RAILWAY
ENGINEERING
By
RaviKumarGARRE,
AssistantProfessor,
DepartmentofCivilEngineering,
St.Peter’sEngineeringCollege,
Hyderabad.
Contents covered
1. Different modes of transport
2. Road transport Vs Rail transport
3. Railway alignment
4. Engineering surveys
Different Modes ofTransport
• Our environment consists of land, air and water. These
media have provided scope for three modes of transport—
land transport, air transport and water transport.
• Rail transport and road transport are the two components
of land transport.
• Each mode of transport, depending upon its various
characteristics, has intrinsic strengths and weaknesses and
can be best used for a particular type of traffic as given
below.
Rail transport versus road
transport
Features :
1. Tractive Resistance
2. Right ofWay
3. CostAnalysis
4. Gradient andCurves
5. Flexibility of Movements
6. Environmental Pollution
7. Organization andControl
8. Suitability
Tractive Resistance
RailTransport
The movement of steel
wheels on the steel has
the basic advantage of low
rolling resistance.This
reduces haulage cost
because of low tractive
resistance.
RoadTransport
The tractive resistance of a
pneumatic tire on metalled
roads is almost five times
compared to that of wheels
on rails.
Right of Way
RailTransport
A railway track is defined
on to rails and I within
protected limits.Train
woks as per prescribed
schedule and no other
vehicle has the right of way
except at specified level
crossing.
RoadTransport
Roads, though having well
defined limits, can be
used by any vehicular
traffic and even by
pedestrian they are open
to all.
Cost analysis
RailTransport
Owning to the heavy
infrastructure, the initial
as well as maintenance
cost of railway line is high.
RoadTransport
The cost of construction and
maintenance of roads is
comparatively cheaper.
Gradient and Curves
RailTransport
The gradient of railways
tracks are flatter
(normally not more than
1%) and curves are
limited up to only 10
degree on broad gauge.
RoadTransport
Roads are constructed normally
with steeper gradient of up to
4% and relatively much sharper
curves.
Flexibility of Movement
RailTransport
Due to the defined route
and facilitates required for
the reception and dispatch
of train, railways can be
used only between fixed
points.
RoadTransport
Road transport have much
more flexibility in movement
and can provide door-to – door
services.
Environmental Pollution
RailTransport
Railways have minimum
adverse effect on the
environment.
RoadTransport
Road transport create
comparatively greater
pollution than the railway.
Organization and Control
RailTransport
Railways are government
undertaking, with their own
organization.
RoadTransport
Barring member stat
government transport, road
transport is managed by the
private sector.
Suitability
RailTransport
Railways are best suited
for carrying heavy goods
and large number of
passengers over long
distance. .
RoadTransport
Road transport is best suited
for carrying lighter goods and
smaller number of passenger
over shorter distance.
Alignment of Railway Lines
Introduction
Alignment of railway line refers to the direction and
position given to the centre line of the railway
track on the ground in the horizontal and
vertical planes. Horizontal alignment means the
direction of the railway track in the plan
including the straight path and the curves it
follows. Vertical alignment means the direction
it follows in a vertical plane including the level
track, gradients, and vertical curves. The various
factors affecting alignment, and types of track
alignments and their suitability in different
terrains are discussed here
Importance of Good Alignment
A new railway line should be aligned carefully
after proper considerations, as improper
alignment may ultimately prove to be more
costly and may not be able to fulfill the desired
objectives. Railway line constructions are
capital-intensive projects, once constructed, it
is very difficult to change the alignment of a
railway line because of the costly structures
involved, difficulty in getting additional land
for the new alignment, and such other
considerations.
Railway alignment
Railway alignment
Railway alignment
Railway alignment
Railway alignment
Basic Requirements of an Ideal
Alignment
1.Purpose of the New Railway Line:
The alignment of a new railway line should serve
the basic purpose for which the railway line is
being constructed. As brought out earlier, the
purpose may include strategic considerations,
political considerations, developing of
backward areas, connecting new trade
centres, and shortening existing rail lines.
2.Integrated Development
The new railway line should fit in with the general
planning and form a part of the integrated
development of the country.
3.Economic Considerations
i)Shortest route - It is desirable to have the shortest
and most direct route between the connecting
points. The shorter the length of the railway line,
the lower the cost of its construction,
maintenance, and operation. There can, however,
be other practical considerations that can lead to
deviation from the shortest route.
ii)Construction and maintenance cost - The alignment of
the line should be so chosen that the construction cost
is minimum. This can be achieved by a balanced cut
and fill of earthwork, minimizing rock cutting and
drainage crossings by locating the alignment on
