SlideShare a Scribd company logo
1 of 6
Download to read offline
Programmatic
Risk
Management
Risk Management is How
Adults Manage Projects

Glen B. Alleman
Niwot Ridge, LLC
glen.alleman@niwotridge.com
March
Risk Management is How Adults Manage Projects†
                                                                                                                          2008
                                                                                      1
Risk management is essential for the success of any significant project. Information about key project cost,
performance, and schedule attributes is often unknown until the project is underway. Risks identified early in the
project that impacts the project later are often termed “known unknowns.” These risks can be mitigated, reduced,
or retired with a risk management process. For risks that are beyond the vision of the project team, a properly
implemented risk management process can also rapidly quantify the risks impact and provide sound plans for
mitigating their affects.
   Risk management is concerned with the outcome of a future event. Events whose impacts are unknown. Risk
management is about dealing with this uncertainty. Outcomes are categorized as favorable or unfavorable. Risk
management is the art and science of planning, assessing, handling, and monitoring future events to ensure
favorable outcomes. A good risk management process is proactive and fundamentally different than reactive issue
management or problem solving.
      This paper describes the fundamentals of Risk Management with 5 simple concepts:
1. Hope is not a strategy – Hoping that something positive happens or something negative will not happen does
   not lead to success. Preparing for success is the basis of success.
2. All single point estimates are wrong – Single point estimates of cost, schedule, and technical performance are
   no better than 50/50 guesses in the absence of knowledge about the variances of the underlying distribution.
3. Without integrating Cost, Schedule, and Technical Performance, you are driving in the rearview mirror. The
   effort to produce the product or service and the resulting value cannot be made without making these
   connections.
4. Without a model for risk management, you are driving in the dark with the headlights off – Risk management is
   not an ad hoc process that you can make up as you go. A formal foundation for risk management is needed.
   Choose one that has worked in high-risk domains – defense, nuclear power, manned spaceflight, or examples.
5. Risk Communication is everything – Identifying risks without communicating them is a waste of time for all the
   participants.
    Risk management is an important skill that can be applied to a wide variety of projects. In an era of downsizing,
consolidation, shrinking budgets, increasing technological sophistication, and shorter development times, risk
management provides valuable insight to help key project personnel plan for risks. It alerts them to potential risk
issues, which can then be analyzed, and plans develop, implemented, and monitored to address risks before they
surface as issues and adversely affect project cost, performance, and schedule.
Hope is Not a Strategy
   Hoping that the project will proceed as planned is not a strategy for success. Project managers who constantly
seek ways to eliminate or control risk, variance and uncertainly are engaging in a hopeless pursuit.
   Managing “in the presence” of risk, variance, and uncertainty is the key to success. Some projects have few
uncertainties –only the complexity of tasks and relationships is important – but most projects are characterized by
several types of uncertainty. Although each uncertainty type is distinct, a single project may encounter some
                           2
combination of four types:
1. Variation – comes from many small influences and yields a range of values in a particular activity. Attempting to
   control these variances outside their natural boundaries is a waste of time.
2. Foreseen Uncertainties – are identifiable and understood influences that the team cannot be sure will occur.
   There needs to be a mitigation plan for these foreseen uncertainties.
3. Unforeseen Uncertainties – can’t be identified during project planning. When these occur, a new plan is
   needed.
4. Chaos – appears in the presence of “unknown unknowns” and must be addressed through a replanning
   process.

