SlideShare a Scribd company logo
IJSRD - International Journal for Scientific Research & Development| Vol. 1, Issue 4, 2013 | ISSN (online): 2321-0613
All rights reserved by www.ijsrd.com 1002
Abstract-- Any firm typically made a large investment in a
piece of capital machinery and, in theory, it could run 24
hour a day for seven days a week at its optimum Speed. If it
did this you gain the maximum value from the investment.
In reality there is number of element that can affect the
value gained from the investment. So that fully utilization of
equipment can be done. Hence for fully utilization of any
equipment any firm must have to calculate OEE. This paper
represents the methodology applied in increasing the OEE
of an Organization by exchanging the feed mechanism from
Bowl Feeder to a Conveyor.
Keywords: OEE, Conveyor, performance ratio.
I. INTRODUCTION
In every developed country, it is the manufacturing industry
that has spurred economic growth. It not only creates wealth
but more importantly, absorbs and recreates the same many
times over, within the economy. This is also true for India
where the growth in manufacturing sector will provide the
necessary impetus to a sustained growth of the economy
forward and create employment opportunities for our
people.
Nowadays many companies are interested to
improve their maintenance system. Because, they have
come to know that this is the system through which
companies can reduce the cost of their products and can
develop a reliable production process. A well designed
maintenance structure can be helpful for the companies to
get the competitive advantages. But majority of companies
are not able to manage a maintenance system. The two main
reasons for that are the lack of proper measurement and the
lack of control systems for maintenance. The main goal of
the maintenance is to reduce the failures of the industrial
plant, machinery and equipments. This goal can be achieved
by using different maintenance approaches such as
corrective maintenance and preventive maintenance etc. A
good maintenance approach and schedule can not be 100
percent effective at all the time. Unforeseen equipment
breakdowns and requests reduce the efficiency of the plan.
Even now a good maintenance schedule can get 70 to 90
percent efficiency. The idea with this project is to see the
current situation of the company. Is the company using its
manufacturing equipments in a proper way to get the
competitive advantages? If not, then find out the main
reason for that. Which kind of problem is there i.e.
availability, quality or performance efficiency?
Vibratory bowl feeders are common devices used
to feed individual component parts for assembly on
industrial production lines. They are used when a randomly
sorted bulk package of small components must be fed into
another machine one-by-one, oriented in a particular
direction.
Fig.1: Older arrangement
Vibratory feeders rely on the mechanical behaviour of a
part, such that when gently shaken down a conveyor chute
that is shaped to fit the part, they will gradually be shaken so
that they are all aligned. They thus leave the feeder's
conveyor one-by-one, all in the same orientation.
Orientation relies on the shape and mechanical
behaviour of an object, particular the position of its centre of
mass in relation to its centre of volume. It thus works well
for parts with rotational symmetry and a clear asymmetry to
one heavy end. The exit orientation of a bowl feeder
depends on the part's shape and mass distribution. Where
this is not the orientation needed for the following assembly
step, a feeder is often followed by a twisted conveyor that
turns the part over, as needed.
With increasing integration across an entire
production process, the need for feeders is sometimes
reduced by supplying the components on tape packages or
similar, that keep them oriented the same way during
shipping and storage. These are most common in fields such
as electronics, where components must be used in a
particular orientation, but this cannot be detected
mechanically.
OEE is the series of matrices which can be use for
the utilization of machine at the job level, shift level, overall
plan or enterprise level. Any firm typically made a large
investment in a piece of capital machinery and, in theory, it
could run 24 hour a day for seven days a week at its
optimum Speed. If it did this you gain the maximum value
from the investment. In reality there is number of element
that can be affect the value gained from the investment. So
that fully utilization of equipment can be done. Hence for
fully utilization of any equipment any firm must have to
calculate OEE.
OEE is stands for overall equipment effectiveness.
Essential it is a single figure that significances the
utilization of machine. This can be at a job level, shift level,
overall plan or enterprise level. OEE is a measure of total
equipment performance. OEE is also a three part analysis
tool for equipment performance based on actual availability,
Performance Analysis using OEE
Mayur N. Nagdiya1
Mr. Kiran Bhabhor2
1
ME Student 2
Associate Professor
1, 2
Department of Mechanical Engineering
1, 2
GEC, Dahod (GTU, Ahmadabad)
Performance Analysis using OEE
(IJSRD/Vol. 1/Issue 4/ 2013/0045)
All rights reserved by www.ijsrd.com 1003
performance efficiency, and quality of product or output.
OEE is used in two format OEE data (information)” (the
original intent) and a calculated “OEE percentage.” OEE
data (information) are quantified loss reasons categorized
by specific equipment related loss types. OEE percentage
is a calculated relative comparison metric used for a specific
equipment or process over a period of time.
OEE is broken down into three measuring matrix of:
1) Availability ratio (AR)
2) Performance ratio (PR)
3) Quality rate (QR)
A. Availability Rate (AR)
The availability rate is the time the equipment is really
running versus the time it could have been running. A
reduced availability rate is an indication of equipment
failure and issues around setup and adjustment
Availability Rate = Run Time / Total Time
B. Performance Rate (PR)
The performance rate is the quantity of material produced
during the running time versus the quantity of material that
could have been produced when taking in to account the
manufacturers documented speed of the equipment. A low
performance rate can be seen as a result of idling minor
stoppages and reduced speed operation
Performance Rate = Actual Prod. / Standard Prod.
C. Quality Rate (QR)
The quality rate is the amount of acceptable material versus
the total amount of material that is manufactured. A low
quality rate is an indication of startup losses and the amount
of scrap material.
Quality rate = Good Count / Total Count
II. CALCULATATION OF OEE WITH BOWL FEEDER
By definition OEE is calculated as the product of
availability, performance and quality rate
OEE = AVAILABILITY x PERFORMANCE x QUALITY
RATE
In HARSHA ENGINEERS LTD. on 10th of November the
data for OEE during one shift as below,
SPM of press is 250
L+UL time 3
Batch no SLAC1211141
Item 32205 BJ2 (T8-line) SKF
Shift A
No of pockets 18
Line 4A
1) Now for the calculation of Availability,
Total availability = 510min
Available Min = 425 min
M/c Cleaning = 60 min
Tool Regrind and Resetting= 25 min
So, by definition of availability,
Availability Rate = Run Time / Total Time
Here run time is 425 and total time is 510
Availability % = 425/510
Availability % = 83.33%
2) Now for calculation of performance rate
Piece per minute = 8.19
Standard production rate = Act. Planned min. x piece per
min.
= 3480.00
Performance efficiency % = Actual. Production / standard
production = 2750 / 3480
Performance efficiency % = 79.02 %
3) Now for calculation of quality rate,
No. Scrap part = 20
By definition of quality rate,
Quality rate % = Good Count / Total Count.
= 2730 / 2750
Quality rate % = 99.27%
Now by the definition of the OEE, OEE is calculate as,
OEE = AVAILABILITY x PERFORMANCE x QUALITY
RATE
= 83.33 % x 79.02 % x 99.27 %
OEE = 65.36 %
III. WORLD CLASS OEE
OEE is essentially the ratio of Fully Productive Time to
Planned Production Time (refer to the OEE Factors section
for a graphic representation). In practice, however, as we
discussed above OEE is calculated as the product of its three
contributing factors:
OEE = Availability x Performance x Quality
This type of calculation makes OEE a severe test.
For example, if all three contributing factors are 90.0%, the
OEE would be 72.9%. In practice, the generally accepted
World- Class goals for each factor are quite different from
each other, as is shown in the table below.
OEE FACTOR WORLD CLASS
1) AVAILABILITY 85%
2) PERFORMANCE 100%
3) QUALITY RATE 100%
So as above,
OEE 85%
Of course, every manufacturing plant is different.
Worldwide studies indicate that the average OEE rate in
manufacturing plants is 60%. As you can see from the above
table, a World Class OEE is considered to be 85% or better.
Hence comparing organization’s OEE and world class OEE