watershed lines, and such other technical
considerations. Maintenance costs can be reduced by
avoiding steep gradients and sharp curves, which cause
heavy wear and tear of rails and rolling stock.
iii)Minimum operational expenses - The alignment
should be such that the operational or transportation
expenses are minimum. This can be done by
maximizing the haulage of goods with the given power
of the locomotive and traction mix. This can he
achieved by providing easy gradients, avoiding sharp
curves, and adopting a direct route
iv)Maximum Safety and Comfort
The alignment should be such that it provides
maximum safety and comfort to the travelling
public. This can be achieved by designing curves
with proper transition lengths, providing vertical
curves for gradients, and incorporating other such
technical features.
v)Aesthetic Considerations
While deciding the alignment, aesthetic aspects
should also be given due weightage. A journey by
rail should be visually pleasing. This can be done
by avoiding views of borrow pits and passing the
alignment through natural and beautiful
surroundings with scenic beauty.
Selection of a Good Alignment
Normally, a direct straight route connecting two
points is the shortest and most economical
route for a railway line, but there are practical
problems and other compulsions which
necessitate deviation from this route. The
various factors involved is the selection of a
good alignment for a railway line are given
below.
1.Choice of Gauge:
The gauge can be a BG (1676 mm), an MG (1000
mm), or even an NG (762 mm). As per the
latest policy of the Government of India, new
railway lines are constructed on BG only.
2. Obligatory or Controlling Points:
These are the points through which the railway
line must pass due to political, strategic, and
commercial reasons as well as due to technical
considerations. The following are obligatory or
controlling points.
Important cities and towns- These are mostly
intermediate important towns, cities, or places which
of commercial, strategic, or political importance.
Major bridge sites and river crossings - The construction
of major bridges for large rivers is very expensive and
suitable bridge sites become obligatory points for a
good alignment.
Existing passes and saddles in hilly terrain - Existing
passes and saddles should be identified for crossing a
hilly terrain in order to avoid deep cuttings and high
banks.
Sites for tunnels - The option of a tunnel in place of a
deep cut in a hilly terrain is better from the
economical viewpoint. The exact site of such a tunnel
becomes an obligatory point.
3. Topography of the Country:
Plane alignment - When the topography is plane
and flat, the alignment presents no problems
and can pass through obligatory points and yet
have very easy gradients.
Valley alignment - The alignment of a railway line
in valley is simple and does not pose any
problem. If two control points lie in the same
valley, a straight line is provided between these
points with a uniform gradient.
4. Geometrical Standards:
Geometrical standards should be so adopted as to
economize as much as possible as well as provide safety
and comfort to passengers. This can be done by
adopting gradients and curves within permissible limits.
Transition as well as vertical curves should be used to
provide better comfort and safety.
5.Geological Formation:
The alignment should be so selected that it normally runs
on good and stable soil formation as far as possible.
Weak soil and marshy land present a number of
problems including those of maintenance. Though
rocky soil, provides a stable formation, it is a costly
proposal.
6.Position of Roads and Road Crossings
A railway line should cross a road at right angles so
as to have a perpendicular level crossing and
avoid accidents.
7.Proximity of Labour and Material
The availability and proximity of local labour and
good and cheap building material should also be
considered when deciding the alignment.
8.Location of Railway Stations and Yards
Railway stations and yards should be located on
level stretches of land, preferably on the outskirts
of a town or village so as to have enough area for
the free flow of traffic.
9. Religious and Historical Monuments
The alignment should avoid religious and
historical monuments, as it is normally not
possible to dismantle these buildings.
10.Political Considerations:
The alignment should take into account political
considerations. It should not enter foreign soil
and should preferably be away from common
border areas.
Engineering Surveys and
Construction of New Lines
Introduction
The construction of a new railway line is a
capital-intensive project and each kilometre of
a new railway line costs in the range of Rs 6 to
10 million depending upon the topography of
the area, the standard of construction, and
such other features. It is, therefore, natural
that a lot of thought be given when making a
final decision as to whether a new railway line
is at all necessary or not.
Need for Construction of a New
Railway Line
The need for construction of a new railway line arises
because of one or more of the following
considerations.
(a)Strategic reasons It is sometimes necessary to extend
the existing railway line to a new point of strategic
importance so that the defence forces can move
