This document specifies requirements for telescopic tubular steel poles used to support overhead electric lines. It provides details on:
1. Pole materials, manufacture, corrosion protection, and testing requirements to ensure poles can withstand specified design loads.
2. Pole sections must be designed to fit together frictionally without bolts. Welds must withstand pole loads.
3. Poles must be hot dip galvanized and painted, and undergo permanent set testing where load is incrementally applied until failure to ensure strength and durability standards are met.
Learn how we design these components for high temperature, high pressure, and/or corrosive environments. Discover the different materials used based on a variety of applications. View some of the very unique and intricate Sweco custom designs, and corresponding technical drawings. Sweco designs and manufactures Pressure Vessels and Tanks, Pig Launchers and Receivers, Duct Work, Transition Pieces, Bellmouth Reducers, Spectacle and Line Blinds, Air Intake Stacks and Dampers, Conical Strainers, Instrument Stands and other custom fabricated products.
Learn how we design these components for high temperature, high pressure, and/or corrosive environments. Discover the different materials used based on a variety of applications. View some of the very unique and intricate Sweco custom designs, and corresponding technical drawings. Sweco designs and manufactures Pressure Vessels and Tanks, Pig Launchers and Receivers, Duct Work, Transition Pieces, Bellmouth Reducers, Spectacle and Line Blinds, Air Intake Stacks and Dampers, Conical Strainers, Instrument Stands and other custom fabricated products.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
1. Sec.VI :- Standard Specification
24 Bidding Document for ICB - PMD –DSAEP-071/72 – 02, Lot3
I. LINE MATERIAL
A.POLE
A1.TELESCOPIC TUBULAR STEEL POLE
1. Scope
1.1 This Specification covers the design, fabrication, testing and supply of telescopic tubular
steel poles to be used to support overhead electric lines and equipment.
2. Description
2.1 The poles shall be telescopic, uniformly tapered circular in cross-section. The poles shall be
fabricated in sections as specified in Table 2 out of welded tubes of suitable lengths. The
diameters of the top and the bottom end of the completely assembled pole shall be as
specified therein.
2.2 The sections of the steel poles shall be designed such that the butt end of the top section fits
on the top end of the second section, the butt end of the second section fits on the top end of
the third section and so on. The various sections shall be fitted together by pressed friction
joints. The completely assembled telescopic pole shall have the design loads as specified in
Table 1. The separate pole cap shall be provided with top section of the pole. The bottom
section of the pole shall be provided with a base plate.
3. Material
3.1 The telescopic pole sections and fittings shall be manufactured from standard steel as per BS
4360 Grades 43 C,D,E or 50 C, D, E or equivalent national/ international standards.
3.2 The steel tubes shall confirm to the requirements of BS 6323 Parts 1 to 8 Steel Tubes.
4. Manufacture
4.1 The pole shall be erected by friction joint without involvement of through bolt, site welding
or any type of additional device of joint at the time of erection.
4.2 It shall be the responsibility of the Bidder to determine the thickness of the tubing adequate
to sustain the load and test requirements. The Bidder shall determine the thickness of the
tubing to develop the required pole strength in accordance with the Bidder's method of
fabrication. However, the thickness of the tubing shall not be less than 2.5 mm, and the
following tolerances shall be maintained:
2. Sec.VI :- Standard Specification
25 Bidding Document for ICB - PMD –DSAEP-071/72 – 02, Lot3
a) Tolerance on diameter: +/- 1% from Bidder's data sheet.
b) Tolerance on weight: +/- 10% on each pole.
+/- 7.5% on a bulk load of up to 20 tons.
c) Tolerance on thickness: +/- 10% on each sheet.
d) Tolerance on telescopic poles: After assembly the telescopic poles shall not exceed
+/-75 mm of their stated length in the Technical data
sheet.
e) The out-of-straightness of the assembled pole shall not exceed 1/600 of the height.
4.3 All welding of the poles shall be carried out at the manufacturers' plant.
4.4 Welds parallel to the longitudinal axis of the poles shall be fillet welds. No circumferential
joints/welds of the tubes are permitted. All welds shall be capable of withstanding, without
failure or cracking, the stresses in a pole when subjected to its ultimate design loads.