1
    “Risk Management during Requirements,” Tom DeMarco and Tim Lister, IEEE Software, September/October, 2003
2
    “Managing Project Uncertainty: From Variation to Chaos,” Arnoud De Meyer, Christoph H. Loch and Michael T. Pich, MIT Sloan Management
   Review, Winter 2002
† “How Much Risk is Too Much Risk,” Tim Lister, Boston SPIN, 20 January 2004
           2    Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
March
Risk Management is How Adults Manage Projects†
                                                                                                                                 2008
    Plans are strategies for the successful completion of the project. Plans are different than schedules. Schedules
show “how” the project will be executed. Plans show “what” accomplishments must be performed and the success
criteria for these accomplishments along the way to completion.
   The Plan describes the increasing maturity of the project
through assessment points. The unit of measure for this
maturity must be meaningful to the stakeholders.
Something that can be connected to the investment they
have made in the project.
    When we speak the word “Hope,” it lays the foundation
for failure. In the use of Hope, we really mean “success is
possible but not probable.” When we speak the word
                                                                   Figure 1 – The Plan for the project must assure risk is being
“Plan,” it does not assure success, but success is a probable      reduced in proportion to the project’s tolerance for risk
outcome. It is the definition of the probability of success
P(s), that is the foundation of the Plan. Having a Plan–A, Plan–B, and possibly a Plan–C exposes risk, assigns
                                                        3
mitigations, and measures the probability of success.
   The idea of a Plan as a Strategy is critical to making changes in the behavior of the project teams that can lead
to “risk adjusted project management.” Without a Plan, the schedule is simply a list of activities to be performed.
The reason for their performance may be understood, but it is unlikely these activities fit in any cohesive Strategy.
Strategies have goals, critical success factors, and key performance indicators. Project Strategies – the Master Plan
– must also contain goals, critical success factors, and key performance indicators that assure the project is making
physical progress in the presence of uncertainty in cost, schedule, and technical performance.
No Single Point Estimate of Cost, Schedule or Technical Performance Can Correct
   How long will this take? How much is it going to cost? Will the product or service meet the requirements that
are defined for any specific point in time? What is the confidence in those numbers? These are three questions
that must be answered for the project team to have a credible discussion with the stakeholders about success.
Deciding what accuracy is needed to provide a credible answer is a starting point. But that does not address the
question – “how can that accuracy be obtained.”
   There are many checklists for estimating cost and schedule, with simple guidance on how to build estimates.
Most of this advice is wrong in a fundamental way. The numbers produced by the estimating process do not have
their variance defined in any statistically sound manner. By statistically sound it means that the underlying
probability distributions are known. If they are not known, then some form of estimating taking this unknown into
account must be used.
    The Project Management Institute (PMI) advices producing three estimates – optimistic, most likely,
pessimistic. But these numbers are fraught with error. We can’t
tell how these numbers were arrived at? Are they based on
best engineering judgment? Based in historical data? What is
                                                          nd
the variance on the variance of this distribution – the 2
standard deviation? In the absence of this information, they are
of little use in estimating risk.
    The use of point estimates for duration and cost is the first
approach in an organization low on the project management
maturity scale. Understanding that cost and durations are
actually “random variables,” drawn from an underlying
distribution of possible value is the starting point for managing
in the presence of uncertainty.
                                                                                       Figure 2 – triangle distributions are useful when there is
                                                                                       limited information about the characteristics of the
                                                                                       random variables are all that is available.
3
  “Probability of Success Operations Guide, Acquisition, Logistics & Technology Enterprise Systems & Services, Office of the Assistant Security of
the Army for Acquisition
         3    Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
March
Risk Management is How Adults Manage Projects†
                                                                                                        2008
   In probability theory, every random variable is attributed to a probability distribution. The probability
distribution associated with cost or duration describes the variance of these random variables. A common
distribution of probabilistic estimates for cost and schedule is the Triangle Distribution.
   The Triangle Distribution in Figure 2 can be used as a subjective description of a population for which there is
only limited sample data, and especially where the relationship between variables is known but data is scarce. It is
based on the knowledge of the minimum and maximum and a “best guess” of the modal value (the Most Likely).
   Using the Triangle Distribution for cost and duration, a Monte Carlo simulation of the network of activities and
their costs can be performed. In technical terms, Monte Carlo methods numerically transform and integrate the
posterior quantitative risk assessment into a confidence interval. The result is a “confidence” model for the cost
and completion times for the project based on the upper and lower bounds of each distribution assigned to the
duration and cost.
Integrating Cost, Schedule, and Technical Performance
   In many project management methods – cost, schedule, and quality
are described as an “Iron Triangle.” Change one and the other two
must change. This is too narrow a view of what's happening on a
project. It’s the Technical Performance Measurement that replaces
Quality. Quality is one Technical Performance measure.
   Cost and Schedule are obvious elements of the project. Technical
Performance Measures (TPM) describes the status of technical
achievement of the project at any point in time. The planned technical
achievement is part of the Performance Measurement Baseline (PMB).
    The Technical Performance Measurement System (TPMS) uses the
                                                                        Figure 3 – the “new” triangle must be used.
techniques of risk analysis and probability to provide project managers
                                                                        One where cost, schedule, and technical
with the early warnings needed to avoid unplanned costs and slippage    performance are interconnected.
in schedule. Systems engineering uses technical performance
measurements to balance cost, schedule, and performance throughout the project life cycle.
   Connecting Cost, Schedule, and Technical Performance Measures closes the loop on how well a project is
achieving its technical performance requirements while maintaining its cost and schedule goals. IEEE 1220, EIA
632, and "A Guide to the Project Management Body of Knowledge“all provide guidance for TPM planning and
                                                                                                      4
measurement and for integrating TPM with cost and schedule performance measures (Earned Value).
   Technical performance measurements compare actual versus planned technical development and design. They
report the degree to which system requirements are met in terms of performance, cost, schedule, and progress in
implementing risk retirement. Technical Performance Measures are traceable to user–defined capabilities.
Integrating these three attributes produce a Performance Measurement Baseline that:
 Is a plan driven by product quality requirements rather than work or effort requirements?
 Focuses on technical maturity and quality, in addition to cost and schedule.
 Focuses on progress toward meeting success criteria of technical reviews.
 Enables insightful variance analysis.
 Ensures a lean and cost–effective approach to project planning and controls.
 Enables scalable scope and complexity depending on risk.
 Integrates risk management activities with the performance measurement baseline.
 Integrates risk management outcomes into the Estimate at Completion.
   The Cost and Schedule “measures” are straightforward in most cases. The measures of Technical Performance
involve measures Effectiveness and Performance.
   Measures of Effectiveness (MOE) are the operational mission success factor defined by the customer. These
are:


