall have 4 years or more experience in PV
design.
• Engineer
• Shall have a degree from an accredited
university or college in engineering, science,
or technology with 4 years of full-time study,
and having 4 years of experience in PV
design.
Mandatory Appendix 47 (cont’d)
• Designer
• Shall have completed an accredited
engineering technician or associate degree,
requiring 2 years of study, plus have a
minimum of 6 years of experience in the PV
design, or
• Shall have a minimum of 10 years of
experience in PV design.
ASME SECTION VIII DIV. 1
47
Ir. Decky Antony Kifta, ST, MM
THANK YOU

More Related Content

What's hot

Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
AshifuddinAli
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wireImran Jamil
 
How to review wps part 1 (mau company)
How to review wps part 1 (mau company)How to review wps part 1 (mau company)
How to review wps part 1 (mau company)
Mohamed Farouk
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
vaasuBandaru
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
Mohamed Farouk
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1
MOHAMMAD ATIF ALI
 
ASME SEC IX PPT.pdf
ASME SEC IX PPT.pdfASME SEC IX PPT.pdf
ASME SEC IX PPT.pdf
PKNanavati
 
Asme sec ix
Asme sec ixAsme sec ix
Saes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) pipingSaes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) piping
abhi10apr
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
University of Sarajevo, Manufacturing Technology:
 
Pressure vessel course by Hossein Sadeghi
Pressure vessel course by Hossein SadeghiPressure vessel course by Hossein Sadeghi
Pressure vessel course by Hossein Sadeghi
Hossein Sadeghi
 
Asmesectionix
Asmesectionix Asmesectionix
Asmesectionix
Nuri Cesur
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
Saqib Rasool
 
NACE introduction and related terms
NACE introduction and related termsNACE introduction and related terms
NACE introduction and related terms
Hsu Pouway
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
Jithu John
 

What's hot (20)

Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
 
How to review wps part 1 (mau company)
How to review wps part 1 (mau company)How to review wps part 1 (mau company)
How to review wps part 1 (mau company)
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
 
CSWIP Intro
CSWIP IntroCSWIP Intro
CSWIP Intro
 
Welder qualification
Welder qualificationWelder qualification
Welder qualification
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1
 
Aws d1.1 guides
Aws d1.1 guidesAws d1.1 guides
Aws d1.1 guides
 
ASME SEC IX PPT.pdf
ASME SEC IX PPT.pdfASME SEC IX PPT.pdf
ASME SEC IX PPT.pdf
 
Asme sec ix
Asme sec ixAsme sec ix
Asme sec ix
 
Saes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) pipingSaes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) piping
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
 
API_510_for_Exam.pdf
API_510_for_Exam.pdfAPI_510_for_Exam.pdf
API_510_for_Exam.pdf
 
Pressure vessel course by Hossein Sadeghi
Pressure vessel course by Hossein SadeghiPressure vessel course by Hossein Sadeghi
Pressure vessel course by Hossein Sadeghi
 
Asmesectionix
Asmesectionix Asmesectionix
Asmesectionix
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
 
Presentation on SECVIII
Presentation on SECVIIIPresentation on SECVIII
Presentation on SECVIII
 
NACE introduction and related terms
NACE introduction and related termsNACE introduction and related terms
NACE introduction and related terms
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
 

Similar to Introduction to ASME VIII Div 1 (ATS).pdf

ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
Sam Jose
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
Praj Industries Ltd.
 
Pontofocal-textos-regulamentos-chn 785-suppl_1
 Pontofocal-textos-regulamentos-chn 785-suppl_1 Pontofocal-textos-regulamentos-chn 785-suppl_1
Pontofocal-textos-regulamentos-chn 785-suppl_1
André Paredes
 
asmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdfasmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdf
NithinGanesh3
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Versli Lietuva (Enterprise Lithuania)
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Denis Senin
 
181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-email181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-email
daniel sandoval
 
What does cold stretching mean
What does cold stretching meanWhat does cold stretching mean
What does cold stretching mean
Jiun Fa ,Lai
 
S2011-6.pdf
S2011-6.pdfS2011-6.pdf
S2011-6.pdf
CalibioNhavene1
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Gaurav Singh Rajput
 
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdfINSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
Teddy Setiady
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Telescopic poles nea
Telescopic poles  neaTelescopic poles  nea
Telescopic poles nea
kapil pudasaini
 
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET Journal
 
02 custodie eng
02 custodie eng02 custodie eng
02 custodie engHai Pham
 
Civil engineer reference documents extended
Civil engineer reference documents   extended Civil engineer reference documents   extended
Civil engineer reference documents extended
NimeshPoddar
 
Inspection Resume, Robert Jones, 15 May 15
Inspection Resume, Robert Jones, 15 May 15Inspection Resume, Robert Jones, 15 May 15
Inspection Resume, Robert Jones, 15 May 15Robert Jones
 

Similar to Introduction to ASME VIII Div 1 (ATS).pdf (20)

ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
 
Pontofocal-textos-regulamentos-chn 785-suppl_1
 Pontofocal-textos-regulamentos-chn 785-suppl_1 Pontofocal-textos-regulamentos-chn 785-suppl_1
Pontofocal-textos-regulamentos-chn 785-suppl_1
 
asmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdfasmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdf
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
 
181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-email181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-email
 
AGP-13-R
AGP-13-RAGP-13-R
AGP-13-R
 
What does cold stretching mean
What does cold stretching meanWhat does cold stretching mean
What does cold stretching mean
 
S2011-6.pdf
S2011-6.pdfS2011-6.pdf
S2011-6.pdf
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdfINSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Telescopic poles nea
Telescopic poles  neaTelescopic poles  nea
Telescopic poles nea
 
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
 
Ged 2318
Ged 2318Ged 2318
Ged 2318
 
02 custodie eng
02 custodie eng02 custodie eng
02 custodie eng
 
Civil engineer reference documents extended
Civil engineer reference documents   extended Civil engineer reference documents   extended
Civil engineer reference documents extended
 
Inspection Resume, Robert Jones, 15 May 15
Inspection Resume, Robert Jones, 15 May 15Inspection Resume, Robert Jones, 15 May 15
Inspection Resume, Robert Jones, 15 May 15
 

Recently uploaded

Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 

Recently uploaded (20)

Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 

Introduction to ASME VIII Div 1 (ATS).pdf

  • 1. INTRODUCTION TO ASME VIII DIV 1 FABRICATION & INSPECTION (U, UG, UW & UCS) Batam, 04 July 2023 1 (Ir. Decky Antony Kifta, ST, MM)
  • 2. ASME SECTION VIII RULES FOR CONSTRUCTION OF PRESSURE VESSELS • ASME VIII Div. 1 is for Pressure Vessels with pressure above 15 psig to 3,000 psig (20 MPa) • ASME VIII Div. 2 is for Pressure Vessels with pressure above 15 psig to 10,000 psig (70 MPa) • ASME VIII Div. 3 is for Pressure Vessels with pressure above 10,000 psig (70 MPa) • ASME VIII Div. 1 regulates stamps: U, UM, and PRT VIII-1. • ASME VIII Div. 2 regulates stamps: U2 and PRT VIII-2 • ASME VIII Div. 3 regulates stamps: U3 • Requirements of Certification Markings of UV, UD, UV3 & UD3 were transferred to ASME XIII • ASME VIII is issued every 2 years, the latest one was issued on 1st July 2023 and next issuance will be on 1st July 2025. The Edition will be effective 6 months after issuance. • Contract signed prior to the effective date may use the older edition. • Revision is indicated by (Year) or (23) at the page margin. Common PV standards other than ASME VIII • PD 5500 • EN 13445 • AS 1210 2 Ir. Decky Antony Kifta, ST, MM
  • 3. ASME SECTION VIII DIV. 1 3 Ir. Decky Antony Kifta, ST, MM Certification Marks/ Stamps covered in this Division (based on Year 2023 Edition)
  • 4. ASME VIII Div. 1 is divided into 3 subsections: • Subsection A: General Requirements • Part UG : General Requirements for all methods of constructions and materials • Subsection B: Requirements Pertaining to Methods of Fabrication PV • Part UW : Welding • Part UF : Forging • Part UB : Brazing • Subsection C: Requirements Pertaining to Classes of Materials • Part UCS : Carbon & Low Alloy Steels • Part UNF : Non-Ferrous Materials • Part UHA : High Alloy Steels • Part UCI : Cast Iron • Part UCL : Cladding, Overlay Cladding & Linings • Part UCD : Cast Ductile Iron • Part UHT : Heat Treated enhanced Tensile Ferritic Steels • Part ULW : Layered Construction • Part ULT : Low Temperature • Part UHX : Shell & Tube Heat Exchanger • Part UIG : Impregnated Graphite ASME SECTION VIII DIV. 1 4 Ir. Decky Antony Kifta, ST, MM
  • 5. [U-1] Vessels/pressure parts excluded from the scope are: • Piping components (pipe, flange, fittings, valves, etc.) • Vessels having an internal or external pressure not exceeding 15 psig. • Vessels having inside diameter, width, height or cross-sectional diagram not exceeding 6-in. • Pressure vessels for human occupancy. • Vessels having design pressure exceeding 3,000 psig. [U-1(j) The requirements of UM pressure vessels. ASME SECTION VIII DIV. 1 [U-2] User’s Design form and involvement of RPE is required when below conditions are design requirements: • Superimposed static reactions • Cyclic or dynamic reactions • Loadings due to wind, snow or seismic reactions • Impact reactions • Temperature effects • Abnormal pressures [U-4] Units of Measurements • U.S. Customary, SI, or any local customary units may be used to demonstrate compliance with requirements of this edition related to materials, fabrication, and overpressure protection, however, only one or single system of units shall be used for all aspects of design except otherwise permitted by this Division. 5 Ir. Decky Antony Kifta, ST, MM
  • 6. SUBSECTION A PART UG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION AND ALL MATERIALS 6 Ir. Decky Antony Kifta, ST, MM
  • 7. ASME SECTION VIII DIV. 1 [UG-4] General: • Materials used shall conform with ASME Sect II Part D • ASTM materials may be used provided conforming to ASME Sect II Part A, Table II-200-1, i.e. within the year specified in the table. This is also applicable for SB materials. [UG-10] • Material identified with a specification not permitted by this division and identified to a single production lot as permitted by a permitted specification may be accepted provided documentation is provided to the pressure manufacturer that all applicable chemical and mechanical properties meeting the permitted specification. When no documentation is available the PV manufacturer can perform chemical analysis and mechanical test and the results are compared with a permitted specification. [UG-5] Plate, [UG-6] Forgings, [UG-7] Castings, [UG- 8] Pipe and Tubes, and [UG-9] welding materials 7 Ir. Decky Antony Kifta, ST, MM [UG-10] Cont’d. • Pressure vessels manufacturer may re-certify and mark the materials to the permitted specification. • Material without identification shall not be used.
  • 8. ASME SECTION VIII DIV. 1 [UG-11] Prefabricated and preformed items may be produced by other than PV manufacturer without a certification mark as long as no permanent welding involved. Permanent welding including weld overlay, except for welded shell, heads or QOC, may be subcontracted to non- ASME stamped shop provided the requirements specified in this section are satisfied (UG-11(e). [UG-12] Bolts & Studs, [UG-13] Nuts & Washers, [UG-14] Rods & Bars, [UG-15] Product Specification [UG-16 to UG-34] Design Issues (not discussed) except UG- 20(f) below 8 Ir. Decky Antony Kifta, ST, MM [UG-20(f)] Impact test exemption for P-1 materials • Impact test per UG-84 is not mandatory for PV materials satisfying the bellow: • The material shall be limited to P-1 gr. 1 & 2 and thickness shall not exceed: • 13 mm materials for curve A • 25 mm materials for curve B • The PV shall be hydro-tested & designed temp. Shall be from -29 to 345 °C. [UG-35] Other Type of Closures • Dished Covers (Dished head with bolting flanges) • Quick Actuating Closures • Quick Opening Closures (QOC) [UG-36 to UG-53] Design Issues (not discussed)
