SlideShare a Scribd company logo
// Measuring Risk Exposure through
       Risk Range Certainty (RRC)
          Overcoming the Shortcomings of Schedule Confidence Levels




         Dr. Dan Patterson, PMP
          CEO & President, Acumen

              October 2009




                           +1 512 291 6261 // info@projectacumen.com

                                    www.projectacumen.com
Table of Contents
Introduction ..................................................................................................................... 3

Traditional Risk Metrics ................................................................................................... 3
   Confidence Level .......................................................................................................... 3
          Figure 1 – Low Schedule Confidence Level............................................................ 4
   Risk Contingency ......................................................................................................... 4
   Joint Confidence Level .................................................................................................. 5
          Figure 2 – Reporting JCL ....................................................................................... 5
   Why is a high JCL Target Almost Impossible to Achieve? .............................................. 5

An Alternate Solution: Risk Range Certainty (RRC) .......................................................... 6
          Figure 3 – Risk Range Certainty (RRC) Reporting ................................................. 6

Conclusion ....................................................................................................................... 7

Additional Information ..................................................................................................... 7




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                        2
Introduction
This paper discusses the use of an alternate risk exposure metric called Risk Range
Certainty (RRC). This metric has been developed due to risk reporting biases resulting
from focus on risk confidence level and Joint Confidence Level (JCL).

Schedule confidence level is often used as a risk indicator and recently, Joint
Confidence Level (JCL) has evolved from this to tie both cost and schedule risk
exposure together. However, in practice, schedule confidence level and JCL suffer from
a schedule risk characteristic known as merge bias that causes these metrics to be
heavily skewed towards the pessimistic. As such, when using a JCL as a target, we are
potentially setting ourselves up for failure by targeting a goal that is extremely difficult to
achieve. This paper discusses how Risk Range Certainty (RRC) can be used to
overcome this issue and provide a more realistic and true picture of project risk
exposure.


Traditional Risk Metrics
First, consider three risk metrics: confidence level, contingency and Joint Confidence
Level.

Confidence Level
Confidence level is the probability of achieving a given target (typically a given finish
date or target budget cost). In isolation of each other, confidence levels have some
value in determining risk exposure, yet all too often can give misleading results.

Schedule confidence level has a major flaw: CPM schedules inherently carry low
confidence levels somewhat irrespective of the project’s risk level. The reason is this:

A sound CPM schedule will contain a single start milestone, a single finish milestone
and potentially multiple paths in between with at least one (longest) path known as the
critical path. Each and every one of the various paths through the CPM network
ultimately has to converge through to the completion milestone. As a result, when risk
analysis is conducted on a CPM schedule, the probability of all of the various paths
leading to the completion milestone coming in on time is small – this is known as
merge bias. It is analogous to a coin toss. Consider an experiment where we are
tasked with tossing a coin five times and asked the probability of landing five
consecutive heads. The result is not 50% but instead 50%*50%*50%*50*50% or
3.125%. Likewise, if our schedule has only five parallel paths in it, even with, say a
symmetrical +/- 10%, range of uncertainty, the chance of all these paths not impacting
the finish milestone is again well down in the single digits. Reporting a 3% confidence
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       3
on a project whose activities have been risk loaded with an equal chance of being early
or late is hard to defend. As such, schedule confidence level should be used with
caution. Experience with tens and tens of major CAPEX projects each containing
several thousand activities has shown that a schedule confidence level of between 10
and 20% is quiet reasonable yet this percentage would normally (yet perhaps falsely)
ring alarm bells with a project manager or company board room.




                                   4% confidence




                         Figure 1 – Low Schedule Confidence Level

Figure 1 shows risk results for an example project with a very tight risk range applied to
it (-10/+20%) with a resultant confidence level of 4%. This low confidence level is
largely driven by the high number of parallel paths in the schedule and not the risk
inputs.

Risk Contingency
Risk Contingency is also a commonly used metric to determine risk exposure.
Contingency is always represented within the context of a given confidence level. The
amount of required contingency needed on a project at say a very aggressive 20%
confidence is going to be less than the required contingency on the same project at a
much less risky P80 level. Risk-appetite for the project drives the confidence level
against which contingency is reported.