4
    Performance Based Earned Value, Paul Solomon and Ralph Young, John Wiley & Sons, 2006.

           4    Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
March
Risk Management is How Adults Manage Projects†
                                                                                                            2008
1.    Stated from the customer point of view
2.    Focused on the most critical mission performance needs
3.    Independent of any particular solution
4.    Actual measures at the end of development
     Measures of Performance (MOP) characterize physical or functional attributes relating to the system operation:
5.   Supplier’s point of view
6.   Measured under specified testing or operational conditions
7.   Assesses delivered solution performance against critical system level specified requirements
8.   Risk indicators that are monitored progressively
Programmatic Risk Must Follow a Well Defined Process
    Using an ad hoc risk management process is its self risky. The
first place to start to look for risk management processes is where
managing risk is mandatory – aerospace, defense, and mission
critical projects and projects. These also include ERP and
Enterprise IT projects.
    Technical performance is a concept absent from the traditional
approaches to risk management. Yet it is the primary driver of risk
in many technology intensive projects. Cost growth and schedule
slippage often occur when unrealistically high levels of
performance are required and little flexibility is provided to
degrade performance during the course of the project. Quality is    Figure 4 – this risk management process is the “gold
                                                                    standard.” Anything less is inviting additional risk.
often a cause rather than an impact to the project and can
generally be broken down into Cost, Performance, and Schedule components.
      The framework shown in Figure 4 provides guidance for:
    Risk management policy
    Risk management structure
    Risk Management Process Model
    Organizational and behavioral considerations for implementing risk management
    The performance dimension of consequence of occurrence
    The performance dimension of Monte Carlo simulation modeling
    A structured approach for developing a risk handling strategy
Risk Communication
   To be effective the activities of risk management must properly communicate risk to all the participants. Risk is
usually a term to be avoided in normal business. Being in the risk management business is not desirable in most
businesses – except insurance. It is common to “avoid” the discussion of risk.
    Communicating risk is the first step in managing risk. Listing the risks and making them public is necessary but
far from sufficient. Risk communication is the basis of risk mitigation and retirement. It serves no purpose to have
a risk management plan and the defined mitigations in the absence of a risk communication.
   The Risk Management Plan must address:
 Executive summary – a short summary of the project and the risks associated with the activities of the project.
  Each risk needs an ordinal rank, a planned mitigation is the risk is active (a risk approved by the Risk Board), and
  the mitigations shown in the schedule with associated costs.
 Project description – a detailed description of the project and the risk associated with each of the deliverables.
 Risk reduction activities by phase – using some formal risk management process that connects risk, mitigation
  and the IMS. The efforts for mitigation need to be in the schedule.