we seen that the company OEE is very low compare to
world class OEE, so our target is to achieve that figure.
IV. DESIGN OF FLAT BELT CONVEYOR
i. Live load = 3.30 kg/m
Performance Analysis using OEE
(IJSRD/Vol. 1/Issue 4/ 2013/0045)
All rights reserved by www.ijsrd.com 1004
ii. Total Live Load = 3.30 × Length of conveyor
= 3.30 × 1.8 = 5.952 kg.
iii. Dead Load = The load consist of weight of roller
belting and drive pulley = 52.8 kg
iv. Belt pull = (A+B) × co-efficient of friction
= (5.952 + 52.8) × 0.05 = 2.9376 kg
v. Effective Belt Pull = total belt pull × 1.25
= 2.9376 × 1.25 = 3.672 kg
vi. Tension T1 = effective belt pull × T1 factor
= 3.672 × 1.42 = 5.2142 kg
vii. Belt width = = = 110 mm
viii. Effective Tension (Te) = Total empty friction + Load
friction + Load slope tension
Here,
Return side Tension= Fe × W × L × 0.4
= 0.020 × 16.1 × 1.8 × 0.4
= 0.2318 kg/m
Total Empty friction = Fe × (L + tf) ×W
= 0.020 × (1.8+3) ×16.1
= 1.5456 kg.
Carring Side empty Friction = Total friction – Return
side friction
= 1.5456 – 0.2318
= 1.3138 kg.
Load Friction = F1 × (L+tf) ×
= 0.025 × (1.8+3) × 3.30
= 0.396 kg.
Load slope tension =
= 3.30 × 1.20
= 3.96 kg.
So, effective tension Te = Total Empty Friction + Load
Friction + Load slope
tension
= 1.5456 + 0.396 + 3.96
= 5.9016 kg.
Te = 5.9016 kg. or Te = 57.9 N
ix. Power Calculation:
P = = = 0.44 HP
x. Motor RPM Calculation:
N =
Here,
Mt = × D × (F + µwg)
= 0.5 ×0.120 × (2.9376 + 0.3×16.1×9.81)
= 3.02 Nm
N = = 1390 RPM
Diameter of shaft:
Total Load on Shaft = total live load + dead load
= 5.952 + 52.8
= 58.752 kg
= 576.36 N
Load at Point C = load at Point D =
= 288.18 N
Here, Bending moment @ A=0
Bending moment @ B=0
So,
. . B × 180 =0
RB × 180 = 51872.37
RB = 288.18 N
Here,
RA + RB = Total load
So,
RA = 288.18 N
Bending Moment @ C = 288.15 × 15
= 4322.7 N-mm
Bending Moment @ D = 288.15 × 15
= 4322.7 N-mm
So, Maximum Bending Moment M = 4322.7 N-mm
Here Torque, T =
=
= 22.1328 N-M
= 22.1328 × 103
N-mm
Te = √
=√
= 22.55 × 103
N-mm
We know, Te = × × d3
22.55 × 103
= × 42 × d3
d3
=
d= 14.2 mm
take d = 18 mm
V. CALCULATATION OF OEE WITH CONVEYOR
In Harsha Engineers Ltd. On 15th of March the data for OEE
during one shift are as below,
SPM of press is 250
L+UL time 3
Performance Analysis using OEE
(IJSRD/Vol. 1/Issue 4/ 2013/0045)
All rights reserved by www.ijsrd.com 1005
Batch no SLAC1303126
Item R - 30 - 76XJ NSK (SUZHOU, CHINA)
Shift A
No of pockets 18
Line 4A
1) Now for the calculation of Availability,
Total availability = 510min
Available Min = 405 min
Total Down Time = 105 min
So, by definition of availability,
Availability Rate = Run Time / Total Time
Here run time is 405 and total time is 510
Availability % = 405/510
Availability % = 79.41%
2) Now for calculation of performance rate,
Piece per minute = 8.19
Standard production rate = Act. Planned min. x piece per
min. = 3480.00
Performance efficiency % = Actual Production / standard
production = 3283 / 3480
Performance efficiency % = 94.33 %
3) Now for calculation of quality rate,
No. Scrap part = 179 pices.
By definition of quality rate,
Quality rate % = Good Count / Total Count.
= 3104 / 3283
Quality rate % = 94.55%
Now by the definition of the OEE, OEE is calculate as,
OEE = AVAILABILITY x PERFORMANCE x QUALITY
RATE
= 79.41 % x 94.33 % x 94.55 %
OEE = 70.82 %
Fig.2: New arrangement
VI. COMPARISON OF OEE’S FOR BOTH SYSTEMS
1) Average OEE:
2) Availability ratio (AR):
3) Performance ratio (PR):
Performance Analysis using OEE
(IJSRD/Vol. 1/Issue 4/ 2013/0045)
All rights reserved by www.ijsrd.com 1006
4) Quality Rate
VII. DEFECT REJECTION STATUS DURING
PRODUCTION
Fig. 3: Defect Rejection Diagram
VIII. ANALYSIS OF DATA AND CONCLUSION
Now as above discussed data we can say after using
conveyors OEE increases but the drawback is, AR and QR
decreases. The reasons for this are as follow:
(1) Cages were falling down from the conveyors. Due to
this, defects like bend, dent, missing of cages and line marks
on cages were found. Now for avoiding this, guide ways of
M.S. were placed on both the sides of the conveyor. Because
of this, cages stopped falling. But now, by applying guide
ways, the cage comes in the contact with the guide way
material and this results in the dents in the cages.
To overcome this problem, we replaced the material of the
guide way from M.S. to Aluminum because of its low wear
rate. Also nylon rubber sheet were introduced between the
material contacts so that it doesn’t go weak and dents were
avoided by this.
(2) The above mentioned remedy was useful to stop the
falling of the cages but as we all know the capacity of the
facing is double than that of notching. So whenever 1 piece
undergoes the notching operation, 2 pieces finishes the
facing operation. Now due to this the conveyor gets filled
within 4-5 minutes and cages have to stay awaiting one over
the other.
(3) Since the cages are not arranged in a proper manner on
the conveyor, it results in uneven loading in the notching
process and it doesn’t fit on the collets. Due to this, defects
like bottom height variation, pocket missing and pocket
shifting are generated.
(4) For the solution of this problem we placed block sensors
in such a manner that its master panel is functioned with
ON-OFF Delay Time for the Facing process. Here the facing
machine is given the ON Delay Time of 2 seconds and OFF
Delay Time of 3 seconds.
(5) But due to this, feeding has to be done manually in
different parts in accordance with the part numbers. If this
was not done, the cage would overflow and ultimately defect
gets generated.
(6) This way by using conveyor OEE is improved as per our
target. PR increases up to 14.49 % but AR gets decreased by
5.13 % and due to the generation of various defects QR also
foes down by 3.46%.
As discussed above AR goes down because of the
following losses:
(1) Set Up Losses: Suppose cages gets fit unevenly on the
collets and when the notching process starts, according to
the cage design there remains gap between the cage and the
die punch, die punch has to be re-grinded and during this
period machine remains OFF which ultimately affects the
A . Also “BU S” are seen on the cages.
(2) By die punch re-grinding tool rework loss increases and
this also directly affects the AR.
(3) After the die punch re-grinding, its settings are
configured. Then onwards 2-3 pieces are hindered for
quality checking which affects the QR and rejection is also
increased.
(4) Lines are often reset because either cages fall down or
get blocked or gets one over the other. This generates “Line
Organization Losses”.
(5) After making the die punch it has to be set and adjusted
according to the measurements. In this way this loss is also
generated.
Performance Analysis using OEE
(IJSRD/Vol. 1/Issue 4/ 2013/0045)
All rights reserved by www.ijsrd.com 1007
Ultimately AR reduces to 5.13 %, PR Increase to
14.49 % and QR reduces to 3.46%.
This way we started the analysis again. Our target
OEE is 85% whereas OEE achieved is 70.91 % so further
modifications are to be done by analysis and data collection.
IX. CONCLUSION
For fully utilization of any equipment any firm must have to
calculate OEE. This paper represents the methodology
applied in increasing the OEE of an Organization by
exchanging the feed mechanism from Bowl Feeder to a
Conveyor. Hence our main focus is on first pillar i.e. overall
equipment efficiency . Today Harsha’s bench mark is 70%
OEE. But as per world class OEE measure is 85% for a
single line. So we have to achieve that target for achieving
company’s goal.
So after achieving 85% OEE we have increase the
production. Also improve in quality of product and
performance of machine.
REFERENCES
[ ] Seema S. Vanamane, Pravin A. Mane “Design,
Manufacture and Analysis of Belt Conveyor System
used for Cooling of Mould”, International Journal of
Engineering Research and Applications (IJERA).
[2] A. M. Guthrie and J. R. Pilcher, Moreland Technical and
Engineering Consultants ltd. “The Design of Belt
Conveyors for Bulk Sugar Handling”, Presented at
Proceedings of The South Africun Sugar
Technologists' Association.
[3] Mr. aghvendra Singh gurjar “Failure Analysis of Belt
Conveyor system in a Thermal Power plant”, IJATE .
[4] A.W. Roberts and A. Harrison, Dean, Faculty of
Engineering, University of New Castle, Australia,
Principal Research Scientist, Division of Applied
Physics, Csiro, Australia, “ ecent esearch
Developments In Belt Conveyor Technology”.
[5] Prof.dr.ir. Gabriel Lodewijks Delft University of
Technology, The Netherlands “Two Decades
Dynamics of Belt Conveyor Systems”
[6] G. Lodewijks, The Netherlands “The Design of High
Speed Belt Conveyors”
[7] Ulf Richter, ABB Automation, Germany “Large belt
conveyor systems”
[8] Industrial Engineering By L C Jhamb, 4th edition
Everest Publishing House.
[9] M. A. Alspaugh, Overland Conveyor Co., Inc. “Latest
Developments in Belt Conveyor Technology”,
Presented at MINExpo 2004 Las Vegas, NV, USA
[10] G. Lodewijks, The Design of High Speed Belt
Conveyors The Netherlands.