  • 9. ASME SECTION VIII DIV. 1 [UG-54] Supports: All vessels shall be supported, and the supporting members shall be attached to withhold maximum imposed loadings. [UG-55] Lugs for platforms, ladders, and other attachments to vessel walls Lugs or clips may be welded, brazed, or bolted to the outside or inside of the vessel support ladders, platforms, etc. [UG-76] Cutting plates and other stock Plates, edges of heads, and other parts may be cut to shape and size by mechanical means such as machining, shearing, grinding or by oxygen or arc cutting. After oxygen or arc cutting all slags and detrimental discoloration shall be removed by mechanical means. [UG-77] Material identification The manufacturer shall maintain traceability of the materials to the original identification markings by either or combination of: [1] accurate transfer of identification (heat no.), [2] use of coded marking (unique no.) traceable to the original marking, [3] recording the material identification on the tabulation (traceability sheet) or as built drawings which ensure that identification of each material during fabrication to vessel completion. 9 Ir. Decky Antony Kifta, ST, MM
  • 10. ASME SECTION VIII DIV. 1 [UG-78] Repair of Defects in Materials Defects in material may be repaired provided accepted by AI (Authorized Inspector) [UG-79] Forming Pressure Parts Shells or heads may be rolled or formed provided extreme fiber elongation (forming strains) are observed and when required subsequent heat treatment shall be performed. [UG-80] Permissible Out-of-Roundness of Cylindrical, Conical and Spherical Shells The difference between the maximum and minimum inside diameters at any cross section shall not exceed 1% of the nominal diameter at the cross section under consideration. 10 Ir. Decky Antony Kifta, ST, MM
  • 11. ASME SECTION VIII DIV. 1 [UG-81] Tolerance for Formed Heads The inner surface of head shall not deviate outside of the specified shape by more than 1-1/4% of D nor inside of the specified the specified shape by more than 5/8% of D, where D is the nominal inside diameter of the vessel shell at point of attachment. [UG-82] Lugs & Fitting Attachments [UG-84] Charpy Impact Test • Test procedure to follow: ASME SA-370 or ISO 148 • Test specimen shall be as per Fig. UG-84 & Fig. UG-84.5 • Acceptance criteria shall be as per Fig. UG-84.1 • When impact test on production required one test plate shall be made for each welding procedure used for Category A and B, however, when manufacturer uses same welding procedure for both categories, only Category A can represent the test plate. [UG-84(i)(1) – (3)]. • For production weld impact test, the test to be performed on weld metal and heat affected zone. [UG-85] Heat Treatment Heat treatment of plate may be performed by PV manufacturer 11 Ir. Decky Antony Kifta, ST, MM
  • 12. ASME SECTION VIII DIV. 1 [UG-90] Inspection and Tests: Manufacturer’s responsibility (1) Maintain Certificate of Authorization (2) Prepare drawings & design calculations (3) Materials identifications used for Construction (4) Obtain Partial Data Reports (if any) (5) Prepare access for the Inspector (6) Examination of materials, materials identification, and traceability. (7) Document impact tests and other tests (8) Concurrence of the Inspector prior to any base metal repairs. (9) Examination of heads & shells are properly formed. (10) Qualification of welding procedures (11) Qualification of welders & welding operators (12) Examination of all parts prior to joining for welding (13) Examination of parts for material marking, defects, and dimensional geometry. (14) Provisions of controls to ensure that all required heat treatments are performed. (15) Provisions of records of NDT including RT images. (16) Making the required hydrotest or pneumatic test & arranging witness by the Inspector. (17) Applying the required stamping/ nameplate to the vessel (18) Preparing the required Manufacturer’s Data Reports & certifying by Inspector (19) Providing the retention of RT & UT reports Manufacturer’s Data Reports and other records. 12 Ir. Decky Antony Kifta, ST, MM
  • 13. ASME SECTION VIII DIV. 1 [UG-93] Inspection of Materials • Plates shall require materials test reports • All other product forms can be accepted when the product has the correct marking of specification including grade, type and class of the materials. [UG-92] Inspection of Materials • Manufacturer shall arrange free access to AI for performing inspection on PV. [UG-91] The Inspector • Individual employed by ASME Accredited Authorized Inspection Agency (AIA) as per ASME QAI-1. [UG-94] Marking on Materials • If the material identifying marks are obliterated or material is divided into two or more parts, the marks shall be properly transferred by the Manufacturer. [UG-95] Examination of surfaces during fabrication, [UG-96] Dimensional check of component parts & [UG- 97] Inspection During Fabrication. 13 Ir. Decky Antony Kifta, ST, MM
  • 14. ASME SECTION VIII DIV. 1 [UG-98] Maximum Allowable working pressure • MAWP is the maximum pressure permissible at the top of the vessel in its normal operating position at the designated coincident temperature specified for that pressure. [UG-99] Standard Hydrostatic Test • Vessels designed for internal pressure shall be subjected to a hydrostatic test pressure that at every point in the vessel is at least equal to 1.3 x MAWP multiplied by LSR (Lowest Stress Ratio) for the pressure boundary materials of which the vessel is constructed. • The vessel shall not be hydrotested with paint or internal lining unless approved by user or his designated agent. • The minimum temperature during hydrotest shall be 17 °C warmer than MDMT and maximum test temperature is 48 °C. • Vessel with Lethal service shall not be painted or internally lined prior to hydrotest. 14 Ir. Decky Antony Kifta, ST, MM