          5   Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
March
Risk Management is How Adults Manage Projects†
                                                                                                                             2008
                                                                                                                  5
 Risk management methodology – using the DoD Risk Management process is a good start. This approach is
  proven and approved by high risk, high reward projects. The steps in the processes are not optional and should
  be executed for ALL risk processes.
   In order to communicate risk, a clear and concise language is
needed. English is not the best choice. Ambiguity and
interpretation are two issues. Communicating in mathematical
terms is also a problem, since the symbols and units of measure
may be confusing.
                                                      6
    Figure 5 is from the Active Risk Manager tool that connects
risk management with the scheduling system. ARM is a proprietary
risk management system, but illustrates how risk is retired over
time in accordance with a plan. The concept shows explicitly when
each risk will be “bought down” or “retired” during the project
execution. The Risk Registry and the Integrated Master Schedule
must be connected in some way. Without this connection, there is
no Risk Management process that can be used to forecast impacts
on cost or schedule.                                                                  Figure 5 – this risk retirement waterfall shows
                                                                                      where in the plan risk will be mitigated or retired.
    At each project maturity point, current risks, the planned
retirements of these risks, and the impact of the project must be
visible in the schedule. With these connections, project managers can then answer the questions:
 What happens if this risk is not retired?
 What effort is needed to retire this risk before a specific point in time?
 If this risk becomes an issue, what is Plan-B? How much will Plan-B cost? What is the impact of Plan-B on the
   deliverables?
 What cost and schedule reserve is needed to cover all the currently active risks?
Wrap Up
    Once cost, schedule, and techncial performance are integrated into the Performance Measurement Baseline,
risk management can be applied to all three elements. With these connections in place, the project management
team can say with confidence – “we are doing risk management on this project.”
   The final reminder is to make sure all five elements of risk management are present. Leaving one out not only
reduces the effectiveness of the risk management process, but increases in the risk to the project. Project risk
management is a Practice. The theory of Project Risk Management is important, but the Practice is how project risk
gets managed.
    Risk Management Process
                                             Without identifying all risk, providing mitigations and retirement plans, and having
    Hope is not a strategy
                                             Plan-B’s for all risks, hope is the only result
                                             Each value for cost, duration, and technical performance is actually a random variable.
    Single point estimates are wrong         Knowing the underlying probability distribution is the start of understanding the
                                             impact of this randomness on the success of the project
    Integrate Cost, Schedule, and            Managing the tradeoffs between these three dependent variables is the role of project
    Technical Performance                    management in the presence of uncertainty
    Use a Formal Risk Management             Following the guidance of proven methods is simply good project management. Go it
    Process                                  alone, or making it up as you go is simply poor project management
                                             In order to “manage in the presence of uncertainty” all participates must be on the
    Risk Communication is everything         same page. Communication is the glue that engages all the participants in the
                                             conversation about managing in the presence of risk.



5
    Risk Management Guide for DoD Acquisition 2003 (Fifth Edition, Version 2.0), www.dau.mil/pubs/gbbks/risk_management.asp
6
    www.strategicthought.com
           6    Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503

More Related Content

What's hot

Introduction to the Logical Framework Approach
Introduction to the Logical Framework ApproachIntroduction to the Logical Framework Approach
Introduction to the Logical Framework ApproachDamien Sweeney
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk ManagementKelvin Fredson
 
Business risk assessment
Business risk assessmentBusiness risk assessment
Business risk assessmentUzair Khan
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniquesMarco De Santis, PMP, CFPP
 
Risk Management
Risk ManagementRisk Management
Risk Managementrajuinstru
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2Anand Bobade
 
Lecture 06: Advanced Project Management Project Organization and Integration
Lecture 06: Advanced Project Management  Project Organization and IntegrationLecture 06: Advanced Project Management  Project Organization and Integration
Lecture 06: Advanced Project Management Project Organization and IntegrationFida Karim 🇵🇰
 
Pmbok 6 th Edition
Pmbok 6 th EditionPmbok 6 th Edition
Pmbok 6 th EditionAshraf Ali
 
Project Cycle Management
Project Cycle Management Project Cycle Management
Project Cycle Management Mohammed Yaqub
 
Lecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-IntroductionLecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-IntroductionFida Karim 🇵🇰
 
Introduction to Participatory Monitoring-Evaluation
Introduction to Participatory Monitoring-EvaluationIntroduction to Participatory Monitoring-Evaluation
Introduction to Participatory Monitoring-EvaluationFIDAfrique-IFADAfrica
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management NotesHaris Hassan
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
16. MIS for Project Monitoring and Evaluation
16. MIS for Project Monitoring and Evaluation 16. MIS for Project Monitoring and Evaluation
16. MIS for Project Monitoring and Evaluation ifadseahub
 

What's hot (20)

Risk management
Risk managementRisk management
Risk management
 
Introduction to the Logical Framework Approach
Introduction to the Logical Framework ApproachIntroduction to the Logical Framework Approach
Introduction to the Logical Framework Approach
 
CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
Risk appetite
Risk appetite Risk appetite
Risk appetite
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
Risk ITTO
Risk ITTORisk ITTO
Risk ITTO
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
Business risk assessment
Business risk assessmentBusiness risk assessment
Business risk assessment
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniques
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2
 
Lecture 06: Advanced Project Management Project Organization and Integration
Lecture 06: Advanced Project Management  Project Organization and IntegrationLecture 06: Advanced Project Management  Project Organization and Integration
Lecture 06: Advanced Project Management Project Organization and Integration
 
Pmbok 6 th Edition
Pmbok 6 th EditionPmbok 6 th Edition
Pmbok 6 th Edition
 
Project Cycle Management
Project Cycle Management Project Cycle Management
Project Cycle Management
 
Lecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-IntroductionLecture 01: Advanced Project Management-Introduction
Lecture 01: Advanced Project Management-Introduction
 
Introduction to Participatory Monitoring-Evaluation
Introduction to Participatory Monitoring-EvaluationIntroduction to Participatory Monitoring-Evaluation
Introduction to Participatory Monitoring-Evaluation
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management Notes
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
16. MIS for Project Monitoring and Evaluation
16. MIS for Project Monitoring and Evaluation 16. MIS for Project Monitoring and Evaluation
16. MIS for Project Monitoring and Evaluation
 

Similar to Risk Management is Essential for Project Success

Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)Glen Alleman
 
Risk management 4th in a series
Risk management 4th in a seriesRisk management 4th in a series
Risk management 4th in a seriesGlen Alleman
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)Glen Alleman
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy PiecesGlen Alleman
 
Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule riskGlen Alleman
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as OpportunityGlen Alleman
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleGlen Alleman
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baselineGlen Alleman
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy PiecesGlen Alleman
 
IT Risk managment combined
IT Risk managment combinedIT Risk managment combined
IT Risk managment combinedGlen Alleman
 
Risky Business
Risky BusinessRisky Business
Risky Business3gamma
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project ManagementVenkatesh Ganapathy
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual EssayPrince Bertrand
 
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITYRISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITYAshim Sharma
 

Similar to Risk Management is Essential for Project Success (20)

Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)
 
Risk management 4th in a series
Risk management 4th in a seriesRisk management 4th in a series
Risk management 4th in a series
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy Pieces
 
Managing cost and schedule risk
Managing cost and schedule riskManaging cost and schedule risk
Managing cost and schedule risk
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and Schedule
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baseline
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy Pieces
 
IT Risk managment combined
IT Risk managment combinedIT Risk managment combined
IT Risk managment combined
 
Risky Business
Risky BusinessRisky Business
Risky Business
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project Management
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual Essay
 
Risk guideline
Risk guidelineRisk guideline
Risk guideline
 
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITYRISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Recently uploaded

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 

Recently uploaded (20)