More Related Content

What's hot

5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload
eSAT Publishing House
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET Journal
 
A012430106
A012430106A012430106
A012430106
IOSR Journals
 
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
IRJET-  	  Six Axis Pneumatic Materials Handling Robotic ArmIRJET-  	  Six Axis Pneumatic Materials Handling Robotic Arm
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
IRJET Journal
 
Implementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyImplementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiency
Laukik Raut
 
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed ManufacturingIRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET Journal
 
Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!
Mahibur Rahman
 
Saurabh kumar 03 scm presentation
Saurabh kumar 03 scm presentationSaurabh kumar 03 scm presentation
Saurabh kumar 03 scm presentation
Saurabh Kumar
 
Design of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysemDesign of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysem
Maheer Sohbat
 
Gis on vikash industry
Gis on  vikash industryGis on  vikash industry
Gis on vikash industry
Saurabh Kumar
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
InfoStream Solutions
 
2015 workers and machine performance modeling in manufacturing system jcsb 08...
2015 workers and machine performance modeling in manufacturing system jcsb 08...2015 workers and machine performance modeling in manufacturing system jcsb 08...
2015 workers and machine performance modeling in manufacturing system jcsb 08...
Kassu Jilcha (PhD)
 
2015 workers and machine performance modeling in manufacturing
2015  workers and machine performance modeling in manufacturing2015  workers and machine performance modeling in manufacturing
2015 workers and machine performance modeling in manufacturing
Kassu Jilcha (PhD)
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
Jitesh Gaurav
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...
ijtsrd
 
Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...IAEME Publication
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations Management
Mayank Jain
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
Kailas Sree Chandran
 

What's hot (18)

5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
 
A012430106
A012430106A012430106
A012430106
 
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
IRJET-  	  Six Axis Pneumatic Materials Handling Robotic ArmIRJET-  	  Six Axis Pneumatic Materials Handling Robotic Arm
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
 
Implementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyImplementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiency
 
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed ManufacturingIRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
 
Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!Industrial Engineering Tools & Activities of a RMG !!!
Industrial Engineering Tools & Activities of a RMG !!!
 
Saurabh kumar 03 scm presentation
Saurabh kumar 03 scm presentationSaurabh kumar 03 scm presentation
Saurabh kumar 03 scm presentation
 
Design of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysemDesign of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysem
 
Gis on vikash industry
Gis on  vikash industryGis on  vikash industry
Gis on vikash industry
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
 
2015 workers and machine performance modeling in manufacturing system jcsb 08...
2015 workers and machine performance modeling in manufacturing system jcsb 08...2015 workers and machine performance modeling in manufacturing system jcsb 08...
2015 workers and machine performance modeling in manufacturing system jcsb 08...
 
2015 workers and machine performance modeling in manufacturing
2015  workers and machine performance modeling in manufacturing2015  workers and machine performance modeling in manufacturing
2015 workers and machine performance modeling in manufacturing
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...
 
Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations Management
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 

Viewers also liked

An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...
An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...
An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...
ijsrd.com
 
Comparative study on growth status of Teen age Male Volleyball players on sel...
Comparative study on growth status of Teen age Male Volleyball players on sel...Comparative study on growth status of Teen age Male Volleyball players on sel...
Comparative study on growth status of Teen age Male Volleyball players on sel...
ijsrd.com
 
Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...
Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...
Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...
ijsrd.com
 
Application of Plasma Technology for Coated Textile
Application of Plasma Technology for Coated TextileApplication of Plasma Technology for Coated Textile
Application of Plasma Technology for Coated Textile
ijsrd.com
 
Multiparameter Web Sensor
Multiparameter Web SensorMultiparameter Web Sensor
Multiparameter Web Sensor
ijsrd.com
 
Super-Resolution of Multispectral Images
Super-Resolution of Multispectral ImagesSuper-Resolution of Multispectral Images
Super-Resolution of Multispectral Images
ijsrd.com
 
Introduction to VIP with PCI Express Technology
Introduction to VIP with PCI Express TechnologyIntroduction to VIP with PCI Express Technology
Introduction to VIP with PCI Express Technology
ijsrd.com
 
ON Fuzzy Linear Programming Technique Application
ON Fuzzy Linear Programming Technique ApplicationON Fuzzy Linear Programming Technique Application
ON Fuzzy Linear Programming Technique Application
ijsrd.com
 
Analysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its ComparisonAnalysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its Comparison
ijsrd.com
 
A Survey of Techniques Used To Detect Selfish Nodes in MANET
 A Survey of Techniques Used To Detect Selfish Nodes in MANET A Survey of Techniques Used To Detect Selfish Nodes in MANET
A Survey of Techniques Used To Detect Selfish Nodes in MANET
ijsrd.com
 
A survey on Efficient Enhanced K-Means Clustering Algorithm
 A survey on Efficient Enhanced K-Means Clustering Algorithm A survey on Efficient Enhanced K-Means Clustering Algorithm
A survey on Efficient Enhanced K-Means Clustering Algorithm
ijsrd.com
 
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...ijsrd.com
 
Clustering Algorithm for Gujarati Language
Clustering Algorithm for Gujarati LanguageClustering Algorithm for Gujarati Language
Clustering Algorithm for Gujarati Language
ijsrd.com
 
Text Based Fuzzy Clustering Algorithm to Filter Spam E-mail
Text Based Fuzzy Clustering Algorithm to Filter Spam E-mailText Based Fuzzy Clustering Algorithm to Filter Spam E-mail
Text Based Fuzzy Clustering Algorithm to Filter Spam E-mailijsrd.com
 
Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...
Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...
Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...
ijsrd.com
 
A Decision Tree Based Classifier for Classification & Prediction of Diseases
A Decision Tree Based Classifier for Classification & Prediction of DiseasesA Decision Tree Based Classifier for Classification & Prediction of Diseases
A Decision Tree Based Classifier for Classification & Prediction of Diseases
ijsrd.com
 
A review on techniques for optimizing process parameters for TIG Welding Alum...
A review on techniques for optimizing process parameters for TIG Welding Alum...A review on techniques for optimizing process parameters for TIG Welding Alum...
A review on techniques for optimizing process parameters for TIG Welding Alum...
ijsrd.com
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
ijsrd.com
 

Viewers also liked (18)

An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...
An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...
An Efficient Approach for Image Enhancement Based on Image Fusion with Retine...
 
Comparative study on growth status of Teen age Male Volleyball players on sel...
Comparative study on growth status of Teen age Male Volleyball players on sel...Comparative study on growth status of Teen age Male Volleyball players on sel...
Comparative study on growth status of Teen age Male Volleyball players on sel...
 
Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...
Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...
Hydrostatic Continuous Variable Power Transmission Drive for Two wheelers usi...
 
Application of Plasma Technology for Coated Textile
Application of Plasma Technology for Coated TextileApplication of Plasma Technology for Coated Textile
Application of Plasma Technology for Coated Textile
 
Multiparameter Web Sensor
Multiparameter Web SensorMultiparameter Web Sensor
Multiparameter Web Sensor
 
Super-Resolution of Multispectral Images
Super-Resolution of Multispectral ImagesSuper-Resolution of Multispectral Images
Super-Resolution of Multispectral Images
 
Introduction to VIP with PCI Express Technology
Introduction to VIP with PCI Express TechnologyIntroduction to VIP with PCI Express Technology
Introduction to VIP with PCI Express Technology
 
ON Fuzzy Linear Programming Technique Application
ON Fuzzy Linear Programming Technique ApplicationON Fuzzy Linear Programming Technique Application
ON Fuzzy Linear Programming Technique Application
 
Analysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its ComparisonAnalysis of Different Parking Space and its Comparison
Analysis of Different Parking Space and its Comparison
 
A Survey of Techniques Used To Detect Selfish Nodes in MANET
 A Survey of Techniques Used To Detect Selfish Nodes in MANET A Survey of Techniques Used To Detect Selfish Nodes in MANET
A Survey of Techniques Used To Detect Selfish Nodes in MANET
 
A survey on Efficient Enhanced K-Means Clustering Algorithm
 A survey on Efficient Enhanced K-Means Clustering Algorithm A survey on Efficient Enhanced K-Means Clustering Algorithm
A survey on Efficient Enhanced K-Means Clustering Algorithm
 
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
 
Clustering Algorithm for Gujarati Language
Clustering Algorithm for Gujarati LanguageClustering Algorithm for Gujarati Language
Clustering Algorithm for Gujarati Language
 
Text Based Fuzzy Clustering Algorithm to Filter Spam E-mail
Text Based Fuzzy Clustering Algorithm to Filter Spam E-mailText Based Fuzzy Clustering Algorithm to Filter Spam E-mail
Text Based Fuzzy Clustering Algorithm to Filter Spam E-mail
 
Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...
Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...
Improved Frequent Pattern Mining Algorithm using Divide and Conquer Technique...
 