While contingency is a powerful risk metric, is does little for addressing the root cause
of risk but instead acts as a buffer against risk – it is more risk acceptance than risk
reduction. Conversely, risk mitigation is a pro-active risk response technique that truly

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                        4
attempts to reduce risk exposure and thus reducing the amount of additional required
contingency.

Joint Confidence Level
JCL is a risk metric that gives a probability of achieving a combined target schedule
confidence and target cost confidence. Based on the combination of cost and schedule
confidence (described above), it can be used as a target risk level for which a project to
achieve. In theory, this is an excellent approach as it ensures we don’t focus risk
reduction efforts solely in one dimension (cost or schedule) at the expense or neglect of
the other. In practice, it is an extremely difficult target to achieve.




                                   Figure 2 – Reporting JCL

Figure 2 shows an example JCL report in the form of a scatter diagram where the target
cost and schedule confidence levels have been set to 70%. As a result, the combined
probability of achieving a 70% JCL in this example is 62%. It should be understood that
a target JCL of 70% does NOT mean a target schedule confidence level of 70% and a
respective target cost confidence level of 70%. Instead, the JCL is calculated by
determining the percentage of risk simulation iterations that achieve both a given
cost/schedule confidence level. In short: cost/schedule P70 confidence does not
equate to a P70 JCL.

Why is a high JCL Target Almost Impossible to Achieve?
As described above, JCL is dependent on two factors: cost and schedule confidence
level. As we’ve already seen, schedule confidence suffers heavily from merge bias and
so basing JCL so heavily around schedule confidence level results in very skewed
results.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       5
Even if we consider a project with a very high cost confidence (say 90%) with activities
that have an equal chance of being early or late, when we calculate the JCL, we are left
with a very low percentage JCL. Thus tasking a project with a JCL of say 70% is
extremely aggressive and depending on the complexity of the project, close to
impossible to truly achieve.


An Alternate Solution: Risk Range Certainty (RRC)
Traditional risk range is defined as the difference between the best and worse case
scenarios from a risk analysis (otherwise known as the difference between the P100
and P0 results). Risk range is an extremely valuable risk metric as it gives a true
indication to the degree of risk exposure.

Taking this a step further, if we represent the range as a percentage of the remaining
work left in the project, we give context against the remaining scope of work. A three-
month risk range represents a very different risk exposure on a six-month project to
that of the same range on say a ten year project. Representing range as a percentage,
therefore, overcomes this.

To introduce Risk Range Certainty (RRC), consider the example two-year project in
figure 3 whose schedule risk range is calculated as 138 days. 138 days on a remaining
two years worth of work equates to 19% risk range on the remaining duration – that is
to say, the remaining duration on the project may vary by up to 19%. With 19% range
uncertainty, we may also view this as having 81% schedule risk range certainty (RRC).
With only a 19% range of risk, reporting this as 81% schedule certainty gives a truer
indication of the risk exposure for schedule. What is more useful? Reporting 4%
confidence or having insight into the fact that we have 81% range certainty in our
project.

                                   138 days range,
                                   81% Risk Range
                                     Confidence



                              4% confidence




                      Figure 3 – Risk Range Certainty (RRC) Reporting
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                         6
Conclusion
Reporting risk exposure through the likes of confidence levels and statistical analysis
can be challenging especially to a project audience that is focused on finite and
deterministic goals. Add to this the fact that schedule confidence is driven not only by
risk but more significantly by the structure of the schedule (parallel paths) and the task
of successful risk reporting quickly becomes a major problem.

Understanding both cost and schedule risk exposure is without doubt a necessity but
tying these together through the product of these percentages is highly questionable as
explained above.

These issues can be largely overcome by reporting risk in a manner that gives true
meaning and context. As a result, the Risk Range Certainty (RRC) factor is experiencing
a highly favorable response within project teams and executives alike.


