SCHOOL OF ARCHITECHURAL, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
Integrated Assignment
Measurement 1(QSB 60104)
Construction Technology 1(BLD 60104)
Building Materials(BLD 62003)
Site Visit Report
STUDENT NAME: CHONG HUI YIK
STUDENT ID: 0326165
DATE OF SUBMISSION: 27/11/2015
Index
NO. TITLE PAGES
1. Introduction & Details 1
2. Objective 2
3. Contents and Technical Observations 3-8
4. Photo Descriptions 9-10
5. Conclusion 11
Introduction
The title of this assignment is technical site visit to site. In this assignment, we
are required to have a site visit and produce a site report for this construction site visit.
This activity was organized by our lecturer, Ms. Ang Fuey Lin. The location of the site
that we visited is at Hulu Selangor. This is an individual assignment which is combining
with 3 subjects. There are Measurement 1, Building Material and Construction
Technology. This construction proposed to build 96 units 2 floors of semi detached
house, there are divided into 3 types, which is 38 units in type 1, 12 units in type 2 which
is (split up & spilt down) and 10 units of type 3.
On 19 November 2015, all of the semester one students have attended the site
visit. We gathered at 8am and set off to the site at 8:30am. We are required to wear
safety helmet, long pants and sport shoes while visit the site construction.
Details of the Construction Site
1) Project: Proposed to build 96 units of semi detached with 2 floors in three types.
2) Building Teams
 Developers: Perbadanan Kemajuan Negeri Selangor (PKNS)
 Architect: Zain Hamzah Architect
 Structural Engineer: Wawasan Bersatu Sdn. Bhd
 Infra Engineer: Wawasan Bersatu Sdn. Bhd
 M&E Engineering: ZNVA & Associated
 Quantity Surveyor: MCM Associates Sdn. Bhd
 Contractor: AJ- Corp Sdn. Bhd
Objective
The objectives of site visit are:
 Understand the basics of the construction process
 Witness the usage of construction equipment on site including mechanical plants.
 Explore and identity various types of building materials and technology on site.
 Awareness of the important of safety on site and understanding of safety
problems and site conditions
 Ability to communicate with the construction team members on site and to feel
the importance of teamwork in the building team.
 To enable students to understand the building structure and the sequences of
constructing a building.
 To let students to experience the actual working environment and know more
about the knowledge on site.
 To gain the knowledge of construction technology and understand about the
construction process.
 Ability to communicate with the construction team members on site and to feel
the importance of teamwork in the building team.
Contents &Technical Observation
At the entrance of the construction site, there is a project information board.The action
of the project information board is to mention the character of the contractor who
involved in the project
At the site, it’s very hot. Therefore, there is providing a small cabin room near the site.
This room is for construction team to discuss or meeting at the site and also a place for
storage doucuments.
The site is divided into 3 types, but we have only visited 2a and 2b area. 2a is higher
level which is required 1200mm excavations starting from reduce level whereas 2b is
lower level which is required 2800mm excavation starting from reduce level . 2a area
has finished pad footing construction but 2b area haven’t start pad footing construction.
The projectinformationboard
the placedat the entrance of
the site.
Accommodationforworkers
Planof the site.
Pad Footing
Introduction
The foundation of a structure is defined as a part of the structure in direct contact with
the ground and which transmits the load of the building to the ground. Foundations can
be classified as shallow and deep foundations. These can be further divided into many
types of foundations.
How to choose a suitable foundation? The main conditions governing the choice of
foundation for a structure comprise:
a) Function of the structure and loads it must carry
b) The sub surface condition
c) Cost of foundation in comparison with cost of the superstructure
Pad Footing
For this construction site, they are using pad footing. Pad footing is used to support
individual or multiple columns, spreading the load to the ground below. They are
generally square or rectangular in plan. The shape in plan will be dictated by the
arrangement of the columns and the load to be transferred into the soil.
Foundation
Shallow
Shallow
Deep
ep
Shallow
Shallow
Shallow
Footing
Shallow
Raft
Shallow
Shallow
Shallow
Strip Pile
Shallow
Pad Footing on site.
How a pad footing is constructed?
Step 1: Site Clearance
Site clearance would include the removal of waste, old foundations, tree stumps, root
balls and hardcore.
Step2: Excavations
Excavate earth to required depth and plan dimensions. Excavate pits to receive pad
footing.
Step3: Pour a layer of lean concrete onthe surface
Step4: Buildthe formwork
Step5: Insert rebar
Add some spacer block, lay the main rebar and transverse rebar. Then, erect the
reinforcement for column stump and add more ties to the formwork.
Step6: Pour concrete intothe formwork.
Step7: Remove formwork
After the concrete has harden and gain sufficient strength, dismantle the formwork.
1.Site Clearance 2.Excavation 3.Lean concrete
4.Formwork 5.Rebar 6.Concrete informwork
7.Formworkremoved
Materials
Concrete
Introduction
Concrete is a major building materials used in building construction. It is used in all parts
of a building like foundations, superstructure and so on. Concrete is a rocklike material
produced by mixing coarse and fines aggregates, cement and water and sometimes
allowing the mixture to be more harden. Some of the additives used are plasticizers,
retarders, accelerators and others admixture. There are 27 types of common cement,
