IAS 11: Construction Contracts




                          Roshankumar S Pimpalkar




roshankumar.2007@rediffmail.com
This standard prescribes the accounting of costs and revenues associated
      with construction contracts.

      Key Definitions:

      Construction contract is a contract specifically negotiated for the construction
      of an asset or a combination of assets that are closely interrelated or
      interdependent in terms of design, technology and function or their ultimate
      purpose or use.

      Fixed Price contract is a construction contract in which the contractor agrees
      to a fixed contract price or a fixed rate per unit of output, which in some cases
      is subject to cost escalation clauses.

      Cost Plus contract is a construction contract in which a contractor is
      reimbursed for allowable or otherwise defined costs, plus a percentage of
      these costs or a fixed price.

      Guidance by IFRIC 15: Agreements for Construction of Real Estate.

      An agreement for construction of a real estate is a construction contract within
      the scope of IAS 11 only when the buyer is able to specify the major structural
      elements of the design of the real estate before the construction begins and/or
      specify major structural changes once construction is in progress (whether he
      exercises that ability or not). If the buyer does not have that ability then IAS 18
      applies.

      Combining and Segmenting Construction Contracts

      When a contract covers number of assets construction of each asset should
      be considered as a separate construction contract when:

             Separate proposals have been submitted for each asset
             Each asset has been submitted for separate negotiation and the
             contractor and customer have been able to accept or reject that part of
             the contract relating to each asset and
             The costs and revenues of each asset can be identified.

      A group of contract, whether with a single customer or with several
      customers, should be treated as single construction contract when:

             The group of contract is negotiated as single package
             The contracts are so closely interrelated that they are, in effect, a part
             of a single project with an overall profit margin, and
             The contracts are performed concurrently or in a continuous sequence.

      A contract may provide construction of an additional asset at the option of the
      customer or may be amended to include the construction of an additional




roshankumar.2007@rediffmail.com
asset. The construction of an additional asset should be treated as a separate
      construction contract when:

             The asset differs significantly in design, technology or function from the
             asset or asset covered by the original contract, or
             The price of the asset is negotiated without regard to the original
             contract price.




      Contract Revenue

      Contract revenue should comprise:

              The initial amount of revenue agreed in the contract; and
              Variations in the work, claim and incentive payments:
                  o To the extent that is probable that they will result in revenue i.e.
                      the customer will approve the variation and amount of
                      revenue arising out of variation; and
                  o They are capable of being reliably measured
              Incentive payments are additional amounts paid to the contractor is
              specified performance standards are met or exceeded. It is included in
              the contract revenue when:
                  o The contract is sufficiently advanced that it is probable that the
                      specified performance standards will be met or exceeded, and
                  o The amount of incentive payment can be measured reliably.
              A claim is an amount which a contractor seeks from the customer or
              another party as a reimbursement for costs not included in contract
              price. It is included in contract price when:
                  o Negotiations have reached advanced stage such that it is
                      probable that the customer will accept the claim; and
                  o The amount of claim can be measured reliably.
              Probability means more likely than not.

       Contract Cost

       Contract costs should comprise of

              Costs that relate directly to the specific contract
              Costs that are attributable to the contract in general and can be
              allocated to the contract, and
              Such other costs as are specifically chargeable to the customer under
              the terms of the contract




roshankumar.2007@rediffmail.com
Costs incurred in securing the contract are also included in contract
              costs they can be identified, reliably measured and it is probable that
              the contract will be obtained. However if such costs are recognised as
              an expense in the period in which they are incurred then they are not
              included in contract cost when the contract is obtained in a subsequent
              period.

       Recognition

       Contract revenue and contract costs associated with a construction contract
       should be recognised as revenue and expenses respectively by reference to
       the stage of completion of the contract activity at the end of the reporting
       period when the outcome of the construction contract can be estimated
       reliably.

       Any expected loss on the contract should be recognised as an expense
       immediately.

       Fixed Price Contract

       In this type of contract the outcome can be estimated reliably when all of the
       following conditions are satisfied:

              Total contract revenue can be measured reliably
              It is probable that economic benefits associated with contract will flow
              to the enterprise
              Both the contract cost to complete the contract and stage of
              completion can be measured reliably, and
              Contract costs attributable to the contract can be measured reliably
              and can be identified clearly, so that the actual costs incurred can be
              compared with prior estimates.

       Cost Plus Contract

       In this type of contract outcome can be estimated reliably when all of the
       following conditions are satisfied

              It is probable that the economic benefits associated with the contract
              will flow to the enterprise; and
              Contract costs attributable to the contract, whether or not specifically
              reimbursable, can be clearly identified and measured reliably.

       Capitalisation of costs

       Contract costs incurred that relate to future activity on the contract are
       recognised as an asset provided it is probable that they will be recovered.




roshankumar.2007@rediffmail.com
Such costs represents amount due from customer and are classified as work
       in progress.

       When an uncertainty about the collectability of revenue already
       recognised in the statement of comprehensive income arises, the
       uncollectable amount is recognised as an expense rather than an adjustment
       to contract revenue.

       When the outcome of the construction contract cannot be estimated
       reliably:

              Revenue should be recognised only to the extent of contract costs
              incurred and if the recovery is probable; and
              Contract costs should be recognised as an expense in the period in
              which they are incurred

        In this case no profit is recognised. Once the outcome of construction
       contract can be estimated reliably, profit can be recognised.

       When it is probable that that total contract cost will exceed total contract
       revenue, the expected loss should be recognised as an expense
       immediately. In such case amount of loss to be recognised is expected loss
       plus profit recognised earlier less loss recognised in current year.

