This paper discusses the importance of establishing a sound schedule basis and ensuring valid risk inputs so as to generate an accurate and realistic schedule risk model. A technique for ensuring both of these criteria is discussed using specific metrics targeted at risk model validation.
www.projectacumen.com
@projectacumen
This white paper covers a new approach to tracking project performance which identifies variance gaps between the baseline plan and actual performance for the project as a whole as well as specific deliverables, contractors, locations, or any other group of activities.
This white paper covers a new approach to tracking project performance which identifies variance gaps between the baseline plan and actual performance for the project as a whole as well as specific deliverables, contractors, locations, or any other group of activities.
A Greedy Heuristic Approach for Sprint Planning in Agile Software DevelopmentIJTET Journal
Abstract— With tremendous growth in electronic commerce, the e-shopping users are facing more and more problems in their day to day life. Most important of them are identity theft and spear phishing attacks. In this paper, we will be addressing those issues by the combined use of Hierarchical Visual Cryptography and keyless image steganography techniques. Firstly, we recommend the use of a certified third party payment gateway, which involves generating image shares using HVCS and secondly we recommend the use of image steganography technique to hide the user’s passphrase or ATM Pin or password in the image share to achieve cheating prevention from malicious insiders of both merchant as well as third party payment gateway. Further, we propose the use of image share as secure SiteKey which prevents spear phishing attack targeting high profile customers.
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareSong Love
Liberty University BUSI 313 quiz 3 complete solutions correct answers slideshare
Four different versions
https://www.coursemerit.com/solution-details/20164/Liberty-University-BUSI-313-quiz-3-complete-solutions-correct-answers-A-work
Technical and programmatic disruptions in project plans don’t need to negatively impact cost, performance or schedule metrics. But traditional approaches to planning are not an adequate defense. This white paper outlines the six steps for building a risk-tolerant schedule using a field proven approach.
In a perfect scenario, the need for either owner or contractor driven claims arguably wouldn't arise. However, in reality, this is rarely the case. This paper introduces a technique that helps with determining root cause of project delays resulting in claims.
Risk management is essential for any significant project. Certain information about key project cost, performance, and schedule attributes are often unknown until the project is underway.
The Cause and Effect Diagram (CAED) organizes and graphically represents the causes of a particular problem. It is also referred to as the Ishikawa Diagram, or Fishbone Diagram. Another definition is: “A graphic tool used to explore and display opinion about sources of variation in a process”
Managing Risk in Agile Development: It Isn’t MagicTechWell
Has the adoption of agile techniques magically erased risk from software projects? When we change the project and product environment by adopting agile, have we tricked ourselves into thinking that risk has been abolished—when it hasn’t? Agile risk management is a continuous process that makes risk management part of how the team works so they get value from the activity. Thomas Cagley suggests that we develop user stories that specifically address risk so it is prioritized, planned, and executed as part of the normal agile cadence. Agile techniques—daily standups, demonstrations, retrospectives, and sprint-planning activities—provide a platform for monitoring and controlling risks. The built-in feedback loops act as a safety net to ensure eyes are continuously looking at what is happening and what could be happening. By constantly evaluating risk, agile processes avoid spending significant time analyzing risks that are not on the horizon, while making it very difficult for an unseen risk to sneak up on your project.
How Traditional Risk Reporting Has Let Us DownAcumen
This white paper discusses risk reporting techniques and ways of interpreting risk analysis results that actually enable the project team to make pro-active changes in reducing their risk exposure.
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
This paper discusses why the emerging 14 Point Schedule Assessment, developed by the Defense Contract Management Agency (DCMA), is fast becoming an established standard within the scheduling community across multiple industries.
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Pedram Danesh-Mand
As a quantitative risk analysis tool, Schedule Risk Analysis enables stakeholders to identify and quantify the project risks and opportunities and, through comparative analysis of possible scenarios, to develop project programmes and budgets with a more level of confidence.
This paper introduces benchmarking as a concept that not only helps provide a framework and a repeatable approach to developing structurally sound schedules (based upon accepted Critical Path/CPM techniques), but equally importantly, bring realism to the schedule.