quickly to the some areas in case of any emergency
such as the threat of war.
(b)Political reasons A new line sometimes becomes
necessary to serve the political needs of the country,
for example, the railway line from Pathankot to
Jammu.
(c)Development of backward areas Railway lines are
sometimes constructed to develop backward areas.
Experience has shown that once railway
communication is available, backward areas develop
very fast. The Assam rail link can be classified in this
category.
(d)To connect new trade centres Sometimes new trade
centres are connected with railway lines for the quick
transportation of goods between two trade centres or
from the point of production to the point of
consumption.
(e) To shorten the existing rail link: The existing
routes between two important points may be
longer than required. New railway lines are
constructed on a shorter alignment in such
cases. A short route is not only economical,
but also helps in the faster movement of goods
and passengers. The Konkan Railway is a
typical example.
Types of Surveys
The following types of surveys are normally
conducted:
(a) Traffic survey
(b) Reconnaissance survey
(c) Preliminary survey
(d) Final location survey
Traffic survey
Traffic survey includes a detailed study of the
traffic conditions in the area with a view to
determine the
Most promising route for the railway in the
area,
Possible traffic the railway line will carry, and
Standard of railway line to be followed.
Traffic survey consists of an economic study of the area keeping in mind the
following considerations, information on which should be collected in detail:
(a) Human resources
(b) Agricultural and mineral resources
(c) Pattern of trade and commerce
(d) Industries located and projected
(e) Prospects of tourist traffic
(f) Existing transport facilities
(g) Locations of important government and private offices
(h) Planning for economic development of the area
• The traffic survey team should make an assessment of the
traffic likely to be carried by to the new line. While
carrying out the survey, details of traffic likely to be
offered by various government organizations, public
bodies, or private enterprises should be gathered
Reconnaissance Survey
This survey consists of a rapid and rough
investigation of the area with a view to determine
the technical feasibility of the proposal as well as
the rough cost of one or more alternatives to the
new line. The reconnaissance survey (RECCE) is
normally based on contoured survey maps and
other data already available without carrying out
detailed investigations in the field. With the help
of the maps, different alternative alignments of
the new line are studied.
Survey Instruments
Prismatic compass - Toget magnetic bearings of
the proposed alignment.
Aneroid barometer - To ensure relative heights
of various points.
Abney level or hand level or clinometer - To
measure the gradients or angles of slopes.
Binocular - Toview the physical features.
Pedometer - To get an idea of the total length
traversed while walking.
Preliminary Survey
The preliminary survey consists of a detailed
instrumental examination of the route to be
selected as a result of the reconnaissance
survey in order to estimate the cost of the
proposed railway line. Based on the
preliminary and traffic survey reports, the
railway administration decides whether or not
the proposed railway line is to be constructed.
Instruments for Preliminary Survey
(a)Theodolite for traversing and pegging the
centre line
(b) Tacheometer for plotting the main features
(c)Dumpy level for taking the longitudinal and
cross levels
(d)Plane table for getting details of various
features
(e)Prismatic compass for measuring the
magnetic bearings of a particular alignment
Final Location Survey
Once a decision has been taken for a particular
railway line to be constructed, a final location
survey is done. The instruments used are
generally the same as in the case of the
preliminary survey. Final location survey is
done to prepare working details and make
accurate cost estimates in certain cases.
The principal differences between the preliminary
survey and the final survey are as follows.
(a) In the final location survey, the alignment is
fully staked with the help of a theodolite,
whereas it is not obligatory to do so in the case
of preliminary survey.
(b)In the final location survey, a more detailed
project report is prepared and submitted.
(c)All working drawings are prepared in the final
location survey.
The following tasks are carried out in the final location survey.
(a) The centre line is fully marked by pegs at
20m. At each 100 m, a large peg should be
used.
(b)Masonry pillars are built at tangent points of
curves and along the centre line at intervals of
500 m.
(c)Longitudinal and cross levelling is done to
ascertain the final gradient of the alignment.
All gradients are compensated for curves.
(d)The sites for station yards are fully
demarcated.
In the final location survey, the following set of drawings is
prepared.
(a) General map of the country traversed by the
projet at a scale of about 20km to 1cm.
(b) Index map, scale about 2.5 km to 1 cm
(c) Index plan and sections
(d) Detailed plans and sections
(e) Plans and cross section
(f) Plans of station yards
(g) Detailed drawings of structures
(h) Plans of junction arrangements
THANK YOU

