SlideShare a Scribd company logo
Central Networks Earthing Manual 
Section E2 
Earthing Guidance Notes 
Version: 2 Date of Issue: September 2007 
Author: Nigel Johnson Job Title: Earthing Specialist 
Approver: John Simpson Job Title: Head of Network Engineering
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
Revision Log 
Version 2 Prepared by Nigel Johnson Date August 2007 
Revision and update of section to be issued as part of a combined Earthing 
Manual. 
The main alterations are:- 
Section E1 and E2 have been re-arranged/revamped for increased clarity. 
Section E2.2 to E2.5 - greater detail on recent changes to earthing policy, including 
classification of Distribution sites as either Hot or Cold. 
Section E2.7 - detailed requirements for provision of Primary Substation Hot site 
register 
Section E2.8 - detailed description of earth systems used throughout Company’s 
networks from LV to 132kV, including new 11kV NER earthing arrangements. 
Version 1 Prepared by Tony Haggis Date February 2001 
Version 2 Date of Issue - September 2007 Page 2 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
First draft.
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
Contents 
E2 EARTHING GUIDANCE NOTES 4 
E2.1 INTRODUCTION 4 
E2.2 WHAT ARE SIGNIFICANT RECENT CHANGES? 4 
E2.3 WHAT MAKES A DISTRIBUTION SUBSTATION ‘HOT’ OR ‘COLD’? 5 
E2.4 SEGREGATED HV AND LV EARTHS AT DISTRIBUTION SUBSTATIONS 5 
E2.5 STANDARD DISTRIBUTION EARTHING METHODOLOGY 6 
E2.6 DIFFICULT OR NON-STANDARD SITUATIONS 6 
E2.7 HOT PRIMARY AND GRID SITES 7 
E2.8 METHODS OF EARTHING USED ON THE COMPANY’S NETWORKS 7 
E2.8.1 132kV Network.....................................................................................................................7 
E2.8.2 66kV & 33kV Networks ........................................................................................................7 
E2.8.3 25kV Networks.....................................................................................................................8 
E2.8.4 11kV (& 6.6kV) Networks.....................................................................................................8 
E2.8.5 Earthing of Low Voltage Networks.....................................................................................10 
E2.8.5.1 Provision of LV Earthing Terminal ..................................................................................11 
Version 2 Date of Issue - September 2007 Page 3 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
E2 Earthing Guidance Notes 
E2.1 Introduction 
There have been few changes to Electricity Supply Industry earthing standards and practices 
since the introduction of Protective Multiple Earthing in the 1970’s. 
However, the widespread introduction of electronic equipment used in conjunction with 
telephone lines (i.e. fax machines, computer modems etc.) has highlighted the issue of Earth 
Potential Rise (EPR) and Transferred Potentials. 
There have been incidents of damage to electronic equipment during supply system earth faults 
and also transfers of potential into telecommunications systems. The European 
telecommunications industry has been increasingly concerned over the danger to their 
equipment and staff from transferred potentials. 
The problem has been further exacerbated by the use of cables with plastic oversheaths (Alpex, 
PIAS, Triplex etc). This means there is now more reliance on substation earth electrodes 
instead of the lead cable sheaths that provided much of the earthing system in the past. Another 
factor is the reduction in size of distribution plant which enables substations to be built on 
smaller plots which are then more difficult to earth. 
This has resulted in the European telecommunications industry driving through changes to 
earthing standards that now place onerous duties on the electricity supply industry to protect 
persons from electric shock due to Earth Potential Rise which results in Touch, Step & Transfer 
Potentials. 
This legislation is risk assessment based. The effects of electricity on persons varies between 
people depending on such things as their age, state of health, type of footwear duration of fault 
etc, Also the effectiveness of earthing system varies according to soil types, surface cover 
material, weather conditions etc. It is incumbent on individual electricity companies to design, 
install and maintain their systems such that they satisfy the objectives set by of legislation. 
This section of the Earthing Manual highlights the main changes now incorporated into Central 
Networks standards in order to fulfil our obligations. 
E2.2 What are Significant Recent Changes? 
Version 2 Date of Issue - September 2007 Page 4 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
• Hot/Cold Distribution Sites 
The greatest recent change is the classification of ground mounted distribution sites as 
either ‘Hot’ or ‘Cold’. 
• One Ohm Rule 
Previously, regulations permitted combining HV and LV earths at ground mounted 
distribution sites when the resistance was below 1 ohm. This rule is no longer valid for 
new sites. 
• 3m Separation Pole Mounted Earths 
In the past HV and LV earths were separated by 3m at pole mounted transformers. This 
separation is now no longer sufficient.
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
Version 2 Date of Issue - September 2007 Page 5 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
• 11kV Neutral Earthing 
A new NER arrangement has been adopted for earthing of 11kV systems. 
E2.3 What makes a distribution substation ‘Hot’ or ‘Cold’? 
At Grid or Primary Substations the EPR will be calculated on a site by site basis. However, this 
approach is not practicable for distribution sites because of the large numbers involved, 
therefore some simplified rules are used to determine ‘Hot’ or ‘Cold’ status. These rules are:- 
• The site is considered ‘Cold’ if the installation is connected to a Primary or Grid 
Substation via an underground cable without any overhead line in the route. In this 
case the majority of the earth fault current will return to source via the cable sheath 
and not through the ground – hence the EPR will be below 430 volts. The HV & LV 
Earth can be combined. 
• The site is considered ‘Hot’ if there is not a continuous underground cable back to 
the Primary or Grid Substation. Earth fault current must return to source through the 
ground and this causes an EPR which is assumed to be above the 430 volt limit. The 
HV & LV Earths must be segregated to prevent voltages in excess of 430 volts from 
being transferred into the LV neutral/earth system 
The alternative backfeeding arrangements must also be considered when assessing the 
hot/cold status. For normal running conditions the site may be cold (i.e. underground fed) but 
could be classified as hot if all the alternative backfeeds have overhead lines as part of the 
circuit back to the source. If the normal feed is all underground and at least one backfeed is also 
all underground then the site can be classified as cold since the substation is unlikely to be 
disconnected from a low resistance primary substation site. 
To achieve an EPR less than 430 volts at an overhead fed 11kV distribution substation, then the 
overall earth value would typically need to be less than 0.3 - 0.5 ohms. Often it is impractical to 
achieve such low earth resistance values at distribution sites hence the HV and LV earths will 
usually be segregated. However, if it is decided to combine the HV and LV earths then a site 
specific calculation must be made to confirm the EPR is actually below 430volts. 
Existing distributions sites shall be assessed to determine the site classification when significant 
material changes occur. This is especially important when an 11kV network is being 
reconfigured to make sure a site is not inadvertently made hot without further precautions being 
taken. 
Also distribution substations may also become hot if they are connected via cable to a nearby 
Hot Primary or Grid site. 
E2.4 Segregated HV and LV earths at Distribution Substations 
It is accepted that at some sites the earths will be unnecessarily segregated. This is particularly 
true in large villages or small towns which have a reasonably large earth system which is 