The Art and Science Behind Successful Risk WorkshopsAcumen
This paper discusses how a well-structured balance of risk process combined with sound workshop facilitation can provide more value to a project’s bottom line than most typically ever realize. Imagine a silver bullet that enables you to objectively determine accurate project costs; contingency; strategic insight into which projects should be considered portfolio inclusion; and how realistic a project plan is. Sound too good to be true? Read on…
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
This paper discusses why the emerging 14 Point Schedule Assessment, developed by the Defense Contract Management Agency (DCMA), is fast becoming an established standard within the scheduling community across multiple industries.
www.projectacumen.com
@projectacumen
U.s. air force probability of program success (po ps) spreadsheet operations ...FrancisYee1
A Risk Methodology Focus Area was formed to address the following objectives:
• Develop a risk methodology that accounts for the various risk sources that threaten the outcome of an acquisition program
• Provide program managers, program executive officers and senior decision makers with a credible and realistic assessment of the risks facing an acquisition program
• Provide a viable alternative to ACAT designations for tailoring program oversight needs
• Lay the foundation for a risk-based approach to allocating resources
• Insert a realistic, credible risk measurement as a dominant factor in major program decisions
• Supplement Expectation Management Agreements with a documented history of risk acceptance, trending, and the impact of mitigation efforts
• Identify other applications such as: source selection, contract structure, contract incentives, etc
A Greedy Heuristic Approach for Sprint Planning in Agile Software DevelopmentIJTET Journal
Abstract— With tremendous growth in electronic commerce, the e-shopping users are facing more and more problems in their day to day life. Most important of them are identity theft and spear phishing attacks. In this paper, we will be addressing those issues by the combined use of Hierarchical Visual Cryptography and keyless image steganography techniques. Firstly, we recommend the use of a certified third party payment gateway, which involves generating image shares using HVCS and secondly we recommend the use of image steganography technique to hide the user’s passphrase or ATM Pin or password in the image share to achieve cheating prevention from malicious insiders of both merchant as well as third party payment gateway. Further, we propose the use of image share as secure SiteKey which prevents spear phishing attack targeting high profile customers.
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareSong Love
Liberty University BUSI 313 quiz 3 complete solutions correct answers slideshare
Four different versions
https://www.coursemerit.com/solution-details/20164/Liberty-University-BUSI-313-quiz-3-complete-solutions-correct-answers-A-work
Technical and programmatic disruptions in project plans don’t need to negatively impact cost, performance or schedule metrics. But traditional approaches to planning are not an adequate defense. This white paper outlines the six steps for building a risk-tolerant schedule using a field proven approach.
In a perfect scenario, the need for either owner or contractor driven claims arguably wouldn't arise. However, in reality, this is rarely the case. This paper introduces a technique that helps with determining root cause of project delays resulting in claims.
Risk management is essential for any significant project. Certain information about key project cost, performance, and schedule attributes are often unknown until the project is underway.
The Cause and Effect Diagram (CAED) organizes and graphically represents the causes of a particular problem. It is also referred to as the Ishikawa Diagram, or Fishbone Diagram. Another definition is: “A graphic tool used to explore and display opinion about sources of variation in a process”
Managing Risk in Agile Development: It Isn’t MagicTechWell
Has the adoption of agile techniques magically erased risk from software projects? When we change the project and product environment by adopting agile, have we tricked ourselves into thinking that risk has been abolished—when it hasn’t? Agile risk management is a continuous process that makes risk management part of how the team works so they get value from the activity. Thomas Cagley suggests that we develop user stories that specifically address risk so it is prioritized, planned, and executed as part of the normal agile cadence. Agile techniques—daily standups, demonstrations, retrospectives, and sprint-planning activities—provide a platform for monitoring and controlling risks. The built-in feedback loops act as a safety net to ensure eyes are continuously looking at what is happening and what could be happening. By constantly evaluating risk, agile processes avoid spending significant time analyzing risks that are not on the horizon, while making it very difficult for an unseen risk to sneak up on your project.
How Traditional Risk Reporting Has Let Us DownAcumen
This white paper discusses risk reporting techniques and ways of interpreting risk analysis results that actually enable the project team to make pro-active changes in reducing their risk exposure.
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
This paper discusses why the emerging 14 Point Schedule Assessment, developed by the Defense Contract Management Agency (DCMA), is fast becoming an established standard within the scheduling community across multiple industries.
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Pedram Danesh-Mand
As a quantitative risk analysis tool, Schedule Risk Analysis enables stakeholders to identify and quantify the project risks and opportunities and, through comparative analysis of possible scenarios, to develop project programmes and budgets with a more level of confidence.