More Related Content

What's hot

well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
Arman Hashmi
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Shanmugaraj M
 
NEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODNEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHOD
ADIL BIN AYOUB
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
srinivas2036
 
Bridges: history, forces, and types
Bridges: history, forces, and typesBridges: history, forces, and types
Bridges: history, forces, and types
czachatack
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
Akhilesh Shukla
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
Mani Vel
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
VATSAL PATEL
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
Himanshu Batra
 
Bridges and their types
Bridges and their typesBridges and their types
Bridges and their types
Prof. A.Balasubramanian
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
Sudhan Sathe
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their design
Bhavya Jaiswal
 
Introduction of basic transportation engineering
Introduction of basic transportation engineeringIntroduction of basic transportation engineering
Introduction of basic transportation engineering
Ghan Shyam
 
LOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAYLOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAY
Ghulam Yasin
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Pooja Lonare
 
Railway Engineering: Points and crossings
Railway Engineering: Points and crossingsRailway Engineering: Points and crossings
Railway Engineering: Points and crossings
Bathla Tuition Centre
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
Arbaz Kazi
 
Introduction of bridges
Introduction of bridgesIntroduction of bridges
Introduction of bridges
Shekhar Mehta
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
Souvik Mondal
 
road construction
road constructionroad construction
road construction
Rebwar Anwar
 

What's hot (20)

well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
NEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODNEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHOD
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Bridges: history, forces, and types
Bridges: history, forces, and typesBridges: history, forces, and types
Bridges: history, forces, and types
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
Bridges and their types
Bridges and their typesBridges and their types
Bridges and their types
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their design
 
Introduction of basic transportation engineering
Introduction of basic transportation engineeringIntroduction of basic transportation engineering
Introduction of basic transportation engineering
 
LOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAYLOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAY
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Railway Engineering: Points and crossings
Railway Engineering: Points and crossingsRailway Engineering: Points and crossings
Railway Engineering: Points and crossings
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
 
Introduction of bridges
Introduction of bridgesIntroduction of bridges
Introduction of bridges
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
 
road construction
road constructionroad construction
road construction
 

Similar to Introduction, alignment & surveys

3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway lines
Mani Vel
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Malyar Talash
 
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
EduHUBOnline
 
Railway.pdf
Railway.pdfRailway.pdf
Railway.pdf
abhijitsaha99
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
Gowtham G
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
BalpreetSingh47890
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
ashish502848
 
Track Alignment of Railway Line | Civil TechMate
Track Alignment of Railway Line | Civil TechMateTrack Alignment of Railway Line | Civil TechMate
Track Alignment of Railway Line | Civil TechMate
Civil TechMate
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
IRJET Journal
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieering
Mani Vel
 
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
Er. Bam Bhandari
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
2018kumaranurag
 
ROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYINGROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYING
manashkedia098
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
RESHMAFEGADE
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
RESHMAFEGADE
 
1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf
ShivamKumar423966
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gauge
Mani Vel
 
Transportation engineering 2
Transportation engineering   2Transportation engineering   2
Transportation engineering 2
R VIJAYAKUMAR
 

Similar to Introduction, alignment & surveys (20)

3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway lines
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
 
Railway.pdf
Railway.pdfRailway.pdf
Railway.pdf
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
Track Alignment of Railway Line | Civil TechMate
Track Alignment of Railway Line | Civil TechMateTrack Alignment of Railway Line | Civil TechMate
Track Alignment of Railway Line | Civil TechMate
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieering
 
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
 
R E T 565construction Technology Infrastructure
R E T 565construction Technology InfrastructureR E T 565construction Technology Infrastructure
R E T 565construction Technology Infrastructure
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
ROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYINGROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYING
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gauge
 
Transportation engineering 2
Transportation engineering   2Transportation engineering   2
Transportation engineering 2
 

More from GARRE RAVI KUMAR

Eia for railway project
Eia for railway projectEia for railway project
Eia for railway project
GARRE RAVI KUMAR
 
Railway engineering part3
Railway engineering part3Railway engineering part3
Railway engineering part3
GARRE RAVI KUMAR
 
Railway engineering part2
Railway engineering part2Railway engineering part2
Railway engineering part2
GARRE RAVI KUMAR
 