‘islanded’ because the incoming circuits are all overhead. If the cost of segregation is 
prohibitively high or impractical then the cost of a full earthing study may be justified.
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
In the past most pole transformers have had separate HV/LV earths, whereas the 
vast majority of ground mounted substations have had a combined HV/LV earth. 
Previously the regulations permitted joining the HV and LV earths when their 
combined resistance was less than 1 ohm. This has now changed – the old ‘1 ohm 
rule’ is no longer valid for new sites. 
If in doubt, treat it as ‘Hot’ and segregate the two earths. 
The LV earth system must be located outside of the 430 volt potential contour that surrounds 
the HV earth electrode during an 11kV earth fault. This distance varies and depends on the type 
of installation, the local soil resistivity value and the size of the HV earth mat. In very high 
resistivity soils this separation can be over 40 metres for a pole mounted site. 
Typically pole mounted HV & LV earths were separated by 3 metres to avoid 
transferring excessive voltages via the ground. The 3m separation distance is now 
no longer sufficient. 
The new separation distances have been calculated by an earth modelling computer 
programme and are detailed in Section “E5 Distribution Standard Earthing Layouts”. 
E2.5 Standard Distribution Earthing Methodology 
Because there are numerous distribution installations, standard earthing arrangements have 
been adopted. The following three sections of the Earthing Manual can be used to predict the 
type and size of the earth system for the most common values of soil resistivity. 
E3 Soil Resistivity Measurements 
E4 Earth Electrode Resistance Tests 
E5 Distribution Standard Earthing Layouts 
This will help advise landowners of the extent of proposed earthing excavation before work 
starts and to estimate the quantity of earthing materials required to complete the installation. 
E2.6 Difficult or non-standard situations 
The Distribution Standard Earthing Layouts are designed to cover the majority of situations and 
a standard solution should be the first approach. Sometimes this may mean placing a 
transformer some distance away from a third party installation in order to maintain adequate 
HV/LV segregation. 
However, there will be occasions where the standard approach is not practical or the soil 
resistivity is so high that specialist advice is required to overcome specific site difficulties. The 
cost of this has to be borne by the project. 
For advice please contact the Central Networks Earthing Specialist or initiate a survey using 
one of the approved earth consultants listed in Section AE1.1. 
Version 2 Date of Issue - September 2007 Page 6 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
E2.7 Hot Primary and Grid Sites 
All Primary or Grid sites shall have the EPR assessed and the details recorded on the 
Company’s hot site register. This information shall be made available to the relevant 
telecommunications companies. The owner of the Central Network’s hot site register shall be 
listed on the Energy Networks Association’s, Rise of Earth Potential website to provide the 
telecommunication companies with a point of contact. The information to be made available on 
request is:- 
• Hot/Cold site classification (based on either 650 or 430 volt limits) 
• Grid Reference or address of the site 
• Extent of the hot zone (if known), otherwise quote 100m (as detailed in ENA ER 
Version 2 Date of Issue - September 2007 Page 7 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
S36). 
Hot Primary/Grid sites require an isolation unit fitting to all incoming telecomms circuits. 
Telecomms circuits passing through the hot zone surrounding a primary or grid site require no 
specific precautions unless the EPR at the point of the telecomms circuit exceeds 1700 Volts for 
sites with fast protection clearance (i.e. less than 0.2 seconds) or 1150 volts for slower 
protection clearance times. ENA ER S36 provides more detail. 
Where reasonably practicable all new primary/grid sites shall be designed as cold sites. Where 
a cold site is impractical then any distribution sites that are cable connected to the new site shall 
be assessed to determine the EPR at that location. If the distribution site is declared hot for a 
fault at the primary substation then the HV and LV earths must be segregated. 
In general new LV supplies feeding a Primary or Grid site shall be derived from a dedicated on-site 
transformer. This transformer should not be used to provide LV supplies to customers off 
the site. If in doubt or where existing LV supplies are involved with supplying off-site third parties 
then refer to the Central Networks Earthing Specialist for further advice. 
E2.8 Methods of Earthing used on the Company’s Networks 
An application guide is available that provides greater detail on neutral earthing requirements 
for the Company’s HV and EHV networks. Figure E2.1 shows typical neutral earthing 
arrangements found on Central Networks systems. 
E2.8.1 132kV Network 
The 132kV network is a three wire, three phase network, except for the railway traction 
supplies which is a single phase 25kV system, with one pole earthed. 
All 400/132kV and 275/132kV transformers have their star points solidly connected to earth. 
Transformers at 132/66kV, 132/33kV and 132/11kV will also have the star point of each 132kV 
winding solidly connected to earth, in effect forming a multiple earthed system. This multiple 
direct earthing gives rise to the large earth fault currents experienced on the 132kV system. 
E2.8.2 66kV & 33kV Networks 
The 132/66kV and 132/33kV transformers are usually delta connected on the secondary side. 
These 33 or 66kV windings will be earthed by an earthing transformer. In the past the earthing
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
transformer may have been low impedance in which case an NER would also be required to 
limit the earth fault current to an acceptable value. 
For new installations each earthing transformer should be high impedance to limit the 
prospective earth fault current to match the full load current of the main transformer up to a 
maximum of 1000Amps. 
Table E2.3 Earth fault limits for 132/33 and 132/66kV transformers 
Version 2 Date of Issue - September 2007 Page 8 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
Main Transformer 
rating 
(MVA) 
33kV High Impedance 
Earthing Transformer -Earth 
Fault Rating (Amps) 
66kV High Impedance 
Earthing Transformer – 
Earth Fault Rating (Amps) 
15 260 - 
20 350 175 
30 525 260 
40 700 350 
45 800 400 
60 1000 525 
75 1000 650 
90 1000 800 
120 and above 1000 1000 
E2.8.3 25kV Networks 
This is a single phase system for provision of supplies for railway traction systems. One pole 
of the secondary output of the 132/25kV winding is solidly earthed. The pole to be earthed is 
governed by and set out in Engineering Recommendation P24 “A. C. Traction Supplies to 
British Railways.” 
E2.8.4 11kV (& 6.6kV) Networks 
Depending on the vector group, 132/11kV, 66/11kV and 33/11kV transformers can have the 
secondary winding either delta or star connected. These transformers will be earthed on the 
secondary side either by an earthing transformer (if delta connected) or via the star point. 
Historically, small rating transformers (typically those less than 10MVA) had their 
secondary neutral solidly connected to earth. On all other transformers the 
secondary neutral was impedance earthed i.e. via a resistor or reactor. 
There are a number of existing arrangements for NER configurations at 11kV. In general either 
one NER was used across the site to earth all the transformer neutrals or alternatively each 
transformer had its own individual NER. 
The existing 11kV neutral earthing philosophy has three main requirements:- 
• to limit the overall prospective earth fault currents for any site to be less than 
1500Amps for normal running arrangements. This has the benefit of reducing 
EPRs throughout the whole 11kV network. 
• to ensure there is sufficient earth fault current to operate protection at remote 
ends of the 11kV network.
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
• to ensure the transformer neutrals are not solidly earthed at any time. This 