This paper introduces benchmarking as a concept that not only helps provide a framework and a repeatable approach to developing structurally sound schedules (based upon accepted Critical Path/CPM techniques), but equally importantly, bring realism to the schedule.
The Art and Science Behind Successful Risk WorkshopsAcumen
This paper discusses how a well-structured balance of risk process combined with sound workshop facilitation can provide more value to a project’s bottom line than most typically ever realize. Imagine a silver bullet that enables you to objectively determine accurate project costs; contingency; strategic insight into which projects should be considered portfolio inclusion; and how realistic a project plan is. Sound too good to be true? Read on…
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
This paper discusses why the emerging 14 Point Schedule Assessment, developed by the Defense Contract Management Agency (DCMA), is fast becoming an established standard within the scheduling community across multiple industries.
www.projectacumen.com
@projectacumen
U.s. air force probability of program success (po ps) spreadsheet operations ...FrancisYee1
A Risk Methodology Focus Area was formed to address the following objectives:
• Develop a risk methodology that accounts for the various risk sources that threaten the outcome of an acquisition program
• Provide program managers, program executive officers and senior decision makers with a credible and realistic assessment of the risks facing an acquisition program
• Provide a viable alternative to ACAT designations for tailoring program oversight needs
• Lay the foundation for a risk-based approach to allocating resources
• Insert a realistic, credible risk measurement as a dominant factor in major program decisions
• Supplement Expectation Management Agreements with a documented history of risk acceptance, trending, and the impact of mitigation efforts
• Identify other applications such as: source selection, contract structure, contract incentives, etc
The notion of integrating cost, schedule, technical performance, and risk is possible in theory. In practice care is needed to assure credible information is provided to the Program Manager.
Measuring Risk Exposure through Risk Range CertaintyAcumen
A white paper on how to overcome the challenges of project risk exposure reporting. Introducing a new, more meaningful risk metric, Risk Range Certainty (RRC).
Developing Standards for Enterprise Schedule QualityAcumen
This white papers addresses the need to implement a standard for schedule quality and explains how ensuring quality in the IMS (Integrated Master Schedule) can be achieved through a three-step process.
Simplifiying cost and schedule risk analysis with acumen riskAcumen
Schedule risk analysis doesn’t have to be complicated. In this webinar learn how Acumen Risk™ uses a more intuitive approach to evaluating risk to achieve truly integrated cost and schedule risk analysis.
Benchmarking Execution Performance and Earned ValueAcumen
Determining historic PV, BAC, EAC and other EVM measures in order to benchmark for future projects is a valuable technique for ensuring realistic and achievable forecasts. Determining historic EV performance using prior similar projects validates those forecasts. Additionally, the value of benchmarking increases exponentially as the benchmark basis improves. From previous iterations of the schedule to a database of thousands of projects, EVM indicators have a strong correlation with execution performance over time.
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
A webinar presentation with clients from the industries with some of the costliest, most complex projects on earth: Oil & Gas and Energy. Learn how these project teams manage the complexities of engineering, procurement, construction, and regulation using Acumen Fuse. Panelists include Marathon Oil, Florida Power & Light, and other major energy companies.
Acumen has completed the first leg of the World Tour. This presentation is an in-depth overview of Acumen's solutions, as well as several Fuse use cases from Fuse clients
Does Better Scheduling Drive Execution Success?Acumen
Delivered at PMI SCoP's 9th Annual Scheduling Conference, this presentation discusses the results from a recently conducted research project showing the correlation between the quality of a plan and overall project success, as well as a means of assessing schedule quality and forecasting accuracy using metric analysis.
Meet or Exceed Schedule Expectations through Intelligent AccelerationAcumen
Delivered at PMI SCoP's 9th Annual Scheduling Conference, this presentation is an introduction of a new approach which enables a project to undergo iterative "what if" scenarios until a balance between successful acceleration and achievability.
Dr. McNatty Webinar: An Introduction to Acumen 360Acumen
Dr. Dan Patterson delivered a sneak peek presentation of the soon-to-be-released Acumen 360. The presentation was first look at how Acumen 360 is capable of optimizing projects with its revolutionary scenario generating, criteria building and project integrating capabilities.
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
Dr. Dan Patterson presented a one-hour webinar on effective scheduling using metrics analysis. He reviewed some of the common problems found in schedules and the research that backs the claim that, in the end, the schedule drives project success.