group into 5 categories.
At this construction site, they have used reinforce concrete to construct the building
elements like pad footing. Pad footings are using Grade 30 reinforce concrete. Besides
that, the most important property of concrete is its high compressive strength. Water-
cement ration is the ratio mixing water with the weight of cement used in concrete. The
strength of concrete will increase when the water- cement ratio decreasing.
What is grade???
Grade is a number that indicates the minimum compressive strength gained by the
cement- sand mortar mix in 28 days.
Lean Concrete
Concrete with high water content is considered lean because it has a lower
concentration of cement compared to other kinds of paving and building materials of
that class.A lean concrete mix is measured in pounds per square inch. In the right
conditions, lean concrete flows like a liquid and makes for easy applications. It usually is
not used in cases where more than 2 inches of sub-base or ground clearance is
necessary.Lean concrete is used to provide a level surface, where main foundation (raft,
isolated or any other type) can be placed. The another purpose is to protect to main
foundation from soil below, as moisture or other chemicals in soil like sulphates may
attack concrete and can weaken it.
Type 1 Normal Cement (Most Common)
Type 2 Moderate Sulfate Resistance (Slow- reacting)
Type 3 High Early Strength (Fast- setting)
Type 4 Low heat Hydration (Low heat generation)
Type 5 High Sulfate Resistance
Formwork
Formwork is an ancillary construction, used as a mould for a structure. Into this mould,
fresh concrete is placed only to harden subsequently. The construction of formwork
takes time and involves expenditure up to 20 to 25% of the cost of the structure or even
more. Design of these temporary structures are made to economic expenditure. The
operation of removing the formwork is known as stripping. Stripped formwork can be
reused. Reusable forms are known as panel forms and non-usable are called stationary
forms.
A good formwork should satisfy the following requirements:
1. It should be strong enough to withstand all types of dead and live loads.
2. It should be rigidly constructed and efficiently propped and braced both
horizontally and vertically, so as to retain its shape.
3. The joints in the formwork should be tight against leakage of cement grout.
4. Construction of formwork should permit removal of various parts in desired
sequences without damage to the concrete.
5. The material of the formwork should be cheap, easily available and should be
suitable for reuse.
6. The formwork should be set accurately to the desired line and levels should have
plane surface.
7. It should be as light as possible.
8. The material of the formwork should not warp or get distorted when exposed to
the elements.
9. It should rest on firm base.
Timber is the most common material for formwork and it’s also applied in this
construction site.
Timber for formwork should satisfy the following requirement:
It should be
1. well seasoned
2. light in weight
3. easily workable with nails without splitting
4. free from loose knots
Rebar
Concrete is a material that is very strong in compression, but relatively weak in tension.
To compensate for this imbalance in concrete's behavior, rebar is cast into it to carry the
tensile loads. Rebar is common steel reinforcing bar, an important component of
reinforced concrete. It is usually formed from mild steel, and is given ridges for better
frictional adhesion to the concrete. However, high tensile steel is used in this
construction site and it is Y16. High tensile steel commonly used as a tensioning device
in reinforced concrete and reinforced masonry structures holding the concrete in
compression. It is usually formed from carbon steel, and is given ridges for better
mechanical anchoring into the concrete.
Photo Descriptions
IndependentScaffolding
The workersare removingthe
formwork.
Thisworkeristyingthe stirrupson
rebar.
Workeris drivingonsite with
bigvehicle.
Pilesinsection3
Formwork forfloorslab.
Rebarcage
The instructoris explainingthe planforus.
Conclusion
After visited the site, I’ve learned more useful knowledge about the construction
and how is the things being constructed. I found that it is interesting when I saw the
things like pad footing, rebar, big vehicles, excavated trench and others became real in
front of me instead of only learn them through notes. I’ve learn about how a pad footing
being constructed and how is the formwork removed by worker after the concrete is
harden. I very appreciate that Mr.Mohd. Hafizi Mohammad was leading us and explain
to us patiently. Moreover, I also appreciate that Ms Ang Fuey Lin and Ms Azrina have
organized this activity for us to learn more outside the book.
I found that teamwork is very important. Coorperation and communication
between the workers and contractor is needed. Without teamwork, the construction
building will not be completed on time and won’t process fluency.
Moreover, safety is very important at construction site. Safety helmet is needed
when we visit to construction site to ensure our safety. The safety of a building is also
very important for people who staying inside, our responsible is to provide them a
safety and comfortable building. Therefore, as a professional and responsible building
team, we should not cheating on workmanship and materials.
In a conclusion, I have learned so much things which is became real instead of
only study on notes. I believe that this is a nice experience for us. I feel respect and
appreciate to those workers who willing to work hard under the sun and also the
contractors who are working on site. They are responsible and knowledgable. I wish I
could become a successful quantity surveyor like them. Thank you.