Railway engineering part1
Railway engineering part1Railway engineering part1
Railway engineering part1
GARRE RAVI KUMAR
 
Introduction to particulate matter
Introduction to particulate matterIntroduction to particulate matter
Introduction to particulate matter
GARRE RAVI KUMAR
 
Air pollution introduction
Air pollution introductionAir pollution introduction
Air pollution introduction
GARRE RAVI KUMAR
 
Kinetics and thermodynamics of air pollutants
Kinetics and thermodynamics of air pollutantsKinetics and thermodynamics of air pollutants
Kinetics and thermodynamics of air pollutants
GARRE RAVI KUMAR
 
Monitoring of Particulate matter
Monitoring of Particulate matterMonitoring of Particulate matter
Monitoring of Particulate matter
GARRE RAVI KUMAR
 
Monitoring of gaseous pollutants
Monitoring of gaseous pollutantsMonitoring of gaseous pollutants
Monitoring of gaseous pollutants
GARRE RAVI KUMAR
 
Methods to control s ox emissions
Methods to control s ox emissionsMethods to control s ox emissions
Methods to control s ox emissions
GARRE RAVI KUMAR
 
Urban heat islands
Urban heat islandsUrban heat islands
Urban heat islands
GARRE RAVI KUMAR
 
Ozone layer depletion
Ozone layer depletionOzone layer depletion
Ozone layer depletion
GARRE RAVI KUMAR
 
Greenhouse effect and global warming
Greenhouse effect and global warmingGreenhouse effect and global warming
Greenhouse effect and global warming
GARRE RAVI KUMAR
 
Effects of air pollutants on plants
Effects of air pollutants on plantsEffects of air pollutants on plants
Effects of air pollutants on plants
GARRE RAVI KUMAR
 
Effects of air pollutants on materials
Effects of air pollutants on materialsEffects of air pollutants on materials
Effects of air pollutants on materials
GARRE RAVI KUMAR
 
Effects of air pollutants on human
Effects of air pollutants on humanEffects of air pollutants on human
Effects of air pollutants on human
GARRE RAVI KUMAR
 
Acid rains
Acid rainsAcid rains
Acid rains
GARRE RAVI KUMAR
 
Episoeds of air pollution
Episoeds of air pollutionEpisoeds of air pollution
Episoeds of air pollution
GARRE RAVI KUMAR
 
General methods to control gaseous pollutants
General methods to control gaseous pollutantsGeneral methods to control gaseous pollutants
General methods to control gaseous pollutants
GARRE RAVI KUMAR
 
Methods to control n ox emissions
Methods to control n ox emissionsMethods to control n ox emissions
Methods to control n ox emissions
GARRE RAVI KUMAR
 

More from GARRE RAVI KUMAR (20)

Eia for railway project
Eia for railway projectEia for railway project
Eia for railway project
 
Railway engineering part3
Railway engineering part3Railway engineering part3
Railway engineering part3
 
Railway engineering part2
Railway engineering part2Railway engineering part2
Railway engineering part2
 
Railway engineering part1
Railway engineering part1Railway engineering part1
Railway engineering part1
 
Introduction to particulate matter
Introduction to particulate matterIntroduction to particulate matter
Introduction to particulate matter
 
Air pollution introduction
Air pollution introductionAir pollution introduction
Air pollution introduction
 
Kinetics and thermodynamics of air pollutants
Kinetics and thermodynamics of air pollutantsKinetics and thermodynamics of air pollutants
Kinetics and thermodynamics of air pollutants
 
Monitoring of Particulate matter
Monitoring of Particulate matterMonitoring of Particulate matter
Monitoring of Particulate matter
 
Monitoring of gaseous pollutants
Monitoring of gaseous pollutantsMonitoring of gaseous pollutants
Monitoring of gaseous pollutants
 
Methods to control s ox emissions
Methods to control s ox emissionsMethods to control s ox emissions
Methods to control s ox emissions
 
Urban heat islands
Urban heat islandsUrban heat islands
Urban heat islands
 
Ozone layer depletion
Ozone layer depletionOzone layer depletion
Ozone layer depletion
 
Greenhouse effect and global warming
Greenhouse effect and global warmingGreenhouse effect and global warming
Greenhouse effect and global warming
 
Effects of air pollutants on plants
Effects of air pollutants on plantsEffects of air pollutants on plants
Effects of air pollutants on plants
 
Effects of air pollutants on materials
Effects of air pollutants on materialsEffects of air pollutants on materials
Effects of air pollutants on materials
 