Smarter Project Analysis and Improved Project PerformanceAcumen
A seminar presentation on the importance of baseline compliance and how the faster, easier metric, logic and forensic analyzers and informative visualization options of Fuse 2.1 support project performance and success.
Acumen teamed up with PT&C for this seminar presentation which covered the standards and best practices for project scheduling and using the proper framework to analyze schedules.
This presentation was given by Acumen CEO, Dr. Dan Patterson, and Kurt Voytell, Acumen customer and project manager at Constellation Energy. Created for the Oracle Primavera Special Interest Group webinar, it includes a comprehensive overview and a case study of the use of Fuse at Constellation Energy.
Acumen & ARES delivered this presentation on the need to properly build, analyze and cost-load a schedule. Acumen gave a special sneak peek of Fuse 3.0 and 360.
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
A one-hour webinar introducing Acumen 360. Acumen 360 gives you the ability to accelerate time frames effortlessly in seconds. It provides pinpointed focus, intelligent optimization and selects the most efficient means of achieving your schedule goals.
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
An overview of Fuse 3.0. This one-hour webinar presentation focused on providing insight into the advanced project planning quality and execution performance assessment provided by Fuse.
Presented at the 2012 Construction CPM Conference, this presentation walks through the challenges of owner/contractor and JV disputes and reviews solutions and prevention techniques using Fuse.
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAcumen
This webinar presentation walks through a case study on a major capital expenditure project that was able to achieve a faster, risk-adjusted, and still achievable schedule using a combination of schedule and risk analytics based on Acumen's S1>S5 schedule maturity framework.
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Acumen
A presentation on project analysis, visualization and resolution including tips, tools and techniques for improved project intelligence through advanced analytics. Project benchmarking with Acumen Cloud was also introduced.
The Art of the Pitch: WordPress Relationships and SalesLaura Byrne
Clients don’t know what they don’t know. What web solutions are right for them? How does WordPress come into the picture? How do you make sure you understand scope and timeline? What do you do if sometime changes?
All these questions and more will be explored as we talk about matching clients’ needs with what your agency offers without pulling teeth or pulling your hair out. Practical tips, and strategies for successful relationship building that leads to closing the deal.
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdfPeter Spielvogel
Building better applications for business users with SAP Fiori.
• What is SAP Fiori and why it matters to you
• How a better user experience drives measurable business benefits
• How to get started with SAP Fiori today
• How SAP Fiori elements accelerates application development
• How SAP Build Code includes SAP Fiori tools and other generative artificial intelligence capabilities
• How SAP Fiori paves the way for using AI in SAP apps
UiPath Test Automation using UiPath Test Suite series, part 4DianaGray10
Welcome to UiPath Test Automation using UiPath Test Suite series part 4. In this session, we will cover Test Manager overview along with SAP heatmap.
The UiPath Test Manager overview with SAP heatmap webinar offers a concise yet comprehensive exploration of the role of a Test Manager within SAP environments, coupled with the utilization of heatmaps for effective testing strategies.
Participants will gain insights into the responsibilities, challenges, and best practices associated with test management in SAP projects. Additionally, the webinar delves into the significance of heatmaps as a visual aid for identifying testing priorities, areas of risk, and resource allocation within SAP landscapes. Through this session, attendees can expect to enhance their understanding of test management principles while learning practical approaches to optimize testing processes in SAP environments using heatmap visualization techniques
What will you get from this session?
1. Insights into SAP testing best practices
2. Heatmap utilization for testing
3. Optimization of testing processes
4. Demo
Topics covered:
Execution from the test manager
Orchestrator execution result
Defect reporting
SAP heatmap example with demo
Speaker:
Deepak Rai, Automation Practice Lead, Boundaryless Group and UiPath MVP
State of ICS and IoT Cyber Threat Landscape Report 2024 previewPrayukth K V
The IoT and OT threat landscape report has been prepared by the Threat Research Team at Sectrio using data from Sectrio, cyber threat intelligence farming facilities spread across over 85 cities around the world. In addition, Sectrio also runs AI-based advanced threat and payload engagement facilities that serve as sinks to attract and engage sophisticated threat actors, and newer malware including new variants and latent threats that are at an earlier stage of development.