More Related Content

What's hot

Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)Shane Ah
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formworkchaitanyakrsk
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measuressabnisajit
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGAtiq Iqbal
 
Partial Replacement of Steel Reinforcement by Bamboo (G+2)
Partial Replacement of Steel Reinforcement by Bamboo (G+2)Partial Replacement of Steel Reinforcement by Bamboo (G+2)
Partial Replacement of Steel Reinforcement by Bamboo (G+2)vivatechijri
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork adarshkaushik6
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
Concrete framework
Concrete frameworkConcrete framework
Concrete frameworkJustin Myint
 
Site visit report
Site visit reportSite visit report
Site visit reportWen Crystal
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 

What's hot (20)

Formwork
FormworkFormwork
Formwork
 
Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Formwork
FormworkFormwork
Formwork
 
Form Work
Form Work Form Work
Form Work
 
Shuttering (Formwork)
Shuttering (Formwork)Shuttering (Formwork)
Shuttering (Formwork)
 
Assignment 2 edited
Assignment 2 editedAssignment 2 edited
Assignment 2 edited
 
Formwork
FormworkFormwork
Formwork
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formwork
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measures
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERING
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Partial Replacement of Steel Reinforcement by Bamboo (G+2)
Partial Replacement of Steel Reinforcement by Bamboo (G+2)Partial Replacement of Steel Reinforcement by Bamboo (G+2)
Partial Replacement of Steel Reinforcement by Bamboo (G+2)
 
ppt on training civil report on shuttering
ppt on training civil report on shutteringppt on training civil report on shuttering
ppt on training civil report on shuttering
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Concrete framework
Concrete frameworkConcrete framework
Concrete framework
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 

Similar to Site report

Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docxShze Hwa Lee
 
Final Report
Final Report Final Report
Final Report Jack Ng
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Arthur Wilson
 
An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildingshlksd
 
Site visit report
Site visit reportSite visit report
Site visit reportshensin1015
 
Site report
Site reportSite report
Site reportvaylu
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShareYung Kai
 
Site report
Site reportSite report
Site reportEric Teo
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit reportMomo Poyi
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1Jing Chuang
 

Similar to Site report (20)

Site report 1
Site report 1Site report 1
Site report 1
 
Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docx
 
Final Report
Final Report Final Report
Final Report
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Bachelor in quantity surveying 2
Bachelor in quantity surveying 2
 
An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildings
 
Site report
Site reportSite report
Site report
 
Site report
Site reportSite report
Site report
 
Ez
EzEz
Ez
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site report
Site reportSite report
Site report
 
simplex report 2
simplex report 2simplex report 2
simplex report 2
 
Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
 
Site report
Site reportSite report
Site report
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
 