Effects of air pollutants on human
Effects of air pollutants on humanEffects of air pollutants on human
Effects of air pollutants on human
 
Acid rains
Acid rainsAcid rains
Acid rains
 
Episoeds of air pollution
Episoeds of air pollutionEpisoeds of air pollution
Episoeds of air pollution
 
General methods to control gaseous pollutants
General methods to control gaseous pollutantsGeneral methods to control gaseous pollutants
General methods to control gaseous pollutants
 
Methods to control n ox emissions
Methods to control n ox emissionsMethods to control n ox emissions
Methods to control n ox emissions
 

Recently uploaded

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

Introduction, alignment & surveys

  • 2. Contents covered 1. Different modes of transport 2. Road transport Vs Rail transport 3. Railway alignment 4. Engineering surveys
  • 3. Different Modes ofTransport • Our environment consists of land, air and water. These media have provided scope for three modes of transport— land transport, air transport and water transport. • Rail transport and road transport are the two components of land transport. • Each mode of transport, depending upon its various characteristics, has intrinsic strengths and weaknesses and can be best used for a particular type of traffic as given below.
  • 4. Rail transport versus road transport Features : 1. Tractive Resistance 2. Right ofWay 3. CostAnalysis 4. Gradient andCurves 5. Flexibility of Movements 6. Environmental Pollution 7. Organization andControl 8. Suitability
  • 5. Tractive Resistance RailTransport The movement of steel wheels on the steel has the basic advantage of low rolling resistance.This reduces haulage cost because of low tractive resistance. RoadTransport The tractive resistance of a pneumatic tire on metalled roads is almost five times compared to that of wheels on rails.
  • 6. Right of Way RailTransport A railway track is defined on to rails and I within protected limits.Train woks as per prescribed schedule and no other vehicle has the right of way except at specified level crossing. RoadTransport Roads, though having well defined limits, can be used by any vehicular traffic and even by pedestrian they are open to all.
  • 7. Cost analysis RailTransport Owning to the heavy infrastructure, the initial as well as maintenance cost of railway line is high. RoadTransport The cost of construction and maintenance of roads is comparatively cheaper.
  • 8. Gradient and Curves RailTransport The gradient of railways tracks are flatter (normally not more than 1%) and curves are limited up to only 10 degree on broad gauge. RoadTransport Roads are constructed normally with steeper gradient of up to 4% and relatively much sharper curves.
  • 9. Flexibility of Movement RailTransport Due to the defined route and facilitates required for the reception and dispatch of train, railways can be used only between fixed points. RoadTransport Road transport have much more flexibility in movement and can provide door-to – door services.
  • 10. Environmental Pollution RailTransport Railways have minimum adverse effect on the environment. RoadTransport Road transport create comparatively greater pollution than the railway.
  • 11. Organization and Control RailTransport Railways are government undertaking, with their own organization. RoadTransport Barring member stat government transport, road transport is managed by the private sector.
  • 12. Suitability RailTransport Railways are best suited for carrying heavy goods and large number of passengers over long distance. . RoadTransport Road transport is best suited for carrying lighter goods and smaller number of passenger over shorter distance.
  • 14. Introduction Alignment of railway line refers to the direction and position given to the centre line of the railway track on the ground in the horizontal and vertical planes. Horizontal alignment means the direction of the railway track in the plan including the straight path and the curves it follows. Vertical alignment means the direction it follows in a vertical plane including the level track, gradients, and vertical curves. The various factors affecting alignment, and types of track alignments and their suitability in different terrains are discussed here
  • 15. Importance of Good Alignment A new railway line should be aligned carefully after proper considerations, as improper alignment may ultimately prove to be more costly and may not be able to fulfill the desired objectives. Railway line constructions are capital-intensive projects, once constructed, it is very difficult to change the alignment of a railway line because of the costly structures involved, difficulty in getting additional land for the new alignment, and such other considerations.
  • 21. Basic Requirements of an Ideal Alignment 1.Purpose of the New Railway Line: The alignment of a new railway line should serve the basic purpose for which the railway line is being constructed. As brought out earlier, the purpose may include strategic considerations, political considerations, developing of backward areas, connecting new trade centres, and shortening existing rail lines.
  • 22. 2.Integrated Development The new railway line should fit in with the general planning and form a part of the integrated development of the country. 3.Economic Considerations i)Shortest route - It is desirable to have the shortest and most direct route between the connecting points. The shorter the length of the railway line, the lower the cost of its construction, maintenance, and operation. There can, however, be other practical considerations that can lead to deviation from the shortest route.