Additional Information
Acumen specializes in project analytics and is the author of Acumen Fuse™, a project
assessment tool. More information on project assessment through metric analysis, risk
assessment and Fuse™ can be found at www.projectacumen.com or by calling +1 512
291 6261.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       7

More Related Content

What's hot

Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Glen Alleman
 
Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk management
Glen Alleman
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Association for Project Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Russell Taylor BEng CEng FAPM FIET
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
Mike Tulkoff
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMR
Glen Alleman
 
Risk Adjusted Estimating Techniques
Risk Adjusted Estimating TechniquesRisk Adjusted Estimating Techniques
Risk Adjusted Estimating Techniques
Government Contract Pricing Summit
 
Introduction to NetRisk
Introduction to NetRiskIntroduction to NetRisk
Introduction to NetRisk
Tessa Broek
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk management
Glen Alleman
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Song Love
 
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Association for Project Management
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)
Glen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
Glen Alleman
 
Project risk management
Project risk managementProject risk management
Project risk management
Er Swati Nagal
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
Glen Alleman
 
Transforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty managementTransforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty management
Hani Saad
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk Management
Glen Alleman
 
QRA for overall project risk - Dr David Hillson
QRA for overall project risk - Dr David HillsonQRA for overall project risk - Dr David Hillson
QRA for overall project risk - Dr David Hillson
Association for Project Management
 

What's hot (20)

Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)
 
Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk management
 
RISK EVALUATION-1
RISK EVALUATION-1RISK EVALUATION-1
RISK EVALUATION-1
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMR
 
Risk Adjusted Estimating Techniques
Risk Adjusted Estimating TechniquesRisk Adjusted Estimating Techniques
Risk Adjusted Estimating Techniques
 
Introduction to NetRisk
Introduction to NetRiskIntroduction to NetRisk
Introduction to NetRisk
 
Analyzing the data
Analyzing the dataAnalyzing the data
Analyzing the data
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk management
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
 
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
Adam Suchley - Predictive Delivery Assurance - APM Assurance SIG Conference 2018
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
 
Transforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty managementTransforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty management
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk Management
 
QRA for overall project risk - Dr David Hillson
QRA for overall project risk - Dr David HillsonQRA for overall project risk - Dr David Hillson
QRA for overall project risk - Dr David Hillson
 

Similar to Measuring Risk Exposure through Risk Range Certainty

The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
Acumen
 
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk AnalysisAdopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Ricardo Viana Vargas
 
Risk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projectsRisk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projects
Advisian
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
Glen Alleman
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project Management
Venkatesh Ganapathy
 
Ignou 10 no. project
Ignou 10 no. projectIgnou 10 no. project
Ignou 10 no. project
AnupamDubey34
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Mihai Buta
 
Risk And Uncertainty Lecture 2
Risk And Uncertainty Lecture 2Risk And Uncertainty Lecture 2
Risk And Uncertainty Lecture 2Muhammad Ijaz Syed
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
Mudassir Iqbal
 
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docx
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docxRisk and Procurement ManagementDr Paul BaguleyClass Slides.docx
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docx
lillie234567
 
Payback model of risk management by Dr. B. J. Mohite
Payback model of risk management by Dr. B. J. MohitePayback model of risk management by Dr. B. J. Mohite
Payback model of risk management by Dr. B. J. Mohite
Zeal Education Society, Pune
 
Stephen cresswell risk are we missing a trick - 25th june
Stephen cresswell   risk are we missing a trick - 25th juneStephen cresswell   risk are we missing a trick - 25th june
Stephen cresswell risk are we missing a trick - 25th june
Association for Project Management
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
Mohamed Salah Eldien Mohamed Ali
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Pedram Danesh-Mand
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
Glen Alleman
 
SPM3.pptx
SPM3.pptxSPM3.pptx
SPM3.pptx
AnjanaS53
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
mohamed Ismail
 

Similar to Measuring Risk Exposure through Risk Range Certainty (20)

The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
 
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk AnalysisAdopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
 
Risk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projectsRisk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projects
 
Ch 12
Ch 12Ch 12
Ch 12
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
Druker
DrukerDruker
Druker
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project Management
 
Pm 6
Pm 6Pm 6
Pm 6
 
Ignou 10 no. project
Ignou 10 no. projectIgnou 10 no. project
Ignou 10 no. project
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 
Risk And Uncertainty Lecture 2
Risk And Uncertainty Lecture 2Risk And Uncertainty Lecture 2
Risk And Uncertainty Lecture 2
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docx
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docxRisk and Procurement ManagementDr Paul BaguleyClass Slides.docx
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docx
 
Payback model of risk management by Dr. B. J. Mohite
Payback model of risk management by Dr. B. J. MohitePayback model of risk management by Dr. B. J. Mohite
Payback model of risk management by Dr. B. J. Mohite
 