        Determining the stage of completion

       Depending on the nature of construction contract the method used to
       determine the stage of completion of the contract are as follows:

              The ratio – contract cost incurred to for the work performed to date /
              estimated total contract cost
              Surveys of work performed; or
              Completion of physical proportion of contract




roshankumar.2007@rediffmail.com

IAS 11

  • 1.
    IAS 11: ConstructionContracts Roshankumar S Pimpalkar roshankumar.2007@rediffmail.com
  • 2.
    This standard prescribesthe accounting of costs and revenues associated with construction contracts. Key Definitions: Construction contract is a contract specifically negotiated for the construction of an asset or a combination of assets that are closely interrelated or interdependent in terms of design, technology and function or their ultimate purpose or use. Fixed Price contract is a construction contract in which the contractor agrees to a fixed contract price or a fixed rate per unit of output, which in some cases is subject to cost escalation clauses. Cost Plus contract is a construction contract in which a contractor is reimbursed for allowable or otherwise defined costs, plus a percentage of these costs or a fixed price. Guidance by IFRIC 15: Agreements for Construction of Real Estate. An agreement for construction of a real estate is a construction contract within the scope of IAS 11 only when the buyer is able to specify the major structural elements of the design of the real estate before the construction begins and/or specify major structural changes once construction is in progress (whether he exercises that ability or not). If the buyer does not have that ability then IAS 18 applies. Combining and Segmenting Construction Contracts When a contract covers number of assets construction of each asset should be considered as a separate construction contract when: Separate proposals have been submitted for each asset Each asset has been submitted for separate negotiation and the contractor and customer have been able to accept or reject that part of the contract relating to each asset and The costs and revenues of each asset can be identified. A group of contract, whether with a single customer or with several customers, should be treated as single construction contract when: The group of contract is negotiated as single package The contracts are so closely interrelated that they are, in effect, a part of a single project with an overall profit margin, and The contracts are performed concurrently or in a continuous sequence. A contract may provide construction of an additional asset at the option of the customer or may be amended to include the construction of an additional roshankumar.2007@rediffmail.com
  • 3.
    asset. The constructionof an additional asset should be treated as a separate construction contract when: The asset differs significantly in design, technology or function from the asset or asset covered by the original contract, or The price of the asset is negotiated without regard to the original contract price. Contract Revenue Contract revenue should comprise: The initial amount of revenue agreed in the contract; and Variations in the work, claim and incentive payments: o To the extent that is probable that they will result in revenue i.e. the customer will approve the variation and amount of revenue arising out of variation; and o They are capable of being reliably measured Incentive payments are additional amounts paid to the contractor is specified performance standards are met or exceeded. It is included in the contract revenue when: o The contract is sufficiently advanced that it is probable that the specified performance standards will be met or exceeded, and o The amount of incentive payment can be measured reliably. A claim is an amount which a contractor seeks from the customer or another party as a reimbursement for costs not included in contract price. It is included in contract price when: o Negotiations have reached advanced stage such that it is probable that the customer will accept the claim; and o The amount of claim can be measured reliably. Probability means more likely than not. Contract Cost Contract costs should comprise of Costs that relate directly to the specific contract Costs that are attributable to the contract in general and can be allocated to the contract, and Such other costs as are specifically chargeable to the customer under the terms of the contract roshankumar.2007@rediffmail.com
  • 4.
    Costs incurred insecuring the contract are also included in contract costs they can be identified, reliably measured and it is probable that the contract will be obtained. However if such costs are recognised as an expense in the period in which they are incurred then they are not included in contract cost when the contract is obtained in a subsequent period. Recognition Contract revenue and contract costs associated with a construction contract should be recognised as revenue and expenses respectively by reference to the stage of completion of the contract activity at the end of the reporting period when the outcome of the construction contract can be estimated reliably. Any expected loss on the contract should be recognised as an expense immediately. Fixed Price Contract In this type of contract the outcome can be estimated reliably when all of the following conditions are satisfied: Total contract revenue can be measured reliably It is probable that economic benefits associated with contract will flow to the enterprise Both the contract cost to complete the contract and stage of completion can be measured reliably, and Contract costs attributable to the contract can be measured reliably and can be identified clearly, so that the actual costs incurred can be compared with prior estimates. Cost Plus Contract In this type of contract outcome can be estimated reliably when all of the following conditions are satisfied It is probable that the economic benefits associated with the contract will flow to the enterprise; and Contract costs attributable to the contract, whether or not specifically reimbursable, can be clearly identified and measured reliably. Capitalisation of costs Contract costs incurred that relate to future activity on the contract are recognised as an asset provided it is probable that they will be recovered. roshankumar.2007@rediffmail.com
  • 5.
    Such costs representsamount due from customer and are classified as work in progress. When an uncertainty about the collectability of revenue already recognised in the statement of comprehensive income arises, the uncollectable amount is recognised as an expense rather than an adjustment to contract revenue. When the outcome of the construction contract cannot be estimated reliably: Revenue should be recognised only to the extent of contract costs incurred and if the recovery is probable; and Contract costs should be recognised as an expense in the period in which they are incurred In this case no profit is recognised. Once the outcome of construction contract can be estimated reliably, profit can be recognised. When it is probable that that total contract cost will exceed total contract revenue, the expected loss should be recognised as an expense immediately. In such case amount of loss to be recognised is expected loss plus profit recognised earlier less loss recognised in current year. Determining the stage of completion Depending on the nature of construction contract the method used to determine the stage of completion of the contract are as follows: The ratio – contract cost incurred to for the work performed to date / estimated total contract cost Surveys of work performed; or Completion of physical proportion of contract roshankumar.2007@rediffmail.com