  • 15. Ir. Decky Antony Kifta, ST, MM 15 [UG-100] Pneumatic Test • Vessels shall be pneumatic tested that at every point in the vessel is at least equal to 1.1 x MAWP multiplied by LSR (Lowest Stress Ratio) for the pressure boundary materials of which the vessel is constructed. • The vessel shall not be pneumatic tested with paint or internal lining unless approved by user or his designated agent. • The minimum temperature during hydrotest shall be 17 °C warmer than MDMT and maximum test temperature is 48 °C. • Vessel with Lethal service shall not be painted or internally lined prior to pneumatic testing.
  • 16. ASME SECTION VIII DIV. 1 16 Ir. Decky Antony Kifta, ST, MM Hydrotest Operation
  • 17. ASME SECTION VIII DIV. 1 [UG-101] Proof Tests to establish MAWP • Where design rule do not exist in this Division therefore this proof test method to be performed [U-2 (g)(1)] [UG-102] Test Gages • Dial indicating pressure gage used in testing shall be graduated over a range of about doble the intended maximum test pressure, but in no case shall the range be less than 1-1/2 nor 4 times that pressure. Digital reading pressure gages having wider range of pressure may be used, provided the readings give the same or greater degree of accuracy as obtained with dial pressure gage. [UG-103] NDT • MPI shall be performed as per Mandatory Appendix 6 and PT shall be as per Mandatory Appendix 8. [UG-115] Marking and Reports • The unit of measurement used in Manufacturer’s Data Reports (U Stamp), Manufacturer’s Certificates of Compliance (UM Stamp) and capacity certification of pressure relief devices and in marking or stamping pressure vessels, vessel parts and pressure relief devices, required by this Division, shall be either US Customary Units or any local customary units and a single system of units shall be used for all aspects of design [U-4(b)] 17 Ir. Decky Antony Kifta, ST, MM
  • 18. ASME SECTION VIII DIV. 1 [UG-116] Required Marking • Each PV shall be marked with the following [UG-116] Required Marking • When RT or UT examination has been performed • RT-1 when all pertaining butt welds other than Category B and C butt welds associated with nozzles and communicating chambers that neither exceeds NPS 10 nor 1-1/8 in. wall thickness satisfy the full RT requirements for their full length [UW-11(a)] 18 Ir. Decky Antony Kifta, ST, MM
  • 19. ASME SECTION VIII DIV. 1 [UG-116] Required Marking (Cont’d) • RT-2 when the complete vessel satisfies the requirement UW-11(a)(5) (full RT on LS) and when the spot radiography requirements of UW-11(a)(5)(-b) (spot RT on circ seam which intersect with LS) have been applied. • RT-3 when the complete PV satisfies the spot RT as per UW-11b. • RT-4 when only part of the complete PV has satisfied the RT [UW-11(a)] or where none of the markings RT-1, RT-2 or RT-3 are applicable. [UG-116] Required Marking (Cont’d) • Parts of vessels for Which partial Data Reports are required in UG-120 (c) shall be marked by the manufacturer of the part, with a nameplate or stamping, with the following: • The U Designator shall stamp the word ‘PART’ below the Certification Mark. • The PRT Designator shall stamp the name of the manufacturer after/below the words ‘certified by’ and the manufacturer’s serial number. The word PART may not be stamped. 19 Ir. Decky Antony Kifta, ST, MM
  • 20. ASME SECTION VIII DIV. 1 [UG-117] Certificates of Authorization and Certification Marks • UM Certification Mark is granted by the Society and is used by the manufacturer • UM Designator shall employ a Certified Individual qualified to ASME CA-1 and meeting the requirements of ASME QAI-1 • Certified Individual shall certify Form U-3, U- 3A or U-3P (Manufacturer’s Certificate of Compliances) • UM Designator shall already have S or U certificate. • UM certification is valid for 1 year but the 1st and 2nd reviews can be done by AI and AI Supervisor. The third review or joint review will be performed after 3 years • Any Manufacturer holding U, UM & PRT VIII-1 Certification marks shall have QC System (Manual) as per Appendix 10 & ASME CA-1. [UG-118 & 119] Methods of Stamping & Nameplate • The required marking shall be applied by one of the following methods: • Nameplate • Stamped directly on the vessel • Electrochemically etched 20 Ir. Decky Antony Kifta, ST, MM
  • 21. ASME SECTION VIII DIV. 1 21 Ir. Decky Antony Kifta, ST, MM U stamp Nameplates (Samples)
  • 22. ASME SECTION VIII DIV. 1 22 Ir. Decky Antony Kifta, ST, MM [UG-120] Date Reports • Manufacturer’s Data reports to be filled by U Designator are: • Form U-1, U-1A or U-1P (Plate Heat Exchanger) and U-4 (attachment) when required. • Form U-5 for Fixed Tube Sheet Heat Exchanger • Manufacturer’s Certificate of Compliance to be issued by UM Designator are: • Form U-3, U-3A or U-3P • Parts manufacturer shall fill in Form U-2 or U- 2A. [UG-120] Date Reports (Cont’d) • U Designator shall maintain the Manufacturer’s Data Reports for at least 3 years • UM Designator shall maintain the Manufacturer’s Certificate of Compliance for at least 5 years. • Vessel (U or UM) to be registered to National Board, the Manufacturer’s Data Reports or Manufacturer’s Certificate of Compliance shall be sent to National Board of Boiler and Pressure Vessel Inspector in Ohio, USA. [UG-150 to 156] regarding the pressure relieve valves or devices (not discussed)
  • 23. SUBSECTION B PART UW REQUIREMENTS PERTAINING METHODS OF FABRICATION OF PRESSURE VESSELS 23 Ir. Decky Antony Kifta, ST, MM