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 

Risk Management is Essential for Project Success

  • 1. Programmatic Risk Management Risk Management is How Adults Manage Projects Glen B. Alleman Niwot Ridge, LLC glen.alleman@niwotridge.com
  • 2. March Risk Management is How Adults Manage Projects† 2008 1 Risk management is essential for the success of any significant project. Information about key project cost, performance, and schedule attributes is often unknown until the project is underway. Risks identified early in the project that impacts the project later are often termed “known unknowns.” These risks can be mitigated, reduced, or retired with a risk management process. For risks that are beyond the vision of the project team, a properly implemented risk management process can also rapidly quantify the risks impact and provide sound plans for mitigating their affects. Risk management is concerned with the outcome of a future event. Events whose impacts are unknown. Risk management is about dealing with this uncertainty. Outcomes are categorized as favorable or unfavorable. Risk management is the art and science of planning, assessing, handling, and monitoring future events to ensure favorable outcomes. A good risk management process is proactive and fundamentally different than reactive issue management or problem solving. This paper describes the fundamentals of Risk Management with 5 simple concepts: 1. Hope is not a strategy – Hoping that something positive happens or something negative will not happen does not lead to success. Preparing for success is the basis of success. 2. All single point estimates are wrong – Single point estimates of cost, schedule, and technical performance are no better than 50/50 guesses in the absence of knowledge about the variances of the underlying distribution. 3. Without integrating Cost, Schedule, and Technical Performance, you are driving in the rearview mirror. The effort to produce the product or service and the resulting value cannot be made without making these connections. 4. Without a model for risk management, you are driving in the dark with the headlights off – Risk management is not an ad hoc process that you can make up as you go. A formal foundation for risk management is needed. Choose one that has worked in high-risk domains – defense, nuclear power, manned spaceflight, or examples. 5. Risk Communication is everything – Identifying risks without communicating them is a waste of time for all the participants. Risk management is an important skill that can be applied to a wide variety of projects. In an era of downsizing, consolidation, shrinking budgets, increasing technological sophistication, and shorter development times, risk management provides valuable insight to help key project personnel plan for risks. It alerts them to potential risk issues, which can then be analyzed, and plans develop, implemented, and monitored to address risks before they surface as issues and adversely affect project cost, performance, and schedule. Hope is Not a Strategy Hoping that the project will proceed as planned is not a strategy for success. Project managers who constantly seek ways to eliminate or control risk, variance and uncertainly are engaging in a hopeless pursuit. Managing “in the presence” of risk, variance, and uncertainty is the key to success. Some projects have few uncertainties –only the complexity of tasks and relationships is important – but most projects are characterized by several types of uncertainty. Although each uncertainty type is distinct, a single project may encounter some 2 combination of four types: 1. Variation – comes from many small influences and yields a range of values in a particular activity. Attempting to control these variances outside their natural boundaries is a waste of time. 2. Foreseen Uncertainties – are identifiable and understood influences that the team cannot be sure will occur. There needs to be a mitigation plan for these foreseen uncertainties. 3. Unforeseen Uncertainties – can’t be identified during project planning. When these occur, a new plan is needed. 4. Chaos – appears in the presence of “unknown unknowns” and must be addressed through a replanning process. 1 “Risk Management during Requirements,” Tom DeMarco and Tim Lister, IEEE Software, September/October, 2003 2 “Managing Project Uncertainty: From Variation to Chaos,” Arnoud De Meyer, Christoph H. Loch and Michael T. Pich, MIT Sloan Management Review, Winter 2002 † “How Much Risk is Too Much Risk,” Tim Lister, Boston SPIN, 20 January 2004 2 Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
  • 3. March Risk Management is How Adults Manage Projects† 2008 Plans are strategies for the successful completion of the project. Plans are different than schedules. Schedules show “how” the project will be executed. Plans show “what” accomplishments must be performed and the success criteria for these accomplishments along the way to completion. The Plan describes the increasing maturity of the project through assessment points. The unit of measure for this maturity must be meaningful to the stakeholders. Something that can be connected to the investment they have made in the project. When we speak the word “Hope,” it lays the foundation for failure. In the use of Hope, we really mean “success is possible but not probable.” When we speak the word Figure 1 – The Plan for the project must assure risk is being “Plan,” it does not assure success, but success is a probable reduced in proportion to the project’s tolerance for risk outcome. It is the definition of the probability of success P(s), that is the foundation of the Plan. Having a Plan–A, Plan–B, and possibly a Plan–C exposes risk, assigns 3 mitigations, and measures the probability of success. The idea of a Plan as a Strategy is critical to making changes in the behavior of the project teams that can lead to “risk adjusted project management.” Without a Plan, the schedule is simply a list of activities to be performed. The reason for their performance may be understood, but it is unlikely these activities fit in any cohesive Strategy. Strategies have goals, critical success factors, and key performance indicators. Project Strategies – the Master Plan – must also contain goals, critical success factors, and key performance indicators that assure the project is making physical progress in the presence of uncertainty in cost, schedule, and technical performance. No Single Point Estimate of Cost, Schedule or Technical Performance Can Correct