A Decision Tree Based Classifier for Classification & Prediction of Diseases
A Decision Tree Based Classifier for Classification & Prediction of DiseasesA Decision Tree Based Classifier for Classification & Prediction of Diseases
A Decision Tree Based Classifier for Classification & Prediction of Diseases
 
A review on techniques for optimizing process parameters for TIG Welding Alum...
A review on techniques for optimizing process parameters for TIG Welding Alum...A review on techniques for optimizing process parameters for TIG Welding Alum...
A review on techniques for optimizing process parameters for TIG Welding Alum...
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 

Similar to Performance Analysis using OEE

The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing Productivity
Corey Vodvarka
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing Productivity
Jason Corder
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing Productivity
Parsec_Automation_Corp
 
I012536474
I012536474I012536474
I012536474
IOSR Journals
 
Maintainance engineering and management
Maintainance engineering and managementMaintainance engineering and management
Maintainance engineering and management
bahir dar university
 
OEE
OEEOEE
Overall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction EquipmentsOverall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction Equipments
IRJET Journal
 
Managing OEE o optimize factory performance
Managing OEE o optimize factory performanceManaging OEE o optimize factory performance
Managing OEE o optimize factory performance
Yasmin AbdelAziz
 
The+complete+guide+to+simple+oee
The+complete+guide+to+simple+oeeThe+complete+guide+to+simple+oee
The+complete+guide+to+simple+oeeGalland Tolentino
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)
OEEsystems International
 
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWSTUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
IAEME Publication
 
“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...
IRJET Journal
 
H012535263
H012535263H012535263
H012535263
IOSR Journals
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
Matthew Clemens
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 
Why OEE?
Why OEE?Why OEE?
Why OEE?
AshleyTizard
 
total productive maintenance
total productive maintenancetotal productive maintenance
total productive maintenance
Shankha Goswami
 
Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...
Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...
Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...
International Journal of Business Marketing and Management (IJBMM)
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
IRJET Journal
 

Similar to Performance Analysis using OEE (20)

The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing Productivity
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing Productivity
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing Productivity
 
I012536474
I012536474I012536474
I012536474
 
Maintainance engineering and management
Maintainance engineering and managementMaintainance engineering and management
Maintainance engineering and management
 
OEE
OEEOEE
OEE
 
Overall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction EquipmentsOverall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction Equipments
 
Managing OEE o optimize factory performance
Managing OEE o optimize factory performanceManaging OEE o optimize factory performance
Managing OEE o optimize factory performance
 
The+complete+guide+to+simple+oee
The+complete+guide+to+simple+oeeThe+complete+guide+to+simple+oee
The+complete+guide+to+simple+oee
 
lean & agile
lean & agilelean & agile
lean & agile
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)
 
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWSTUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
 
“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...
 
H012535263
H012535263H012535263
H012535263
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
 
Why OEE?
Why OEE?Why OEE?
Why OEE?
 
total productive maintenance
total productive maintenancetotal productive maintenance
total productive maintenance
 
Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...
Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...
Overall Equipment Effectiveness (OEE) Measurement Analysis for Optimizing Sme...
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
 

More from ijsrd.com

IoT Enabled Smart Grid
IoT Enabled Smart GridIoT Enabled Smart Grid
IoT Enabled Smart Grid
ijsrd.com
 
A Survey Report on : Security & Challenges in Internet of Things
A Survey Report on : Security & Challenges in Internet of ThingsA Survey Report on : Security & Challenges in Internet of Things
A Survey Report on : Security & Challenges in Internet of Things
ijsrd.com
 
IoT for Everyday Life
IoT for Everyday LifeIoT for Everyday Life
IoT for Everyday Life
ijsrd.com
 
Study on Issues in Managing and Protecting Data of IOT
Study on Issues in Managing and Protecting Data of IOTStudy on Issues in Managing and Protecting Data of IOT
Study on Issues in Managing and Protecting Data of IOT
ijsrd.com
 
Interactive Technologies for Improving Quality of Education to Build Collabor...
Interactive Technologies for Improving Quality of Education to Build Collabor...Interactive Technologies for Improving Quality of Education to Build Collabor...
Interactive Technologies for Improving Quality of Education to Build Collabor...
ijsrd.com
 
Internet of Things - Paradigm Shift of Future Internet Application for Specia...
Internet of Things - Paradigm Shift of Future Internet Application for Specia...Internet of Things - Paradigm Shift of Future Internet Application for Specia...
Internet of Things - Paradigm Shift of Future Internet Application for Specia...
ijsrd.com
 
A Study of the Adverse Effects of IoT on Student's Life
A Study of the Adverse Effects of IoT on Student's LifeA Study of the Adverse Effects of IoT on Student's Life
A Study of the Adverse Effects of IoT on Student's Life
ijsrd.com
 
Pedagogy for Effective use of ICT in English Language Learning
Pedagogy for Effective use of ICT in English Language LearningPedagogy for Effective use of ICT in English Language Learning
Pedagogy for Effective use of ICT in English Language Learning
ijsrd.com
 
Virtual Eye - Smart Traffic Navigation System
Virtual Eye - Smart Traffic Navigation SystemVirtual Eye - Smart Traffic Navigation System
Virtual Eye - Smart Traffic Navigation System
ijsrd.com
 
Ontological Model of Educational Programs in Computer Science (Bachelor and M...
Ontological Model of Educational Programs in Computer Science (Bachelor and M...Ontological Model of Educational Programs in Computer Science (Bachelor and M...
Ontological Model of Educational Programs in Computer Science (Bachelor and M...
ijsrd.com
 
Understanding IoT Management for Smart Refrigerator
Understanding IoT Management for Smart RefrigeratorUnderstanding IoT Management for Smart Refrigerator
Understanding IoT Management for Smart Refrigerator
ijsrd.com
 
DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...
DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...
DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...
ijsrd.com
 
A Review: Microwave Energy for materials processing
A Review: Microwave Energy for materials processingA Review: Microwave Energy for materials processing
A Review: Microwave Energy for materials processing
ijsrd.com
 
Web Usage Mining: A Survey on User's Navigation Pattern from Web Logs
Web Usage Mining: A Survey on User's Navigation Pattern from Web LogsWeb Usage Mining: A Survey on User's Navigation Pattern from Web Logs
Web Usage Mining: A Survey on User's Navigation Pattern from Web Logs
ijsrd.com
 
APPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEM
APPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEMAPPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEM
APPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEM
ijsrd.com
 
Making model of dual axis solar tracking with Maximum Power Point Tracking
Making model of dual axis solar tracking with Maximum Power Point TrackingMaking model of dual axis solar tracking with Maximum Power Point Tracking
Making model of dual axis solar tracking with Maximum Power Point Tracking
ijsrd.com
 
A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...
A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...
A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...
ijsrd.com
 
Study and Review on Various Current Comparators
Study and Review on Various Current ComparatorsStudy and Review on Various Current Comparators
Study and Review on Various Current Comparators
ijsrd.com
 
Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...
Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...
Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...
ijsrd.com
 
Defending Reactive Jammers in WSN using a Trigger Identification Service.
Defending Reactive Jammers in WSN using a Trigger Identification Service.Defending Reactive Jammers in WSN using a Trigger Identification Service.
Defending Reactive Jammers in WSN using a Trigger Identification Service.
ijsrd.com
 

More from ijsrd.com (20)

IoT Enabled Smart Grid
IoT Enabled Smart GridIoT Enabled Smart Grid
IoT Enabled Smart Grid
 
A Survey Report on : Security & Challenges in Internet of Things
A Survey Report on : Security & Challenges in Internet of ThingsA Survey Report on : Security & Challenges in Internet of Things
A Survey Report on : Security & Challenges in Internet of Things
 
IoT for Everyday Life
IoT for Everyday LifeIoT for Everyday Life
IoT for Everyday Life
 
Study on Issues in Managing and Protecting Data of IOT
Study on Issues in Managing and Protecting Data of IOTStudy on Issues in Managing and Protecting Data of IOT
Study on Issues in Managing and Protecting Data of IOT
 
Interactive Technologies for Improving Quality of Education to Build Collabor...
Interactive Technologies for Improving Quality of Education to Build Collabor...Interactive Technologies for Improving Quality of Education to Build Collabor...
Interactive Technologies for Improving Quality of Education to Build Collabor...
 