prevents excessive earth fault currents from occurring on the network. 
This can be achieved in a number of ways and depends on the number of transformer at the 
site. This often involves the use of a specially designed switching cubicle for each transformer 
which controls the NER running arrangements across the site. It should be noted that the new 
philosophy prevents the use of high impedance earthing transformers at 11kV. The preferred 
11kV NER size is 1000Amps but this can be modified to either 750 or 1500 Amps as detailed 
in the Neutral Earthing Application Guide. 
For new systems a typical arrangement would be as shown in the figure below. The switches 
would be configured so that one NER earths all transformers. The other ‘un-used’ NER would 
be available when a transformer is switched out for maintenance. 
Some double secondary transformers (also known as double bubble or three winding 
transformers) having delta secondaries have been installed using only one earthing 
transformer in conjunction with a Thompson Strap. The Thompson Strap is an electrical 
connection installed within the transformer tank between the two blue phase (or L3) secondary 
windings. By convention the earthing transformer is then connected to the ‘b’ secondary 
winding. This arrangement also provides an earth return path for faults fed from the ‘a’ 
winding. The use of Thompson Straps is still permitted. 
The new NER policy can still be applied to double secondary transformers as shown below. 
T1 switching cubicle 
B 
Version 2 Date of Issue - September 2007 Page 9 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
A 
C 
B 
T1 NER 
T1 
T1 switching 
cubicle 
A 
C 
B 
T2 NER 
T2 
T2 switching 
cubicle 
A C 
T1 NER 
T1b 
T1a 
To Common Neutral 
Earth Bar & adjacent 
transformer switching 
cubicle(s)
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
T1 switching cubicle 
B 
A C 
T1 NER 
Thompson Strap 
The earthing transformers in these situations will be a low impedance type. A nominal 
impedance must be designed into the earthing transformer to guard against the effects of a 
direct short circuit of the associated NER. 
In a very few instances the transformer secondary may be earthed by using an Arc 
Suppression Coil (ASC or Petersen Coil). The ASC is ‘tuned’ to the capacitance of the 11kV 
cables and overhead lines connected to the substation. This will minimise current at the fault 
position during a single phase to earth fault condition. If the fault persists then the system will 
automatically revert back to the normal resistor earthing arrangement. 
The 11/0.415kV distribution transformers have a delta connection on the primary winding and 
subsequently are therefore not earthed on the 11kV side. 
E2.8.5 Earthing of Low Voltage Networks 
The low voltage side of a three phase distribution transformer is star connected. This star point 
forms the neutral of the LV system and will be solidly connected to earth at all times. For single 
phase transformers one terminal will be designated as the neutral point and will again be 
solidly connected to earth. 
LV distribution networks can have a separate protective conductor (sheath earth system) or 
this can be combined with the neutral conductor (PME). Engineering Recommendation G12/3 
details the specific requirements for the application of PME on low voltage networks. 
• All new underground LV networks shall be constructed using CNE cables to 
establish a network suitable for the provision of PME terminals. 
• All new overhead LV networks shall be constructed using Aerial Bundled 
Conductors (ABC) suitable for providing PME terminals. 
Wherever substantive work (e.g. refurbishment, diversions etc..) is undertaken on LV networks 
then the network shall be brought up to a standard to provide PME supplies. This work should 
also ensure existing sheath earth customers do not have their existing earthing terminal 
compromised. 
Version 2 Date of Issue - September 2007 Page 10 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
T1b 
T1a 
Low Impedance 
Earthing 
Transformer 
To Common Neutral 
Earth Bar & adjacent 
transformer switching 
cubicle(s)
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
E2.8.5.1 Provision of LV Earthing Terminal 
The provision of a LV earthing terminal has been achieved by various means in the past. The 
present company policy with regard to the provision of a LV earth terminal is detailed below :- 
PME Terminal (TN-C-S) 
All new supplies, or existing customers requesting a load increase, will normally be 
offered a PME terminal. However, for reasons of safety some installations are not suitable 
for a PME earth terminal in which case a TT supply will be offered (see Section E6.3 for a 
detailed list of exceptions). Under the ESQC Regulations, the Company is not obliged to 
offer a free PME earth terminal to existing customers that do not already have a PME 
earth. 
Sheath Earth Terminal (TN-S) 
The Company has an ongoing obligation to maintain the integrity of the sheath earth 
terminal of customers which already have this type of earthing. If an existing sheath earth 
customer requests a service alteration or in the event of a fault repair then the existing 
sheath earth must be maintained unless the customer request a PME earth terminal 
instead. A sheath earth terminal shall not be made available to new customers (or existing 
customers if they do not already have an earth terminal). 
PNB Earthing 
PNB is a special method of earthing, similar to PME, where the neutral earth is installed at 
or adjacent to the customer’s installation instead of at the transformer position. This 
method can still be used provided the supply is from a dedicated pole mounted 
transformer supplying a single customer.. 
No Company Earth Terminal (TT) 
It is not possible for the Company to provide a PME earthing terminal where :- 
i) the customer’s installation does not conform to the statutory regulations 
regarding the provision of PME supplies. 
ii) the customers property is deemed to be unsuitable for a PME supply. 
In these circumstances the PME terminal shall be rendered inaccessible to prevent 
unauthorised access by third parties and the customer must be advised that it will be 
necessary to provide their own alternative means of earth fault protection (e.g. their own 
earth electrode and suitably sized RCD). 
Version 2 Date of Issue - September 2007 Page 11 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc
CN Earthing Manual 
Section E2 – Earthing Guidance Notes 
Neutral 
always 
solidly 
earthed. 
Version 2 Date of Issue - September 2007 Page 12 of 12 
The current version of the this document resides in the E.ON UK Documentum database 
CAUTION –any other copies in electronic, printed or other formats may be out of date 
© Central Networks plc 
Grid Supply 
Auto-Transformer 
400(or 275)/132kV 
Grid Substation 
Transformer 
132/33(or 66)kV 
Primary 
Substation 
Transformer 
33(or 66)/11kV 
Distribution 
Substation 
Transformer 
11kV/415V 
132kV 
33(or 66)kV 
11kV 
415V 
LV 
always 
solidly 
earthed 
Earthing 
Transformer 
Grid Supply 
Auto-Transformer 
400(or 275)/132kV 
132kV 
Grid Substation 
Double Secondary 
Transformer 
132/11/11kV 
‘A’ winding ‘B’ winding 
THOMPSON STRAP If only one earthing transformer 
has been used on a delta connected, double 
secondary transformer a connection is installed within 
the transformer tank between the blue phase or L3 
secondary windings. By convention the earthing 
transformer is connected to the ‘B’ winding. This 
arrangement effectively provides an earth return path 
for faults fed from the ‘A’ winding. 
Earthing 
Transformer 
(NOT REQUIRED 
if Thompson 
Strap used) 
Could be 
solid 
(historically), 
resistance or 
reactance 
earthed. 
11kV 11kV 
Earthing 
Transformer 
Figure E2.1 Typical Examples of Existing Neutral Earthing Arrangements 
NER will not be 
required if 
earthing 
transformer has 
high impedance. 
Could be solid 
(historically), 
resistance or 
reactance 
earthed. 
Steelwork earth 
only bonded to 
LV neutral earth 
if site is declared 
Cold. 
Neutral 
always 
solidly 
earthed. 
Could be 
solid 
(historically), 
resistance or 
reactance 
earthed. 
National Grid 
DNO 
National Grid 
DNO 
Note 
Occasionally the 
primary winding here 
may be a star 
connection. In which 
case the star point 
will not be earthed.