How long will this take? How much is it going to cost? Will the product or service meet the requirements that are defined for any specific point in time? What is the confidence in those numbers? These are three questions that must be answered for the project team to have a credible discussion with the stakeholders about success. Deciding what accuracy is needed to provide a credible answer is a starting point. But that does not address the question – “how can that accuracy be obtained.” There are many checklists for estimating cost and schedule, with simple guidance on how to build estimates. Most of this advice is wrong in a fundamental way. The numbers produced by the estimating process do not have their variance defined in any statistically sound manner. By statistically sound it means that the underlying probability distributions are known. If they are not known, then some form of estimating taking this unknown into account must be used. The Project Management Institute (PMI) advices producing three estimates – optimistic, most likely, pessimistic. But these numbers are fraught with error. We can’t tell how these numbers were arrived at? Are they based on best engineering judgment? Based in historical data? What is nd the variance on the variance of this distribution – the 2 standard deviation? In the absence of this information, they are of little use in estimating risk. The use of point estimates for duration and cost is the first approach in an organization low on the project management maturity scale. Understanding that cost and durations are actually “random variables,” drawn from an underlying distribution of possible value is the starting point for managing in the presence of uncertainty. Figure 2 – triangle distributions are useful when there is limited information about the characteristics of the random variables are all that is available. 3 “Probability of Success Operations Guide, Acquisition, Logistics & Technology Enterprise Systems & Services, Office of the Assistant Security of the Army for Acquisition 3 Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
  • 4. March Risk Management is How Adults Manage Projects† 2008 In probability theory, every random variable is attributed to a probability distribution. The probability distribution associated with cost or duration describes the variance of these random variables. A common distribution of probabilistic estimates for cost and schedule is the Triangle Distribution. The Triangle Distribution in Figure 2 can be used as a subjective description of a population for which there is only limited sample data, and especially where the relationship between variables is known but data is scarce. It is based on the knowledge of the minimum and maximum and a “best guess” of the modal value (the Most Likely). Using the Triangle Distribution for cost and duration, a Monte Carlo simulation of the network of activities and their costs can be performed. In technical terms, Monte Carlo methods numerically transform and integrate the posterior quantitative risk assessment into a confidence interval. The result is a “confidence” model for the cost and completion times for the project based on the upper and lower bounds of each distribution assigned to the duration and cost. Integrating Cost, Schedule, and Technical Performance In many project management methods – cost, schedule, and quality are described as an “Iron Triangle.” Change one and the other two must change. This is too narrow a view of what's happening on a project. It’s the Technical Performance Measurement that replaces Quality. Quality is one Technical Performance measure. Cost and Schedule are obvious elements of the project. Technical Performance Measures (TPM) describes the status of technical achievement of the project at any point in time. The planned technical achievement is part of the Performance Measurement Baseline (PMB). The Technical Performance Measurement System (TPMS) uses the Figure 3 – the “new” triangle must be used. techniques of risk analysis and probability to provide project managers One where cost, schedule, and technical with the early warnings needed to avoid unplanned costs and slippage performance are interconnected. in schedule. Systems engineering uses technical performance measurements to balance cost, schedule, and performance throughout the project life cycle. Connecting Cost, Schedule, and Technical Performance Measures closes the loop on how well a project is achieving its technical performance requirements while maintaining its cost and schedule goals. IEEE 1220, EIA 632, and "A Guide to the Project Management Body of Knowledge“all provide guidance for TPM planning and 4 measurement and for integrating TPM with cost and schedule performance measures (Earned Value). Technical performance measurements compare actual versus planned technical development and design. They report the degree to which system requirements are met in terms of performance, cost, schedule, and progress in implementing risk retirement. Technical Performance Measures are traceable to user–defined capabilities. Integrating these three attributes produce a Performance Measurement Baseline that:  Is a plan driven by product quality requirements rather than work or effort requirements?  Focuses on technical maturity and quality, in addition to cost and schedule.  Focuses on progress toward meeting success criteria of technical reviews.  Enables insightful variance analysis.  Ensures a lean and cost–effective approach to project planning and controls.  Enables scalable scope and complexity depending on risk.  Integrates risk management activities with the performance measurement baseline.  Integrates risk management outcomes into the Estimate at Completion. The Cost and Schedule “measures” are straightforward in most cases. The measures of Technical Performance involve measures Effectiveness and Performance. Measures of Effectiveness (MOE) are the operational mission success factor defined by the customer. These are: 4 Performance Based Earned Value, Paul Solomon and Ralph Young, John Wiley & Sons, 2006. 4 Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