  • 23. ii)Construction and maintenance cost - The alignment of the line should be so chosen that the construction cost is minimum. This can be achieved by a balanced cut and fill of earthwork, minimizing rock cutting and drainage crossings by locating the alignment on watershed lines, and such other technical considerations. Maintenance costs can be reduced by avoiding steep gradients and sharp curves, which cause heavy wear and tear of rails and rolling stock. iii)Minimum operational expenses - The alignment should be such that the operational or transportation expenses are minimum. This can be done by maximizing the haulage of goods with the given power of the locomotive and traction mix. This can he achieved by providing easy gradients, avoiding sharp curves, and adopting a direct route
  • 24. iv)Maximum Safety and Comfort The alignment should be such that it provides maximum safety and comfort to the travelling public. This can be achieved by designing curves with proper transition lengths, providing vertical curves for gradients, and incorporating other such technical features. v)Aesthetic Considerations While deciding the alignment, aesthetic aspects should also be given due weightage. A journey by rail should be visually pleasing. This can be done by avoiding views of borrow pits and passing the alignment through natural and beautiful surroundings with scenic beauty.
  • 25. Selection of a Good Alignment Normally, a direct straight route connecting two points is the shortest and most economical route for a railway line, but there are practical problems and other compulsions which necessitate deviation from this route. The various factors involved is the selection of a good alignment for a railway line are given below.
  • 26. 1.Choice of Gauge: The gauge can be a BG (1676 mm), an MG (1000 mm), or even an NG (762 mm). As per the latest policy of the Government of India, new railway lines are constructed on BG only. 2. Obligatory or Controlling Points: These are the points through which the railway line must pass due to political, strategic, and commercial reasons as well as due to technical considerations. The following are obligatory or controlling points.
  • 27. Important cities and towns- These are mostly intermediate important towns, cities, or places which of commercial, strategic, or political importance. Major bridge sites and river crossings - The construction of major bridges for large rivers is very expensive and suitable bridge sites become obligatory points for a good alignment. Existing passes and saddles in hilly terrain - Existing passes and saddles should be identified for crossing a hilly terrain in order to avoid deep cuttings and high banks. Sites for tunnels - The option of a tunnel in place of a deep cut in a hilly terrain is better from the economical viewpoint. The exact site of such a tunnel becomes an obligatory point.
  • 28. 3. Topography of the Country: Plane alignment - When the topography is plane and flat, the alignment presents no problems and can pass through obligatory points and yet have very easy gradients. Valley alignment - The alignment of a railway line in valley is simple and does not pose any problem. If two control points lie in the same valley, a straight line is provided between these points with a uniform gradient.
  • 29. 4. Geometrical Standards: Geometrical standards should be so adopted as to economize as much as possible as well as provide safety and comfort to passengers. This can be done by adopting gradients and curves within permissible limits. Transition as well as vertical curves should be used to provide better comfort and safety. 5.Geological Formation: The alignment should be so selected that it normally runs on good and stable soil formation as far as possible. Weak soil and marshy land present a number of problems including those of maintenance. Though rocky soil, provides a stable formation, it is a costly proposal.
  • 30. 6.Position of Roads and Road Crossings A railway line should cross a road at right angles so as to have a perpendicular level crossing and avoid accidents. 7.Proximity of Labour and Material The availability and proximity of local labour and good and cheap building material should also be considered when deciding the alignment. 8.Location of Railway Stations and Yards Railway stations and yards should be located on level stretches of land, preferably on the outskirts of a town or village so as to have enough area for the free flow of traffic.
  • 31. 9. Religious and Historical Monuments The alignment should avoid religious and historical monuments, as it is normally not possible to dismantle these buildings. 10.Political Considerations: The alignment should take into account political considerations. It should not enter foreign soil and should preferably be away from common border areas.
  • 33. Introduction The construction of a new railway line is a capital-intensive project and each kilometre of a new railway line costs in the range of Rs 6 to 10 million depending upon the topography of the area, the standard of construction, and such other features. It is, therefore, natural that a lot of thought be given when making a final decision as to whether a new railway line is at all necessary or not.