More Related Content

What's hot

Earthing Syatem
Earthing SyatemEarthing Syatem
Earthing SyatemNoman Khan
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Power System Operation
 
surge diverters
surge diverterssurge diverters
surge divertersnehakardam
 
Tiga Earth Mat Presentation
Tiga Earth Mat Presentation Tiga Earth Mat Presentation
Tiga Earth Mat Presentation SOURAV GHOSH
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 
Motor protection
Motor protectionMotor protection
Motor protectionH. Kheir
 
Neutral Grounding
Neutral GroundingNeutral Grounding
Neutral GroundingNoman Nomi
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introductionHimmelstern
 
Alternator protection
Alternator protectionAlternator protection
Alternator protectionjawaharramaya
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adamShaik Abdullah Adam
 
Transformer protection
Transformer protectionTransformer protection
Transformer protectionjawaharramaya
 
Generator grounding
Generator groundingGenerator grounding
Generator groundingmichaeljmack
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONPower System Operation
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 

What's hot (20)

Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
Earthing Syatem
Earthing SyatemEarthing Syatem
Earthing Syatem
 
Substation grounding
Substation grounding Substation grounding
Substation grounding
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
 
Lightning arrester
Lightning arresterLightning arrester
Lightning arrester
 
surge diverters
surge diverterssurge diverters
surge diverters
 
Tiga Earth Mat Presentation
Tiga Earth Mat Presentation Tiga Earth Mat Presentation
Tiga Earth Mat Presentation
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
 
Motor protection
Motor protectionMotor protection
Motor protection
 
Neutral Grounding
Neutral GroundingNeutral Grounding
Neutral Grounding
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Generator grounding
Generator groundingGenerator grounding
Generator grounding
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
Substation Earthing
Substation EarthingSubstation Earthing
Substation Earthing
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 

Similar to HV Substation Earthing Guide - Central Networks

E2 earthing manual earth guidance notes
E2 earthing manual earth guidance notesE2 earthing manual earth guidance notes
E2 earthing manual earth guidance notesbsganwal
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Ivan Rojas Soliz
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses reportkamal soni
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION Ravi Phadtare
 
Presentation best practice earthing and protection
Presentation   best practice earthing and protectionPresentation   best practice earthing and protection
Presentation best practice earthing and protectionMahesh Chandra Manav
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyMahesh Chandra Manav
 
Electrical wiring domestic and industries
Electrical wiring domestic and industriesElectrical wiring domestic and industries
Electrical wiring domestic and industriesPavan Kumar Mallepoola
 
Photovoltaic solar farm: earthing system design for cost reduction and syste...
Photovoltaic solar farm: earthing system design for  cost reduction and syste...Photovoltaic solar farm: earthing system design for  cost reduction and syste...
Photovoltaic solar farm: earthing system design for cost reduction and syste...IJECEIAES
 