  • 24. ASME SECTION VIII DIV. 1 24 Ir. Decky Antony Kifta, ST, MM [UW-2] Service Restrictions • PV contains lethal substances, all butt welds shall be fully radiography • When fabricated using carbon or low alloy materials, PV shall be PWHT at any wall thickness • The meaning of lethal is liquid or gas that a very small amount mixed or not mixed with air is dangerous to life when inhaled. [UW-3] Welded Joint Category • Cat A = longitudinal welded joint (shell & head) and circ seam shell to heads other than the dished head. • Cat B = circumferential welded joint • Cat C = weld connecting flanges, flat head to main shell. • Cat D = weld connecting nozzles to main shells, to heads
  • 25. ASME SECTION VIII DIV. 1 25 Ir. Decky Antony Kifta, ST, MM [UW-5 & UW-6] Materials and Weld Consumables (not discussed) [UW-8 & UW-9] Design (not discussed) [UW-10] PWHT, refer to UW-40 and UCS-56 (for carbon and low alloy steels) [UW-11] Radiography and Ultrasonic Examination • Full radiography to be performed on: • All butt welds in the shell and heads of vessels to contain lethal substances • All butt welds in the shell and heads of vessels with thickness exceed 1-1/2 in (38 mm) or for carbon and low alloy steels as per Table UCS-57. [UW-12] Joint Efficiencies • Refer to Table UW-12 below PAUT (Phased Array UT)
  • 26. ASME SECTION VIII DIV. 1 26 Ir. Decky Antony Kifta, ST, MM
  • 27. Ir. Decky Antony Kifta, ST, MM 27 [UW-13] Attachment Details not designed [UW-14] Openings in or adjacent to welds • Single opening may be located in head-to-shell or Category B or C butt-welded joints, provided the weld meets the radiographic requirements in UW-51 for a length equal to three times the diameter of the opening with the center of the hole at midlength. Defects that are completely removed in cutting the hole shall not be considered in judging the acceptability of the weld. [UW-15 to UW-20] regarding design (not discussed)
  • 28. ASME SECTION VIII DIV. 1 28 Ir. Decky Antony Kifta, ST, MM [UW-26] Fabrication • Each manufacturer shall be responsible for the quality of the welding done by the organization • All welding shall be performed in accordance with Manufacturer’s WPS in accordance with ASME IX. • All welders shall be qualified by the manufacturer in accordance with ASME IX • The manufacturer shall be responsible for Code compliance of the vessel or part, including Certification Mark Stamping and providing Manufacturer’s Data Report Forms properly and countersigned by the Inspector. [UW-27] Welding Processes • The welding processes that may be used in the construction of vessel are limited to those listed in ASME IX. [UW-28] Qualification of welding procedure • Each welding procedure used in joining pressure parts to pressure parts or joining pressure parts to load carrying non-pressure parts, shall be recorded in detail by the manufacturer and qualified in accordance with ASME IX.
  • 29. ASME SECTION VIII DIV. 1 29 Ir. Decky Antony Kifta, ST, MM [UW-29] Tests of welders and welding operators • The welders and welding operators used in welding pressure parts and in joining load- carrying non-pressure parts to pressure parts shall be qualified in accordance with ASME IX. • Each welder and welding operator shall be assigned an identifying number, letter, or symbol by the manufacturer which shall be used to identify the work of that welder or welding operator. • The manufacturer shall maintain a record of the welders and welding operators showing the date and results of tests and identification mark assigned to each. [UW-30] Lowest permissible temperature for welding • It is recommended that no welding of any kind be done when the temperature of the base metal is lower than -20 °C. At temp. between 0 °C and -20 °C, the surface of all areas within 75 mm of the point where a weld is to be started should be heated to a temp. at least warm to the hand (about 15 °C) before welding is started. [UW-31] Cutting, Fitting, and Alignment • When plates are shaped by oxygen or arc cutting, the edges to be welded shall uniform and smooth and shall be free of all loose scale and slag accumulations before welding.
  • 30. ASME SECTION VIII DIV. 1 30 Ir. Decky Antony Kifta, ST, MM [UW-32] Cleaning of Surfaces to be welded • The surfaces to be welded shall be clean and free of scale, rust, oil, grease, slag, detrimental oxides, and other deleterious foreign material. [UW-33] Alignment Tolerance • Alignment of sections at edges to be butt welded shall be such that maximum offset is not greater that the applicable amount for the welded joint category under consideration (Refer to Table UW-33). • Any offset within the allowable tolerance provided in the table above shall be faired at a three to one taper over the width of the finished weld, or if necessary, by adding additional weld metal (buildup) beyond what would otherwise be the edge of the weld. Table UW-33 [UW-32] Finished Longitudinal and Circumferential Joints • Butt-welded joints shall have complete penetration and full fusion. As-welded surfaces are permitted, however, the surface of welds shall be sufficiently free from coarse ripples, grooves, overlaps, and abrupt ridges and valleys to permit proper RT interpretation and NDT inspections.
  • 31. ASME SECTION VIII DIV. 1 31 Ir. Decky Antony Kifta, ST, MM [UW-32] Finished Longitudinal and Circumferential Joints (Cont’d) • Butt-welded joints shall have complete penetration and full fusion. As-welded surfaces are permitted, however, the surface of welds shall be sufficiently free from coarse ripples, grooves, overlaps, and abrupt ridges and valleys to permit proper RT interpretation and NDT inspections. • Reduction in thickness shall not reduce the material of adjoining surfaces below the design thickness at any point. • Reduction in thickness shall not exceed 1mm or 10% of the nominal thickness of the adjoining surface, whichever is less. • The thickness of the weld reinforcement on each face shall not exceed the below table. [UW-36] Fillet welds • Fillet weld shall be deposited in such a way that adequate penetration into the base metal at the root of the weld is secured.