  • 34. Need for Construction of a New Railway Line The need for construction of a new railway line arises because of one or more of the following considerations. (a)Strategic reasons It is sometimes necessary to extend the existing railway line to a new point of strategic importance so that the defence forces can move quickly to the some areas in case of any emergency such as the threat of war. (b)Political reasons A new line sometimes becomes necessary to serve the political needs of the country, for example, the railway line from Pathankot to Jammu.
  • 35. (c)Development of backward areas Railway lines are sometimes constructed to develop backward areas. Experience has shown that once railway communication is available, backward areas develop very fast. The Assam rail link can be classified in this category. (d)To connect new trade centres Sometimes new trade centres are connected with railway lines for the quick transportation of goods between two trade centres or from the point of production to the point of consumption.
  • 36. (e) To shorten the existing rail link: The existing routes between two important points may be longer than required. New railway lines are constructed on a shorter alignment in such cases. A short route is not only economical, but also helps in the faster movement of goods and passengers. The Konkan Railway is a typical example.
  • 37. Types of Surveys The following types of surveys are normally conducted: (a) Traffic survey (b) Reconnaissance survey (c) Preliminary survey (d) Final location survey
  • 38. Traffic survey Traffic survey includes a detailed study of the traffic conditions in the area with a view to determine the Most promising route for the railway in the area, Possible traffic the railway line will carry, and Standard of railway line to be followed.
  • 39. Traffic survey consists of an economic study of the area keeping in mind the following considerations, information on which should be collected in detail: (a) Human resources (b) Agricultural and mineral resources (c) Pattern of trade and commerce (d) Industries located and projected (e) Prospects of tourist traffic (f) Existing transport facilities (g) Locations of important government and private offices (h) Planning for economic development of the area • The traffic survey team should make an assessment of the traffic likely to be carried by to the new line. While carrying out the survey, details of traffic likely to be offered by various government organizations, public bodies, or private enterprises should be gathered
  • 40. Reconnaissance Survey This survey consists of a rapid and rough investigation of the area with a view to determine the technical feasibility of the proposal as well as the rough cost of one or more alternatives to the new line. The reconnaissance survey (RECCE) is normally based on contoured survey maps and other data already available without carrying out detailed investigations in the field. With the help of the maps, different alternative alignments of the new line are studied.
  • 41. Survey Instruments Prismatic compass - Toget magnetic bearings of the proposed alignment. Aneroid barometer - To ensure relative heights of various points. Abney level or hand level or clinometer - To measure the gradients or angles of slopes. Binocular - Toview the physical features. Pedometer - To get an idea of the total length traversed while walking.
  • 42. Preliminary Survey The preliminary survey consists of a detailed instrumental examination of the route to be selected as a result of the reconnaissance survey in order to estimate the cost of the proposed railway line. Based on the preliminary and traffic survey reports, the railway administration decides whether or not the proposed railway line is to be constructed.
  • 43. Instruments for Preliminary Survey (a)Theodolite for traversing and pegging the centre line (b) Tacheometer for plotting the main features (c)Dumpy level for taking the longitudinal and cross levels (d)Plane table for getting details of various features (e)Prismatic compass for measuring the magnetic bearings of a particular alignment
  • 44. Final Location Survey Once a decision has been taken for a particular railway line to be constructed, a final location survey is done. The instruments used are generally the same as in the case of the preliminary survey. Final location survey is done to prepare working details and make accurate cost estimates in certain cases.
  • 45. The principal differences between the preliminary survey and the final survey are as follows. (a) In the final location survey, the alignment is fully staked with the help of a theodolite, whereas it is not obligatory to do so in the case of preliminary survey. (b)In the final location survey, a more detailed project report is prepared and submitted. (c)All working drawings are prepared in the final location survey.
  • 46. The following tasks are carried out in the final location survey. (a) The centre line is fully marked by pegs at 20m. At each 100 m, a large peg should be used. (b)Masonry pillars are built at tangent points of curves and along the centre line at intervals of 500 m. (c)Longitudinal and cross levelling is done to ascertain the final gradient of the alignment. All gradients are compensated for curves. (d)The sites for station yards are fully demarcated.
  • 47. In the final location survey, the following set of drawings is prepared. (a) General map of the country traversed by the projet at a scale of about 20km to 1cm. (b) Index map, scale about 2.5 km to 1 cm (c) Index plan and sections (d) Detailed plans and sections (e) Plans and cross section (f) Plans of station yards (g) Detailed drawings of structures (h) Plans of junction arrangements