Paper Electron Tube Afs Epri R5
Paper   Electron Tube   Afs Epri R5Paper   Electron Tube   Afs Epri R5
Paper Electron Tube Afs Epri R5John Kappenman
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manualCyber4Tech
 
“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...
“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...
“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...IRJET Journal
 
Presentation railtel (railway communication infra company) by jmv lps
Presentation railtel  (railway communication infra company) by jmv lpsPresentation railtel  (railway communication infra company) by jmv lps
Presentation railtel (railway communication infra company) by jmv lpsMahesh Chandra Manav
 
A distributed networked Monitoring and Electrical Energy Storage System to pr...
A distributed networked Monitoring and Electrical Energy Storage System to pr...A distributed networked Monitoring and Electrical Energy Storage System to pr...
A distributed networked Monitoring and Electrical Energy Storage System to pr...Haim R. Branisteanu
 
ppt nrel.pptx
ppt  nrel.pptxppt  nrel.pptx
ppt nrel.pptxgulie
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationSubhrajit Ghosh
 

Similar to HV Substation Earthing Guide - Central Networks (20)

E2 earthing manual earth guidance notes
E2 earthing manual earth guidance notesE2 earthing manual earth guidance notes
E2 earthing manual earth guidance notes
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
 
Solar doc
Solar docSolar doc
Solar doc
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses report
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
 
Presentation best practice earthing and protection
Presentation   best practice earthing and protectionPresentation   best practice earthing and protection
Presentation best practice earthing and protection
 
Presentation jmv internal
Presentation jmv internalPresentation jmv internal
Presentation jmv internal
 
5 power house
5 power house5 power house
5 power house
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periorty
 
Effect of grounding
Effect of groundingEffect of grounding
Effect of grounding
 
Electrical wiring domestic and industries
Electrical wiring domestic and industriesElectrical wiring domestic and industries
Electrical wiring domestic and industries
 
Photovoltaic solar farm: earthing system design for cost reduction and syste...
Photovoltaic solar farm: earthing system design for  cost reduction and syste...Photovoltaic solar farm: earthing system design for  cost reduction and syste...
Photovoltaic solar farm: earthing system design for cost reduction and syste...
 
Paper Electron Tube Afs Epri R5
Paper   Electron Tube   Afs Epri R5Paper   Electron Tube   Afs Epri R5
Paper Electron Tube Afs Epri R5
 
Substation
Substation Substation
Substation
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manual
 
“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...
“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...
“THE PROJECT REPORT ON WIRELESS CHARGING STATION FOR ELECTRIC VEHICLES WITH A...
 
Presentation railtel (railway communication infra company) by jmv lps
Presentation railtel  (railway communication infra company) by jmv lpsPresentation railtel  (railway communication infra company) by jmv lps
Presentation railtel (railway communication infra company) by jmv lps
 
A distributed networked Monitoring and Electrical Energy Storage System to pr...
A distributed networked Monitoring and Electrical Energy Storage System to pr...A distributed networked Monitoring and Electrical Energy Storage System to pr...
A distributed networked Monitoring and Electrical Energy Storage System to pr...
 
ppt nrel.pptx
ppt  nrel.pptxppt  nrel.pptx
ppt nrel.pptx
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv Substation
 

More from Thorne & Derrick International

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Thorne & Derrick International
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptThorne & Derrick International
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018Thorne & Derrick International
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick InternationalThorne & Derrick International
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-AThorne & Derrick International
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...Thorne & Derrick International
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Thorne & Derrick International
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RoweThorne & Derrick International
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandThorne & Derrick International
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DThorne & Derrick International
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...Thorne & Derrick International
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetThorne & Derrick International
 

More from Thorne & Derrick International (20)

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
Itron Fact Sheet
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
 

Recently uploaded

Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersSafe Software
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsPaul Groth
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3DianaGray10
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Alison B. Lowndes
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupCatarinaPereira64715
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingThijs Feryn
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...Elena Simperl
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Jeffrey Haguewood
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfCheryl Hung
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlPeter Udo Diehl
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Product School
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...Product School
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesBhaskar Mitra
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaRTTS
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)Ralf Eggert
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...BookNet Canada
 

Recently uploaded (20)

Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 

HV Substation Earthing Guide - Central Networks

  • 1. Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head of Network Engineering
  • 2. CN Earthing Manual Section E2 – Earthing Guidance Notes Revision Log Version 2 Prepared by Nigel Johnson Date August 2007 Revision and update of section to be issued as part of a combined Earthing Manual. The main alterations are:- Section E1 and E2 have been re-arranged/revamped for increased clarity. Section E2.2 to E2.5 - greater detail on recent changes to earthing policy, including classification of Distribution sites as either Hot or Cold. Section E2.7 - detailed requirements for provision of Primary Substation Hot site register Section E2.8 - detailed description of earth systems used throughout Company’s networks from LV to 132kV, including new 11kV NER earthing arrangements. Version 1 Prepared by Tony Haggis Date February 2001 Version 2 Date of Issue - September 2007 Page 2 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc First draft.
  • 3. CN Earthing Manual Section E2 – Earthing Guidance Notes Contents E2 EARTHING GUIDANCE NOTES 4 E2.1 INTRODUCTION 4 E2.2 WHAT ARE SIGNIFICANT RECENT CHANGES? 4 E2.3 WHAT MAKES A DISTRIBUTION SUBSTATION ‘HOT’ OR ‘COLD’? 5 E2.4 SEGREGATED HV AND LV EARTHS AT DISTRIBUTION SUBSTATIONS 5 E2.5 STANDARD DISTRIBUTION EARTHING METHODOLOGY 6 E2.6 DIFFICULT OR NON-STANDARD SITUATIONS 6 E2.7 HOT PRIMARY AND GRID SITES 7 E2.8 METHODS OF EARTHING USED ON THE COMPANY’S NETWORKS 7 E2.8.1 132kV Network.....................................................................................................................7 E2.8.2 66kV & 33kV Networks ........................................................................................................7 E2.8.3 25kV Networks.....................................................................................................................8 E2.8.4 11kV (& 6.6kV) Networks.....................................................................................................8 E2.8.5 Earthing of Low Voltage Networks.....................................................................................10 E2.8.5.1 Provision of LV Earthing Terminal ..................................................................................11 Version 2 Date of Issue - September 2007 Page 3 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc
  • 4. CN Earthing Manual Section E2 – Earthing Guidance Notes E2 Earthing Guidance Notes E2.1 Introduction There have been few changes to Electricity Supply Industry earthing standards and practices since the introduction of Protective Multiple Earthing in the 1970’s. However, the widespread introduction of electronic equipment used in conjunction with telephone lines (i.e. fax machines, computer modems etc.) has highlighted the issue of Earth Potential Rise (EPR) and Transferred Potentials. There have been incidents of damage to electronic equipment during supply system earth faults and also transfers of potential into telecommunications systems. The European telecommunications industry has been increasingly concerned over the danger to their equipment and staff from transferred potentials. The problem has been further exacerbated by the use of cables with plastic oversheaths (Alpex, PIAS, Triplex etc). This means there is now more reliance on substation earth electrodes instead of the lead cable sheaths that provided much of the earthing system in the past. Another factor is the reduction in size of distribution plant which enables substations to be built on smaller plots which are then more difficult to earth. This has resulted in the European telecommunications industry driving through changes to earthing standards that now place onerous duties on the electricity supply industry to protect persons from electric shock due to Earth Potential Rise which results in Touch, Step & Transfer Potentials. This legislation is risk assessment based. The effects of electricity on persons varies between people depending on such things as their age, state of health, type of footwear duration of fault etc, Also the effectiveness of earthing system varies according to soil types, surface cover material, weather conditions etc. It is incumbent on individual electricity companies to design, install and maintain their systems such that they satisfy the objectives set by of legislation. This section of the Earthing Manual highlights the main changes now incorporated into Central Networks standards in order to fulfil our obligations. E2.2 What are Significant Recent Changes? Version 2 Date of Issue - September 2007 Page 4 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc • Hot/Cold Distribution Sites The greatest recent change is the classification of ground mounted distribution sites as either ‘Hot’ or ‘Cold’. • One Ohm Rule Previously, regulations permitted combining HV and LV earths at ground mounted distribution sites when the resistance was below 1 ohm. This rule is no longer valid for new sites. • 3m Separation Pole Mounted Earths In the past HV and LV earths were separated by 3m at pole mounted transformers. This separation is now no longer sufficient.
  • 5. CN Earthing Manual Section E2 – Earthing Guidance Notes Version 2 Date of Issue - September 2007 Page 5 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc • 11kV Neutral Earthing A new NER arrangement has been adopted for earthing of 11kV systems. E2.3 What makes a distribution substation ‘Hot’ or ‘Cold’? At Grid or Primary Substations the EPR will be calculated on a site by site basis. However, this approach is not practicable for distribution sites because of the large numbers involved, therefore some simplified rules are used to determine ‘Hot’ or ‘Cold’ status. These rules are:- • The site is considered ‘Cold’ if the installation is connected to a Primary or Grid Substation via an underground cable without any overhead line in the route. In this case the majority of the earth fault current will return to source via the cable sheath and not through the ground – hence the EPR will be below 430 volts. The HV & LV Earth can be combined. • The site is considered ‘Hot’ if there is not a continuous underground cable back to the Primary or Grid Substation. Earth fault current must return to source through the ground and this causes an EPR which is assumed to be above the 430 volt limit. The HV & LV Earths must be segregated to prevent voltages in excess of 430 volts from being transferred into the LV neutral/earth system The alternative backfeeding arrangements must also be considered when assessing the hot/cold status. For normal running conditions the site may be cold (i.e. underground fed) but could be classified as hot if all the alternative backfeeds have overhead lines as part of the circuit back to the source. If the normal feed is all underground and at least one backfeed is also all underground then the site can be classified as cold since the substation is unlikely to be disconnected from a low resistance primary substation site. To achieve an EPR less than 430 volts at an overhead fed 11kV distribution substation, then the overall earth value would typically need to be less than 0.3 - 0.5 ohms. Often it is impractical to achieve such low earth resistance values at distribution sites hence the HV and LV earths will usually be segregated. However, if it is decided to combine the HV and LV earths then a site specific calculation must be made to confirm the EPR is actually below 430volts. Existing distributions sites shall be assessed to determine the site classification when significant material changes occur. This is especially important when an 11kV network is being reconfigured to make sure a site is not inadvertently made hot without further precautions being taken. Also distribution substations may also become hot if they are connected via cable to a nearby Hot Primary or Grid site. E2.4 Segregated HV and LV earths at Distribution Substations It is accepted that at some sites the earths will be unnecessarily segregated. This is particularly true in large villages or small towns which have a reasonably large earth system which is ‘islanded’ because the incoming circuits are all overhead. If the cost of segregation is prohibitively high or impractical then the cost of a full earthing study may be justified.