The latest edition of the OT/ICS and IoT security Threat Landscape Report 2024 also covers:
State of global ICS asset and network exposure
Sectoral targets and attacks as well as the cost of ransom
Global APT activity, AI usage, actor and tactic profiles, and implications
Rise in volumes of AI-powered cyberattacks
Major cyber events in 2024
Malware and malicious payload trends
Cyberattack types and targets
Vulnerability exploit attempts on CVEs
Attacks on counties – USA
Expansion of bot farms – how, where, and why
In-depth analysis of the cyber threat landscape across North America, South America, Europe, APAC, and the Middle East
Why are attacks on smart factories rising?
Cyber risk predictions
Axis of attacks – Europe
Systemic attacks in the Middle East
Download the full report from here:
https://sectrio.com/resources/ot-threat-landscape-reports/sectrio-releases-ot-ics-and-iot-security-threat-landscape-report-2024/
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionAggregage
Join Maher Hanafi, VP of Engineering at Betterworks, in this new session where he'll share a practical framework to transform Gen AI prototypes into impactful products! He'll delve into the complexities of data collection and management, model selection and optimization, and ensuring security, scalability, and responsible use.
DevOps and Testing slides at DASA ConnectKari Kakkonen
My and Rik Marselis slides at 30.5.2024 DASA Connect conference. We discuss about what is testing, then what is agile testing and finally what is Testing in DevOps. Finally we had lovely workshop with the participants trying to find out different ways to think about quality and testing in different parts of the DevOps infinity loop.
Essentials of Automations: Optimizing FME Workflows with ParametersSafe Software
Are you looking to streamline your workflows and boost your projects’ efficiency? Do you find yourself searching for ways to add flexibility and control over your FME workflows? If so, you’re in the right place.
Join us for an insightful dive into the world of FME parameters, a critical element in optimizing workflow efficiency. This webinar marks the beginning of our three-part “Essentials of Automation” series. This first webinar is designed to equip you with the knowledge and skills to utilize parameters effectively: enhancing the flexibility, maintainability, and user control of your FME projects.
Here’s what you’ll gain:
- Essentials of FME Parameters: Understand the pivotal role of parameters, including Reader/Writer, Transformer, User, and FME Flow categories. Discover how they are the key to unlocking automation and optimization within your workflows.
- Practical Applications in FME Form: Delve into key user parameter types including choice, connections, and file URLs. Allow users to control how a workflow runs, making your workflows more reusable. Learn to import values and deliver the best user experience for your workflows while enhancing accuracy.
- Optimization Strategies in FME Flow: Explore the creation and strategic deployment of parameters in FME Flow, including the use of deployment and geometry parameters, to maximize workflow efficiency.
- Pro Tips for Success: Gain insights on parameterizing connections and leveraging new features like Conditional Visibility for clarity and simplicity.
We’ll wrap up with a glimpse into future webinars, followed by a Q&A session to address your specific questions surrounding this topic.
Don’t miss this opportunity to elevate your FME expertise and drive your projects to new heights of efficiency.
Elevating Tactical DDD Patterns Through Object CalisthenicsDorra BARTAGUIZ
After immersing yourself in the blue book and its red counterpart, attending DDD-focused conferences, and applying tactical patterns, you're left with a crucial question: How do I ensure my design is effective? Tactical patterns within Domain-Driven Design (DDD) serve as guiding principles for creating clear and manageable domain models. However, achieving success with these patterns requires additional guidance. Interestingly, we've observed that a set of constraints initially designed for training purposes remarkably aligns with effective pattern implementation, offering a more ‘mechanical’ approach. Let's explore together how Object Calisthenics can elevate the design of your tactical DDD patterns, offering concrete help for those venturing into DDD for the first time!
Securing your Kubernetes cluster_ a step-by-step guide to success !KatiaHIMEUR1
Today, after several years of existence, an extremely active community and an ultra-dynamic ecosystem, Kubernetes has established itself as the de facto standard in container orchestration. Thanks to a wide range of managed services, it has never been so easy to set up a ready-to-use Kubernetes cluster.
However, this ease of use means that the subject of security in Kubernetes is often left for later, or even neglected. This exposes companies to significant risks.
In this talk, I'll show you step-by-step how to secure your Kubernetes cluster for greater peace of mind and reliability.
When stars align: studies in data quality, knowledge graphs, and machine lear...