Stephen cresswell risk are we missing a trick - 25th june
Stephen cresswell   risk are we missing a trick - 25th juneStephen cresswell   risk are we missing a trick - 25th june
Stephen cresswell risk are we missing a trick - 25th june
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
SPM3.pptx
SPM3.pptxSPM3.pptx
SPM3.pptx
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
 

More from Acumen

Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
Acumen
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
Acumen
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
Acumen
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
Acumen
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
Acumen
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
Acumen
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Acumen
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
Acumen
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
Acumen
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
Acumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
Acumen
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
Acumen
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
Acumen
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
Acumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
Acumen
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
Acumen
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
Acumen
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Acumen
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Acumen
 

More from Acumen (20)

Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 

Recently uploaded

一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
obyzuk
 
how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.
DOT TECH
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
marketing367770
 
how can I sell/buy bulk pi coins securely
how can I sell/buy bulk pi coins securelyhow can I sell/buy bulk pi coins securely
how can I sell/buy bulk pi coins securely
DOT TECH
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
DOT TECH
 
how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.
DOT TECH
 
US Economic Outlook - Being Decided - M Capital Group August 2021.pdf
US Economic Outlook - Being Decided - M Capital Group August 2021.pdfUS Economic Outlook - Being Decided - M Capital Group August 2021.pdf
US Economic Outlook - Being Decided - M Capital Group August 2021.pdf
pchutichetpong
 
where can I find a legit pi merchant online
where can I find a legit pi merchant onlinewhere can I find a legit pi merchant online
where can I find a legit pi merchant online
DOT TECH
 
how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.
DOT TECH
 
how to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchangehow to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchange
DOT TECH
 
can I really make money with pi network.
can I really make money with pi network.can I really make money with pi network.
can I really make money with pi network.
DOT TECH
 
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
muslimdavidovich670
 
Instant Issue Debit Cards
Instant Issue Debit CardsInstant Issue Debit Cards
Instant Issue Debit Cards
egoetzinger
 
The European Unemployment Puzzle: implications from population aging
The European Unemployment Puzzle: implications from population agingThe European Unemployment Puzzle: implications from population aging
The European Unemployment Puzzle: implications from population aging
GRAPE
 
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Godwin Emmanuel Oyedokun MBA MSc ACA ACIB FCTI FCFIP CFE
 
Pensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdf
Pensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdfPensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdf
Pensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdf
Henry Tapper
 
what is the future of Pi Network currency.
what is the future of Pi Network currency.what is the future of Pi Network currency.
what is the future of Pi Network currency.
DOT TECH
 
一比一原版(UoB毕业证)伯明翰大学毕业证如何办理
一比一原版(UoB毕业证)伯明翰大学毕业证如何办理一比一原版(UoB毕业证)伯明翰大学毕业证如何办理
一比一原版(UoB毕业证)伯明翰大学毕业证如何办理
nexop1
 
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Quotidiano Piemontese
 
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptxSWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
Godwin Emmanuel Oyedokun MBA MSc ACA ACIB FCTI FCFIP CFE
 

Recently uploaded (20)

一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
一比一原版(GWU,GW毕业证)加利福尼亚大学|尔湾分校毕业证如何办理
 
how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
 
how can I sell/buy bulk pi coins securely
how can I sell/buy bulk pi coins securelyhow can I sell/buy bulk pi coins securely
how can I sell/buy bulk pi coins securely
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
 
how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.
 
US Economic Outlook - Being Decided - M Capital Group August 2021.pdf
US Economic Outlook - Being Decided - M Capital Group August 2021.pdfUS Economic Outlook - Being Decided - M Capital Group August 2021.pdf
US Economic Outlook - Being Decided - M Capital Group August 2021.pdf
 
where can I find a legit pi merchant online
where can I find a legit pi merchant onlinewhere can I find a legit pi merchant online
where can I find a legit pi merchant online
 
how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.
 
how to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchangehow to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchange
 
can I really make money with pi network.
can I really make money with pi network.can I really make money with pi network.
can I really make money with pi network.
 