4.5 All seam welds on joint mating surfaces shall be ground flush. All high spots in the
galvanizing on the mating surface shall be ground and if the galvanizing is damaged in the
process, it shall be repaired.
4.6 The pole shall have hole configurations and sizes as shown in the drawings attached to the
Specifications: DP-02: Telescopic Tubular Steel Pole. The hole sizes and the locations of the
hole must however be confirmed with the Project prior to manufacture.
5. Corrosion Protection
All sections of the pole shall be hot dip galvanized both internally and externally in
accordance with IS: 2629-1985 or equivalent national or international standard. After
galvanizing, the external surface of poles below ground level and 500mm above ground level
shall be painted as follows:
a) Thorough clean brush and solvent degrease, then one coat of phosphoric acid based
etch primer both inside and outside followed by,
b) One coat airless spray of epoxy based bituminous black paint of 1x100 microns dry
film thickness inside of the pole base
a. Two successive coat airless spray of epoxy based bituminous black paint of 2x100
microns dry film thickness outside of the pole base.
3. Sec.VI :- Standard Specification
26 Bidding Document for ICB - PMD –DSAEP-071/72 – 02, Lot3
6. Marking of Pole
The pole shall have an identification marked with indelible paint on the pole at a position
approximately 3.5 m. from the butt end, which is clearly and indelibly marked with:
a) Date of manufacture and identification mark of manufacture.
b) Length of pole in meters and its design working loads as defined in this
specification.
The pole shall be marked with a permanent horizontal line at a point 1/6th of the pole height
from the butt end of the assembled pole. The mating depth of the relevant sections of pole
shall also be indelibly marked.
7. Earthing Lug, Base Plate and Pole Cap
Each pole shall be provided with earthing lug at 300 mm below the ground level. Separate
pole cap shall be provided for each pole. The plate for pole cap shall be of 3 mm. minimum
thickness. The dimension of the base plate for 8m, 9m, 10m and 11m poles shall be as per
drawing DWG.1, DWG.3, DWG. 5 and DWG.8 respectively.
8. Design
8.1 The standard overall length of pole manufactured under this contract shall be as per table 1
below. The plantation depth of the pole shall be 1/6th of the overall length of that pole. The
Bidder shall submit a detailed description of the methods of pole manufacture and
detailed calculations for all aspects of design of the pole for NEA approval prior to
manufacture.
8.2 The design working loads in transverse direction shall be as follow:
Table 1: Design Working Load
_________________________________________________________
Pole Length Design Working Load
_______________________________________
Transverse Vertical
_________________________________________________________
8m 150 kgf 150 kgf
9m 200 kgf 200 kgf
10m 350 kgf 350 kgf
11m 350 kgf 350 kgf
The design working load shall be the yield strength reduced by factor of safety of 2.0.
9. Tests
4. Sec.VI :- Standard Specification
27 Bidding Document for ICB - PMD –DSAEP-071/72 – 02, Lot3
9.1 The following test(s) shall be performed for the pole furnished. All testing shall be fully
documented and certified test reports shall be provided to the Project.
- Permanent set test
9.2 Poles selected for testing shall be a representative sample from each lot.
Lot Size No. of poles
Up to 500 5
501 to 1000 8
1001 to 2000 13
2001 to 3000 18
3001 and above 20
9.3 Testing Arrangement: The pole shall be rigidly supported in vertical position for a distance
from the butt end equal to the specified depth of planting of that pole. It shall then be loaded
horizontally with a load applied at the distance from the pole top as specified in Table 2, and the
deflection recorded. Alternatively, for convenience the pole may be fixed horizontally in a
testing arrangement. The testing arrangement shall be provided with sufficient supports to
ensure that bending moments developed by the self-weight of the pole are minimal. These
supports shall be detailed to give no horizontal resistance to the applied loads. The accuracy of
load and deflection measuring equipment shall not be less than +/-2 percent.
