SlideShare a Scribd company logo
ASME Sec. VIII Div. 1 2015ED.
Rules for Construction of Pressure Vessels
MANDATORYAPPENDIX 44
What does
“COLD STRETCHING 冷拉伸”mean?
1
Cold Stretching background(1/2)
 Cold stretching has been in use for more than 30 years, but not
under ASME code rules until 2008(Code Case 2596). Cold
stretching (or cold working) increases the yield limit of a stainless
steel material by work hardening it after all forming and welded
steps are complete. A vessel can be cold stretched by over
pressurizing it 1.5 to 1.6 times design pressure under careful
control of the deformation vs pressure as outlined in VIII-1 App 44.
The resulting permanent plastic deformation increases the diameter
up to 7% and the volume by 14%.
 冷拉伸已經使用超過30年,但直到2008年才符合ASME規範。
冷拉伸(或冷加工)通過在所有成型和焊接步驟完成後加工硬
化來提高不銹鋼材料的屈服極限。 如VIII-1 App 44所述,在小
心控制變形與壓力的情況下,可以通過將容器過度加壓至設計
壓力的1.5至1.6倍來對容器進行冷拉伸。所得永久塑性變形將直
徑增加至7 %和14%的容積。
2
Cold Stretching background(2/2)
Stainless steel stress strain curve showing an increase in yield strength after cold working.
The ASME allowed stress in a vessel made of SA-240 304 stainless is 138MPa for cryogenic
applications. After cold stretching, the allowable stress is increased to 270MPa (Table 44-1-1
in ASME VIII-1). The higher allowable is a combination of both an increase in the yield
stress and a decrease in the factor of safety.
Circumferential Stress
515MPa Safety Factor
3 270MPa 1.9 double
2 138MPa 3.7 double
3
≤ 0.1%/hr
Guidelines such as:
a) AS 1210 Supplement 2 (1999),
b) EN 13458-2 (2002),
c) EN 13530-2 (2002),
d) ISO 20421-1 (2006),
e) ISO 21009-1 (2008),
f) ASME Boiler & Pressure Vessel
Code (BPVC) VIII-1 Appendix 44
(2013).
Elastic Plastic
P
44-1 SCOPE
 designing and constructing cold-stretched austenitic stainless steel(ASS) vessels
Materials Allowable stress of ASS in different standards [MPa]
UNS
No.
Min.
Tensile
Strength
Min.
Yield
Strength
ASME BPVC
VIII-I Code
Case 2596
ASME BPVC II
Part D
GB150
S30408 515 205 270 138 137
S30403 485 170 247 115 120
4
44-2 GENERAL REQUIREMENTS
User or
user’s designated agent
Approval( APP. KK)
t ≤ 30 mm
MDMT ≥ −196°C
MDT ≤ 50°C
limited to single diameter, and nozzles without a reinforcing
pad. uniform nominal thickness.
UTS of the weld filler metal used in construction ≥ the
UTS for the base metals of the weld joint.
Nozzles and opening reinforcement components shall be
designed using this Division and applying the allowable stress
values specified in Section II, Part D.
designed for internal pressure only
Nozzle size ≤ NPS 6 (DN 150)
Nozzle size ≤ NPS 8 (DN 200) at the center of heads
All Cat. A weld joints Type No. 1.
All Cat. B weld joints Type No. 1 or Type No. 2.
5
44-5 DESIGN
 (a) Wall thicknesses shall be calculated before cold stretching.
 (b) Nominal diameters may be used in the design calculations
 (c) Pc shall be between 1.5 and 1.6 times P
 (d) The inside knuckle radius of formed torispherical heads
shall not be less than 10% of the inside crown radius of the
head.
 (e) Butt welded joints full RT or by UT.
 (f) All nozzles shall be attached with full-penetration welds.
 (g) The thickness of a support pad shall not exceed the
thickness of the shell at the attachment location.
 (h) Full-thickness fillet welds shall be provided at support-pad
attachment locations.
Note :Pc = cold-stretching pressure;P = design pressure 6
44-6 FABRICATION PROCESS
 44-6.1 WELDING AND EXAMINATION
a) For all Category A joints, the reinforcement ≤ 10% of the
plate thickness or 3 mm, whichever is less.
b) Welder and welding operator identification shall be marked
with a paint pen or maintained by weld maps.
c) Butt welded joints full RT or by UT.
d) All Cat. A or B weld joints and all attachment welds shall
be examined externally for their entire lengths using the PT.
e) Renewed cold stretching shall be performed if cold stretched
parts of the vessel have been welded after cold stretching,
except for attachment or tack welds(點焊) less than 6 mm in
length.
7
44-6.2 COLD-STRETCHING OPERATION
a) Fill the vessel with water, the vents open for at least 15 min.
b) the circumference of all shell courses shall be measured, All
measurements shall be made with instruments that have been
calibrated to an accuracy of ±0.05%. Additional measurements of
the vessel while under Pc shall be taken as necessary to calculate
the strain rate. The strain rate during the cold-stretching operation
shall be calculated over the full circumference.
c) cold-stretching operation (witnessed by AI):
1. The pressure shall be increased until Pc is reached. Pc shall be
maintained until the calculated strain rate has dropped to ≤ 0.1%/hr.
2. The minimum holding time ≥ 1 hr.
3. The calculated strain rate shall be determined by repeated or
continuous measurements of the circumference while the vessel is
under Pc. The required maximum strain rate of 0.1%/hr shall be met
during the last half hour. 8
44-6.3 COLD-STRETCHING PROCEDURE (CSP)
 A written record shall be prepared containing at least the
following information:
(a) pressurizing sequence specifying pressure readings and time
(b) circumference measurement before, during, and after
pressurization; or alternatively, time, pressure, and the elongation
of circumference
(c) strain-rate calculations
(d) notes of any significant changes of shape and size relevant to
the functioning of the vessel
9
44-7 STAMPING AND CERTIFICATION
 (a) The Certification Mark on the nameplate shall include
marking with “CS” under the Certification Mark, indicating
the vessel was constructed using cold-stretching methods.
 (b) The Manufacturer shall indicate in the Remarks section of
the Manufacturer’s Data Report: “This vessel has been
constructed using cold-stretching processes in accordance
with Mandatory Appendix 44.”
10