Improved Schedule Risk Analysis through Metric Assessment
1. // Improved Schedule Risk Analysis
(SRA) through Metric Assessment
Enhanced Schedule Delay Forensics through Project Metrics and Ribbon Analysis
Dr. Dan Patterson, PMP
CEO & President, Acumen
February 2010
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com
2. Table of Contents
Contents ...................................................................................................................... 2
Introduction ................................................................................................................. 3
Background to Schedule Risk Analysis ................................................................ 3
How Does a Monte Carlo Schedule Risk Analysis (SRA) Work? ............................. 3
Figure 1 – SRA Analysis and the Changing Critical Path ......................... 4
Figure 2 – SRA Showing a 36% Chance of Achieving Completion Date.... 5
Creating a Risk-Ready Schedule ................................................................................. 5
Sound Logic ......................................................................................................... 5
Figure 3 – Example Schedule with Missing Successor on Task 1 ............. 6
Figure 4 – Flawed Risk results due to Missing Logic ................................ 6
Minimal Use of Constraints ................................................................................. 6
Figure 5 – Constraints Invalidating a Network Path During a SRA ........... 7
Other Criteria for Risk-Ready Schedules .............................................................. 7
Risk-Check Metric Analysis ......................................................................................... 7
Figure 6 – Analysis of Schedule Assessing Risk-Readiness ..................... 7
Figure 7 – Example of Risk Input Metrics being applied to a Project........ 8
Figure 8 – Analysis of Risk Inputs Looking at Average Risk Range .......... 9
Risk Exposure Metric Analysis ..................................................................................... 9
Figure 9 – Risk Exposure Analysis by Discipline ....................................... 9
Figure 10 – Risk Exposure Analysis by Discipline ................................... 10
Figure 11 – Risk Hot Spots ..................................................................... 11
Concluding Comments .............................................................................................. 11
Additional Information ............................................................................................... 11
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 2
3. Introduction
This paper discusses the importance of establishing a sound schedule basis and ensuring valid
risk inputs so as to generate an accurate and realistic schedule risk model. A technique for
ensuring both of these criteria is discussed using specific metrics targeted at risk model
validation.
Once a risk analysis is completed, interpreting the results can often be a challenge. This is
especially true within large projects, and so a complimentary approach to interpreting risk
results, pinpointing true risk exposure, understanding when in time the project is at greatest
risk and providing this in a language that is easy to relay to the project team and stakeholders
is also discussed.
Background to Schedule Risk Analysis
Schedule Risk Analysis (SRA) is fast becoming an integral part of project planning.
Instead of forecasting a single deterministic completion date through CPM scheduling, more
and more projects are now leaning towards providing a range of completion dates within the
context of a given confidence level. The technique for calculating such information is based on
an accepted approach using a Monte Carlo analysis. This simulates all possible outcomes in
light of what is known as scope uncertainty and risk events (the two primary sources of
schedule risk).
Unlike other forms of Monte Carlo simulation, a SRA is highly dependent on the structure and
quality of the project schedule itself. In fact, the outputs from a SRA are dependent on two
moving parts:
1. The project schedule: the CPM schedule containing activities, logic links, calendars,
resources and other standard components that make up a CPM schedule.
2. The risk inputs: ranges of uncertainty and discrete risk events typically provided by the
project team that get overlaid onto the schedule prior to running an analysis.
How Does a Monte Carlo Schedule Risk Analysis (SRA) Work?
A SRA analysis is an evolution of a traditional CPM analysis. Rather than each activity having a
single duration value, activities carry a range of durations (often described as a three point
distribution e.g. min, most likely, max values). During each run of a simulation, values are
sampled from the defined ranges of each activity duration and are then applied to a CPM
analysis (calculating early and late dates). Subsequent simulations are then run so that a
representative range of possible outcomes is established giving the analyst a confidence level
surrounding project completion dates.
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 3
4. SRA is different to standard Monte Carlo analysis in that a delay on an activity does not
necessarily result in a delay to the overall project. An activity with 10 days of float may incur up
to 10 days of risk delay without actually becoming critical (and thus impacting the project
completion). For simple networks this may seem like an obvious statement but apply this to
large schedules with multiple parallel and interlinking paths and the equation can really only be
solved through simulation.
Even more significant than the duration of a schedule changing, is the changing of the location
of the critical path itself! Activities that may be non critical in the deterministic schedule often
can become critical due to risk. Figure 1 shows a schedule with 2 parallel paths. Task 3 is on
the critical path with tasks 1 and 2 having 2 days of float. During a risk simulation, Tasks 1 and
2 may incur delay due to risk which in turn will make their sequence of work longer than task 3,
thus forcing them onto the critical path. In iteration 1, Task 1 and 2 have high float (non critical)
whereas in iteration 2, risk actually causes them to become critical with Task 3 ending up with
3 days of float.