9.4 The load shall be gradually and uniformly applied in increments of 10 percent of the design-
working load up to 120 percent of the design-working load. At each increment of load
deflection of the pole tip shall be measured. The 120% loading shall be maintained for 5
minutes. The load shall then be gradually reduced to zero and the amount of permanent
deflection of the pole tip recorded.
The test load shall be gradually reapplied up to the design working load and the deflection
recorded. The load shall then be increased in 10 percent increments until failure occurs. At
each load increment, the load and deflection shall be recorded.
The following particulars shall be recorded:
a. Manufacturer's name and plant location;
b. Batch No. of steel plate or tubing;
c. Test date;
d. Pole type;
e. Dimensions of pole;
f. Increments of load and the deflections at each increment of load;
g. Permanent deflection;
h. Load of failure;
9.5 The pole shall be considered acceptable if:
a) The permanent deflection of the tip of the pole does not exceed 2 mm, 3 mm, 3.5. and 4
mm. per meter of pole length for 8m,9m,10m and 11 m pole respectively. (The
permanent deflection is the deflection of tip of the pole on removal of load equal to
5. Sec.VI :- Standard Specification
28 Bidding Document for ICB - PMD –DSAEP-071/72 – 02, Lot3
120% of design working load of pole after 5 minutes of the application of that load.
Clause 9.4)
b) The failure load of the pole tested equals or exceeds 200% of design working load.
9.6 Should any of the poles first selected fail to pass any of the tests specified above two further
poles shall be selected for testing from the same batch i.e. same pole length manufactured
on the same day from the same steel plate or tubing in respect of each failure. Should one or
both these additional poles fail, the test material represented by the test samples shall be
deemed as not complying with this specification.
10. Bid Documentation
10.1 The Bidder shall provide with the Bid two (2) clear copies of the governing standards for
selection of tubings, fabrication and testing of Telescopic Tubular Steel Poles and two (2)
clear copies of all other relevant standards referenced therein..
10.2 The Bidder shall provide a complete design, description and certified dimensional drawings of
each type of pole.
10.3 Two (2) clear certified copies of all type tests performed on similar type of poles and similar
working loads.
10.4 A clause-by-clause commentary on specification, specifying compliance and deviations, if
any.
TABLE 2
Pole Attributes
Overall Length 11m 10 m 9m 8m
Total Number of Sections 5 5 5 4
Diameter of the assembled pole in meter:
Top in mm 170 170 170 150
Bottom in mm 402 380 360 350
Application of
Load from top of pole in meter 0.6 0.6 0.6 0.075
Depth of Planting in meter 1.8 1.8 1.5 1.5
6. Sec.VI :- Standard Specification
29 Bidding Document for ICB - PMD –DSAEP-071/72 – 02, Lot3
TECHNICAL DATA SHEETS
(To be completed by Bidder)
Item Telescopic Tubular Steel Poles
Description Unit 11m. 10m 9m 8m
1. Manufacturer
2. Governing Standards for tubing
manufacturing and testing
3. Governing Standard for Galvaniation
4. Copies of Standards Attached? Yes/No
4. Overall Length meters
5. No. of sections No.
6. Sections starting from the top:
Section: 1
-Length m
-Thickness mm
-Top dia. (outer) mm
-Butt dia. (outer) mm
-Weight kg
Section: 2
-Length m
-Thickness mm
-Top dia. (outer) mm
-Butt dia. (outer) mm
-Weight kg
Section: 3
-Length m
-Thickness mm
-Top dia. (outer) mm
-Butt dia. (outer) mm
-Weight kg
7. Sec.VI :- Standard Specification
30 Bidding Document for ICB - PMD –DSAEP-071/72 – 02, Lot3
Description Unit 11m. 10m 9m 8m
Section: 4
-Length m
-Thickness mm
-Top dia. (outer) mm
-Butt dia. (outer) mm
-Weight kg
Section: 5
-Length m
-Thickness mm
-Top dia. (outer) mm
-Butt dia. (outer) mm
-Weight kg
7. Weight of the pole kg
8. Guaranteed minimum kgf
Transverse Failure Load
9. Guaranteed maximum mm
Permanent deflection