More Related Content

What's hot

Fabrication of storage buffer vessel
Fabrication of storage buffer vesselFabrication of storage buffer vessel
Fabrication of storage buffer vesselNishant Rao Boddeda
 
38785106 api-tank-design
38785106 api-tank-design38785106 api-tank-design
38785106 api-tank-design
141jdf
 
Process piping b31.3 detailed
Process piping b31.3 detailedProcess piping b31.3 detailed
Process piping b31.3 detailed
Adeel Mazhar
 
Tutorial caesars II
Tutorial caesars IITutorial caesars II
Tutorial caesars II
manuedlf
 
pipe stress analysis for piping engineering
pipe stress analysis for piping engineeringpipe stress analysis for piping engineering
pipe stress analysis for piping engineering
Yoga Sathish
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
leo040490
 
Pressure vessel
Pressure vesselPressure vessel
Pressure vessel
Ayman Hasprapo
 
[Point] pipe stress analysis by computer-caesar ii
[Point] pipe stress analysis by computer-caesar ii[Point] pipe stress analysis by computer-caesar ii
[Point] pipe stress analysis by computer-caesar ii
Luis Luis
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
Piping Technology & Products, Inc.
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
Sam Jose
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answers
Jasminder singh
 
Piping design and flexibility analysis
Piping design and flexibility analysisPiping design and flexibility analysis
Piping design and flexibility analysis
Sarath Krishnakumar
 
B31.3 process piping course 02 metallic pipe & fitting selection
B31.3 process piping course   02 metallic pipe & fitting selectionB31.3 process piping course   02 metallic pipe & fitting selection
B31.3 process piping course 02 metallic pipe & fitting selection
Ahmedhelal_Metito Helal
 