  • 5. March Risk Management is How Adults Manage Projects† 2008 1. Stated from the customer point of view 2. Focused on the most critical mission performance needs 3. Independent of any particular solution 4. Actual measures at the end of development Measures of Performance (MOP) characterize physical or functional attributes relating to the system operation: 5. Supplier’s point of view 6. Measured under specified testing or operational conditions 7. Assesses delivered solution performance against critical system level specified requirements 8. Risk indicators that are monitored progressively Programmatic Risk Must Follow a Well Defined Process Using an ad hoc risk management process is its self risky. The first place to start to look for risk management processes is where managing risk is mandatory – aerospace, defense, and mission critical projects and projects. These also include ERP and Enterprise IT projects. Technical performance is a concept absent from the traditional approaches to risk management. Yet it is the primary driver of risk in many technology intensive projects. Cost growth and schedule slippage often occur when unrealistically high levels of performance are required and little flexibility is provided to degrade performance during the course of the project. Quality is Figure 4 – this risk management process is the “gold standard.” Anything less is inviting additional risk. often a cause rather than an impact to the project and can generally be broken down into Cost, Performance, and Schedule components. The framework shown in Figure 4 provides guidance for:  Risk management policy  Risk management structure  Risk Management Process Model  Organizational and behavioral considerations for implementing risk management  The performance dimension of consequence of occurrence  The performance dimension of Monte Carlo simulation modeling  A structured approach for developing a risk handling strategy Risk Communication To be effective the activities of risk management must properly communicate risk to all the participants. Risk is usually a term to be avoided in normal business. Being in the risk management business is not desirable in most businesses – except insurance. It is common to “avoid” the discussion of risk. Communicating risk is the first step in managing risk. Listing the risks and making them public is necessary but far from sufficient. Risk communication is the basis of risk mitigation and retirement. It serves no purpose to have a risk management plan and the defined mitigations in the absence of a risk communication. The Risk Management Plan must address:  Executive summary – a short summary of the project and the risks associated with the activities of the project. Each risk needs an ordinal rank, a planned mitigation is the risk is active (a risk approved by the Risk Board), and the mitigations shown in the schedule with associated costs.  Project description – a detailed description of the project and the risk associated with each of the deliverables.  Risk reduction activities by phase – using some formal risk management process that connects risk, mitigation and the IMS. The efforts for mitigation need to be in the schedule. 5 Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503
  • 6. March Risk Management is How Adults Manage Projects† 2008 5  Risk management methodology – using the DoD Risk Management process is a good start. This approach is proven and approved by high risk, high reward projects. The steps in the processes are not optional and should be executed for ALL risk processes. In order to communicate risk, a clear and concise language is needed. English is not the best choice. Ambiguity and interpretation are two issues. Communicating in mathematical terms is also a problem, since the symbols and units of measure may be confusing. 6 Figure 5 is from the Active Risk Manager tool that connects risk management with the scheduling system. ARM is a proprietary risk management system, but illustrates how risk is retired over time in accordance with a plan. The concept shows explicitly when each risk will be “bought down” or “retired” during the project execution. The Risk Registry and the Integrated Master Schedule must be connected in some way. Without this connection, there is no Risk Management process that can be used to forecast impacts on cost or schedule. Figure 5 – this risk retirement waterfall shows where in the plan risk will be mitigated or retired. At each project maturity point, current risks, the planned retirements of these risks, and the impact of the project must be visible in the schedule. With these connections, project managers can then answer the questions:  What happens if this risk is not retired?  What effort is needed to retire this risk before a specific point in time?  If this risk becomes an issue, what is Plan-B? How much will Plan-B cost? What is the impact of Plan-B on the deliverables?  What cost and schedule reserve is needed to cover all the currently active risks? Wrap Up Once cost, schedule, and techncial performance are integrated into the Performance Measurement Baseline, risk management can be applied to all three elements. With these connections in place, the project management team can say with confidence – “we are doing risk management on this project.” The final reminder is to make sure all five elements of risk management are present. Leaving one out not only reduces the effectiveness of the risk management process, but increases in the risk to the project. Project risk management is a Practice. The theory of Project Risk Management is important, but the Practice is how project risk gets managed. Risk Management Process Without identifying all risk, providing mitigations and retirement plans, and having Hope is not a strategy Plan-B’s for all risks, hope is the only result Each value for cost, duration, and technical performance is actually a random variable. Single point estimates are wrong Knowing the underlying probability distribution is the start of understanding the impact of this randomness on the success of the project Integrate Cost, Schedule, and Managing the tradeoffs between these three dependent variables is the role of project Technical Performance management in the presence of uncertainty Use a Formal Risk Management Following the guidance of proven methods is simply good project management. Go it Process alone, or making it up as you go is simply poor project management In order to “manage in the presence of uncertainty” all participates must be on the Risk Communication is everything same page. Communication is the glue that engages all the participants in the conversation about managing in the presence of risk. 5 Risk Management Guide for DoD Acquisition 2003 (Fifth Edition, Version 2.0), www.dau.mil/pubs/gbbks/risk_management.asp 6 www.strategicthought.com 6 Niwot Ridge, LLC, 4347 Pebble Beach, Niwot, Colorado, 80503