Internet of Things - Paradigm Shift of Future Internet Application for Specia...
Internet of Things - Paradigm Shift of Future Internet Application for Specia...Internet of Things - Paradigm Shift of Future Internet Application for Specia...
Internet of Things - Paradigm Shift of Future Internet Application for Specia...
 
A Study of the Adverse Effects of IoT on Student's Life
A Study of the Adverse Effects of IoT on Student's LifeA Study of the Adverse Effects of IoT on Student's Life
A Study of the Adverse Effects of IoT on Student's Life
 
Pedagogy for Effective use of ICT in English Language Learning
Pedagogy for Effective use of ICT in English Language LearningPedagogy for Effective use of ICT in English Language Learning
Pedagogy for Effective use of ICT in English Language Learning
 
Virtual Eye - Smart Traffic Navigation System
Virtual Eye - Smart Traffic Navigation SystemVirtual Eye - Smart Traffic Navigation System
Virtual Eye - Smart Traffic Navigation System
 
Ontological Model of Educational Programs in Computer Science (Bachelor and M...
Ontological Model of Educational Programs in Computer Science (Bachelor and M...Ontological Model of Educational Programs in Computer Science (Bachelor and M...
Ontological Model of Educational Programs in Computer Science (Bachelor and M...
 
Understanding IoT Management for Smart Refrigerator
Understanding IoT Management for Smart RefrigeratorUnderstanding IoT Management for Smart Refrigerator
Understanding IoT Management for Smart Refrigerator
 
DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...
DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...
DESIGN AND ANALYSIS OF DOUBLE WISHBONE SUSPENSION SYSTEM USING FINITE ELEMENT...
 
A Review: Microwave Energy for materials processing
A Review: Microwave Energy for materials processingA Review: Microwave Energy for materials processing
A Review: Microwave Energy for materials processing
 
Web Usage Mining: A Survey on User's Navigation Pattern from Web Logs
Web Usage Mining: A Survey on User's Navigation Pattern from Web LogsWeb Usage Mining: A Survey on User's Navigation Pattern from Web Logs
Web Usage Mining: A Survey on User's Navigation Pattern from Web Logs
 
APPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEM
APPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEMAPPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEM
APPLICATION OF STATCOM to IMPROVED DYNAMIC PERFORMANCE OF POWER SYSTEM
 
Making model of dual axis solar tracking with Maximum Power Point Tracking
Making model of dual axis solar tracking with Maximum Power Point TrackingMaking model of dual axis solar tracking with Maximum Power Point Tracking
Making model of dual axis solar tracking with Maximum Power Point Tracking
 
A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...
A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...
A REVIEW PAPER ON PERFORMANCE AND EMISSION TEST OF 4 STROKE DIESEL ENGINE USI...
 
Study and Review on Various Current Comparators
Study and Review on Various Current ComparatorsStudy and Review on Various Current Comparators
Study and Review on Various Current Comparators
 
Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...
Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...
Reducing Silicon Real Estate and Switching Activity Using Low Power Test Patt...
 
Defending Reactive Jammers in WSN using a Trigger Identification Service.
Defending Reactive Jammers in WSN using a Trigger Identification Service.Defending Reactive Jammers in WSN using a Trigger Identification Service.
Defending Reactive Jammers in WSN using a Trigger Identification Service.
 

Recently uploaded

一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 

Recently uploaded (20)