Recently uploaded

Building Dreams: Newman Leech's Visionary Approach to Real Estate Investment
Building Dreams: Newman Leech's Visionary Approach to Real Estate InvestmentBuilding Dreams: Newman Leech's Visionary Approach to Real Estate Investment
Building Dreams: Newman Leech's Visionary Approach to Real Estate InvestmentNewman George Leech
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDFMs Riya
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdfManishSaxena95
 
9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhi9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhidelhimodel235
 
9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhi9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhidelhimodel235
 
Low Rate Call Girls in Triveni Complex Delhi Call 9990771857
Low Rate Call Girls in Triveni Complex Delhi Call 9990771857Low Rate Call Girls in Triveni Complex Delhi Call 9990771857
Low Rate Call Girls in Triveni Complex Delhi Call 9990771857delhimodel235
 
Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
The Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdfThe Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdfkratirudram
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | GurgaonFULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaonsoniya singh
 
9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhi9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhidelhimodel235
 
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...delhimodel235
 
Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...delhimodel235
 
Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)jessica288382
 
Call Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICECall Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICESapana Sha
 
Call girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi Ncr
Call girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi NcrCall girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi Ncr
Call girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi Ncrasmaqueen5
 
Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...
Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...
Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...Newman George Leech
 
Omaxe Dwarka In Delhi E Brochure Pdf
Omaxe Dwarka In Delhi E Brochure     PdfOmaxe Dwarka In Delhi E Brochure     Pdf
Omaxe Dwarka In Delhi E Brochure Pdfashiyadav24
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

Building Dreams: Newman Leech's Visionary Approach to Real Estate Investment
Building Dreams: Newman Leech's Visionary Approach to Real Estate InvestmentBuilding Dreams: Newman Leech's Visionary Approach to Real Estate Investment
Building Dreams: Newman Leech's Visionary Approach to Real Estate Investment
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
 
VIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts Service
VIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts ServiceVIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts Service
VIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts Service
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
 
9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhi9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 10 Noida (Call Girls) Delhi
 
9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhi9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 34 Noida (Call Girls) Delhi
 
Low Rate Call Girls in Triveni Complex Delhi Call 9990771857
Low Rate Call Girls in Triveni Complex Delhi Call 9990771857Low Rate Call Girls in Triveni Complex Delhi Call 9990771857
Low Rate Call Girls in Triveni Complex Delhi Call 9990771857
 
Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Pitampura Delhi 💯Call Us 🔝8264348440🔝
 
Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Inderpuri Delhi 💯Call Us 🔝8264348440🔝
 
The Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdfThe Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdf
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | GurgaonFULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
 
9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhi9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhi
9990771857 Call Girls in Noida Sector 11 Noida (Call Girls) Delhi
 
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
 
Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 12 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
 
Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)Nanke Area Estate commercial ( Dir. Kat Kuo)
Nanke Area Estate commercial ( Dir. Kat Kuo)
 
Call Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICECall Girls in Khan Market 9654467111 ESCORTS SERVICE
Call Girls in Khan Market 9654467111 ESCORTS SERVICE
 
Call girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi Ncr
Call girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi NcrCall girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi Ncr
Call girls in Jeewan Park .Delhi↫8447779280↬ ꧂Escorts Service In Delhi Ncr
 
Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...
Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...
Eco-Efficient Living: Redefining Sustainability through Leech's Green Design ...
 
Omaxe Dwarka In Delhi E Brochure Pdf
Omaxe Dwarka In Delhi E Brochure     PdfOmaxe Dwarka In Delhi E Brochure     Pdf
Omaxe Dwarka In Delhi E Brochure Pdf
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
 