  • 6. CN Earthing Manual Section E2 – Earthing Guidance Notes In the past most pole transformers have had separate HV/LV earths, whereas the vast majority of ground mounted substations have had a combined HV/LV earth. Previously the regulations permitted joining the HV and LV earths when their combined resistance was less than 1 ohm. This has now changed – the old ‘1 ohm rule’ is no longer valid for new sites. If in doubt, treat it as ‘Hot’ and segregate the two earths. The LV earth system must be located outside of the 430 volt potential contour that surrounds the HV earth electrode during an 11kV earth fault. This distance varies and depends on the type of installation, the local soil resistivity value and the size of the HV earth mat. In very high resistivity soils this separation can be over 40 metres for a pole mounted site. Typically pole mounted HV & LV earths were separated by 3 metres to avoid transferring excessive voltages via the ground. The 3m separation distance is now no longer sufficient. The new separation distances have been calculated by an earth modelling computer programme and are detailed in Section “E5 Distribution Standard Earthing Layouts”. E2.5 Standard Distribution Earthing Methodology Because there are numerous distribution installations, standard earthing arrangements have been adopted. The following three sections of the Earthing Manual can be used to predict the type and size of the earth system for the most common values of soil resistivity. E3 Soil Resistivity Measurements E4 Earth Electrode Resistance Tests E5 Distribution Standard Earthing Layouts This will help advise landowners of the extent of proposed earthing excavation before work starts and to estimate the quantity of earthing materials required to complete the installation. E2.6 Difficult or non-standard situations The Distribution Standard Earthing Layouts are designed to cover the majority of situations and a standard solution should be the first approach. Sometimes this may mean placing a transformer some distance away from a third party installation in order to maintain adequate HV/LV segregation. However, there will be occasions where the standard approach is not practical or the soil resistivity is so high that specialist advice is required to overcome specific site difficulties. The cost of this has to be borne by the project. For advice please contact the Central Networks Earthing Specialist or initiate a survey using one of the approved earth consultants listed in Section AE1.1. Version 2 Date of Issue - September 2007 Page 6 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc
  • 7. CN Earthing Manual Section E2 – Earthing Guidance Notes E2.7 Hot Primary and Grid Sites All Primary or Grid sites shall have the EPR assessed and the details recorded on the Company’s hot site register. This information shall be made available to the relevant telecommunications companies. The owner of the Central Network’s hot site register shall be listed on the Energy Networks Association’s, Rise of Earth Potential website to provide the telecommunication companies with a point of contact. The information to be made available on request is:- • Hot/Cold site classification (based on either 650 or 430 volt limits) • Grid Reference or address of the site • Extent of the hot zone (if known), otherwise quote 100m (as detailed in ENA ER Version 2 Date of Issue - September 2007 Page 7 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc S36). Hot Primary/Grid sites require an isolation unit fitting to all incoming telecomms circuits. Telecomms circuits passing through the hot zone surrounding a primary or grid site require no specific precautions unless the EPR at the point of the telecomms circuit exceeds 1700 Volts for sites with fast protection clearance (i.e. less than 0.2 seconds) or 1150 volts for slower protection clearance times. ENA ER S36 provides more detail. Where reasonably practicable all new primary/grid sites shall be designed as cold sites. Where a cold site is impractical then any distribution sites that are cable connected to the new site shall be assessed to determine the EPR at that location. If the distribution site is declared hot for a fault at the primary substation then the HV and LV earths must be segregated. In general new LV supplies feeding a Primary or Grid site shall be derived from a dedicated on-site transformer. This transformer should not be used to provide LV supplies to customers off the site. If in doubt or where existing LV supplies are involved with supplying off-site third parties then refer to the Central Networks Earthing Specialist for further advice. E2.8 Methods of Earthing used on the Company’s Networks An application guide is available that provides greater detail on neutral earthing requirements for the Company’s HV and EHV networks. Figure E2.1 shows typical neutral earthing arrangements found on Central Networks systems. E2.8.1 132kV Network The 132kV network is a three wire, three phase network, except for the railway traction supplies which is a single phase 25kV system, with one pole earthed. All 400/132kV and 275/132kV transformers have their star points solidly connected to earth. Transformers at 132/66kV, 132/33kV and 132/11kV will also have the star point of each 132kV winding solidly connected to earth, in effect forming a multiple earthed system. This multiple direct earthing gives rise to the large earth fault currents experienced on the 132kV system. E2.8.2 66kV & 33kV Networks The 132/66kV and 132/33kV transformers are usually delta connected on the secondary side. These 33 or 66kV windings will be earthed by an earthing transformer. In the past the earthing
  • 8. CN Earthing Manual Section E2 – Earthing Guidance Notes transformer may have been low impedance in which case an NER would also be required to limit the earth fault current to an acceptable value. For new installations each earthing transformer should be high impedance to limit the prospective earth fault current to match the full load current of the main transformer up to a maximum of 1000Amps. Table E2.3 Earth fault limits for 132/33 and 132/66kV transformers Version 2 Date of Issue - September 2007 Page 8 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc Main Transformer rating (MVA) 33kV High Impedance Earthing Transformer -Earth Fault Rating (Amps) 66kV High Impedance Earthing Transformer – Earth Fault Rating (Amps) 15 260 - 20 350 175 30 525 260 40 700 350 45 800 400 60 1000 525 75 1000 650 90 1000 800 120 and above 1000 1000 E2.8.3 25kV Networks This is a single phase system for provision of supplies for railway traction systems. One pole of the secondary output of the 132/25kV winding is solidly earthed. The pole to be earthed is governed by and set out in Engineering Recommendation P24 “A. C. Traction Supplies to British Railways.” E2.8.4 11kV (& 6.6kV) Networks Depending on the vector group, 132/11kV, 66/11kV and 33/11kV transformers can have the secondary winding either delta or star connected. These transformers will be earthed on the secondary side either by an earthing transformer (if delta connected) or via the star point. Historically, small rating transformers (typically those less than 10MVA) had their secondary neutral solidly connected to earth. On all other transformers the secondary neutral was impedance earthed i.e. via a resistor or reactor. There are a number of existing arrangements for NER configurations at 11kV. In general either one NER was used across the site to earth all the transformer neutrals or alternatively each transformer had its own individual NER. The existing 11kV neutral earthing philosophy has three main requirements:- • to limit the overall prospective earth fault currents for any site to be less than 1500Amps for normal running arrangements. This has the benefit of reducing EPRs throughout the whole 11kV network. • to ensure there is sufficient earth fault current to operate protection at remote ends of the 11kV network.