Summary of pressure vessel 1
Summary of pressure vessel 1Summary of pressure vessel 1
Summary of pressure vessel 1
Mohamed Basyoni
 
Pressure vessel
Pressure vesselPressure vessel
Pressure vessel
Dhiraj Bhaskar
 
ASME Section viii Div-1 Traing ppt..pdf
ASME Section viii Div-1  Traing ppt..pdfASME Section viii Div-1  Traing ppt..pdf
ASME Section viii Div-1 Traing ppt..pdf
Baber6
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
Jithu John
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
MOHAMMAD ATIF ALI
 
Tank design - word
Tank design - wordTank design - word
Tank design - word
moamen mohamed
 

What's hot (20)

Fabrication of storage buffer vessel
Fabrication of storage buffer vesselFabrication of storage buffer vessel
Fabrication of storage buffer vessel
 
38785106 api-tank-design
38785106 api-tank-design38785106 api-tank-design
38785106 api-tank-design
 
Process piping b31.3 detailed
Process piping b31.3 detailedProcess piping b31.3 detailed
Process piping b31.3 detailed
 
Tutorial caesars II
Tutorial caesars IITutorial caesars II
Tutorial caesars II
 
236135365 heat-treatment-manual
236135365 heat-treatment-manual236135365 heat-treatment-manual
236135365 heat-treatment-manual
 
pipe stress analysis for piping engineering
pipe stress analysis for piping engineeringpipe stress analysis for piping engineering
pipe stress analysis for piping engineering
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
Pressure vessel
Pressure vesselPressure vessel
Pressure vessel
 
[Point] pipe stress analysis by computer-caesar ii
[Point] pipe stress analysis by computer-caesar ii[Point] pipe stress analysis by computer-caesar ii
[Point] pipe stress analysis by computer-caesar ii
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answers
 
Piping design and flexibility analysis
Piping design and flexibility analysisPiping design and flexibility analysis
Piping design and flexibility analysis
 
B31.3 process piping course 02 metallic pipe & fitting selection
B31.3 process piping course   02 metallic pipe & fitting selectionB31.3 process piping course   02 metallic pipe & fitting selection
B31.3 process piping course 02 metallic pipe & fitting selection
 
Summary of pressure vessel 1
Summary of pressure vessel 1Summary of pressure vessel 1
Summary of pressure vessel 1
 
Pressure vessel
Pressure vesselPressure vessel
Pressure vessel
 
ASME Section viii Div-1 Traing ppt..pdf
ASME Section viii Div-1  Traing ppt..pdfASME Section viii Div-1  Traing ppt..pdf
ASME Section viii Div-1 Traing ppt..pdf
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Tank design - word
Tank design - wordTank design - word
Tank design - word
 

Similar to What does cold stretching mean

Establishing asme b16.5 blind flanges ratings for reduced thicknesses
Establishing asme b16.5 blind flanges ratings for reduced thicknessesEstablishing asme b16.5 blind flanges ratings for reduced thicknesses
Establishing asme b16.5 blind flanges ratings for reduced thicknesses
Farid Masood
 
Study of Ball Valve and Design of Thickness of Shell and Flange
Study of Ball Valve and Design of Thickness of Shell and FlangeStudy of Ball Valve and Design of Thickness of Shell and Flange
Study of Ball Valve and Design of Thickness of Shell and Flange
IRJET Journal
 
Asme guides weld canada
Asme guides weld canadaAsme guides weld canada
Asme guides weld canada
Subhan Jibran B.E( I M ) NED
 
office final ppt [7760835] final update
office final ppt [7760835] final updateoffice final ppt [7760835] final update
office final ppt [7760835] final updateAashish Soin
 