Site report

  • 1. SCHOOL OF ARCHITECHURAL, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) Integrated Assignment Measurement 1(QSB 60104) Construction Technology 1(BLD 60104) Building Materials(BLD 62003) Site Visit Report STUDENT NAME: CHONG HUI YIK STUDENT ID: 0326165 DATE OF SUBMISSION: 27/11/2015
  • 2. Index NO. TITLE PAGES 1. Introduction & Details 1 2. Objective 2 3. Contents and Technical Observations 3-8 4. Photo Descriptions 9-10 5. Conclusion 11
  • 3. Introduction The title of this assignment is technical site visit to site. In this assignment, we are required to have a site visit and produce a site report for this construction site visit. This activity was organized by our lecturer, Ms. Ang Fuey Lin. The location of the site that we visited is at Hulu Selangor. This is an individual assignment which is combining with 3 subjects. There are Measurement 1, Building Material and Construction Technology. This construction proposed to build 96 units 2 floors of semi detached house, there are divided into 3 types, which is 38 units in type 1, 12 units in type 2 which is (split up & spilt down) and 10 units of type 3. On 19 November 2015, all of the semester one students have attended the site visit. We gathered at 8am and set off to the site at 8:30am. We are required to wear safety helmet, long pants and sport shoes while visit the site construction. Details of the Construction Site 1) Project: Proposed to build 96 units of semi detached with 2 floors in three types. 2) Building Teams  Developers: Perbadanan Kemajuan Negeri Selangor (PKNS)  Architect: Zain Hamzah Architect  Structural Engineer: Wawasan Bersatu Sdn. Bhd  Infra Engineer: Wawasan Bersatu Sdn. Bhd  M&E Engineering: ZNVA & Associated  Quantity Surveyor: MCM Associates Sdn. Bhd  Contractor: AJ- Corp Sdn. Bhd
  • 4. Objective The objectives of site visit are:  Understand the basics of the construction process  Witness the usage of construction equipment on site including mechanical plants.  Explore and identity various types of building materials and technology on site.  Awareness of the important of safety on site and understanding of safety problems and site conditions  Ability to communicate with the construction team members on site and to feel the importance of teamwork in the building team.  To enable students to understand the building structure and the sequences of constructing a building.  To let students to experience the actual working environment and know more about the knowledge on site.  To gain the knowledge of construction technology and understand about the construction process.  Ability to communicate with the construction team members on site and to feel the importance of teamwork in the building team.
  • 5. Contents &Technical Observation At the entrance of the construction site, there is a project information board.The action of the project information board is to mention the character of the contractor who involved in the project At the site, it’s very hot. Therefore, there is providing a small cabin room near the site. This room is for construction team to discuss or meeting at the site and also a place for storage doucuments. The site is divided into 3 types, but we have only visited 2a and 2b area. 2a is higher level which is required 1200mm excavations starting from reduce level whereas 2b is lower level which is required 2800mm excavation starting from reduce level . 2a area has finished pad footing construction but 2b area haven’t start pad footing construction. The projectinformationboard the placedat the entrance of the site. Accommodationforworkers Planof the site.
  • 6. Pad Footing Introduction The foundation of a structure is defined as a part of the structure in direct contact with the ground and which transmits the load of the building to the ground. Foundations can be classified as shallow and deep foundations. These can be further divided into many types of foundations. How to choose a suitable foundation? The main conditions governing the choice of foundation for a structure comprise: a) Function of the structure and loads it must carry b) The sub surface condition c) Cost of foundation in comparison with cost of the superstructure Pad Footing For this construction site, they are using pad footing. Pad footing is used to support individual or multiple columns, spreading the load to the ground below. They are generally square or rectangular in plan. The shape in plan will be dictated by the arrangement of the columns and the load to be transferred into the soil. Foundation Shallow Shallow Deep ep Shallow Shallow Shallow Footing Shallow Raft Shallow Shallow Shallow Strip Pile Shallow Pad Footing on site.
  • 7. How a pad footing is constructed? Step 1: Site Clearance Site clearance would include the removal of waste, old foundations, tree stumps, root balls and hardcore. Step2: Excavations Excavate earth to required depth and plan dimensions. Excavate pits to receive pad footing. Step3: Pour a layer of lean concrete onthe surface Step4: Buildthe formwork Step5: Insert rebar Add some spacer block, lay the main rebar and transverse rebar. Then, erect the reinforcement for column stump and add more ties to the formwork. Step6: Pour concrete intothe formwork. Step7: Remove formwork After the concrete has harden and gain sufficient strength, dismantle the formwork. 1.Site Clearance 2.Excavation 3.Lean concrete 4.Formwork 5.Rebar 6.Concrete informwork 7.Formworkremoved