Deterministic Schedule
Risk Iteration #1
Risk Iteration #2
Task 1 & 2 now
critical
Figure 1 – SRA Analysis and the Changing Critical Path
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 4
5. When enough of these simulations are run, a distribution of results can be seen as per figure 2.
36% Confidence
Figure 2 – SRA Results Showing a 36% Chance of Achieving the Deterministic Completion Date
Creating a Risk-Ready Schedule
All too often, a SRA is run against a schedule that cannot sustain a valid risk analysis. That is,
the schedule has structural flaws in it that prohibits a sound simulation to be run.
After spending the last decade working in the field of risk management and facilitating
countless risk workshops, the most common question asked is, “Is my schedule ready for a
risk analysis?” In reality, the answer is very simple: if the schedule is of sound integrity then it is
ready for a risk analysis. Because SRA is little more than running a CPM time analysis, albeit
running it thousands of times (see previous section), the criteria for a sound risk analysis are
really the same as those required for a sound schedule.
Risk-ready schedules should have certain characteristics. Some of these are described below:
Sound Logic
The backbone of a sound CPM schedule is the sequence of activities and the links between
them (precedence logic). Omit these and the dates calculated by the CPM engine become
overly optimistic and schedule forecasts become unrealistic. Equating this to a risk analysis,
any activities that have, for example, open ends (missing logic) and are exposed to schedule
delay due to risk will not have a true knock-on effect on any successor activities and thus the
impact of the risk will not be reflected in the schedule.
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 5
6. Take the example schedule shown in figure 1 and let’s consider the impact of Task 1 having
missing logic. Everything in this new scenario is the same except there is a missing FS relation
between Task 1 and Task 2. When the SRA is run, any delay on Task 1 will have zero impact
on the rest of the schedule because it is ‘open ended’. What may seem like a minor flaw in the
schedule has a massive negative impact on the risk results – in effect making them invalid.
Missing Successor
Figure 3 – Example Schedule with Missing Successor on Task 1
Figure 4 is now wrongly reporting that our example project has a 57% chance of completion on
time (was originally 36%). In short: the results are overly optimistic due to the missing logic.
Overly Optimistic
Confidence Level
Figure 4 – Flawed Risk results due to Missing Logic
Minimal Use of Constraints
The use of constraints generally goes against the principle of CPM analysis (as the CPM
calculation cannot freely calculate dates because the activities are already artificially held in
place with the constraint). This is an even bigger issue for SRA. Again, take our example
project from figure 1 but this time consider task 2 having a constraint applied to it. By adding
an artificial constraint to Task 2, during the SRA iterations, any knock-on effect of task 1 being
delayed does not get reflected through to task 2, in essence making that network path
irrelevant to the risk analysis. Any upstream delay gets reflected as negative float rather than
being cascaded down through to the end of the project as a true delay.
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 6
7. Deterministic
Negative
float
created
due
to
Risk Iteration #1
constraint
Figure 5 – Constraints Invalidating a Network Path During a SRA
Other Criteria for Risk-Ready Schedules
There are numerous other checks that should be applied to a schedule in order to validate that
it is risk ready. These include but are not limited to:
• Consistent Level of Detail
• Appropriate use of Calendars
• Avoidance of Lags
Risk-Check Metric Analysis
To help with such validation, a library of risk-check metrics has been developed based on over
ten years of research and hands-on experience with developing risk models. These risk-check
metrics are now an integral part of Acumen Fuse and should be used when validating any
schedule prior to running a SRA.
Figure 6 shows an example Fuse analysis looking at whether a schedule is sound and is risk
ready or not prior to an analysis. By grouping activities (and analyzing) by the likes of project
discipline, we can quickly pinpoint which areas of the schedule need addressing.
Pinpointed Hard
Constraints
Figure 6 – Analysis of Schedule Assessing Risk-Readiness
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 7
8. In addition to validating the schedule, a second library of risk-check metrics has been
developed that actually validates and critiques the risk inputs themselves! Anyone with
experience of SRA will know that the results can quickly be changed (read ‘skewed’) simply by
going back and ‘tweaking’ or adjusting the risk inputs. While SRA is a powerful analysis, it is
terribly prone to the inputs fed into the model.