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
 
Instant Issue Debit Cards
Instant Issue Debit CardsInstant Issue Debit Cards
Instant Issue Debit Cards
 
The European Unemployment Puzzle: implications from population aging
The European Unemployment Puzzle: implications from population agingThe European Unemployment Puzzle: implications from population aging
The European Unemployment Puzzle: implications from population aging
 
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
 
Pensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdf
Pensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdfPensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdf
Pensions and housing - Pensions PlayPen - 4 June 2024 v3 (1).pdf
 
what is the future of Pi Network currency.
what is the future of Pi Network currency.what is the future of Pi Network currency.
what is the future of Pi Network currency.
 
一比一原版(UoB毕业证)伯明翰大学毕业证如何办理
一比一原版(UoB毕业证)伯明翰大学毕业证如何办理一比一原版(UoB毕业证)伯明翰大学毕业证如何办理
一比一原版(UoB毕业证)伯明翰大学毕业证如何办理
 
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
 
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptxSWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
 

Measuring Risk Exposure through Risk Range Certainty

  • 1. // Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels Dr. Dan Patterson, PMP CEO & President, Acumen October 2009 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents Introduction ..................................................................................................................... 3 Traditional Risk Metrics ................................................................................................... 3 Confidence Level .......................................................................................................... 3 Figure 1 – Low Schedule Confidence Level............................................................ 4 Risk Contingency ......................................................................................................... 4 Joint Confidence Level .................................................................................................. 5 Figure 2 – Reporting JCL ....................................................................................... 5 Why is a high JCL Target Almost Impossible to Achieve? .............................................. 5 An Alternate Solution: Risk Range Certainty (RRC) .......................................................... 6 Figure 3 – Risk Range Certainty (RRC) Reporting ................................................. 6 Conclusion ....................................................................................................................... 7 Additional Information ..................................................................................................... 7 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2
  • 3. Introduction This paper discusses the use of an alternate risk exposure metric called Risk Range Certainty (RRC). This metric has been developed due to risk reporting biases resulting from focus on risk confidence level and Joint Confidence Level (JCL). Schedule confidence level is often used as a risk indicator and recently, Joint Confidence Level (JCL) has evolved from this to tie both cost and schedule risk exposure together. However, in practice, schedule confidence level and JCL suffer from a schedule risk characteristic known as merge bias that causes these metrics to be heavily skewed towards the pessimistic. As such, when using a JCL as a target, we are potentially setting ourselves up for failure by targeting a goal that is extremely difficult to achieve. This paper discusses how Risk Range Certainty (RRC) can be used to overcome this issue and provide a more realistic and true picture of project risk exposure. Traditional Risk Metrics First, consider three risk metrics: confidence level, contingency and Joint Confidence Level. Confidence Level Confidence level is the probability of achieving a given target (typically a given finish date or target budget cost). In isolation of each other, confidence levels have some value in determining risk exposure, yet all too often can give misleading results. Schedule confidence level has a major flaw: CPM schedules inherently carry low confidence levels somewhat irrespective of the project’s risk level. The reason is this: A sound CPM schedule will contain a single start milestone, a single finish milestone and potentially multiple paths in between with at least one (longest) path known as the critical path. Each and every one of the various paths through the CPM network ultimately has to converge through to the completion milestone. As a result, when risk analysis is conducted on a CPM schedule, the probability of all of the various paths leading to the completion milestone coming in on time is small – this is known as merge bias. It is analogous to a coin toss. Consider an experiment where we are tasked with tossing a coin five times and asked the probability of landing five consecutive heads. The result is not 50% but instead 50%*50%*50%*50*50% or 3.125%. Likewise, if our schedule has only five parallel paths in it, even with, say a symmetrical +/- 10%, range of uncertainty, the chance of all these paths not impacting the finish milestone is again well down in the single digits. Reporting a 3% confidence +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3