  • 8. Materials Concrete Introduction Concrete is a major building materials used in building construction. It is used in all parts of a building like foundations, superstructure and so on. Concrete is a rocklike material produced by mixing coarse and fines aggregates, cement and water and sometimes allowing the mixture to be more harden. Some of the additives used are plasticizers, retarders, accelerators and others admixture. There are 27 types of common cement, group into 5 categories. At this construction site, they have used reinforce concrete to construct the building elements like pad footing. Pad footings are using Grade 30 reinforce concrete. Besides that, the most important property of concrete is its high compressive strength. Water- cement ration is the ratio mixing water with the weight of cement used in concrete. The strength of concrete will increase when the water- cement ratio decreasing. What is grade??? Grade is a number that indicates the minimum compressive strength gained by the cement- sand mortar mix in 28 days. Lean Concrete Concrete with high water content is considered lean because it has a lower concentration of cement compared to other kinds of paving and building materials of that class.A lean concrete mix is measured in pounds per square inch. In the right conditions, lean concrete flows like a liquid and makes for easy applications. It usually is not used in cases where more than 2 inches of sub-base or ground clearance is necessary.Lean concrete is used to provide a level surface, where main foundation (raft, isolated or any other type) can be placed. The another purpose is to protect to main foundation from soil below, as moisture or other chemicals in soil like sulphates may attack concrete and can weaken it. Type 1 Normal Cement (Most Common) Type 2 Moderate Sulfate Resistance (Slow- reacting) Type 3 High Early Strength (Fast- setting) Type 4 Low heat Hydration (Low heat generation) Type 5 High Sulfate Resistance
  • 9. Formwork Formwork is an ancillary construction, used as a mould for a structure. Into this mould, fresh concrete is placed only to harden subsequently. The construction of formwork takes time and involves expenditure up to 20 to 25% of the cost of the structure or even more. Design of these temporary structures are made to economic expenditure. The operation of removing the formwork is known as stripping. Stripped formwork can be reused. Reusable forms are known as panel forms and non-usable are called stationary forms. A good formwork should satisfy the following requirements: 1. It should be strong enough to withstand all types of dead and live loads. 2. It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape. 3. The joints in the formwork should be tight against leakage of cement grout. 4. Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete. 5. The material of the formwork should be cheap, easily available and should be suitable for reuse. 6. The formwork should be set accurately to the desired line and levels should have plane surface. 7. It should be as light as possible. 8. The material of the formwork should not warp or get distorted when exposed to the elements. 9. It should rest on firm base. Timber is the most common material for formwork and it’s also applied in this construction site. Timber for formwork should satisfy the following requirement: It should be 1. well seasoned 2. light in weight 3. easily workable with nails without splitting 4. free from loose knots
  • 10. Rebar Concrete is a material that is very strong in compression, but relatively weak in tension. To compensate for this imbalance in concrete's behavior, rebar is cast into it to carry the tensile loads. Rebar is common steel reinforcing bar, an important component of reinforced concrete. It is usually formed from mild steel, and is given ridges for better frictional adhesion to the concrete. However, high tensile steel is used in this construction site and it is Y16. High tensile steel commonly used as a tensioning device in reinforced concrete and reinforced masonry structures holding the concrete in compression. It is usually formed from carbon steel, and is given ridges for better mechanical anchoring into the concrete.
  • 11. Photo Descriptions IndependentScaffolding The workersare removingthe formwork. Thisworkeristyingthe stirrupson rebar. Workeris drivingonsite with bigvehicle.
  • 13. Conclusion After visited the site, I’ve learned more useful knowledge about the construction and how is the things being constructed. I found that it is interesting when I saw the things like pad footing, rebar, big vehicles, excavated trench and others became real in front of me instead of only learn them through notes. I’ve learn about how a pad footing being constructed and how is the formwork removed by worker after the concrete is harden. I very appreciate that Mr.Mohd. Hafizi Mohammad was leading us and explain to us patiently. Moreover, I also appreciate that Ms Ang Fuey Lin and Ms Azrina have organized this activity for us to learn more outside the book. I found that teamwork is very important. Coorperation and communication between the workers and contractor is needed. Without teamwork, the construction building will not be completed on time and won’t process fluency. Moreover, safety is very important at construction site. Safety helmet is needed when we visit to construction site to ensure our safety. The safety of a building is also very important for people who staying inside, our responsible is to provide them a safety and comfortable building. Therefore, as a professional and responsible building team, we should not cheating on workmanship and materials. In a conclusion, I have learned so much things which is became real instead of only study on notes. I believe that this is a nice experience for us. I feel respect and appreciate to those workers who willing to work hard under the sun and also the contractors who are working on site. They are responsible and knowledgable. I wish I could become a successful quantity surveyor like them. Thank you.