一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 

Performance Analysis using OEE

  • 1. IJSRD - International Journal for Scientific Research & Development| Vol. 1, Issue 4, 2013 | ISSN (online): 2321-0613 All rights reserved by www.ijsrd.com 1002 Abstract-- Any firm typically made a large investment in a piece of capital machinery and, in theory, it could run 24 hour a day for seven days a week at its optimum Speed. If it did this you gain the maximum value from the investment. In reality there is number of element that can affect the value gained from the investment. So that fully utilization of equipment can be done. Hence for fully utilization of any equipment any firm must have to calculate OEE. This paper represents the methodology applied in increasing the OEE of an Organization by exchanging the feed mechanism from Bowl Feeder to a Conveyor. Keywords: OEE, Conveyor, performance ratio. I. INTRODUCTION In every developed country, it is the manufacturing industry that has spurred economic growth. It not only creates wealth but more importantly, absorbs and recreates the same many times over, within the economy. This is also true for India where the growth in manufacturing sector will provide the necessary impetus to a sustained growth of the economy forward and create employment opportunities for our people. Nowadays many companies are interested to improve their maintenance system. Because, they have come to know that this is the system through which companies can reduce the cost of their products and can develop a reliable production process. A well designed maintenance structure can be helpful for the companies to get the competitive advantages. But majority of companies are not able to manage a maintenance system. The two main reasons for that are the lack of proper measurement and the lack of control systems for maintenance. The main goal of the maintenance is to reduce the failures of the industrial plant, machinery and equipments. This goal can be achieved by using different maintenance approaches such as corrective maintenance and preventive maintenance etc. A good maintenance approach and schedule can not be 100 percent effective at all the time. Unforeseen equipment breakdowns and requests reduce the efficiency of the plan. Even now a good maintenance schedule can get 70 to 90 percent efficiency. The idea with this project is to see the current situation of the company. Is the company using its manufacturing equipments in a proper way to get the competitive advantages? If not, then find out the main reason for that. Which kind of problem is there i.e. availability, quality or performance efficiency? Vibratory bowl feeders are common devices used to feed individual component parts for assembly on industrial production lines. They are used when a randomly sorted bulk package of small components must be fed into another machine one-by-one, oriented in a particular direction. Fig.1: Older arrangement Vibratory feeders rely on the mechanical behaviour of a part, such that when gently shaken down a conveyor chute that is shaped to fit the part, they will gradually be shaken so that they are all aligned. They thus leave the feeder's conveyor one-by-one, all in the same orientation. Orientation relies on the shape and mechanical behaviour of an object, particular the position of its centre of mass in relation to its centre of volume. It thus works well for parts with rotational symmetry and a clear asymmetry to one heavy end. The exit orientation of a bowl feeder depends on the part's shape and mass distribution. Where this is not the orientation needed for the following assembly step, a feeder is often followed by a twisted conveyor that turns the part over, as needed. With increasing integration across an entire production process, the need for feeders is sometimes reduced by supplying the components on tape packages or similar, that keep them oriented the same way during shipping and storage. These are most common in fields such as electronics, where components must be used in a particular orientation, but this cannot be detected mechanically. OEE is the series of matrices which can be use for the utilization of machine at the job level, shift level, overall plan or enterprise level. Any firm typically made a large investment in a piece of capital machinery and, in theory, it could run 24 hour a day for seven days a week at its optimum Speed. If it did this you gain the maximum value from the investment. In reality there is number of element that can be affect the value gained from the investment. So that fully utilization of equipment can be done. Hence for fully utilization of any equipment any firm must have to calculate OEE. OEE is stands for overall equipment effectiveness. Essential it is a single figure that significances the utilization of machine. This can be at a job level, shift level, overall plan or enterprise level. OEE is a measure of total equipment performance. OEE is also a three part analysis tool for equipment performance based on actual availability, Performance Analysis using OEE Mayur N. Nagdiya1 Mr. Kiran Bhabhor2 1 ME Student 2 Associate Professor 1, 2 Department of Mechanical Engineering 1, 2 GEC, Dahod (GTU, Ahmadabad)
  • 2. Performance Analysis using OEE (IJSRD/Vol. 1/Issue 4/ 2013/0045) All rights reserved by www.ijsrd.com 1003 performance efficiency, and quality of product or output. OEE is used in two format OEE data (information)” (the original intent) and a calculated “OEE percentage.” OEE data (information) are quantified loss reasons categorized by specific equipment related loss types. OEE percentage is a calculated relative comparison metric used for a specific equipment or process over a period of time. OEE is broken down into three measuring matrix of: 1) Availability ratio (AR) 2) Performance ratio (PR) 3) Quality rate (QR) A. Availability Rate (AR) The availability rate is the time the equipment is really running versus the time it could have been running. A reduced availability rate is an indication of equipment failure and issues around setup and adjustment Availability Rate = Run Time / Total Time B. Performance Rate (PR) The performance rate is the quantity of material produced during the running time versus the quantity of material that could have been produced when taking in to account the manufacturers documented speed of the equipment. A low performance rate can be seen as a result of idling minor stoppages and reduced speed operation Performance Rate = Actual Prod. / Standard Prod. C. Quality Rate (QR) The quality rate is the amount of acceptable material versus the total amount of material that is manufactured. A low quality rate is an indication of startup losses and the amount of scrap material. Quality rate = Good Count / Total Count II. CALCULATATION OF OEE WITH BOWL FEEDER By definition OEE is calculated as the product of availability, performance and quality rate OEE = AVAILABILITY x PERFORMANCE x QUALITY RATE In HARSHA ENGINEERS LTD. on 10th of November the data for OEE during one shift as below, SPM of press is 250 L+UL time 3 Batch no SLAC1211141 Item 32205 BJ2 (T8-line) SKF Shift A No of pockets 18 Line 4A 1) Now for the calculation of Availability, Total availability = 510min Available Min = 425 min M/c Cleaning = 60 min Tool Regrind and Resetting= 25 min So, by definition of availability, Availability Rate = Run Time / Total Time Here run time is 425 and total time is 510 Availability % = 425/510 Availability % = 83.33% 2) Now for calculation of performance rate Piece per minute = 8.19 Standard production rate = Act. Planned min. x piece per min. = 3480.00 Performance efficiency % = Actual. Production / standard production = 2750 / 3480 Performance efficiency % = 79.02 % 3) Now for calculation of quality rate, No. Scrap part = 20 By definition of quality rate, Quality rate % = Good Count / Total Count. = 2730 / 2750 Quality rate % = 99.27% Now by the definition of the OEE, OEE is calculate as, OEE = AVAILABILITY x PERFORMANCE x QUALITY RATE = 83.33 % x 79.02 % x 99.27 % OEE = 65.36 % III. WORLD CLASS OEE OEE is essentially the ratio of Fully Productive Time to Planned Production Time (refer to the OEE Factors section for a graphic representation). In practice, however, as we discussed above OEE is calculated as the product of its three contributing factors: OEE = Availability x Performance x Quality This type of calculation makes OEE a severe test. For example, if all three contributing factors are 90.0%, the OEE would be 72.9%. In practice, the generally accepted World- Class goals for each factor are quite different from each other, as is shown in the table below. OEE FACTOR WORLD CLASS 1) AVAILABILITY 85% 2) PERFORMANCE 100% 3) QUALITY RATE 100% So as above, OEE 85% Of course, every manufacturing plant is different. Worldwide studies indicate that the average OEE rate in manufacturing plants is 60%. As you can see from the above table, a World Class OEE is considered to be 85% or better. Hence comparing organization’s OEE and world class OEE we seen that the company OEE is very low compare to world class OEE, so our target is to achieve that figure. IV. DESIGN OF FLAT BELT CONVEYOR i. Live load = 3.30 kg/m