Introduction to ASME VIII Div 1 (ATS).pdf
Introduction to ASME VIII Div 1 (ATS).pdfIntroduction to ASME VIII Div 1 (ATS).pdf
Introduction to ASME VIII Div 1 (ATS).pdf
deckyantony
 
pv_rules.pdf
pv_rules.pdfpv_rules.pdf
pv_rules.pdf
MnstalinMnstalin
 
pv_rules.pdf
pv_rules.pdfpv_rules.pdf
pv_rules.pdf
ChatriKriengyakul
 
Flange Bolting
Flange BoltingFlange Bolting
Flange Bolting
Austin Pwrs
 
Design and Analysis of Vapour Absorbing Machine
Design and Analysis of Vapour Absorbing MachineDesign and Analysis of Vapour Absorbing Machine
Design and Analysis of Vapour Absorbing Machine
IJMER
 
Design of Self Regulating Pressure Valve using Transient Finite Element Analysis
Design of Self Regulating Pressure Valve using Transient Finite Element AnalysisDesign of Self Regulating Pressure Valve using Transient Finite Element Analysis
Design of Self Regulating Pressure Valve using Transient Finite Element Analysis
IRJET Journal
 
Ijmer 46063339
Ijmer 46063339Ijmer 46063339
Ijmer 46063339IJMER
 
Ijmer 46063339
Ijmer 46063339Ijmer 46063339
Ijmer 46063339IJMER
 
2015 1 tech-presentation_ball
2015 1 tech-presentation_ball2015 1 tech-presentation_ball
2015 1 tech-presentation_ball
AbdulHadiAhmed2
 
Telescopic poles nea
Telescopic poles  neaTelescopic poles  nea
Telescopic poles nea
kapil pudasaini
 
Process Tank Blanketing Valve
Process Tank Blanketing ValveProcess Tank Blanketing Valve
Process Tank Blanketing Valve
Miller Energy, Inc.
 
010 115-001-03 ESPECIFICACIONES DE TUBERÍA
010 115-001-03 ESPECIFICACIONES DE TUBERÍA010 115-001-03 ESPECIFICACIONES DE TUBERÍA
010 115-001-03 ESPECIFICACIONES DE TUBERÍA
Juan Novillo Ramos
 
Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...
Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...
Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...
IRJET Journal
 
IS 4985 : 2000
IS 4985 : 2000IS 4985 : 2000
IS 4985 : 2000
Jisha John
 
Kammer Severe Service Valves For Industry
Kammer Severe Service Valves For IndustryKammer Severe Service Valves For Industry
Kammer Severe Service Valves For Industry
CTi Controltech
 

Similar to What does cold stretching mean (20)

Establishing asme b16.5 blind flanges ratings for reduced thicknesses
Establishing asme b16.5 blind flanges ratings for reduced thicknessesEstablishing asme b16.5 blind flanges ratings for reduced thicknesses
Establishing asme b16.5 blind flanges ratings for reduced thicknesses
 
Study of Ball Valve and Design of Thickness of Shell and Flange
Study of Ball Valve and Design of Thickness of Shell and FlangeStudy of Ball Valve and Design of Thickness of Shell and Flange
Study of Ball Valve and Design of Thickness of Shell and Flange
 
Asme guides weld canada
Asme guides weld canadaAsme guides weld canada
Asme guides weld canada
 
office final ppt [7760835] final update
office final ppt [7760835] final updateoffice final ppt [7760835] final update
office final ppt [7760835] final update
 
Introduction to ASME VIII Div 1 (ATS).pdf
Introduction to ASME VIII Div 1 (ATS).pdfIntroduction to ASME VIII Div 1 (ATS).pdf
Introduction to ASME VIII Div 1 (ATS).pdf
 
pv_rules.pdf
pv_rules.pdfpv_rules.pdf
pv_rules.pdf
 
pv_rules.pdf
pv_rules.pdfpv_rules.pdf
pv_rules.pdf
 
Flange Bolting
Flange BoltingFlange Bolting
Flange Bolting
 
Design and Analysis of Vapour Absorbing Machine
Design and Analysis of Vapour Absorbing MachineDesign and Analysis of Vapour Absorbing Machine
Design and Analysis of Vapour Absorbing Machine
 