  • 9. CN Earthing Manual Section E2 – Earthing Guidance Notes • to ensure the transformer neutrals are not solidly earthed at any time. This prevents excessive earth fault currents from occurring on the network. This can be achieved in a number of ways and depends on the number of transformer at the site. This often involves the use of a specially designed switching cubicle for each transformer which controls the NER running arrangements across the site. It should be noted that the new philosophy prevents the use of high impedance earthing transformers at 11kV. The preferred 11kV NER size is 1000Amps but this can be modified to either 750 or 1500 Amps as detailed in the Neutral Earthing Application Guide. For new systems a typical arrangement would be as shown in the figure below. The switches would be configured so that one NER earths all transformers. The other ‘un-used’ NER would be available when a transformer is switched out for maintenance. Some double secondary transformers (also known as double bubble or three winding transformers) having delta secondaries have been installed using only one earthing transformer in conjunction with a Thompson Strap. The Thompson Strap is an electrical connection installed within the transformer tank between the two blue phase (or L3) secondary windings. By convention the earthing transformer is then connected to the ‘b’ secondary winding. This arrangement also provides an earth return path for faults fed from the ‘a’ winding. The use of Thompson Straps is still permitted. The new NER policy can still be applied to double secondary transformers as shown below. T1 switching cubicle B Version 2 Date of Issue - September 2007 Page 9 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc A C B T1 NER T1 T1 switching cubicle A C B T2 NER T2 T2 switching cubicle A C T1 NER T1b T1a To Common Neutral Earth Bar & adjacent transformer switching cubicle(s)
  • 10. CN Earthing Manual Section E2 – Earthing Guidance Notes T1 switching cubicle B A C T1 NER Thompson Strap The earthing transformers in these situations will be a low impedance type. A nominal impedance must be designed into the earthing transformer to guard against the effects of a direct short circuit of the associated NER. In a very few instances the transformer secondary may be earthed by using an Arc Suppression Coil (ASC or Petersen Coil). The ASC is ‘tuned’ to the capacitance of the 11kV cables and overhead lines connected to the substation. This will minimise current at the fault position during a single phase to earth fault condition. If the fault persists then the system will automatically revert back to the normal resistor earthing arrangement. The 11/0.415kV distribution transformers have a delta connection on the primary winding and subsequently are therefore not earthed on the 11kV side. E2.8.5 Earthing of Low Voltage Networks The low voltage side of a three phase distribution transformer is star connected. This star point forms the neutral of the LV system and will be solidly connected to earth at all times. For single phase transformers one terminal will be designated as the neutral point and will again be solidly connected to earth. LV distribution networks can have a separate protective conductor (sheath earth system) or this can be combined with the neutral conductor (PME). Engineering Recommendation G12/3 details the specific requirements for the application of PME on low voltage networks. • All new underground LV networks shall be constructed using CNE cables to establish a network suitable for the provision of PME terminals. • All new overhead LV networks shall be constructed using Aerial Bundled Conductors (ABC) suitable for providing PME terminals. Wherever substantive work (e.g. refurbishment, diversions etc..) is undertaken on LV networks then the network shall be brought up to a standard to provide PME supplies. This work should also ensure existing sheath earth customers do not have their existing earthing terminal compromised. Version 2 Date of Issue - September 2007 Page 10 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc T1b T1a Low Impedance Earthing Transformer To Common Neutral Earth Bar & adjacent transformer switching cubicle(s)
  • 11. CN Earthing Manual Section E2 – Earthing Guidance Notes E2.8.5.1 Provision of LV Earthing Terminal The provision of a LV earthing terminal has been achieved by various means in the past. The present company policy with regard to the provision of a LV earth terminal is detailed below :- PME Terminal (TN-C-S) All new supplies, or existing customers requesting a load increase, will normally be offered a PME terminal. However, for reasons of safety some installations are not suitable for a PME earth terminal in which case a TT supply will be offered (see Section E6.3 for a detailed list of exceptions). Under the ESQC Regulations, the Company is not obliged to offer a free PME earth terminal to existing customers that do not already have a PME earth. Sheath Earth Terminal (TN-S) The Company has an ongoing obligation to maintain the integrity of the sheath earth terminal of customers which already have this type of earthing. If an existing sheath earth customer requests a service alteration or in the event of a fault repair then the existing sheath earth must be maintained unless the customer request a PME earth terminal instead. A sheath earth terminal shall not be made available to new customers (or existing customers if they do not already have an earth terminal). PNB Earthing PNB is a special method of earthing, similar to PME, where the neutral earth is installed at or adjacent to the customer’s installation instead of at the transformer position. This method can still be used provided the supply is from a dedicated pole mounted transformer supplying a single customer.. No Company Earth Terminal (TT) It is not possible for the Company to provide a PME earthing terminal where :- i) the customer’s installation does not conform to the statutory regulations regarding the provision of PME supplies. ii) the customers property is deemed to be unsuitable for a PME supply. In these circumstances the PME terminal shall be rendered inaccessible to prevent unauthorised access by third parties and the customer must be advised that it will be necessary to provide their own alternative means of earth fault protection (e.g. their own earth electrode and suitably sized RCD). Version 2 Date of Issue - September 2007 Page 11 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc
  • 12. CN Earthing Manual Section E2 – Earthing Guidance Notes Neutral always solidly earthed. Version 2 Date of Issue - September 2007 Page 12 of 12 The current version of the this document resides in the E.ON UK Documentum database CAUTION –any other copies in electronic, printed or other formats may be out of date © Central Networks plc Grid Supply Auto-Transformer 400(or 275)/132kV Grid Substation Transformer 132/33(or 66)kV Primary Substation Transformer 33(or 66)/11kV Distribution Substation Transformer 11kV/415V 132kV 33(or 66)kV 11kV 415V LV always solidly earthed Earthing Transformer Grid Supply Auto-Transformer 400(or 275)/132kV 132kV Grid Substation Double Secondary Transformer 132/11/11kV ‘A’ winding ‘B’ winding THOMPSON STRAP If only one earthing transformer has been used on a delta connected, double secondary transformer a connection is installed within the transformer tank between the blue phase or L3 secondary windings. By convention the earthing transformer is connected to the ‘B’ winding. This arrangement effectively provides an earth return path for faults fed from the ‘A’ winding. Earthing Transformer (NOT REQUIRED if Thompson Strap used) Could be solid (historically), resistance or reactance earthed. 11kV 11kV Earthing Transformer Figure E2.1 Typical Examples of Existing Neutral Earthing Arrangements NER will not be required if earthing transformer has high impedance. Could be solid (historically), resistance or reactance earthed. Steelwork earth only bonded to LV neutral earth if site is declared Cold. Neutral always solidly earthed. Could be solid (historically), resistance or reactance earthed. National Grid DNO National Grid DNO Note Occasionally the primary winding here may be a star connection. In which case the star point will not be earthed.