  • 32. ASME SECTION VIII DIV. 1 32 Ir. Decky Antony Kifta, ST, MM [UW-37] Miscellaneous Welding Requirements • Each welder and welding operator shall stamp the identifying number, letter, or symbol assigned by the manufacturer, on or adjacent to and at intervals of the manufacturer, on or adjacent to and intervals of not more than 1m along the welds which he makes in steel plates 6mm and over in thickness and in nonferrous plates 13mm and over in thickness; or a record shall be kept by the Manufacturer of welders and welding operators employed on each joint which shall be available to the Inspector. For identifying welds on vessels in wall thickness is less than 6mm for steel material and less than 13mm for nonferrous material, suitable stencil or other surface markings shall be used; or a record shall be kept by the Manufacturer of welders and welding operators employed on each joint which shall be available to the Inspector. [UW-37] Miscellaneous Welding Requirements • The Manufacturer’s Quality Control System (QC Manual) includes a procedure that will identify the welders or welding operators that made such welds on each vessel so that the Inspector can verify that the welders or welding operators were all properly qualified. • Permanent identification of welders or welding operators making tack welds that become part of the final pressure weld is not required provided the manufacturer’s Quality Control System includes a procedure to permit the Inspector to verify that such tack welds were made by qualified welders or welding operators.
  • 33. ASME SECTION VIII DIV. 1 33 Ir. Decky Antony Kifta, ST, MM [UW-38] Repair of Weld Defects • Defects, such as cracks, pinholes, and incomplete fusion, detected visually or by the hydrostatic or pneumatic test or by the examination prescribed in UW-11 shall be removed by mechanical means or by thermal gouging processes, after which the joint shall be rewelded. Re-welded may use groove WPS/PQR [ASME IX – QW-202.3] [UW-39] Peening • Weld metal and heat affected zones may be peened by manual, electric, or pneumatic means when it is deemed necessary or helpful to control distortion, to relieve residual stresses, or to improve the quality of the weld. • Peening is not performed in lieu of any PWHT required by this Code. [UW-40] Procedures for PWHT • Heating the vessel in an enclosed furnace • Heating the vessel in more than one heat in a furnace, provided the overlap of the heated sections of the vessel is at least 5 feet (1.5 M). • Partial PWHT • Internal firing • Localized heating • PWHT shall be done before hydrostatic test and after any welded repairs. [UW-41] Sectioning of welded joints • Welded joint may be examined by sectioning when agreed by user and manufacturer.
  • 34. ASME SECTION VIII DIV. 1 34 Ir. Decky Antony Kifta, ST, MM [UW-42] Weld Metal Buildup • Weld metal buildup is permitted to be performed on the construction base metal and weld to restore the thickness of base metal for strength consideration or to modify the configuration of weld such as taper transition, etc. provided that a groove welding procedure qualification is available and covering the thickness of weld metal deposited. • All weld metal surfaces shall be buildup shall be examined by MT or PT. When the buildup incorporated into the weld joint requires RT (full or spot), the weld metal buildup can be included. Weld metal buildup welding shall may use groove WPS/PQR [ASME IX – QW-202.3] Inspection and Tests [UW-47] Check of Welding Procedure • The Inspector shall ensure that the Welding Procedure employed in the construction has been qualified to ASME IX. [UW-48] Check of Welder and Welding Operator Qualification • The Manufacturer shall certify that all the welders and welding operators employed in construction are qualified for ASME IX. • The Inspector shall have access to check the welder’s or welding operator’s records. [UW-49] Check of PWHT Practice • The Inspector shall check and verify the PWHT practice
  • 35. ASME SECTION VIII DIV. 1 35 Ir. Decky Antony Kifta, ST, MM [UW-50] NDE on welds of Pneumatically tested Vessels • On welded vessels to be pneumatically tested the MPI or PT to be tested on: • All welds around the opening • Fillet welds of pressure parts with throat thickness of more than 6 mm • Exemption may be given to vessels with MAWP not greater than 500 psig. [UW-51] RT of weld joints • Examination to be performed as per ASME V, Article 2. • Defects revealed by RT exceeding the specified criteria shall be repaired • UT may be used as an alternative provided complying with methods specified in UW-53(b) [automated or semi-automated UT] and UW- 53(c) [PAUT] [UW-52] Spot examination of weld joints • One spot shall be examined on each vessel for each 50 ft (15 m) increment of weld • For identical vessels 50 ft (15 m) increment will be taken across all vessels welds. • The minimum length of the spot radiography shall be 6 in. (150 mm) • The acceptability of welds examined by spot radiography shall be as per these paragraphs. • When repair is found on the spot radiography, two additional spots shall be radiography. • If either of the two additional spots reveals repair, the entire increment of weld represented shall be rejected. [UW-53] Ultrasonic examination of welded joints • Ultrasonic examination of welds performed in lieu of RT [as per UW-51(a)(4)] shall be as per ASME VIII Div. 2 para 7.5.5 (automatic or semi- auto UT) or by using of PAUT.