  • 3. Performance Analysis using OEE (IJSRD/Vol. 1/Issue 4/ 2013/0045) All rights reserved by www.ijsrd.com 1004 ii. Total Live Load = 3.30 × Length of conveyor = 3.30 × 1.8 = 5.952 kg. iii. Dead Load = The load consist of weight of roller belting and drive pulley = 52.8 kg iv. Belt pull = (A+B) × co-efficient of friction = (5.952 + 52.8) × 0.05 = 2.9376 kg v. Effective Belt Pull = total belt pull × 1.25 = 2.9376 × 1.25 = 3.672 kg vi. Tension T1 = effective belt pull × T1 factor = 3.672 × 1.42 = 5.2142 kg vii. Belt width = = = 110 mm viii. Effective Tension (Te) = Total empty friction + Load friction + Load slope tension Here, Return side Tension= Fe × W × L × 0.4 = 0.020 × 16.1 × 1.8 × 0.4 = 0.2318 kg/m Total Empty friction = Fe × (L + tf) ×W = 0.020 × (1.8+3) ×16.1 = 1.5456 kg. Carring Side empty Friction = Total friction – Return side friction = 1.5456 – 0.2318 = 1.3138 kg. Load Friction = F1 × (L+tf) × = 0.025 × (1.8+3) × 3.30 = 0.396 kg. Load slope tension = = 3.30 × 1.20 = 3.96 kg. So, effective tension Te = Total Empty Friction + Load Friction + Load slope tension = 1.5456 + 0.396 + 3.96 = 5.9016 kg. Te = 5.9016 kg. or Te = 57.9 N ix. Power Calculation: P = = = 0.44 HP x. Motor RPM Calculation: N = Here, Mt = × D × (F + µwg) = 0.5 ×0.120 × (2.9376 + 0.3×16.1×9.81) = 3.02 Nm N = = 1390 RPM Diameter of shaft: Total Load on Shaft = total live load + dead load = 5.952 + 52.8 = 58.752 kg = 576.36 N Load at Point C = load at Point D = = 288.18 N Here, Bending moment @ A=0 Bending moment @ B=0 So, . . B × 180 =0 RB × 180 = 51872.37 RB = 288.18 N Here, RA + RB = Total load So, RA = 288.18 N Bending Moment @ C = 288.15 × 15 = 4322.7 N-mm Bending Moment @ D = 288.15 × 15 = 4322.7 N-mm So, Maximum Bending Moment M = 4322.7 N-mm Here Torque, T = = = 22.1328 N-M = 22.1328 × 103 N-mm Te = √ =√ = 22.55 × 103 N-mm We know, Te = × × d3 22.55 × 103 = × 42 × d3 d3 = d= 14.2 mm take d = 18 mm V. CALCULATATION OF OEE WITH CONVEYOR In Harsha Engineers Ltd. On 15th of March the data for OEE during one shift are as below, SPM of press is 250 L+UL time 3
  • 4. Performance Analysis using OEE (IJSRD/Vol. 1/Issue 4/ 2013/0045) All rights reserved by www.ijsrd.com 1005 Batch no SLAC1303126 Item R - 30 - 76XJ NSK (SUZHOU, CHINA) Shift A No of pockets 18 Line 4A 1) Now for the calculation of Availability, Total availability = 510min Available Min = 405 min Total Down Time = 105 min So, by definition of availability, Availability Rate = Run Time / Total Time Here run time is 405 and total time is 510 Availability % = 405/510 Availability % = 79.41% 2) Now for calculation of performance rate, Piece per minute = 8.19 Standard production rate = Act. Planned min. x piece per min. = 3480.00 Performance efficiency % = Actual Production / standard production = 3283 / 3480 Performance efficiency % = 94.33 % 3) Now for calculation of quality rate, No. Scrap part = 179 pices. By definition of quality rate, Quality rate % = Good Count / Total Count. = 3104 / 3283 Quality rate % = 94.55% Now by the definition of the OEE, OEE is calculate as, OEE = AVAILABILITY x PERFORMANCE x QUALITY RATE = 79.41 % x 94.33 % x 94.55 % OEE = 70.82 % Fig.2: New arrangement VI. COMPARISON OF OEE’S FOR BOTH SYSTEMS 1) Average OEE: 2) Availability ratio (AR): 3) Performance ratio (PR):
  • 5. Performance Analysis using OEE (IJSRD/Vol. 1/Issue 4/ 2013/0045) All rights reserved by www.ijsrd.com 1006 4) Quality Rate VII. DEFECT REJECTION STATUS DURING PRODUCTION Fig. 3: Defect Rejection Diagram VIII. ANALYSIS OF DATA AND CONCLUSION Now as above discussed data we can say after using conveyors OEE increases but the drawback is, AR and QR decreases. The reasons for this are as follow: (1) Cages were falling down from the conveyors. Due to this, defects like bend, dent, missing of cages and line marks on cages were found. Now for avoiding this, guide ways of M.S. were placed on both the sides of the conveyor. Because of this, cages stopped falling. But now, by applying guide ways, the cage comes in the contact with the guide way material and this results in the dents in the cages. To overcome this problem, we replaced the material of the guide way from M.S. to Aluminum because of its low wear rate. Also nylon rubber sheet were introduced between the material contacts so that it doesn’t go weak and dents were avoided by this. (2) The above mentioned remedy was useful to stop the falling of the cages but as we all know the capacity of the facing is double than that of notching. So whenever 1 piece undergoes the notching operation, 2 pieces finishes the facing operation. Now due to this the conveyor gets filled within 4-5 minutes and cages have to stay awaiting one over the other. (3) Since the cages are not arranged in a proper manner on the conveyor, it results in uneven loading in the notching process and it doesn’t fit on the collets. Due to this, defects like bottom height variation, pocket missing and pocket shifting are generated. (4) For the solution of this problem we placed block sensors in such a manner that its master panel is functioned with ON-OFF Delay Time for the Facing process. Here the facing machine is given the ON Delay Time of 2 seconds and OFF Delay Time of 3 seconds. (5) But due to this, feeding has to be done manually in different parts in accordance with the part numbers. If this was not done, the cage would overflow and ultimately defect gets generated. (6) This way by using conveyor OEE is improved as per our target. PR increases up to 14.49 % but AR gets decreased by 5.13 % and due to the generation of various defects QR also foes down by 3.46%. As discussed above AR goes down because of the following losses: (1) Set Up Losses: Suppose cages gets fit unevenly on the collets and when the notching process starts, according to the cage design there remains gap between the cage and the die punch, die punch has to be re-grinded and during this period machine remains OFF which ultimately affects the A . Also “BU S” are seen on the cages. (2) By die punch re-grinding tool rework loss increases and this also directly affects the AR. (3) After the die punch re-grinding, its settings are configured. Then onwards 2-3 pieces are hindered for quality checking which affects the QR and rejection is also increased. (4) Lines are often reset because either cages fall down or get blocked or gets one over the other. This generates “Line Organization Losses”. (5) After making the die punch it has to be set and adjusted according to the measurements. In this way this loss is also generated.
  • 6. Performance Analysis using OEE (IJSRD/Vol. 1/Issue 4/ 2013/0045) All rights reserved by www.ijsrd.com 1007 Ultimately AR reduces to 5.13 %, PR Increase to 14.49 % and QR reduces to 3.46%. This way we started the analysis again. Our target OEE is 85% whereas OEE achieved is 70.91 % so further modifications are to be done by analysis and data collection. IX. CONCLUSION For fully utilization of any equipment any firm must have to calculate OEE. This paper represents the methodology applied in increasing the OEE of an Organization by exchanging the feed mechanism from Bowl Feeder to a Conveyor. Hence our main focus is on first pillar i.e. overall equipment efficiency . Today Harsha’s bench mark is 70% OEE. But as per world class OEE measure is 85% for a single line. So we have to achieve that target for achieving company’s goal. So after achieving 85% OEE we have increase the production. Also improve in quality of product and performance of machine. REFERENCES [ ] Seema S. Vanamane, Pravin A. Mane “Design, Manufacture and Analysis of Belt Conveyor System used for Cooling of Mould”, International Journal of Engineering Research and Applications (IJERA). [2] A. M. Guthrie and J. R. Pilcher, Moreland Technical and Engineering Consultants ltd. “The Design of Belt Conveyors for Bulk Sugar Handling”, Presented at Proceedings of The South Africun Sugar Technologists' Association. [3] Mr. aghvendra Singh gurjar “Failure Analysis of Belt Conveyor system in a Thermal Power plant”, IJATE . [4] A.W. Roberts and A. Harrison, Dean, Faculty of Engineering, University of New Castle, Australia, Principal Research Scientist, Division of Applied Physics, Csiro, Australia, “ ecent esearch Developments In Belt Conveyor Technology”. [5] Prof.dr.ir. Gabriel Lodewijks Delft University of Technology, The Netherlands “Two Decades Dynamics of Belt Conveyor Systems” [6] G. Lodewijks, The Netherlands “The Design of High Speed Belt Conveyors” [7] Ulf Richter, ABB Automation, Germany “Large belt conveyor systems” [8] Industrial Engineering By L C Jhamb, 4th edition Everest Publishing House. [9] M. A. Alspaugh, Overland Conveyor Co., Inc. “Latest Developments in Belt Conveyor Technology”, Presented at MINExpo 2004 Las Vegas, NV, USA [10] G. Lodewijks, The Design of High Speed Belt Conveyors The Netherlands.