Design of Self Regulating Pressure Valve using Transient Finite Element Analysis
Design of Self Regulating Pressure Valve using Transient Finite Element AnalysisDesign of Self Regulating Pressure Valve using Transient Finite Element Analysis
Design of Self Regulating Pressure Valve using Transient Finite Element Analysis
 
Ijmer 46063339
Ijmer 46063339Ijmer 46063339
Ijmer 46063339
 
Ijmer 46063339
Ijmer 46063339Ijmer 46063339
Ijmer 46063339
 
2015 1 tech-presentation_ball
2015 1 tech-presentation_ball2015 1 tech-presentation_ball
2015 1 tech-presentation_ball
 
Telescopic poles nea
Telescopic poles  neaTelescopic poles  nea
Telescopic poles nea
 
Process Tank Blanketing Valve
Process Tank Blanketing ValveProcess Tank Blanketing Valve
Process Tank Blanketing Valve
 
Butt fusion welding procedure eng
Butt fusion welding procedure engButt fusion welding procedure eng
Butt fusion welding procedure eng
 
010 115-001-03 ESPECIFICACIONES DE TUBERÍA
010 115-001-03 ESPECIFICACIONES DE TUBERÍA010 115-001-03 ESPECIFICACIONES DE TUBERÍA
010 115-001-03 ESPECIFICACIONES DE TUBERÍA
 
Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...
Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...
Introduction to Design of Trunnion Mounted Ball Valve (Size- DN1200, Rating- ...
 
IS 4985 : 2000
IS 4985 : 2000IS 4985 : 2000
IS 4985 : 2000
 
Kammer Severe Service Valves For Industry
Kammer Severe Service Valves For IndustryKammer Severe Service Valves For Industry
Kammer Severe Service Valves For Industry
 

Recently uploaded

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 

Recently uploaded (20)