  • 4. on a project whose activities have been risk loaded with an equal chance of being early or late is hard to defend. As such, schedule confidence level should be used with caution. Experience with tens and tens of major CAPEX projects each containing several thousand activities has shown that a schedule confidence level of between 10 and 20% is quiet reasonable yet this percentage would normally (yet perhaps falsely) ring alarm bells with a project manager or company board room. 4% confidence Figure 1 – Low Schedule Confidence Level Figure 1 shows risk results for an example project with a very tight risk range applied to it (-10/+20%) with a resultant confidence level of 4%. This low confidence level is largely driven by the high number of parallel paths in the schedule and not the risk inputs. Risk Contingency Risk Contingency is also a commonly used metric to determine risk exposure. Contingency is always represented within the context of a given confidence level. The amount of required contingency needed on a project at say a very aggressive 20% confidence is going to be less than the required contingency on the same project at a much less risky P80 level. Risk-appetite for the project drives the confidence level against which contingency is reported. While contingency is a powerful risk metric, is does little for addressing the root cause of risk but instead acts as a buffer against risk – it is more risk acceptance than risk reduction. Conversely, risk mitigation is a pro-active risk response technique that truly +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4
  • 5. attempts to reduce risk exposure and thus reducing the amount of additional required contingency. Joint Confidence Level JCL is a risk metric that gives a probability of achieving a combined target schedule confidence and target cost confidence. Based on the combination of cost and schedule confidence (described above), it can be used as a target risk level for which a project to achieve. In theory, this is an excellent approach as it ensures we don’t focus risk reduction efforts solely in one dimension (cost or schedule) at the expense or neglect of the other. In practice, it is an extremely difficult target to achieve. Figure 2 – Reporting JCL Figure 2 shows an example JCL report in the form of a scatter diagram where the target cost and schedule confidence levels have been set to 70%. As a result, the combined probability of achieving a 70% JCL in this example is 62%. It should be understood that a target JCL of 70% does NOT mean a target schedule confidence level of 70% and a respective target cost confidence level of 70%. Instead, the JCL is calculated by determining the percentage of risk simulation iterations that achieve both a given cost/schedule confidence level. In short: cost/schedule P70 confidence does not equate to a P70 JCL. Why is a high JCL Target Almost Impossible to Achieve? As described above, JCL is dependent on two factors: cost and schedule confidence level. As we’ve already seen, schedule confidence suffers heavily from merge bias and so basing JCL so heavily around schedule confidence level results in very skewed results. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5
  • 6. Even if we consider a project with a very high cost confidence (say 90%) with activities that have an equal chance of being early or late, when we calculate the JCL, we are left with a very low percentage JCL. Thus tasking a project with a JCL of say 70% is extremely aggressive and depending on the complexity of the project, close to impossible to truly achieve. An Alternate Solution: Risk Range Certainty (RRC) Traditional risk range is defined as the difference between the best and worse case scenarios from a risk analysis (otherwise known as the difference between the P100 and P0 results). Risk range is an extremely valuable risk metric as it gives a true indication to the degree of risk exposure. Taking this a step further, if we represent the range as a percentage of the remaining work left in the project, we give context against the remaining scope of work. A three- month risk range represents a very different risk exposure on a six-month project to that of the same range on say a ten year project. Representing range as a percentage, therefore, overcomes this. To introduce Risk Range Certainty (RRC), consider the example two-year project in figure 3 whose schedule risk range is calculated as 138 days. 138 days on a remaining two years worth of work equates to 19% risk range on the remaining duration – that is to say, the remaining duration on the project may vary by up to 19%. With 19% range uncertainty, we may also view this as having 81% schedule risk range certainty (RRC). With only a 19% range of risk, reporting this as 81% schedule certainty gives a truer indication of the risk exposure for schedule. What is more useful? Reporting 4% confidence or having insight into the fact that we have 81% range certainty in our project. 138 days range, 81% Risk Range Confidence 4% confidence Figure 3 – Risk Range Certainty (RRC) Reporting +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6
  • 7. Conclusion Reporting risk exposure through the likes of confidence levels and statistical analysis can be challenging especially to a project audience that is focused on finite and deterministic goals. Add to this the fact that schedule confidence is driven not only by risk but more significantly by the structure of the schedule (parallel paths) and the task of successful risk reporting quickly becomes a major problem. Understanding both cost and schedule risk exposure is without doubt a necessity but tying these together through the product of these percentages is highly questionable as explained above. These issues can be largely overcome by reporting risk in a manner that gives true meaning and context. As a result, the Risk Range Certainty (RRC) factor is experiencing a highly favorable response within project teams and executives alike. Additional Information Acumen specializes in project analytics and is the author of Acumen Fuse™, a project assessment tool. More information on project assessment through metric analysis, risk assessment and Fuse™ can be found at www.projectacumen.com or by calling +1 512 291 6261. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7