To help give structure and provide a framework for objective and accurate risk range inputs,
new metrics have been developed. Examples of some of the checks include looking at those
activities that have one-way risk ranges or flagging those activities that have a large
percentage of aggressive risk ranges (ranges that indicate large downside but little scope for
upside).
Typically, if there are a large number of overly-aggressive or conservative activities, then this is
an indication that the underlying schedule estimates may need to be revised (or the team aren’t
bought into the schedule).
Additional checks (metrics) include looking at the range of uncertainty. Those activities that
have a very broad risk range should be re-estimated and reviewed prior to a risk analysis.
Likewise, activities with very large uncertainty range skews often reflect the presence of a risk
event. This then becomes an issue if risk events are also being tracked in a risk register as their
impact ends up getting ‘double-counted’ in a risk analysis.
Aggressive Engineering
Activities
Figure 7 – Example of Risk Input Metrics Applied to a Project
One of the most valuable forms of risk input validation is to look at the project team’s
perception of risk over the entire duration of the project. By examining risk input metrics such
as average risk range, we can determine whether the team need to revisit their inputs either
with respect to a specific discipline or for a specific period of time.
Figure 8 shows an example project being analyzed for average risk range. The early stages of
the project have a low average risk range but then this increases dramatically in late 2010
before dropping back down in 2012. Further, by looking at average risk range by discipline
(through the ribbons), the construction discipline can be seen to carry the largest perceived risk
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 8
9. range. This type of insight is invaluable when it comes to determining which areas/periods
within a project to focus risk reduction efforts.
Increased Risk
Range
Figure 8 – Analysis of Risk Inputs Looking at Average Risk Range
Risk Exposure Metric Analysis
In addition to analyzing the quality of the schedule and the quality of the risk inputs, metrics
can also be used to interpret the results from a risk analysis (i.e. risk exposure).
Hidden
Critical
Path
Figure 9 – Risk Exposure Analysis by Discipline
Figure 9 shows various risk exposure metrics including:
• High criticality: those activities that often fall on the critical path (thus having an impact
on the completion date of the project).
• Risk Hot Spots: activities that are high risk and that have a high number of successors.
These characteristics combined are an indication of a risk hot spot that should be
monitored very closely and ideally eliminated.
• High Contingency: Those activities that require a large amount of contingency in order
to resolve them.
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 9
10. • Hidden Paths: those activities that are not on the critical path but become critical due to
risk.
Figure 10 – Risk Exposure Analysis by Discipline
Further, looking at risk exposure over time is a very useful insight. Figure 10 shows the average
criticality (an indication of risk exposure) over time. Interestingly, the number of activities with
high criticality is higher at the start of the project than at the end. This is showing a front-end
loaded risk schedule. In reality, it means that it is extremely important that risk control and
mitigation measures are put in place early in the project otherwise these up-front risks will have
a hard-to-recover impact on the rest of the project.
Even more interesting is the fact that when we re-review the team’s risk inputs (figure 8), the
perception of risk was actually back-end loaded towards the end of the project. In reality, the
most risk is actually front-end loaded. How can this be given the team provided larger risk
ranges towards the end of the project? The explanation for this lies in the structure and logic of
the project. While the early activities may have smaller ranges, due to their logic and inter
dependences, they actually are more prone to risk exposure than some of the latter activities
that are carrying more float.
In addition, one further time-phased metric looking at risk hot spots shows that these lie not
only in the early phases of the project but also that they lie specifically within the engineering
discipline.
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com 10
11. Engineering Carrying
Risk Hot Spots
Figure 11 – Risk Hot Spots
This type of insight can only be obtained through metric analysis and is an excellent example
of how true risk exposure can be understood by slicing and dicing schedule and risk data
through ribbons and metrics.
Concluding Comments
Schedule Risk Analysis (SRA) is a powerful forecasting technique yet relies heavily on having a
sound basis of schedule and accurate risk inputs. Through the combined use of schedule-
check and risk-check metrics, risk models can now be validated prior to a risk analysis,
ensuring that the results generated are sound and representative of the project’s true risk
exposure.
By slicing and dicing projects by ribbons and phases using analysis tools such as Acumen
Fuse, a unique insight into the root causes of schedule delay, risk hot spots and areas of focus
for mitigation can now be identified.
Additional Information
Acumen specializes in project analytics and is the author of Acumen Fuse, a project
assessment tool. More information on project assessment through metric analysis and Fuse
can be found at www.projectacumen.com/fuse or by calling +1 512 291 6261.