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 

What does cold stretching mean

  • 1. ASME Sec. VIII Div. 1 2015ED. Rules for Construction of Pressure Vessels MANDATORYAPPENDIX 44 What does “COLD STRETCHING 冷拉伸”mean? 1
  • 2. Cold Stretching background(1/2)  Cold stretching has been in use for more than 30 years, but not under ASME code rules until 2008(Code Case 2596). Cold stretching (or cold working) increases the yield limit of a stainless steel material by work hardening it after all forming and welded steps are complete. A vessel can be cold stretched by over pressurizing it 1.5 to 1.6 times design pressure under careful control of the deformation vs pressure as outlined in VIII-1 App 44. The resulting permanent plastic deformation increases the diameter up to 7% and the volume by 14%.  冷拉伸已經使用超過30年,但直到2008年才符合ASME規範。 冷拉伸(或冷加工)通過在所有成型和焊接步驟完成後加工硬 化來提高不銹鋼材料的屈服極限。 如VIII-1 App 44所述,在小 心控制變形與壓力的情況下,可以通過將容器過度加壓至設計 壓力的1.5至1.6倍來對容器進行冷拉伸。所得永久塑性變形將直 徑增加至7 %和14%的容積。 2
  • 3. Cold Stretching background(2/2) Stainless steel stress strain curve showing an increase in yield strength after cold working. The ASME allowed stress in a vessel made of SA-240 304 stainless is 138MPa for cryogenic applications. After cold stretching, the allowable stress is increased to 270MPa (Table 44-1-1 in ASME VIII-1). The higher allowable is a combination of both an increase in the yield stress and a decrease in the factor of safety. Circumferential Stress 515MPa Safety Factor 3 270MPa 1.9 double 2 138MPa 3.7 double 3 ≤ 0.1%/hr Guidelines such as: a) AS 1210 Supplement 2 (1999), b) EN 13458-2 (2002), c) EN 13530-2 (2002), d) ISO 20421-1 (2006), e) ISO 21009-1 (2008), f) ASME Boiler & Pressure Vessel Code (BPVC) VIII-1 Appendix 44 (2013). Elastic Plastic P
  • 4. 44-1 SCOPE  designing and constructing cold-stretched austenitic stainless steel(ASS) vessels Materials Allowable stress of ASS in different standards [MPa] UNS No. Min. Tensile Strength Min. Yield Strength ASME BPVC VIII-I Code Case 2596 ASME BPVC II Part D GB150 S30408 515 205 270 138 137 S30403 485 170 247 115 120 4
  • 5. 44-2 GENERAL REQUIREMENTS User or user’s designated agent Approval( APP. KK) t ≤ 30 mm MDMT ≥ −196°C MDT ≤ 50°C limited to single diameter, and nozzles without a reinforcing pad. uniform nominal thickness. UTS of the weld filler metal used in construction ≥ the UTS for the base metals of the weld joint. Nozzles and opening reinforcement components shall be designed using this Division and applying the allowable stress values specified in Section II, Part D. designed for internal pressure only Nozzle size ≤ NPS 6 (DN 150) Nozzle size ≤ NPS 8 (DN 200) at the center of heads All Cat. A weld joints Type No. 1. All Cat. B weld joints Type No. 1 or Type No. 2. 5
  • 6. 44-5 DESIGN  (a) Wall thicknesses shall be calculated before cold stretching.  (b) Nominal diameters may be used in the design calculations  (c) Pc shall be between 1.5 and 1.6 times P  (d) The inside knuckle radius of formed torispherical heads shall not be less than 10% of the inside crown radius of the head.  (e) Butt welded joints full RT or by UT.  (f) All nozzles shall be attached with full-penetration welds.  (g) The thickness of a support pad shall not exceed the thickness of the shell at the attachment location.  (h) Full-thickness fillet welds shall be provided at support-pad attachment locations. Note :Pc = cold-stretching pressure;P = design pressure 6
  • 7. 44-6 FABRICATION PROCESS  44-6.1 WELDING AND EXAMINATION a) For all Category A joints, the reinforcement ≤ 10% of the plate thickness or 3 mm, whichever is less. b) Welder and welding operator identification shall be marked with a paint pen or maintained by weld maps. c) Butt welded joints full RT or by UT. d) All Cat. A or B weld joints and all attachment welds shall be examined externally for their entire lengths using the PT. e) Renewed cold stretching shall be performed if cold stretched parts of the vessel have been welded after cold stretching, except for attachment or tack welds(點焊) less than 6 mm in length. 7
  • 8. 44-6.2 COLD-STRETCHING OPERATION a) Fill the vessel with water, the vents open for at least 15 min. b) the circumference of all shell courses shall be measured, All measurements shall be made with instruments that have been calibrated to an accuracy of ±0.05%. Additional measurements of the vessel while under Pc shall be taken as necessary to calculate the strain rate. The strain rate during the cold-stretching operation shall be calculated over the full circumference. c) cold-stretching operation (witnessed by AI): 1. The pressure shall be increased until Pc is reached. Pc shall be maintained until the calculated strain rate has dropped to ≤ 0.1%/hr. 2. The minimum holding time ≥ 1 hr. 3. The calculated strain rate shall be determined by repeated or continuous measurements of the circumference while the vessel is under Pc. The required maximum strain rate of 0.1%/hr shall be met during the last half hour. 8
  • 9. 44-6.3 COLD-STRETCHING PROCEDURE (CSP)  A written record shall be prepared containing at least the following information: (a) pressurizing sequence specifying pressure readings and time (b) circumference measurement before, during, and after pressurization; or alternatively, time, pressure, and the elongation of circumference (c) strain-rate calculations (d) notes of any significant changes of shape and size relevant to the functioning of the vessel 9
  • 10. 44-7 STAMPING AND CERTIFICATION  (a) The Certification Mark on the nameplate shall include marking with “CS” under the Certification Mark, indicating the vessel was constructed using cold-stretching methods.  (b) The Manufacturer shall indicate in the Remarks section of the Manufacturer’s Data Report: “This vessel has been constructed using cold-stretching processes in accordance with Mandatory Appendix 44.” 10