  • 36. ASME SECTION VIII DIV. 1 36 Ir. Decky Antony Kifta, ST, MM SUBSECTION C PART UCS REQUIREMENTS FOR PRESSURE VESSELS CONSTRUCTED OF CARBON AND LOW ALLOY STEELS
  • 37. ASME SECTION VIII DIV. 1 37 Ir. Decky Antony Kifta, ST, MM Materials [UCS-5] General • All carbon and low alloy steel material used for pressure vessels shall be as per ASME II and limited to Table UCS-23 except as permitted in UG-10 &UG-11 [UCS 6 to UCS-12] These paragraphs explain the materials similar to UCS-5 requirements, therefore, not discussed. Design [UCS-16 to UCS-33] Not discussed
  • 38. ASME SECTION VIII DIV. 1 38 Ir. Decky Antony Kifta, ST, MM [UCS-56] Requirements for PWHT • The temperature of the furnace shall not exceed 425 °C when the vessel is placed in the furnace • Above 425 °C, the heating rate shall be not more than 222 °C/hr divided by PV max. thickness. During the heating, the temp variation shall be max. 140 °C within any 4.6 m. • Holding temp. shall be as per Table UCS-56-1 and the temp. variation during the holding temp. shall be within 83 °C. • Above 425 °C, the cooling rate shall be not more than 280 °C/hr divided by PV max. thickness. During the cooling, the temp variation shall be max. 140 °C within any 4.6 m. • Repair, after PWHT can be performed without subsequent re-PWHT, provided the vessel is made from P No. 1 Group 1, 2, and 3 materials and total repair depth shall not exceed 1-1/2 in thickness.
  • 39. ASME SECTION VIII DIV. 1 39 Ir. Decky Antony Kifta, ST, MM Furnace PWHT PWHT Internal Firing Localized Heating Band PWHT
  • 40. ASME SECTION VIII DIV. 1 40 Ir. Decky Antony Kifta, ST, MM Table UCS-56.1 Alternative Heat Treatment Requirements for Carbon and Low Alloy Steels. The holding temperature may be decreased, however, the holding time will become longer. [UCS-57] Radiography examination • In addition to the requirement of UW-11, a complete radiography examination is required for PV with thickness: see below Table UCS-57
  • 41. ASME SECTION VIII DIV. 1 41 Ir. Decky Antony Kifta, ST, MM Low-Temperature Operation [UCS-66 to UCS-68] Impact test Exemption • Impact exemption based on UG-20(f) • Impact exemption based on Fig. UCS-66 and Table UCS-66. • Reduction temp based on the coincident ratio when the ratio < 1, a reduction to exemption may be given as per Fig. UCS-66.1. Deduct the MDMT from Table UCS to find the new MDMT exempted from the impact test. • [UCS-68(c)] allows reduction temp. by 17 °C when the material is to be stress relieved (without Code requirements) Low-Temperature Operation – for example [UCS-66 to UCS-68] Impact test Exemption • Material of SA 516-70 Normalized with thickness 32 mm, coincident ratio 0.64, and the vessel will be PWHT as per Client request, what will be the MDMT? • As per Fig.UCS-66 material SA 516-70 belongs to Curve D • Based on Table UCS-66 Curve D with a thickness of 32 mm showing MDMT of -30 °C • As per Fig. UCS-66.1 with the coincident ratio of 0.64 will give a reduction of 20 °C, this will give new MDMT of -30 – 20 °C becomes -50 ° • The vessel will be heat treated and when performed the final MDMT will be -50 -17 °C = -67 °C [Refer to UCS 68(c)].
  • 42. Ir. Decky Antony Kifta, ST, MM 42 Figure UCS-66M
  • 43. Ir. Decky Antony Kifta, ST, MM 43 Table UCS-66 Figure UCS-66.1M -30 °C Reduction 20 °C
  • 44. ASME SECTION VIII DIV. 1 44 Ir. Decky Antony Kifta, ST, MM Fabrication [UCS-75 to UCS-79] • Carbon & low alloy steel plates shall not be formed cold by blows, however, may be formed by blows at a forging temperature. • P No. 1 Gr No. 1 & 2 materials heat treatment is required when extreme fiber elongation of forming exceeds 40% or if the extreme fiber elongation exceeds 5% and any of the following conditions exist: • The vessel will contain lethal substances • Material requires impact test • Nominal thickness before cold forming exceeds 16 mm. • The thickness reduction by cold forming is more than 10% at any location where the extreme fiber elongation exceeds 5%. [UCS-85] • The material used in the vessel shall be represented by test specimens that have been subjected to the same heat treatments exceeding 900 °F (480 °C), except as exempted below: • The materials belong to P No. 1 Gr. 1 & 2 and all carbon and low alloy steels used in the annealed condition as permitted by the material specification are exempt from the above testing requirement provided that heat treatments are limited to PWHT at below lower transformation temp. of the steel, except for SA-841.
  • 45. ASME SECTION VIII DIV. 1 45 Ir. Decky Antony Kifta, ST, MM MANDATORY APPENDIX 47
  • 46. ASME SECTION VIII DIV. 1 46 Ir. Decky Antony Kifta, ST, MM Mandatory Appendix 47 • Certifying Engineer • As RPE registered in USA or Canada, or • Authorized member of the International Professional Engineers Agreement (IPEA), or • Authorized member of Asia Pacific Economic Operation (APEC), or • Authorized member of the European Federation of National Engineering Association (FEANI) • Shall have 4 years or more experience in PV design. • Engineer • Shall have a degree from an accredited university or college in engineering, science, or technology with 4 years of full-time study, and having 4 years of experience in PV design. Mandatory Appendix 47 (cont’d) • Designer • Shall have completed an accredited engineering technician or associate degree, requiring 2 years of study, plus have a minimum of 6 years of experience in the PV design, or • Shall have a minimum of 10 years of experience in PV design.
  • 47. ASME SECTION VIII DIV. 1 47 Ir. Decky Antony Kifta, ST, MM THANK YOU